This is a Performance Work Statement (PWS) for the Surveillance Towed Array Sensor System-Expeditionary (SURTASS-E) Support Vessel, a long-term vessel charter requirement supporting U.S. Navy operations under Military Sealift Command. The PWS establishes comprehensive technical and operational requirements for a U.S.-flagged or foreign-flagged (to be reflagged) vessel capable of worldwide operations, including Arctic and Antarctic regions during ice-free periods, to tow a passive acoustic monitoring array at 4-6 knots for up to 45-day missions while maintaining precise heading control within 5 degrees. The vessel must be classed by an International Association of Classification Societies (IACS) member, meet American Bureau of Shipping (ABS) standards for vessels under 90 meters, maintain a valid Certificate of Inspection, and operate with a crew of U.S. citizens, including officers holding U.S. SECRET security clearances. The vessel must provide permanent integrated accommodation for 30 personnel (6 officer equivalent, 24 unlicensed equivalent), with comprehensive life-saving and emergency medical equipment per Safety of Life at Sea (SOLAS) requirements.
The vessel must support installation and integration of approximately 4,224 to 5,008 square feet of Government Furnished Equipment (GFE) consisting of 7 to 10 ISO vans and associated systems, including winch and acoustic handling systems, hydraulic power units, processing and communications equipment, with total equipment weight of 304,100 to 404,285 pounds. Critical vessel characteristics include minimum transit speed of 10 knots sustained, capability to tow in Sea State 5 conditions (22-27 knot winds, 2.5-4.0 meter waves), minimum freeboard of 10 feet at mission deck, deck cargo capacity of 615 pounds per square foot with 190 long tons minimum load capacity, 150 kW of stable 440/460/480 VAC three-phase electrical power, and 5-ton shipboard crane capacity. Additional requirements specify radiated noise limitations per ABS Underwater Noise guidelines, provision of 500 gallons per day non-potable freshwater and 40 gallons per minute seawater at fantail, VSAT/INMARSAT communication capability with 4M x 2M bandwidth, and compressed air service for deck operations. The contractor must complete GFE installation and certification within four calendar days of receipt and demobilization within two calendar days, absorb all associated costs for mobilization, demobilization, and six annual GFE change-out instances, coordinate with government planning conferences three times annually, and maintain a 12-month maintenance schedule without inspections exceeding seven-day in-port periods during the first contract year.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PERFORMANCE WORK STATEMENT (ATTACHMENT 7)
Surveillance Towed Array Sensor System-Expeditionary (SURTASS-E) Support Vessel (long-term)
1.1 Mission: The Military Sealift Command (MSC) requests one US flagged or foreign flagged (to be reflagged US) vessel required to tow an acoustic array in support of U.S. Navy Operations. This is a mission essential requirement which will require a mission essential contractor services plan (MECSP, Part X(z)).
1.2 Area of Operation: The vessel must be capable of worldwide operations. This includes support in all ocean basins of the world from the Arctic to the Antarctic during seasonally ice- free periods, when waters are navigable without ice-breaking classification but must comply with Category C of the IMO Polar Code for open-water polar transits. The vessel operator must also be capable of sustaining the vessel worldwide.
1.3 Operating Scenario: The vessel will tow a passive acoustic monitoring system, between 4-6 knots, 24hours/day for up to a 45-day event. The ship will need to be able to tow on a directed heading within 5 degrees for extended periods at slow speed. Because of the type of acoustic system employed, the ability of the vessel to maintain heading stability is critical.
1.4 Operational Support: Military Sealift Command Operations
1.5 Reserved
1.5.1 Pre-Delivery Site Survey (PDSS): The Contractor shall permit government personnel to visit the ship no less than 10 days and no more than 30 days after award date to conduct a PDSS. The purpose of this PDSS shall be to, at a minimum, identify lay-down locations of government furnished equipment (GFE) equipment, identify locations of electrical sources, and limit potential obstructions to SURTASS-E operations.
1.6 Government Furnished Equipment (GFE): Government International Organization for Standardization (ISO) vans. The mission system is designed to be a self-contained accredited Military System, capable of rapid mobilization on a Vessel of Opportunity (VOO). See Table 1.
Items 1- 10 provide minimum capability for all mobilizations. Items 2 through 8 are ISOVAN. Some vans are certified as ABS/USCG Portable Accommodation Module (PAM). Items 1-8 are mounted on an ABS approved support structure to distribute the load.
Item 1 - Winch and Acoustic System Handling System with stern chute, Item 2 - Hydraulic Power Unit Van for the winch (PAM), Item 3 - OBRP Module Storage Reels Van, Item 4 - Processing equipment Van (PAM), Item 5 - Operations Van (PAM), Item 6 - C4I Suite / communications Van (PAM) Item 7 - Acoustic system workshop Van (PAM), Item 8 - Power Distribution Unit Van (PAM), Item 9 - Deck Equipment Support Structures & Mounts (to include 6 “platforms”), Item 10 - is the walkway from the 7-van or 10-van configurations to the ship’s deckhouse. The exact length of the walkway will be based on ship configuration. Item 14 includes all platforms, mounting hardware, and associated safety railings.
Item 11 - Acoustic system workshop/technician Van (PAM) Item 12 - OBRP Module Storage Reels, Item 13 - Processing System Van (PAM) Item 14 - is Deck Equipment Support Structures & Mounts necessary to support the addition of the vans identified as items 11-13 (if required).
NOTE: Items 11-14 supports the alternate mission system configuration and may be installed at the discretion of the government. Some vans are certified as ABS/USCG Portable Accommodation Module (PAM).
Items 11-13 may be mounted on an ABS approved support structure to distribute the load, if required.
Recompete25
Basic Mission Configuration Table 1
| Item |
| Description |
| area (ft2) |
| weight (lbs) |
| 1 |
| Winch and Acoustic System Handling System with Stern Chute |
| 1,476 |
| 52,500 |
| 2 |
| Winch Hydraulic Power Unit (HPU) |
| 170 |
| 31,000 |
| 3 |
| OBRP Module Storage Reels |
| 170 |
| 28,000 |
| 4 |
| Processing |
| 170 |
| 31,000 |
| 5 |
| Operations |
| 170 |
| 31,000 |
| 6 |
| Communications |
| 170 |
| 31,000 |
| 7 |
| Acoustic System Workshop |
| 170 |
| 31,000 |
| 8 |
| Power Distribution Unit |
| 170 |
| 31,000 |
| 9 |
| Deck Equipment, Support Structures & Mounts |
| 1,078 |
| 32,000 |
| 10 |
| Deck Walkway |
| 480 |
| 5,600 |
| Sub-Total |
| 4,224 |
| 304,100 |
| Item |
| Description |
| area (ft2) |
| weight (lbs) |
| 1-10 |
| Basic Mission Configuration Items 1-10 Total Area & Weight |
| 4,224 |
| 304,100 |
| 11 |
| Acoustic system workshop/technician Van (PAM) |
| 170 |
| 31,000 |
| 12 |
| OBRP Module Storage Reels |
| 170 |
| 31,000 |
| 13 |
| Processing |
| 170 |
| 31,000 |
| 14 |
| Additional Deck Equipment and Support Structures (under vans) |
| 274 |
| 7,185 |
| Total |
| 5,008 |
| 404,285 |
1.7 Requirements:
| No. |
| SURTASS –E VOO |
Capability Mandatory Requirements
| 1 |
| Vessel Classification and General Conditions |
| a. Shall be classed by an International Association of Classification Society (IACS) member. |
b. Shall meet the requirements outlined in American Bureau of Shipping (ABS) Guide for Steel Vessels, under 90 meters in length (2019) or the equivalent certification standard of a IACS member.
c. The vessel shall be US Flagged.
d. Shall be certified for Open Ocean Manned Operations per applicable United States Coast Guard (USCG) and/or ABS (or IACS member) regulations.
e. A valid Certificate Of Inspection (COI) shall be maintained for the entire duration of vessel lease. The COI shall allow operations in accordance with 46 CFR Subchapter I - Cargo and Miscellaneous Vessels and must support the installation of Government Furnished Equipment, which consists of Portable Accommodation Modules (PAMs) as defined by the US Coast Guard.
f. The Master, officers, and entire crew shall be U.S. citizens. At least one corporate officer and all deck officers like the Master, Chief Mate, Second & Third Mate are required to hold a U.S. SECRET security clearance prior to assignment on the vessel. The SECRET access will allow the officers to attend the Secure Video Teleconferences (SVTC) for classified briefings up to Secret level as required and for the Master to have access, as necessary, to the shipboard operations center to receive situational awareness briefings from the Military mission commander. All personnel onboard assigned must either have a current security clearance or have passed a national agency background check and have the ability to obtain a Common Access Card (CAC). Personnel not categorized as deck officers require a Tier One background investigation for suitability as needed for recurrent base access. The contractor shall confirm their ability to meet the citizenship and security clearance requirements found in the RFP Part V (a).
| No. |
| SURTASS –E VOO |
Capability Mandatory Requirements
g. The following vessel security measures shall be required:
1. Provide access control such that only authorized Ship and government approved visitors are allowed onboard. Government will provide list of their authorized visitors.
2. In port, a ship roving watch will inspect the status of government spaces, locked or unlocked and manned, and report any unexpected conditions to a designated government representative. The rover shall inspect each of the secure containers at least once every four hours when they are unmanned. Each inspection shall include verifying that each secure container entrance door is closed, secured, and personnel shall write the current date, their initials, and the time of the inspection on the Standard Form 702 attached to outside of each entrance door.
3. When in a non-U.S. controlled port facility, (defined as any port facility that is not a U.S. or North Atlantic Treaty Organization (NATO) member military base), The Contractor shall provide a continuous, 24-hour physical security watch at the gangway/access point to prevent unauthorized access to the ship. This 24-hour watch shall be maintained continuously for the duration of the in-port period.
h. Shall provide emergency medical services (First Aid) to all embarked personnel.
i. Shall provide sufficient life-saving equipment to meet local regulatory and Safety of Life at Sea (SOLAS) requirements for all embarked SURTASS-E personnel.
j. Shall provide fire-fighting coverage of all SURTASS-E ISO vans and elements on deck using the ship’s existing firefighting equipment.
1. Class A
2. Class B
3. Class C
k. For operating scenarios, the ship, with SURTASS-E installed, shall comply with all intact and damage stability criteria required by the ship's Flag Administration, Classification Society's Rules, and USCG Certificate. (Accommodation must be made to allow Government System PAM vans to be connected to the ship Fire Alarm and Public Address General Alarm (PAGA) system as required by US Coast Guard regulation.)
l. Shall provide permanent, integrated type accommodation inside the skin of the ship for 30 SURTASS-E personnel. (6 officer equivalent, 24 unlicensed equivalent).
1. Six (06) staterooms for individual occupancy – For use by Military Officers In Charge (Commissioned Officer, Chief Warrant Officer and or Chief Petty Officer), Senior SOC Technician (STA) and or senior civilians as identified by MSC (equivalent to Licensed Officers).
2. Two (02) to four (04) person staterooms to accommodate twenty-four (24) personnel – junior enlisted, technicians and persons not in a leadership/management position (equivalent to Unlicensed Mariners).
3. Shall provide hasps, or similar item, on each locker inside the skin of the ship in guest berthing suites to allow for the use of personal padlocks.
m. Forward deployed out of area operations (away from Norfolk, VA area) will require extensive coordination from the company operations manager. Specifically, logistic support for voyage, port calls, and multiple crew turnovers in order to maintain ready for tasking. The duration for each crew rotation/swap is 56 days.
n. The vessel cannot have any mandated USCG or ABS inspections that require in port periods longer than seven days during the first year of charter.
1. Contractor shall be required to provide a minimum of 90-day notice of any maintenance availabilities and shall coordinate so as to not interfere with the mission
2. Contractor must have representation at all planning conferences.
a. In person representation
b. Three times per year
c. Costs shall be included within daily charter rate and will not be reimbursable.
3. Contractor shall provide a 12 month maintenance schedule within 30 days of award and annually thereafter, within 10 days of commencement of Option periods.
| No. |
| SURTASS –E VOO |
Capability Mandatory Requirements
| 2 |
| Vessel Characteristics - General |
| a. Vessel shall be capable of supporting a typical operations cycle of: |
1. 4000 NM transit non-stop; followed by up to 45 Days towing at 4-6 knots
2. Shall be capable of 60 days at sea un-replenished. This includes:
a. fuel
b. food
c. berthing
d. potable water
e. waste disposal (sanitary)
b. Minimum Transit Speed: shall be no less than 10 knots sustained.
c. Operating Speed:
1. Vessel shall be able to tow a long line acoustic system at 4-6 knots for 24 hours/day and maintain course within 5 degrees of desired heading in sea state 5.
2. Turning Rates: The ship must be capable of making controlled turns at 5 degrees/minute in sea state 5.
3. Deployment & Retrieval: The vessel shall be capable of maintaining a stable heading (within 5 degrees of desired course), while deploying and retrieving the acoustic system at speeds varying between 1-2 knots, for periods no less than 4 hours.
4. During towing operations, the ship steerage shall not endanger the acoustic system by creating a thrust direction that would bring the acoustic system into contact with the ship propulsion or steerage equipment.
5. Shall be able to conduct aft deck launch and recovery operations at 1-2 knots in Sea State 5 while maintaining heading. The use of thrusters or dynamic positioning systems to maintain heading during deployment and recovery operations is allowed.
NOTE: Sea states are as defined in NATO Standardization Agreement 4194 (Edition 1) “Standardized Wave and Wind Environments and Shipboard Reporting of Sea Conditions” (1983) as Amended (1985).
Sea State 4: wind 16-21 knots (sustained), wave heights 1.2-2.5m Sea State 5: wind 22-27 knots (sustained), wave heights 2.5-4.0m Sea State 6: wind 28-47 knots (sustained), wave heights 4.0-6.0m
d. Seakeeping:
1. Shall be able to tow the acoustic system on any heading at 4-6 knots in the full range of sea conditions up to and including Sea State 4 as a minimum and best heading in Sea State 5. Safe towing on any heading in higher sea states, greater than Sea State 4, is desired if this can be done safely without endangering personnel or the installed acoustic system.
2. Shall be able to transit in Sea State 6.
3. Shall be able to support safe aft deck operations to deploy/recover the acoustic system in sea states as listed:
a. Deploy acoustic system: Sea State 5
b. Recover acoustic system: Sea State 5
c. Mission Operation within PAMS: Sea State 5; Full range NOTE: Sea states are as defined in NATO Standardization Agreement 4194 (Edition 1) “Standardized Wave and Wind Environments and Shipboard Reporting of Sea Conditions” (1983) as Amended (1985).
Sea State 4: wind 16-21 knots, wave heights 1.25-2.5 m Sea State 5: wind 22-27 knots, wave heights 2.5-4.0 m
e. Freeboard at the mission deck shall be minimum10 ft. (3 m); maximum of 25 ft (7.62m).. NOTE: The ship may be ballasted to achieve this minimum freeboard, provided it does not violate USCG or Classification Society regulations regarding stability.
If ballasted to achieve freeboard, new list & trim shall not exceed 5 degrees.
f. Shall have a deck cargo loading capacity of 615 lb./ft² (3 MT/m²).
g. Shall have a minimum deck load capacity of 190 Long Tons.
| No. |
| SURTASS –E VOO |
Mandatory Requirements
h. Shall provide 150 kW of 440/460/480 VAC, 3-phase, Delta, 50-60 Hz, 200 Amp electric power. Power shall be stable and available 24 hr./day during mobilization, deployment, and de-mobilization. Power distribution panel shall be located no more than 100 ft. forward of stern or within 75 linear feet of the Mission System Power Distribution van, whichever is less. The nominal location of the mission power distribution van is illustrated in Diagram 1.
Note:
1. The vessel shall provide electrical service via either one (1) 200 Amp service or Two
(2) 100 Amp service cables.
2. Non-permanently installed generating equipment must not contribute to the radiated noise of the vessel in excess of the requirements outlined in Requirement 4 of this section.
3. Emergency back-up power shall be available (within 5 minutes) for SURTASS-E equipment.
i. Shall provide up to 500 gallons/day (1893 liters) of non-potable freshwater, no hydrocarbons, to the fantail for wash down of SURTASS-E equipment. Vessel shall provide connection to SURTASS-E systems if required.
j. Shall provide up to 40 gallons/min (151 liters) of seawater at a minimum of 50 psi to the fantail for cooling of the SURTASS-E equipment. Vessel shall provide connection to SURTASS-E systems if required. Water supply must be debris free. No particulate greater than 0.125 inches (0.32cm).
k. Shall provide workshop-quality compressed air to fantail for tools such as air driven wrenches.
l. Shall provide a shipboard crane with a 5-ton capacity, sufficient to lift equipment from the pier to the ship.
m. Shall provide an interface connection panel to the ships telephone system, public announcing (PA), general alarm (GA), and fire alarm (FA) system no more than 100 ft. forward of stern or within 75 linear feet of the Mission System Power Distribution van, whichever is less. This connection should be collocated with the power panel identified in paragraph 2.h of this section. The FA/PA/GA alarm connections shall support connecting all PAM van to the ships monitoring system.
n. Shall provide ships telephone system to allow for communications to and from staterooms and ships bridge to mission system Communications Van and Operations Van.
| 3 |
| Vessel Characteristics - Mission System Support |
| a. The vessel shall have a clear weldable deck area of a minimum of 5,008 ft2 (465.3 m2) for installation of the mission system vans and winch plus an additional approximately 710 ft2 (65.96 m2) for the installation of a walkway from the ship’s main deckhouse to the mission system vans installed on deck. Area shall be clear of any emergency hatches or scuttle locations. Access to any sounding tube or other locations requiring routine service shall not interfere with the mission system placement. The ship’s deck area must accommodate the installation and welding of the mission system as identified in Diagram 1d-1f and installation of three over-boarding poles shown in Diagram 5. The deck layout identified in Diagram 1a-1c represents the nominal deck configuration as currently employed. Adjustments to the location of the major components, shown in Diagram 1a-1f, may be allowed to support vessel underlying deck structural configuration and allowable deck loading. Diagram 2 shows the government furnished walkway and a notional configuration. The walkway is nominally 4 ft. (1.22m) wide and runs along the centerline of the vessel. The exact length of the walkway is determined by the distance from the ship’s deckhouse to the first set of mission vans. The installed government mission equipment can be considered as three regions that may have their physical location modified from the nominal location within the constraints listed below. The walkway shall be flush with Handling System Group (HSG) Platforms. Minor adjustments to the location of major components may be allowed to support vessel structural loading. |
| No. |
| SURTASS –E VOO |
Mandatory Requirements
NOTE: ABS certification for deck configuration must meet government requirement to complete the full installation and certification of the system within 7 days of receipt of materials, exception of unforeseen circumstances beyond the operator’s control. Current government ISO mounting hardware is approved by ABS for single deck configuration. Government will require the contractor to clearly demonstrate, with data, how any alternative configuration can be certified to meet government need. Contractor is responsible for any cost associated with installation of Government Equipment to include, but not limited, to welders, gas free engineering, class surveyors, etc. Diagram 3 provides a nominal deck welding layout and is not a directive for welding installation and cannot be used to form the basis for a request for equitable adjustment. It is the responsibility of the contractor to safely install the GFE. Upon delivery and when all GFE is provided, the Contractor shall ensure that all GFE required is welded to the deck, approved by Class, and is ready in all respects to conduct missions within four days of receipt of GFE.
b. When the government equipment is placed on deck, the following additional conditions must be satisfied:
1. In the deck area adjacent to, and aft of the mission system VAN location, there can be no height obstruction greater than 15 feet (4.572 m).
2. Additionally, the only allowable obstruction can be within a zone +/- 45 degrees, as measure from the centerline of the forward most center VAN, when installed on the deck, as illustrated in Diagram 1a.
3. The allowable obstruction restriction of paragraph 3.b.1. and 3.b.2. applies to the forward most row of vans in the 7-van configuration and from the center row of vans in the 10-van configuration.
4. All deck area must be co-located on one level.
Note: Current government ISO mounting hardware is approved by ABS for single deck configuration.
5. Any proposed deck configuration changes that differ from Diagram 1 must provide the equivalent deck area as outline within Diagram 1. Additionally, all sides of the winch or any van must be accessible and have a minimum of 4 feet of clearance.
c. All deck space must allow the installation of high cube ISO containers on a GFE Support system. ISO Containers fall under both ABS and U.S. Coast Guard regulations.
d. The vessel shall have a stern area allowing the installation of a government furnished stern/over boarding section of 36 ft. x 31.7 ft. (10.97m x 9.7 m) immediately forward of transom for deployment & retrieval of the government mission system to include mission system winch and platforms.
e. The 36 ft. (10.97 m) dimension shall be along the transom. The transom section shall allow for an opening to sea on the stern that must accommodate a 17ft (5.18 m) wide over-boarding chute and associated deck mounting hardware (see diagram 1).
f. Exclusive of the government furnished stern/over boarding section, (3.d), the remaining deck shall be no smaller than 3,456 ft2 (321.1 m2). This deck area must allow for an ISO van layout of 36 ft. x 96 ft. (10.97 m x 18.2 m) as illustrated in Diagram 1f.
NOTE: The SURTASS-E current ABS approved footprint can be found in the Approved ABS Deck Layout, Diagram 1a. Exact deck layout will be based on vessel selection.
g. The vessel shall provide sufficient opening of any stern wall to provide for the unobstructed over-boarding of the SURTASS-E Acoustic system via the government furnished stern chute. A minimum of an 18.5 ft. (5.64 m) opening shall be required, which is included in paragraph (3.d), 36 ft. x 31.7 ft (10.97m x 9.7 m) section. The centerline of the opening must be the same as the centerline of the deck space for the winch section specified in paragraph (3.d).
h. The deck shall be coplanar with a maximum vertical deviation of 2 in (5.1 cm) when measured from the transom to 50 ft. (15.74 m) forward of the transom for SURTASS-E Winch/Acoustic system Handling Equipment.
i. There shall not be any Ship’s deck hardware with a vertical height of 2 in. (5.1 cm) or greater from the deck in the way of SURTASS-E bases.
NOTE: This includes any retractable deck equipment that is needed for routine operations of the vessel to include mooring or maneuvering with tugs.
j. The deck and deck attachment points must not have damage or cracking, cracked welds, excessive pitting or corrosion.
k. Deck attachment shall support welding of mating structures for mission system. The deck may be fitted with standard ISO container attachment points to allow securing acoustic system equipment to deck. Anticipate welding approximately 200 T-joint welds to attach government hardware to the platform in accordance with (IAW) ABS requirements.
l. Shall support winch tow loading of 78,000 lbs. (346,961 Newtons). Tow load (bollard pull) will be 6,500–17,000 lbs. (28,913 – 75,620 Newtons). Contractor shall provide ABS Certificate of deck load certification at award.
m. Freeboard at the mission deck and gunwale shall allow for the deployment of up to three 10-30 ft. (3.05-9.14 m) vertical poles as depicted in Diagram 5: including one supporting an acoustic speed sensor and a second pole supporting a fathometer transducer. All three will be deployed over the side during towing operations. Each over boarding pole will be supported by two welded platforms.
n. The vessel operator shall adhere to all regulatory requirements for the safe installation and removal of the GFE Acoustic Doppler Current Profiler (ADCP) system, so as to ensure its proper operation. This system shall be installed on one of the swing arms identified in paragraph m. The final swing arm location should avoid interference with vessel fixtures (i.e. fuel vent) and be close enough to the van pad to run a 100-foot data power cable between the sensor and the operator van. Sufficient room aft should also be planned to mount the additional beam for the guide wire aft.
o. The vessel shall provide location (inside the skin of the ship, main deck or higher, and near the berthing area) for a GFE small arms locker, which will be welded to the deck per AT/FP requirements.
1. The size of the Ready Service Locker (RSL) which will securely store the Ships self-defense and embarked security team ordnance is: L94” X W65” X H71” Approximate shipping weight is 2500 lbs.
2. The size of the Class V weapons safe for ships self-defense is: H51 ¾” X W22” X D39” Approximate shipping weight is 1080 lbs.
p. The vessel shall provide one Mechanical technician to perform maintenance & repairs on the Hydraulic Power Unit. A qualified chief engineer with hydraulic knowledge is sufficient for this requirement.
q. The vessel shall provide one Electrical technician to perform maintenance & repairs on the Power Distribution System Electrical ISO Van. A qualified chief engineer with electrical knowledge is sufficient for this requirement.
| No. |
| SURTASS –E VOO |
Mandatory Requirements
r. Government Furnished Equipment (GFE) Integration
1. The Contractor is responsible for mobilization, integration, lifecycle change-out, and demobilization of all Government Furnished Equipment (GFE) modules/vans as specified in this PWS. The Contractor shall provide all necessary labor, engineering, equipment (including cranes and rigging), and physical vessel access solutions to perform these tasks All costs associated with these tasks shall be included in the contractor’s fixed price.
· Government Notification: The Government will provide the Contractor (Owner/Operator) with a minimum of seventy-two (72) hours advanced written notification, accompanied by necessary diagrams and drawings, prior to any required GFE installation or change-out.
2. Turnaround Times and Return to Mission – To mitigate losses in operational capability, the Contractor shall adhere to the following strict timelines for GFE actions to ensure vessel availability. The Contractor is fully responsible for executing all necessary logistics and physical access solutions to meet these requirements:
| GFE Actions |
| Required Turnaround Time |
| Turnaround Time Start/Stop Definition |
| GFE / Van Installation & Change-Out (Return to Station) |
| The Stop shall occur within four (4) calendar days of the Start as described in the column to the right. |
| Starts: Upon Contractor’s physical receipt of the GFE at the designated port following the 72-hour notification provided by the Government pursuant to 3.r.1 immediately above. |
Stops: When the GFE is fully installed, secured, tested, and the vessel is accepted by the Contracting Officer’s Representative (COR) as fully mission-capable and ready to return to station.
GFE / Van Final Removal (Demobilization)
| The Stop shall occur within two (2) calendar days of the Start as described in the column to the right. |
| Starts: Upon Contractor’s arrival at port for a scheduled demobilization. |
Stops: When the module and the Ships Integration Template Set (SITS) is safely removed and off-loaded, and custody transferred back to the Government.
3. The contractor is responsible for all costs associated with the GFE actions (mobilization, demobilization, and change-out of GFE) based on the below estimated schedule. These estimated GFE actions shall be included as part of the contractor’s fixed price:
· One (1) Mobilization: Contractor’s fixed price shall be inclusive of all crane services, labor, class surveyor services gas-free engineering, welding services and any other services or supply required for the initial receipt, installation, and integration of GFE.
· One (1) Demobilization: Contractor’s Fixed price shall be inclusive of all crane services, labor class surveyor services gas-free engineering, welding services and any other services or supply necessary to complete for the final removal, off-loading, and transfer of GFE back to the Government.
· Six (6) Instances of GFE change-out: Executed on notice provided pursuant to 3.r.1 (bullet point) above to address container/van replacements, change-outs, or equipment casualties throughout the year. Contractor’s Fixed price should be inclusive of all crane services, labor, class surveyor services gas-free engineering, welding services and any other services or supply necessary to complete the change-out.
· Any Vessel modifications, dismantling, or creating physical access paths for modules required to properly install or accept GFE.
· Any extended shipyard shifts required to meet the mandatory four (4) day “Return to Mission” timeline.
s. The purpose of the government furnished walkway between the deck house and the installed mission systems is to support safe passage of personnel to and from the ship superstructure/main deckhouse and the mission system PAM units. All new and existing walkways and platforms shall be flush to prevent creation of a trip hazard. Walkways are illustrated in Diagrams 2 through 4. The current revision of installation drawings SES-D- 00006 and SES-D-00209 show the details of proposed installation. These drawings will be modified to conform to the vessel’s structure and layout.
t. The vessel shall provide VSAT/INMARSAT capability as a secondary means of communication for command, control and coordination.
1. Due to the extreme Northern Latitudes/Operating Area, an increased bandwidth is required – 4M X 2M (download/upload) capability for all operating areas.
2. The Contractor shall incorporate cost for said service in their daily charter hire rate. The Contractor is entitled to reimbursement if assigned to an area with usage fees above and beyond the known cost of services for 4M X 2M (download/upload) capability.
3. The following countries identified are a sample listing of known areas of operation and is not all-inclusive as the vessel shall be available for world-wide assignment: Iceland, Azores, Norway, England, the Mediterranean, Japan, and South Korea.
u. The government will provide a small form factor Defense Advanced GPS Receiver (DAGR) kit to provide a reliable GPS signal in all environments. The DAGR shall be installed in the pilothouse by the mission system crew with concurrence from the vessel on installation location and power and signal cable routing, prior to each government directed at-sea period. While the vessel is in-port the DAGR receiver shall be removed by the mission system crew and stored in a locked mission system van. The kit contains the GPS receiver, antenna, and cabling inside a protective case. Installation of the antenna and receiver may be accomplished via non-permanent means. The mission system crew will conduct all setup, maintenance, and troubleshooting procedures. The mission system crew will train the vessel crew on basic operations and identification of problems, which shall be reported to the mission system crew upon discovery.
v. The vessel shall provide the following ships navigation data via serial communications over two pairs of bare wire connections. The data shall be provided in accordance with the National Marine Electronics Association (NMEA) formatted message standard and shall be provided at a 1Hz frequency, with a RS-422 physical interface, at 4800 baud, with one (1) start bit, eight (8) data bits, and no parity bit (“8-N-1” format). The data shall be provided at the same location as the connection to ships systems identified in paragraph 2.m.
| Message |
| Ship’s Port |
| Device |
| NMEA ver |
| Description |
| $--DPT |
| 1P18 |
| Depth |
Sounder
| 3.01 |
| Depth |
| $--VBW |
| 1P18 |
| Doppler Speed Log |
| 3.01 |
| Water |
Speed and Heading
| $--ZDA |
| 1P17 |
| GPS or |
equivalent
| 3.01 |
| Time and |
date
| No. |
| SURTASS –E VOO |
Capability Mandatory Requirements
| 4 |
| Vessel Characteristics - Radiated Noise |
| a. During normal towing operations (4-6 knots), the ship radiated noise shall not exceed the requirements (as set forth in the ABS Guide for the Classification Notation: Underwater Noise and External Airborne Noise dated May 2025, Underwater Noise (UWN) requirements for Research Vessels, subsection 3/5 or other classification society equivalent) by no more than five (5) individual narrowband tones across the frequency band of the UWN(R) spectrum. Compliance with the entire specification is applicable and reviewable be the government in deciding if any noise offender will impact mission operations. |
b. The vessel operator / contractor must provide objective quality evidence, test reports, or information, from any accredited noise and vibration organization, showing how the vessel being supplied does not exceed a threshold established in paragraph (4.a).
c. Ship radiated noise profile excursions are permissible if the broadband noise source is no greater than 3dB, and any narrow band source is no greater than 15dB above the requirements of part (4.a). No more than 5 narrowband sources greater than 15dB will be considered acceptable. Both broadband and narrowband limits must be met. Narrowband tones cannot be greater than 15dB above the 1/3 octave band limit. Narrowband limits are compared to the numerical values of the one-third octave band limit. If at any time, the contractor is found to not meet the noise requirements, the Contractor must clearly demonstrate how the noise source can be mitigated. The determination of whether or not a source is or can be adequately mitigated is at the sole discretion of the government.
NOTE: The government reserves the right to verify that the vessel meets the radiated noise requirement (4.a) upon delivery.
The Contractor shall maintain certification throughout the duration of the contract period. The Government retains the right to reinspect and/or run the test on a government facility. Costs associated with this testing will be the responsibility of the Government. If at any time it is determined the vessel does not meet the PWS requirements, the cost to regain compliance is the responsibility of the Contractor.
d. The vessel operator / contractor shall have the hull cleaned on an annual basis. All annual hull cleanings shall be scheduled in a manner that does not interfere with missions. All hull cleanings are at the contractor’s expense and should be included in their daily charter rate.
Approved ABS Deck Layouts
Diagram 1a
Diagram 1b
7-Van Configuration Illustration
Diagram 1c
Note: Diagram 1c shows the physical configuration of the government equipment that can be installed on the platform.
The government layout allows for some variation in the 64inch dimension that represents a platform deck between the aft end of the winch and the raised portion of the “FWD PLATFORM”. The allowed variance is 0-64 inches in the identified dimension. The forward portion of the winch shall not exceed the 64-inch dimension.
Nominal 10-Van Configuration
Diagram 1d
Diagram 1e
10-Van Configuration Illustration
Diagram 1f Notes:
a. Clear deck area of 5,008 ft2 (465.3m2), (see Table 1).
b. All deck area must be co-located on one level.
c. A clear deck area of 36 ft. x 31.7 ft. (10.97m x 9.7m), 1142 ft2 (106.1m2) forward of transom for deployment and retrieval of acoustic system.
d. Diagram 1a-1c shows a 7-van configuration. Three (3) additional ISO vans to be located forward of the Processing, Operator, and Communications vans, illustrated in Diagram 1d-1f, represent the nominal 10 van configuration. The basic mission configuration that must be installed is illustrated in Diagram 1a.-1c. The government reserves the right to add the additional three vans at a later date.
e. The obstruction restriction illustrated in this diagram is measured from the forward most row of vans in the 7-van configuration and the middle row of vans in the 10-van configuration.
Walk Way Dimensions
Diagram 2 Notes:
Length of walkway is set by the distance from the ship superstructure to the forward most van. The width of the walkway is nominally 4 ft (1.22 m).
Nominal Deck Welding Layout
Diagram 3 *For information only. This diagram does not indicate government direction for welding installation and cannot be used to form the basis for a request for equitable adjustment. The contractor is responsible for safely installing GFE* Notes:
1. Anticipate welding approximately 650 fillet welds to attach government hardware to the platform IAW ABS requirements for a 7-van configuration. The number of fillet-joint welds is increased by approximately 90 if 10 vans are installed.
2. This is the underlying footprint for SURTASS-E Van Configurations (Drawing SES-D-00006rev); Bottom portion supports the 36 ft. x 50 ft. section, and top portion supports the 36 ft. x 74 ft. section.
3. An ACAD drawing with all welding instructions and dimensions will be provided to the contractor prior to installation to support COI submission.
4. The distance between the bottom of the mounted Vans and the vessel’s deck is ~18.79”.
7-Van Walk Way Configuration
Diagram 4
Notes:
Diagram 4 shows the complete walkway structure for the vessels with a 7-van configuration.
Overboarding Poles
Diagram 5 Notes:
a. Diagram 5 shows poles in their stowed position which is horizontal and parallel to the ship’s deck or gunwale where installed.
b. During normal operations, the swing arm is rotated 90 degrees to be perpendicular to the ship’s deck or gunwale.
image1.png image2.png image3.png image4.png image5.png image6.jpeg image7.png image8.jpeg image8.png image9.jpeg image11.png image12.jpeg image10.png image12.png image15.png image16.png image13.png image14.jpeg image19.png image20.jpeg image17.png image18.jpeg image23.png image24.jpeg image20.png image21.png image27.png image28.png image22.png image23.jpeg image31.png image32.jpeg image24.png image25.png image26.jpeg image35.png image36.jpeg image29.png image30.png image39.png image40.png