This document contains questions and answers regarding Solicitation Number N00039-18-R-0005 for the NGEN-R Service Management, Integration and Transport (SMIT) contract opportunity.

The Space and Naval Warfare Systems Command (SPAWAR) intends to release a Request for Proposal on or around July 31, 2018 to acquire SMIT services in support of the Naval Enterprise Networks Program Management Office. The services include operating model, service operations, service integration, and transport and productivity. Service management will facilitate planning, provisioning, delivery, operation, and sustainment of interdependent services used on the Navy Marine Corps Intranet, Outside Continental United States Enterprise Network, and Marine Corps Enterprise Network. Integration involves seamless management with other contractors under NGEN-R. Transport includes full life cycle management and support for infrastructure providing network configurations, connectivity, and delivery of internet protocol services. The closing date for proposals will be around October 1, 2018. Pricing will include firm-fixed-price, fixed-price level-of-effort, fixed-price incentive firm target, and cost-plus-fixed-fee line items. The period of performance is a five-year base period and three one-year options.

The questions and answers provide clarification on the small business participation goal evaluation, classification levels of environments, proposal submission requirements, and how hardware and software maintenance costs should be priced under the contract line item numbers.

View the file

Other files

File Type Posted
N00039-18-R-0005-0009 SMIT RFP Amendment 01172019.docx DOCX document
N00039-18-R-0005 SMIT RFP Conformed 0009.docx DOCX document
SMIT Attch L-3 Cost Price Evaluation Template Rev5 01172019.xlsx XLSX spreadsheet
SMIT Attch L-3 Cost Price Evaluation Template Rev4 01112019.xlsx XLSX spreadsheet
N00039-18-R-0005 SMIT RFP Conformed 0008.docx DOCX document
N00039-18-R-0005-0008 SMIT RFP Amendment 01112019.docx DOCX document
N00039-18-R-0005-0007 SMIT RFP Amendment 01102019.docx DOCX document
N00039-18-R-0005 SMIT RFP Conformed 0007.docx DOCX document
SMIT Attch L-3 Cost Price Evaluation Template Rev3 01012019.xlsx XLSX spreadsheet
SMIT Attch J-7 Service Level Requirements (SLR) Matrix_Final Rev2.xlsx XLSX spreadsheet
SMIT RFP Questions and Answers Set 4 12212018.pdf PDF
SMIT_RFP_Amd_01-06_Package.zip ZIP file
Final_SMIT_RFP_Package_10182018.zip ZIP file
SMIT_RFP_Questions_Set1-3.zip ZIP file
N00039-18-R-0005-0005 SMIT RFP Amendment 12172018.docx DOCX document
SMIT Attch J-1 PWS v1.0_Final Rev1.docx DOCX document
A002 SMIT CDRL_ONE-Net Transition Plan Rev 1.docx DOCX document
SMIT Attch L-4 ONE-Net Estimated Transition Support Services Manning Rev1.xlsx XLSX spreadsheet
SMIT Attch L-3 Cost Price Evaluation Template Rev1 12112018.xlsx XLSX spreadsheet
SMIT Attch J-29 NGEN Master Tools Library_Final Rev1.xlsx XLSX spreadsheet
SMIT Attch J-27 Cost and Software Data Rep. (CSDR) Plan_Final Rev1.xlsx XLSX spreadsheet
A001 SMIT CDRL_NMCI Transition Plan_Rev1.docx DOCX document
SMIT Attch J-24 USMC Operations Support Services_Final_Rev2.xlsx XLSX spreadsheet
SMIT Attch J-13 Labor Rate Card Material Discounts Final Rev2.xlsx XLSX spreadsheet
N00039-18-R-0005-0004 SMIT RFP Amendment 12112018.docx DOCX document
N00039-18-R-0005-0003 SMIT RFP Amendment 12032018.docx DOCX document
SMIT Attch J-11 Wage Determination_Final_Rev1.xlsx XLSX spreadsheet
SMIT Attch J-5 Navy Government Furnished Property (GFP)_Final Rev1.xlsx XLSX spreadsheet
SMIT Attch J-13 Labor Rate Card Material Discounts Final Rev1.xlsx XLSX spreadsheet
SMIT RFP Questions and Answers Set 3 12032018.pdf PDF
SMIT Attch J-21 SMIT Navy Data Attributes_Final Rev1.xlsx XLSX spreadsheet
SMIT Attch J-17 Travel Rate Card_Final Rev 1.xlsm XLSM spreadsheet
SMIT Attch J-7 Service Level Requirements (SLR) Matrix_Final Rev1.xlsx XLSX spreadsheet
SMIT Attch J-24 USMC Operations Support Services_Final_Rev1.xlsx XLSX spreadsheet
SMIT Attch L-1 USMC Cost Summary Format Rev1.xlsx XLSX spreadsheet
SMIT Attch J-19 Transport Service Details Supplement_Final Rev1.docx DOCX document
N00039-18-R-0005-0002 SMIT RFP Amendment 11302018.docx DOCX document
SMIT Attch J-14 Network Infrastructure Services Rate Card_Final Rev1.xlsx XLSX spreadsheet
SMIT RFP Questions and Answers Set 2 11292018.pdf PDF
SMIT RFP Questions and Answers Set 1 11172018.pdf PDF
NGEN-R_CommentResolutionMatrix_Industry.xlsx XLSX spreadsheet
N00039-18-R-0005-0001 SMIT RFP Amendment 10262018.docx DOCX document
SMIT Attch J-3 SMIT Award Fee Plan_Final.docx DOCX document
SMIT Attch J-19 Transport Service Details Supplement_Final.docx DOCX document
SMIT_USMC_CDRL_B001_THRU_B040.docx DOCX document
SMIT Attch J-14 Network Infrastructure Services Rate Card_Final.xlsx XLSX spreadsheet
SMIT Attch L-1 USMC Cost Summary Format.xlsx XLSX spreadsheet
SMIT Attch J-30 Identification and Assertion of URD_As-Proposed.docx DOCX document
SMIT USN CDRL's A001-A074.zip ZIP file
SMIT Attch J-13 Labor Rate Card Material Discounts Final.xlsx XLSX spreadsheet
Show 40 more

Latest 50 of 77 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

N00039‐18‐R‐0005 ‐ Service Management, Integration and Transport (SMIT) Question and Answer Set #5 ‐ 09 January 2019

Item No. Document Type/Title Page Number Line Number Section/Block

Number Issue/Comment/Question Government Response

390 J‐5 GFP This is a follow‐on question to the response to Q&A 277. Question:

Is the incoming SMIT contractor required to purchase and maintain hardware and software maintenance agreements above what is required in 3.3.7.4.2 Warranty Management for items listed in J‐5, J‐ 28, and J‐29?

The SMIT contractor is required to maintain hardware and software maintenance agreements on all GFP.

406 J‐1 PWS Clarify how cost for maintenance agreements for Government furnished hardware and software should be priced. Request Government please clarify if the bidder is to include the cost for all OEM maintenance agreements for GFE hardware listed in attachment J‐05 and Government furnished software listed in attachment J‐28.

Costs for hardware and software maintenance agreements supporting Navy Base Services, as defined in RFP Section C‐1, shall be priced in CLIN x010. Costs for hardware and software suppporting all other services shall be priced as part of the CLIN service (e.g. CLIN 0015 VTC Services). The RFP will be revised in an amendment to add a subCLIN within CLIN x010.

416 SMIT RFP Section L Cost Price Evalution Cost Price Evalution

Please confirm the Small Business participation goal of 35% will be evaluated against vendor's proposed price in Attachment L‐3, "E.

Total Evaluated Cost/ Price".

The RFP will be revised in a future amendment to clarify how the offerors should calculate the percentage of total contract value. Specifically the following will be added, "(i) The Offeror shall attest that it will meet the minimum mandatory Small Business Participation goal of 35% of the sum of the total evaluated cost/price as defined in Section M‐3(f)(iv) and CLIN 0001 Transitition Services, as well as the various percentages for each socio‐economic category."

417 Other SPAWAR SE Transformation

Deck

SPAWAR SE

Transformation

Deck

Please confirm the NGEN‐R NIPR NOSS environment will be unclassified.

For the purposes of the proposal, the NMCI NIPR NOSS environment will be unclassified.

418 Other SPAWAR SE Transformation

Deck

SPAWAR SE

Transformation

Deck

Please confirm the NGEN‐R MBSE repository will be unclassified. The intent of the Government is to have the MBSE repository at a classification level that does not require it to reside on SIPRNet.

419 L‐3, and L‐ 4(g)(2)(i)

L‐3 states “Pricing shall only be included in Volume 5, no pricing shall be included in any other volume.” L‐4(g) Volume 6 states “Section 1‐Completed Contract and Representations and Certifications. The Offeror’s proposal shall provide a completed proposal to include the physically signed SF33, Sections B‐K, and any SF30 amendments.” Request the Government please advise whether Volume 6 is to contain pricing in Section B of the Schedule.

Yes, Volume 6 will include Section B CLIN pricing. RFP Section L‐3 will be revised to add the following "Pricing shall only be included in Volumes 5 and 6, no pricing shall be included in any other volume."

420 Can the offeror submit the cover page of each teaming agreement or letter of commitment to meet the requirement of evidence in Section L?

The RFP will be revised in an amendment to clarify the submittal requirements with regards to teaming agreements.

421 L‐2(a)(iv) This is a follow‐up to #377. As part of Gate Criteria 2, we will be submitting signed Teaming Agreements to satisfy the evidence requirement. The nature of these attachments are .pdf and not searchable due to the bi‐lateral signature. Gate Criteria 2 requires the format for the Small Business Plan (SBP) to be .docx. Is it acceptable to submit non‐searchable .pdf Teaming Agreements as attachments to the SBP document?

The RFP will be revised in an amendment to allow the submittal of PDF files.