This document is an amendment to a solicitation for an Indefinite Delivery Indefinite Quantity (IDIQ) Multiple Award Construction Contract for large construction projects for the Marine Corps in North Carolina. Amendment 0012 provides responses to contractor questions regarding required erosion and sediment control measures, interior design and audiovisual requirements, and documentation needed to demonstrate design experience with USGBC-certified projects. Responses clarify that erosion control repairs will be handled through future contract modifications, interior design services are required for Building RR482, and a letter or certificate from USGBC or equivalent is sufficient for the design experience factor.
Amendment 0012
View the file
Other files
Show all 39
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
See Continuation.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 2
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 24-Oct-2019
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N4008519R9048
X 9B. DATED (SEE ITEM 11)
17-Sep-2019
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
24-Oct-2019
CODE
NAVFAC MID ATLANTIC
ACQUISITION CORE
9324 VIRGINIA AVENUE
NORFOLK VA 23511-3095
N40085 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N4008519R9048
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)
The following have been added by full text:
AMENDMENT 0012
1. Provides PPI responses 226, 228, and 229.
Reference
Inquiry Government Response Page Section Paragraph
Varies Amendme nt 9
There are several RFIs addressing that NAVFAC and NCDENR need to finalize the design process for the BMP found on CG301B.
Are we to ignore this sheet for the time being and treat this work as a potential modification after the award or will a amendment 11 be published with the changes?
Contractor is responisble for E&SC measrures shown on drawing CG301B. Any repairs that may be required to the BMP shall be handled through a contract modification at a later date.
Amend ment 09
An RFI in Amendment 09 refers to CLIN 0013 for FF&E and A/V requirements for RR482, stating that the writer could not find anything.
Yet Drawing IF101E indicates and lists item
424 - Chain Link Fence and Gate. The Government response to the RFI is, "Delete
CLIN 0013". Please clarify/confirm 1) Whether or not we are to include any interior design services or CTS-D services for FF&E and A/V for Building RR482 in our proposal; 2)That the
Chain Link Fence and Gates indicated on Drawing IF101E are not required in this contract; and 3) That CLIN 0013 is NOT to be included on our Bid Schedule.
The previous response to delete CLIN 0013 was in error. CLIN 0013 is required and consists of the items listed on Drawing
IF101E.
Factor 1- Experiren ce; (2) Design
Experienc e
Reference Factor 1-Experirence; (2) Design Experience. The last sentence of the 1st paragraph on Page 12 of 57 states, “The Offeror shall provide applicable documentation on projects that were validated and/or certified through U.S. Green Building Council (USGBC) or the equivalent organizations or process.” What type of applicable documentation is required to meet this submission requirement?
Certificate or letter from the organization.
(End of Summary of Changes)