J-2 YRBM Data Requirements List dated 17May21.pdf
PDF 746 KB Posted
- Solicitation number
- N0002421R2253
About this file
This request for proposal from the Naval Sea Systems Command solicits proposals for the design and construction of up to eight Yard Repair, Berthing and Messing berthing barges to support ship repair facilities. One craft will initially be awarded with options for seven additional craft. This procurement is set aside for small businesses. Interested offerors should submit proposals in response to solicitation number N0002421R2253. Proposals are due on the date specified in the RFP. The Navy intends to award a fixed-price incentive contract for the initial craft with cost-plus-fixed-fee options for additional craft. The work includes detail design, construction, testing and delivery of the barges to various shipyards.
View the file
Other files
Show 40 more
Latest 50 of 54 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Data Requirements List, Attachment J-2 Solicitation: N00024-21-NR-53156
Yard, Repair, Berthing & Messing (YRBM)
Data Requirements List Attachment J-2
24 March 2021
Prepared by Naval Sea Systems Command
1333 Isaac Hull Ave. SE Washington Navy Yard, DC 20376-2101
DISTRIBUTION STATEMENT A: Approved for public release; distribution is unlimited.
N00024-21-NR-53156
PAGE | i
FOREWORD
The Data Requirements List (DRL) identifies Contractor Data Item requirements in support of the design and construction of the Yard, Repair, Berthing & Messing (YRBM). This foreword provides direction to clarify administrative and procedural questions. Emergent issues that are not addressed herein or otherwise provided for in source documents should be referred to Program Executive Office Ships PMS325.
I. CONTENT AND FORMAT OF SUBMITTALS
All submittals shall be prepared in the Contractor's format unless otherwise specified in the specific data item. Data item submittals shall be clear, legible, and prepared in the English language. Engineering drawings and associated lists shall be as identified in Engineering Drawing and Related Documentation Practices, American Society of Mechanical Engineers (ASME) Y14.100; Types and Applications of Engineering Drawings, ASME Y14.24 Associated Lists, ASME Y14.34 and Revision of Engineering Drawings and Associated Documents, Y14.35M. Calculations and design data shall be provided in metric standard units or in the inch-pound system; the convention for units of measure shall be consistent throughout the documentation.
Data Items shall be assigned a sequential one-character alphabet designation in the Revision Block to signify a change from the previous submittal. Revision letter designations shall be in alphabetical order. The first submittal of any data item shall be identified as Revision "-".
Revisions of submittals shall include a change log or be prepared in a "red line" format to allow for identification of changes from the previous submittal.
Electronic media and digital files shall be compatible with computers using Windows 7™ operating system, unless otherwise specified. The following electronic format products shall be used: Microsoft Office 2010TM, Microsoft Project 2010™, Adobe Acrobat 10.1TM, WinZip 11.2™, or IGES 5.3™, unless otherwise specified. Schedules shall be Microsoft Project compatible. Alternative software or versions of software may be used if mutually agreed between the Contractor and the Government. Electronic files shall not be password protected. All textual PDF files shall be searchable.
Documents shall not be submitted in PDF format unless specified in the specific data item.
Drawings shall be submitted in an AutoCAD 2013 TM compatible format and PDF format, unless otherwise specified, and shall not be in "read only" format.
The first three characters of each digital filename shall be the Contractor's name or acronym. The filename shall include the applicable Data Item number and a Contractor determined designation, followed by a one-character revision letter, as applicable. The first submittal of each data item shall be assigned the revision"-“. Each file extension shall be the three-or four-character default extension automatically assigned by the applicable software when a document is saved. Electronic files shall not be password protected.
PAGE | ii
All data deliveries shall include a Department of Defense (DoD) Distribution Statement in accordance with DoD Instruction 5230.24. The Contractor shall determine which statement is applicable for the data being delivered.
Each data item submittal shall include the following export restriction:
"WARNING- This document contains technical data whose export is restricted by the Arms Export Control Act (Title 22, U.S.C. Sec 2751 et seq.) or the Export Administration Act of 1979, as amended, Title 50, U.S.C., App 2401, et seq. Violations of these export laws are subject to severe criminal penalties. Disseminate per provisions of OPNAVINST 551 0.161, Withholding of Unclassified Technical Data from Public Disclosure, 29 July 1985."
All submittals shall be provided with a cover sheet. Each data item shall be submitted with a separate letter of transmittal. The cover sheet shall provide the following information:
• Contractor's name, correspondence serial number, and actual date of transmittal.
• The Contract Number, Data Item Number, and Data Item Title.
• Applicable revision letter and revision date.
• Electronic media or digital file name and respective file date.
• A brief explanation of the submittal, the reason for a document's change, or a more detailed discussion in the content of the submittal.
• Distribution and quantity of copies being sent (not applicable to data provided at a shared location).
II. SUBMISSION SCHEDULE
The Contractor shall deliver all data requirements in accordance with the DRL.
DRL submission may address multiple barges, unless otherwise noted in the Data Item.
Periodic submission shall continue through Ship Delivery (SD), including awarded options, unless otherwise noted in the Data Item.
It is the responsibility of the Contract to notify the Government of changes which impact the content and accuracy of a previously submitted document so that the Government may make a determination as to whether the document warrants a revision. If the Government determines that there are significant enough changes which impact the content and accuracy of the document, the document shall be revised appropriately and resubmitted within 30 days or as otherwise agreed to between the Government and the Contractor.
III. QUALITY CONTROL
The Contractor shall maintain internal quality control to ensure submittals are complete and adequate and should not rely on Government review comments to ensure the technical accuracy of data. The Contractor shall review submittals to ensure accuracy of language, PAGE | iii flow, overall readability, as well as proofreading for grammar, spelling, and typographical errors.
IV. ACRONYMS
An alphabetical list of acronyms follows. The list includes those acronyms used most frequently in the Data Requirements List.
PAGE | iv
ACRONYMS
ABS
ACO
American Bureau of Shipping Administrative Contracting Officer
ASME American Society of Mechanical Engineers ACR Accepted Craft Report AT Acceptance Trials AWE Accepted Weight Estimate BI-WKLY Bi-Weekly BT Builder’s Trials CAGE Commercial and Government Entity CLIN Contract Line Item Number CMP Configuration Management Plan CD Craft Delivery DAC Days After Contract Award DARC Days After Receipt of Comments DARP Days After Reporting Period DI Data Item(s) DoD Department of Defense DPT Days Prior To DR Design Review DRL Data Requirements List ECP Engineering Change Proposal GFM Government Furnished Material HVAC Heating, Ventilation, and Air Conditioning ILS Integrated Logistic Support ILSMP Integrated Logistics Support Management Plan IMS Integrated Master Schedule IPR Interim Progress Review IUID Item Unique Identification LGC Logistics Guidance Conference MEL Master Equipment List MTHLY Monthly NECP Non-Engineering Change Proposal PAC Post Award Conference PCO Procuring Contracting Officer O&M Operation and Maintenance
PAGE | v
OEM Original Equipment Manufacturer OPNAVINST Office of the Chief of Naval Operations Instruction PO Purchase Order PR Purchase Request PRR Production Readiness Review QRTLY Quarterly QWR Quarterly Weight Report R/ASR Revisions as Required RFV Request for Variance SDS Safety Data Sheet SHML Ship Hazardous Materials List SOC Start of Construction SWBS Ship Work Breakdown Structure T&S Trim and Stability TM Technical Manual TMI Technical Manual Index VRS Vendor Recommended Spares
WKLY
YRBM
Weekly Yard, Repair, Berthing & Messing Barge
PAGE | vi
V. GLOSSARY
The items listed below are explanations of the headings and blocks on the Data Requirements List
(DRL).
1. PROGRAM NAME: The name of the program.
2. CONTRACT NO.: The Procurement Instrument Identification Number (i.e., the contract number, Purchase Request (PR) number, the Request for Proposal number, or other appropriate designator).
3. CONTRACTOR: The Contractor's name.
4. PREPARED AND APPROVED BY: The name and organization responsible for preparation and approval of the Data Items.
5. DATE: The date the Data Item was approved.
6. BLOCK I-DATA ITEM NO.: An identification number to support data item identified in the Statement of Work or Contract.
7. BLOCK 2-DATA ITEM TITLE: The title of the Data Item.
8. BLOCK 3-REFERENCE: The specific location within the Statement of Work or Contract that contains the tasking that generates a requirement for the data.
9. BLOCK 4-DATA DESCRIPTION: Details regarding the Data Item’s content characteristics and format requirements, if applicable.
10. BLOCK 5- APPROVAL/REVIEW REQUIREMENTS: The Government will review the Contractor’s submittal as indicated. The time period required for Government review will be as specified. The Government will comment on Data Items that require Government comment within the timeframe noted. The Government reserves the right to comment on all deliverables. The time period for Government review, identified in the data requirements list, commences at receipt of the data by the Government.
11. BLOCK 6-SUBMITTAL SCHEDULE: The scheduled date for initial data submission, incremental submittals, and resubmittals, as specified. In addition, details regarding Data Item submittal requirements are included. Submittal dates are often based on Contract events. Days identified are calendar days unless otherwise identified. Where scheduled date for data submission falls on a Saturday, Sunday or Federal Government holiday, the submission due date shall be the following Government working day. Revisions and subsequent periodic submissions shall incorporate the resolution of Government comments.
12. BLOCK 7-DISTRIBUTION: Unless otherwise stated, all deliveries shall be in digital format submitted to the PMS325 Assistant Program Manager.
PAGE | vii
ADDRESSEE COMPLETE ADDRESS
PMS325IDE (NSERC)* DLGR_NSWC_NSERC@navy.mil
PMS325 Liam O’Neill; Project Manager Liam.p.oneill2@navy.mil
Program Manager’s Onsite Representative TBD
Craft TBD
VI. Data Item Extensions
In the event that the Contractor decides to submit separate items to fulfill a DRL Data Item requirement and to ensure that the IDE accounts for each item individually, the Contractor shall request a Data Item Extension/Re-designation from the IDE Data Manager via e-mail. The Data Item Extension/Re-designation allows the IDE to establish separate sub-tier items within the database allowing the Contractor and Government to submit, review, and track each item independently. By requesting a DRL Data Item Extension/Re-designation, the Contractor avoids the need to submit all of the individual items with each submission of the data item, even if only one of the items has been modified since the previous submission.
Examples of when the Contractor shall request DRL Data Item Extension/Re-designation include the Technical Manual data item. In such an instance, the Contractor shall request DRL Data Item Extension/Re-designation to establish separate items for each individual technical manual, thus allowing individual tracking of review comments, independent resubmissions of single technical manuals, and closure of comments on independent technical manuals. Another example would be for data items that require supporting calculations to be submitted with drawings. In such an instance, the Contractor shall request DRL Data Item Extensions/Re-designation to establish separate sub-tier items for the drawing and for the calculations.
Data Item Extension/Re-designation may be used for both the Data Item and a Sub-Data Item.
Examples are as follows: DI-011.01 and DI-021-12.01, where DI-011 and DI-021-12 are the Government assigned DRL item numbers specified herein and the .01 on each represent the number assigned to the DRL Data Item Extension/Re-designation requested by the Contractor. The Contractor shall submit a request for a Data Item Extension/Re-designation no later than 7 days prior to a scheduled data delivery. The request shall identify the Data Item number and title from contract Data Requirements List, Attachment J-2, and a listing of Contractor defined titles for each data component to be added or re-designated. The Government will provide the new designations, in IDE, within 2 business days after the receipt of the Contractor’s request.
Data Item Extension/Re-designations shall not be considered contract modifications, but clarification of data submitted by the Contractor.
Data Item Extension/Re-designations shall comply with the same requirements as specified in the base Data Item. Subsequent deliveries of Data Item Extensions/Re-designations shall be processed in the same manner as the base data item submittals. The “revision” entered during data item upload shall match the revision listed on the data (i.e. drawing or report revision).
PAGE | viii
Revisions of each data item extension/re-designation shall address, at a minimum, the same barges as the previous revision. At option award for follow barges, the Contractor shall identify which data item extensions/re-designations is applicable to the newly awarded barges. If a follow barge requires separate drawings which are not applicable to prior barges, the Contractor shall request new DRL Data Item Extension/Re-designations for the new drawings.
PAGE | ix
Table of Contents and List of Effective Pages Data Item No. Contract
Reference Data Item
Titles And Subtitles Change Status
DI-001 SOW C-3.042a POST AWARD CONFERENCE AGENDA AND
MINUTES
BASIC
DI-002 SOW C-3.042a DESIGN REVIEW AGENDAS AND MINUTES BASIC DI-003 SOW C-3.042a LOGISTICS GUIDANCE CONFERENCE AND
INTEGRATED LOGISTICS SUPPORT MANAGEMENT
TEAM AGENDAS AND MINUTES
BASIC
DI-004 SOW C-3.042a INTERIM PROGRESS REVIEW AGENDAS AND
MINUTES
BASIC
DI-005 SOW C-3.042b PRODUCTION READINESS REVIEW AGENDA, PRESENTATION, AND MINUTES
BASIC
DI-006 SOW C-3.042c INTEGRATED MASTER SCHEDULE BASIC DI-007 SOW C-3.042c DRAWING SCHEDULE AND DOCUMENTATION
SCHEDULE
BASIC
BASIC
DI-008 SOW C-3.042c MATERIAL ORDERING SCHEDULE BASIC DI-009 SOW C-3.042d PURCHASE ORDER INDEX BASIC DI-010 SOW C-3.042e MASTER EQUIPMENT LIST BASIC DI-011 SOW C-3.042f LAUNCHING AND DOCKING INFORMATION BASIC DI-012 SOW C-3.042g CRAFT DAMAGE REPORT BASIC DI-013 SOW C-3.045d FIRE AND FLOODING PROTECTION PLAN BASIC DI-014 SOW C-3.070c CLASSIFICATION SOCIETY OR REGULATORY BODY
COMMUNICATIONS
BASIC
DI-015 SOW C-3.070c CLASSIFICATION SOCIETY AND REGULATORY
BODY CERTIFICATES, STATEMENTS, AND LETTERS
BASIC
DI-016 SOW C-3.077 NAVSEA HAZARDOUS MATERIAL WAIVER REQUEST BASIC
DI-017 SOW C-3.077 SAFETY DATA SHEETS BASIC
DI-018 SOW C-3.080a INTEGRATED LOGISTICS SUPPORT MANAGEMENT
PLAN
BASIC
DI-019 SOW C-3.080b ITEM UNIQUE IDENTIFICATION (IUID)
INFORMATION
BASIC
DI-020 SOW C-3.083 VENDOR RECOMMENDED SPARES LISTING AND
STATISTICS
BASIC
BASIC
DI-021 SOW C-3.085a CONSTRUCTION DRAWINGS AND
DOCUMENTATION
BASIC
DI-021-01 SOW C-3.085a TRIM AND STABILITY BOOKLET BASIC DI-021-02 SOW C-3.085a ACOUSTIC TREATMENT AND INSULATION
SCHEDULE
BASIC
DI-021-03 SOW C-3.085a INTACT AND DAMAGE STABILITY REPORT BASIC DI-021-04 SOW C-3.085a CRAFT DRAWING INDEX BASIC DI-021-05 SOW C-3.085a OEM COMMERCIAL WARRANTY SHEETS AND
REGISTRATION FORMS
BASIC
BASIC
DI-021-06 SOW C-3.085a APPENDAGE DRAWING BASIC
BASIC
DI-021-07 SOW C-3.085a FIRE STRUCTURAL PROTECTION DRAWING BASIC DI-021-08 SOW C-3.085a HULL LINES DRAWING BASIC DI-021-09 SOW C-3.085a MIDSHIP SECTION DRAWING BASIC DI-021-10 SOW C-3.085a SHELL EXPANSION DRAWING BASIC DI-021-11 SOW C-3.085a TYPICAL SECTIONS DRAWING BASIC DI-021-12 SOW C-3.085a COMPARTMENT ARRANGEMENT AND OUTFITTING
DRAWING
BASIC
DI-021-13 SOW C-3.085a GENERAL ARRANGEMENT DRAWING BASIC
BASIC
PAGE | x
Data Item No. Contract
Reference Data Item
Titles And Subtitles Change Status
DI-021-14 SOW C-3.085a TOPSIDE ARRANGEMENT DRAWING BASIC
BASIC
DI-021-15 SOW C-3.085a DECK AND PLATFORM STRUCTURAL DRAWING BASIC DI-021-16 SOW C-3.085a SUPERSTRUCTURE STRUCTURAL DRAWING BASIC DI-021-17 SOW C-3.085a ELECTRICAL DISTRIBUTION SYSTEM ONE-LINE
DIAGRAM
DI-021-18 SOW C-3.085a ELECTRICAL POWER LOAD ANALYSIS BASIC DI-021-19 SOW C-3.085a ELECTRICAL POWER SYSTEM DIAGRAM BASIC DI-021-20 SOW C-3.085a ELECTRICAL SYSTEM FAULT CURRENT ANALYSIS BASIC DI-021-21 SOW C-3.085a LIGHTING SYSTEMS ONE-LINE DIAGRAM BASIC DI-021-22 SOW C-3.085a PROTECTIVE DEVICE COORDINATION STUDY BASIC DI-021-23 SOW C-3.085a SHORE SERVICE CONNECTIONS DRAWING BASIC DI-021-24 SOW C-3.085a COMPUTER NETWORK DIAGRAMMATIC DRAWING BASIC DI-021-25 SOW C-3.085a NAVIGATIONAL LIGHTS DRAWING BASIC DI-021-26 SOW C-3.085a GENERAL ANNOUNCING SYSTEM DRAWING BASIC DI-021-27 SOW C-3.085a INTERIOR COMMUNICATION SYSTEM BLOCK
WIRING DIAGRAMS
BASIC
DI-021-28 SOW C-3.085a TELEPHONE DIRECTORY BASIC DI-021-29 SOW C-3.085a VIDEO SURVEILLANCE SYSTEM DRAWING BASIC DI-021-30 SOW C-3.085a ALARM SYSTEM DRAWING BASIC DI-021-31 SOW C-3.085a LIST OF CLOSURES BASIC DI-021-32 SOW C-3.085a HVAC DIAGRAMS BASIC DI-021-33 SOW C-3.085a STORES HANDLING DRAWING BASIC
BASIC
DI-021-34 SOW C-3.085a FIRE CONTROL AND SAFETY PLANS BASIC DI-021-35 SOW C-3.085a EQUIPMENT REMOVAL DRAWING BASIC
BASIC
DI-021-36 SOW C-3.085a TOWING AND MOORING DRAWING BASIC DI-021-37 SOW C-3.085a FURNITURE AND EQUIPMENT OUTFITTING LIST BASIC DI-021-38 SOW C-3.085a LIST OF LABELS AND MARKINGS BASIC DI-021-39 SOW C-3.085a KEY TAG INDEX BASIC DI-021-40 SOW C-3.085a CATHODIC PROTECTION DRAWING BASIC DI-021-41 SOW C-3.085a PAINT SCHEDULE BASIC DI-021-42 SOW C-3.085a DECK COVERING SCHEDULE BASIC DI-021-43 SOW C-3.085a DOCKING PLAN BASIC DI-021-44 SOW C-3.085a MANEUVERING REPORT BASIC DI-021-45 SOW C-3.085a LADDERS AND HANDRAILS SCHEDULE BASIC
DI-022 SOW C-3.085c PRODUCTION LEVEL DATA PACKAGE BASIC
BASIC
DI-023 SOW C-3.086a COMMERCIAL TECHNICAL MANUALS AND
SUPPLEMENTAL DATA
BASIC
BASIC
DI-024 SOW C-3.086a TECHNICAL MANUAL INDEX BASIC DI-025 SOW C-3.086b CRAFT INFORMATION BOOK BASIC
DI-026 SOW C-3.088 CREW FAMILIARIZATION INFORMATION BASIC
DI-027 SOW C-3.092 TEST PROCEDURES BASIC
DI-028 SOW C-3.092 TEST REPORTS BASIC
DI-029 SOW C-3.094a BUILDER’S TRIAL/ACCEPTANCE TRIAL AGENDAS BASIC DI-030 SOW C-3.094a BUILDER’S TRIAL/ACCEPTANCE TRIAL REPORTS BASIC
DI-031 SOW C-3.095 ILLUMINATION SURVEY REPORT BASIC
DI-032 SOW C-3.095 AIRBORNE NOISE SURVEY REPORT BASIC
DI-033 SOW C-3.096 WEIGHTS BASIC
PAGE | xi
Data Item No. Contract
Reference Data Item
Titles And Subtitles Change Status
DI-033-01 SOW C-3.096 ACCEPTED WEIGHT ESTIMATE BASIC
BASIC
DI-033-02 SOW C-3.096 QUARTERLY WEIGHT REPORT BASIC
DI-033-03 SOW C-3.096 ACCEPTED CRAFT REPORT BASIC
DI-033-04 SOW C-3.096 FINAL WEIGHT REPORT BASIC
DI-034 INTENTIONALLY NOT USED
DI-035 INTENTIONALLY NOT USED
DI-036 INTENTIONALLY NOT USED
DI-037 CLAUSE C-222-H001 ACCESS CONTROL PLAN BASIC
DI-038 CLAUSE C-243-H003 CONFIGURATION MANAGEMENT PLAN BASIC
DI-039 INTENTIONALLY NOT USED
DI-040 REVISED ADDITIONAL PROGRAMMATIC DATA
DI-041 CLAUSE C-243-H003 REQUEST FOR VARIANCE BASIC
DI-042 CLAUSE C-243-H003 EQUIVALENT EQUIPMENT SUBSTITUTION REQUEST BASIC
DI-043 CLAUSE C-211-H005 PLANT PROTECTION PLAN BASIC
DI-044 CLAUSE C-211-H007 ADVERSE ENVIRONMENTAL CONDITION PLAN BASIC
DI-045
DI-046
SOW C-3.077
SOW C-3.085a
LITHIUM BATTERY REPORT
AUXILIARY SYSTEM DESIGN REPORT AND
DIAGRAMMATICS
YRBM BERTHING BARGE
DATA REQUIREMENTS
SOLICITATION NO.: N00024-21-NR-53156
REVIEWED AND DATE: 26 OCTOBER 2020
APPROVED BY DIEGO E. KING, PMS325 DATA MANAGER PAGE | 12
BLOCK 1-DATA ITEM NO.: DI-001
BLOCK 2-DATA ITEM TITLE: POST AWARD CONFERENCE AGENDA AND
MINUTES
BLOCK 3-REFERENCE: SOW C-3.042a
BLOCK 4-DATA DESCRIPTION:
1. The Post Award Conference (PAC) Agenda shall identify the meeting name, date, time and location of the Post Award Conference. Materials to be presented during the Post Award Conference shall be provided with the agenda.
2. The agenda shall include as a minimum a discussion of the following:
a. Personnel Introductions
b. Organization Overview
1) Contractor Organization Discussion
2) Roles and Responsibilities and Points of Contact
3) Communication – Authorized Contractor Representatives
c. Facilities Overview
1) Site Layout
2) Security and Access Control
d. Planned Detail Design and Construction Approach
e. Integrated Logistics Support Approach
f. Regulatory Bodies Involvement
g. Near Term Schedule
1) Key Events
2) Conferences and Reviews
3) Deliverables
h. Data Requirements List Review
i. Government topics:
1) Personnel Introductions
2) Organization Overview
i. Major Organizations involved in the contract
ii. Roles and Responsibilities and Points of Contact
3) Program Overview i.Program Specifics, Contract and Technical Highlights
ii. Government Furnished Property
iii. Government expectations including the demonstration of production readiness iv.Proprietary information/data
4) Communications
i. Authorized Government Representatives
ii. Email and letter correspondence
iii. Regulatory Body correspondence iv.Submission of data
j. Action Item Review
k. Questions
3. The PAC Minutes shall identify date, time, and location of the Post Award Conference and a chronological listing of each topic discussed. The minutes shall include applicable discussions, concerns, action items assigned and completed, and a list of the documentation discussed. A list of attendees shall be included.
Copies of presentations or documents not previously submitted shall also be included and identified in the minutes by document name, document revision, document date, and the digital file name and date.
APPROVED BY DIEGO E. KING, PMS325 DATA MANAGER PAGE | 13
BLOCK 1-DATA ITEM NO.: DI-001 (Continued)
BLOCK 2-DATA ITEM TITLE: POST AWARD CONFERENCE AGENDA AND
BLOCK 5-APPROVAL/REVIEW REQ.:
Allow 4 days for Government review and comment
BLOCK 6-SUBMITTAL SCHEDULE:
Agenda NLT 10 DPT Post Award Conference; R/ASR 3 DARC. Minutes and final presentation materials to be submitted NLT 7 days after the Post Award Conference; R/ASR 7 DARC.
BLOCK 7-DISTRIBUTION: Addressee QTY
PMS325IDE 1
APPROVED BY DIEGO E. KING, PMS325 DATA MANAGER PAGE | 14
BLOCK 1-DATA ITEM NO.: DI-002
BLOCK 2-DATA ITEM TITLE: DESIGN REVIEW AGENDAS AND MINUTES
1. Design Review Agendas shall identify the meeting name, date, time and location of each Design Review.
Draft of materials to be presented during each Design Review meeting shall be provided with the agenda.
2. Design Review Agendas shall provide information regarding potential issues and decisions. Information regarding craft design and construction status and results shall also be discussed. Items that will be updated prior to the next Design Review shall also be discussed.
3. The Design Review Agendas shall include discussion on the following topics, as applicable.
a. Detailed status of the evolving detail design
b. Risk review including mitigation plans for all moderate and high risks
c. Primary design drivers, constraints and other issues that are influencing the craft design
d. Address assumptions and/or interpretations related to omissions, inconsistencies, errors, and conflicts, if any, in the requirements
e. Status of Regulatory Body issues related to design approval and certification, including ABS status.
f. Technical analyses and tradeoffs with supporting calculations and resulting derived design details
g. Review of the 3D Product Model
h. Status of data required by the DRL
i. Status of questions submitted to the Government
j. ECP, NECP, RFV Status
k. Status of items that effect Production Readiness Review (PRR) exit criteria
l. Review of Action Items
4. Minutes shall identify date, time, and location of the applicable review and a chronological listing of each topic discussed. The minutes shall include applicable discussions, concerns, action items assigned and completed, and a list of the documentation discussed. A list of attendees shall be included. Copies of presentations or documents not previously submitted shall also be included and identified in the minutes by document name, document revision, document date, and the digital file name and date.
Agendas NLT 10 DPT each Design Review; R/ASR 3 DARC. Minutes and final presentation material to be submitted NLT 7 days after each Design Review; R/ASR 7 DARC.
APPROVED BY DIEGO E. KING, PMS325 DATA MANAGER PAGE | 15
BLOCK 1-DATA ITEM NO.: DI-003
BLOCK 2-DATA ITEM TITLE: LOGISTICS GUIDANCE CONFERENCE AGENDA
AND MINUTES
1. Agendas shall identify the meeting name, date, time and location of the Logistics Guidance Conference (LGC). Materials to be presented shall be provided with the agenda.
2. In addition, the LGC Meeting agenda shall include the following as a minimum:
a. ILS Program Status
1) Proposed time schedule for discussion topics
2) Overall plan for executing the ILS program
3) ILS DRL Items development and submission
4) Technical Manual (TM) procurement, submission, and load-out
5) Vendor Recommended Spares (VRS) procurement, receipt, and stowage process
6) Craft Familiarization
7) Item Unique Identification (IUID)
8) Other items as required.
3. Minutes shall identify date, time, and location of the LGC and a chronological listing of each topic discussed.
The minutes shall include applicable discussions, concerns, action items assigned and completed, and a list of the documentation discussed. A list of attendees shall be included. Copies of presentations or documents not previously submitted shall also be included and identified in the minutes by document name, document revision, document date, and the digital file name and date.
Agendas NLT 10 DPT each ILS Meeting; R/ASR 3 DARC. Minutes and final presentation material to be submitted NLT 7 days after each ILS Meeting; R/ASR 3 DARC.
APPROVED BY DIEGO E. KING, PMS325 DATA MANAGER PAGE | 16
BLOCK 1-DATA ITEM NO.: DI-004
BLOCK 2-DATA ITEM TITLE: INTERIM PROGRESS REVIEW AGENDAS AND
1. Each Interim Progress Review (IPR) Agenda shall identify the meeting name, date, time and location of each IPR. Materials to be presented during each IPR shall be provided with the agenda.
2. In addition, the IPR agendas shall include the following as a minimum:
a. Review of the progress of the design including schedule performance
b. Review of the progress of the construction including schedule performance
c. Material ordering status, including identification of critical and long-lead time items and their effect on the overall schedule
d. Construction unit/module readiness
e. Drawing status
f. Regulatory Body review and approval status
g. Current and anticipated problems and plans for resolution
h. Quality metrics including process control and rework statistics
i. Test status
j. Risk Item status
k. ILS program status
i. Status of ILS DRL Items development and submission
ii. Technical Manual (TM) Status (to include schedule submissions, submissions to date, and late status)
iii. Vendor Recommended Spares (VRS) procurement and receipt statistics
iv. IUID status
v. Craft Familiarization updates
vi. Other items as required.
l. Schedule assessment and management for each craft to include, at a minimum:
i. Current schedule including description of tasks and events on the critical path and updated forecasts for completion of remaining work
ii. Comparison of current Master Schedule against Master Schedule provided at previous review
iii. Summary of recent and cumulative schedule performance, including any corrective actions taken to mitigate variances and any negative trends impacting schedule performance
iv. Description of approved internal and contractual changes and impacts of each change, both positive and negative, to the Master Schedule and schedule performance
m. Major sub-contractor status, to include manning, schedule, design integration and Master Schedule integration
n. Workload manpower projections, including other ship/craft types currently under or planned to be under construction, at the Contractor’s facility
o. Action Item status
p. Any other issues critical to the craft design and construction
q. Safety Risks
3. IPR Minutes shall identify date, time, and location of the IPR and a chronological listing of each topic discussed. The minutes shall include applicable discussions, concerns, action items assigned and completed, and a list of the documentation discussed. A list of attendees shall be included. Copies of presentations or
APPROVED BY DIEGO E. KING, PMS325 DATA MANAGER PAGE | 17
documents not previously submitted shall also be included and identified in the minutes by document name, document revision, document date, and the digital file name and date.
Agendas NLT 10 DPT each IPR; R/ASR 3 DARC. Minutes and final presentation materials to be submitted NLT 7 days after each IPR; R/ASR 7 DARC.
APPROVED BY DIEGO E. KING, PMS325 DATA MANAGER PAGE | 18
BLOCK 1-DATA ITEM NO.: DI-005
BLOCK 2-DATA ITEM TITLE: PRODUCTION READINESS REVIEW AGENDA,
PRESENTATION, AND MINUTES
BLOCK 3-REFERENCE: SOW C-3.042b
1. The Production Readiness Review Agenda shall identify the meeting name, date, time and location.
2. In addition, the agenda and presentation shall include the following as a minimum:
a. Review of the PRR exit criteria listed in the Statement of Work. The Contractor shall demonstrate that it meets the PRR exit criteria prior to Start of Construction.
b. Status of Regulatory Body plans and Regulatory Body comments on those plans
c. Status of Contract requirements
1) Schedules (All)
2) Other Regulatory Body correspondence not addressed in 1 above
3) Engineering Change Proposals (ECPs)
4) Non-Engineering Change Proposals (NECPs)
d. Review of Inspection System, Facility Certifications, and the Progressing System
3. Review of the Production Information (Work Packages). Review that adequate production work packages are available for production.
4. Materials to be presented shall be provided with the agenda.
5. Minutes shall identify date, time, and location of the meeting and a chronological listing of each topic discussed. The minutes shall include applicable discussions, concerns, action items assigned and completed, and a list of the documentation discussed. A list of attendees shall be included. Copies of presentations or documents not previously submitted shall also be included and identified in the minutes by document name, document revision, document date, and the digital file name and date.
Allow 7 days for Government review and comment.
Agendas 30 DPT the PRR; R/ASR 7 DARC. Presentation 3 DPT the PRR. Minutes 7 days after the PRR; R/ASR 7
DARC.
APPROVED BY DIEGO E. KING, PMS325 DATA MANAGER PAGE | 19
BLOCK 1-DATA ITEM NO.: DI-006
BLOCK 2-DATA ITEM TITLE: INTEGRATED MASTER SCHEDULE
BLOCK 3-REFERENCE: SOW C-3.042c
1. The Integrated Master Schedule (IMS) shall present the overall plan for the design, construction, testing, and delivery of the crafts. The information will be used to verify attainability of program objectives and evaluate progress. The IMS shall depict all activities required for the performance of this Contract. The IMS schedule shall present key events, milestones, and the critical path. The IMS shall be capable of depicting and producing summary and detailed schedules.
2. Detailed schedules shall include all efforts required to complete milestones. Each schedule shall portray in chronological sequence, the actions, events, and requirements with corresponding planned start and completion dates and the actual start and completion dates, which shall be retained on each issue of that schedule. Each schedule shall be kept current with schedule modifications and completed tasks. Human resources shall be expressed in man-hours. As appropriate, a column, line or space shall be provided for comments, explanation of problems encountered, and any remarks providing clarification shall also be identified. The IMS- produced detailed schedules as follows.
a. DETAIL DESIGN SCHEDULE - The Detail Design Schedule shall include the systematic planning of shipbuilder design efforts, and established need dates for supporting requirements; such as engineering analyses, mock-ups, design reviews, Production Readiness Review (PRR) and other pre-construction efforts.
b. ERECTION SEQUENCE SCHEDULE - The Erection Sequence Schedule shall include a systematic planning sequence of starting and completing Shipbuilder construction efforts and established need dates for supporting requirements. Subcontractor and critical construction events including unit construction, module erection, compartment closeout, and machinery installation shall be included.
c. SCHEDULE OF MAJOR MILESTONES AND KEY EVENTS - The Major Milestone and Key Events and Schedule shall identify key events leading up to the Contract milestones and shall identify critical paths for completion of each Contract milestones and shall identify critical paths for completion of each Contract milestone and key event. It shall also identify key events such as PRR, Start of Construction, Keel Laying, Launching, Builder’s Dock Trials, Docking, Undocking, Builder’s Sea Trials, Stability Test, Acceptance Trials (AT), Transit and craft Delivery.
d. TEST AND TRIALS SCHEDULE - The Test And Trials Schedule shall identify the scheduled and actual sequence and completion of all major test and trial events leading to craft delivery. The basic parameters of the Test Schedule shall include, the following:
1) Planned events, such as tests and trials.
2) Commencement and completion dates.
3) Ordering of prerequisite test and event items.
4) The Test Schedule shall clearly display the correct relationship of each prerequisite verification event for each dependent or subsequent verification event on a timeline.
5) The Test Schedule shall include:
6) Test Event number
7) Test Event title.
8) Scheduled start date.
9) Scheduled completion date.
10) Actual start date
11) Actual completion date.
3. Each schedule shall be highlighted to show changes from the previous submittal.
APPROVED BY DIEGO E. KING, PMS325 DATA MANAGER PAGE | 20
BLOCK 1-DATA ITEM NO.: DI-006 (Continued)
BLOCK 2-DATA ITEM TITLE: INTEGRATED MASTER SCHEDULE
BLOCK 5-APPROVAL/REVIEW REQ
45 DAC. R/ASR 14 DPT each DR and/or IPR, 14 DARC.
APPROVED BY DIEGO E. KING, PMS325 DATA MANAGER PAGE | 21
BLOCK 1-DATA ITEM NO.: DI-007
BLOCK 2-DATA ITEM TITLE: DRAWING SCHEDULE AND DOCUMENTATION
SCHEDULE
The Drawing Schedule and Documentation Schedule shall include a tabulated list of all drawings, modeling and simulation reports, analyses, and associated lists. The List shall include the following information:
1. Drawing Title.
2. NAVSEA Drawing Number.
3. Planned Date of Initial Submission.
4. Actual Date of Initial Submission.
5. Scheduled Completion Date.
6. Actual Completion Date.
7. Revised Dates..
8. Date of Regulatory Body Submittal.
9. Regulatory Body approval, as required.
45 DAC. R/ASR 14 DPT each DR and/or IPR, 3 DARC.
APPROVED BY DIEGO E. KING, PMS325 DATA MANAGER PAGE | 22
BLOCK 1-DATA ITEM NO.: DI-008
BLOCK 2-DATA ITEM TITLE: MATERIAL ORDERING SCHEDULE
The Material Ordering Schedule shall list materials, equipment, components and systems ordered and shall include the following:
1. Item and quantity being ordered.
2. Vendor.
3. Scheduled and actual dates of purchase order placement.
4. Shipyard need dates to support production.
5. Vendor promised delivery dates.
6. Actual delivery dates.
7. The initial schedule and order placement dates shall be retained on each issue of the schedule.
45 DAC. R/ASR 14 DPT each DR and/or IPR, 5 DARC.
APPROVED BY DIEGO E. KING, PMS325 DATA MANAGER PAGE | 23
BLOCK 1-DATA ITEM NO.: DI-009
BLOCK 2-DATA ITEM TITLE: PURCHASE ORDER INDEX
BLOCK 3-REFERENCE: SOW C-3.042d
1. The Purchase Order (PO) Index shall contain the following information for both specification and non-specification material:
a. PO Name
b. Vendor’s Name, Address, Phone Number
c. PO Number
d. PO Date of Issue
e. Received Date
f. PO Dollar Value
2. The index shall be provided in spreadsheet format
Allow 14 days for Government review and comment.
PO Index due 60 DAC; MTHLY, 5 DARP thereafter until all PO activity is complete.
APPROVED BY DIEGO E. KING, PMS325 DATA MANAGER PAGE | 24
BLOCK 1-DATA ITEM NO.: DI-010
BLOCK 2-DATA ITEM TITLE: MASTER EQUIPMENT LIST
BLOCK 3-REFERENCE: SOW C-3.042e
BLOCK 4-DATA DESCRIPTION:
1. The Master Equipment List (MEL) shall provide the following characteristics for the items identified as
Master Equipment. The listing and identification of equipment shall be sorted by 3-digit SWBS. The MEL shall contain the following information:
a. Manufacturer
b. Model Number
c. Nomenclature
d. Description
e. Quantity
f. Location
g. Capacity/Rating
h. CAGE Code
i. Country of Manufacture
45 DAC. R/ASR 14 DARC or as the need for change is identified.
APPROVED BY DIEGO E. KING, PMS325 DATA MANAGER PAGE | 25
BLOCK 1-DATA ITEM NO.: DI-011
BLOCK 2-DATA ITEM TITLE: LAUNCHING AND DOCKING INFORMATION
BLOCK 3-REFERENCE: SOW C-3.042f
BLOCK 4-DATA DESCRIPTION:
1. The Launching and Docking Information shall include the following:
a. A description of construction of ground ways, sliding ways, foundation, and dry-dock, as applicable.
b. Inclination and camber of ways.
c. Specify the type and amount of lubricants, method of applications, and estimated coefficients of static and sliding friction.
d. Size and spacing of grease irons.
e. A description of the construction of the cradle, including fore and after poppets.
f. Number, size, and arrangement of wedges.
g. Description of outside shoring and blocking.
h. Description of internal shoring.
i. Arrangements for snubbing.
j. A statement of degree of completion of hull and machinery at launching.
k. Procedure and schedule for removing blocks and shores, removing grease irons, for wedging up, and letting go.
l. Customary launching calculations, indicating the following:
1) Estimated weight and center of gravity of craft.
2) Estimated drafts, list, trim, KM and GM when craft is waterborne.
3) Velocity and travel.
4) Drags, if used.
5) Estimated weight of cradle.
6) Unit pressure on groundways.
7) Expected distance between end of ways and water surface.
8) Way and pressure.
9) Fore poppet at pivoting.
10) Tipping and immersion
11) Other engineering analyses that demonstrate the ability of the hull, appendages, and installed equipment to safely survive, without structural damage, all loads, including hydrodynamic loads, resulting from the launch evolution.
2. When other means of launching are proposed, the launching documentation shall contain information and computation comparable to the level of detail required above.
3. Where an alternate drydocking or launching method is proposed to be used, submit documentation to support the alternate proposal and identify any potential impact/modification to the craft structure, and include certification from an independent naval architectural firm, acceptable to the Contracting Officer, which shall certify that the method being proposed, including equipment and procedures, complies with sound naval architectural principles.
4. Provide Dockmaster qualifications.
5. Provide Docking and undocking procedures.
APPROVED BY DIEGO E. KING, PMS325 DATA MANAGER PAGE | 26
Allow 14 days for Government review, comment and approval for content.
60 DPT craft launch; R/ASR 14 DARC.
BLOCK 1-DATA ITEM NO.: DI-011 (Continued)
BLOCK 2-DATA ITEM TITLE: LAUNCHING AND DOCKING INFORMATION
APPROVED BY DIEGO E. KING, PMS325 DATA MANAGER PAGE | 27
BLOCK 1-DATA ITEM NO.: DI-012
BLOCK 2-DATA ITEM TITLE: CRAFT DAMAGE REPORT
BLOCK 3-REFERENCE: SOW C-3.042g
A Craft Damage Report shall document the occurrence, assessment of the cause, damage sustained, personnel injuries, proposed corrective action, and effects on the craft’s delivery schedule. Preliminary assessment of possible craft damage below the waterline shall be supported by underwater inspection and documented in the Craft Damage Report.
Allow 3 days for Government review and comment.
Notification NLT 24 hours after each incident; submit detailed report NLT 7 days after each incident; R/ASR 7 DARC.
APPROVED BY DIEGO E. KING, PMS325 DATA MANAGER PAGE | 28
BLOCK 1-DATA ITEM NO.: DI-013
BLOCK 2-DATA ITEM TITLE: FIRE AND FLOODING PROTECTION PLAN
BLOCK 3-REFERENCE: SOW C-3.045d
BLOCK 4-DATA DESCRIPTION:
1. The Fire and Flooding Protection Plan shall include, but not be limited to, a damage control organization chart; an outline of protection and detection systems and associated detectors, alarms, and telephones; fire, flooding, evacuation, and watch bills; pertinent instructions outlining the required precautions and actions regarding the following:
a. Flooding, both gross and local, detection, including flooding repair and dewatering procedures during construction.
b. Heavy snow and ice loading, excess firefighting water and flood water, which could cause static instability of the hull when afloat.
c. Welding, cutting, smoking, and electric arcing, and handling of combustible material, such as fuel oil, paint, wood staging and trash that could result in fire ignition.
d. Reduced accessibility on an incomplete craft.
2. The plan shall also contain requirements for inspection by roving patrols, and for controlling fires or flooding in security areas.
3. The plan shall include copies of the fire and flooding protection organization charts and instructions and identify how the fire and flooding protection organization chart and instructions will be kept up to date.
4. The plan shall identify locations of audio/visual alarms and charts in work areas that alert work force of emergency conditions requiring personnel to abandon craft.
5. The plan shall identify the schedule for training drill intervals.
Allow 21 days for Government review, comment and approval for content.
BLOCK 6-SUBMITTAL SCHEDULE:
60 DPT SOC; R/ASR 10 DARC or need for change is identified in the Contractor’s facilities, organization, instructions, procedures, or construction applications that impact the fire/flooding protection requirements.
APPROVED BY DIEGO E. KING, PMS325 DATA MANAGER PAGE | 29
BLOCK 1-DATA ITEM NO.: DI-014
BLOCK 2-DATA ITEM TITLE: CLASSIFICATION SOCIETY OR REGULATORY
BODY COMMUNICATIONS
BLOCK 3-REFERENCE: SOW C-3.070c
Provide copies of all incoming and outgoing communications on technical matters, including attachments/enclosures, between the Classification Society or Regulatory Bodies and the Contractor or his Subcontractors. Communications shall include letters, emails, and conversation notes.
Communications shall be provided 14 DPT each DR and/or IPR; 5 DARP; 14 DARC.
APPROVED BY DIEGO E. KING, PMS325 DATA MANAGER PAGE | 30
BLOCK 1-DATA ITEM NO.: DI-015
BLOCK 2-DATA ITEM TITLE: CLASSIFICATION SOCIETY AND REGULATORY
BODY CERTIFICATES, STATEMENTS, AND
LETTERS
BLOCK 3-REFERENCE: SOW C-3.070c
1. Classification Society and Regulatory Body Certificates, Statements of Compliance, and letters of compliance shall contain the Contract number, a statement that identifies the purpose, applicability of this certification, and verification that the Contractor has complied with the Contract requirements.
2. Where Classification Society and Regulatory Body Certificates of compliance are presented as evidence of quality, such certificates shall indicate that the material or equipment was previously tested and met all performance requirements and shall contain verification data, refer to witnessing inspectors or present other verifiable quality data.
3. Classification Society and Regulatory Body Certificates, Statements, and Letters shall include the following:
a. Interim Class Certificate
b. Certificate of Classification
c. International Load Line Certificate
d. International Tonnage Certificate
e. Panama Canal Tonnage Certificate
f. Stability Approval Letter
g. Survey for Load Lines
h. Load Line Assignment Letter
i. Intact and Damage Stability Report
j. Inclining Experiment Report
k. Statement of Compliance for Institute of Electrical and Electronic Engineers (IEEE) Standard 45 Series
l. Statement of Compliance for USCG Navigation Rules and Regulations Handbook and 72 COLREGS for navigational lights
m. Statement of Compliance for Environmental Protection Agency regulations
n. ABS Statement of Compliance for CDC/USPHS VSP 2011 Construction Guidelines for Sanitary
Construction
o. ABS Statement of Compliance for NAVSHIP Drawing No. 804-4444650-D, Surface Ship Sewage
Discharge Connections for material and design requirements for quick disconnect male coupling and dust cap
p. ABS Statement of Compliance stating that the YRBM craft meets a two-compartment standard of flooding as defined by 46CFR171.017 (b).
Allow 14 days for Government review.
APPROVED BY DIEGO E. KING, PMS325 DATA MANAGER PAGE | 31
BLOCK 1-DATA ITEM NO.: DI-015 (continued)
BLOCK 2-DATA ITEM TITLE: CLASSIFICATION SOCIETY AND REGULATORY
BODY CERTIFICATES, STATEMENTS, AND
LETTERS
Copies of certificates shall be submitted 7 days after receipt; original certificates shall be provided at CD. Certification verification data shall be submitted 10 days after request from the Government for copy of the verification of equipment/ test certification.
Craft 1*
* Originals shall be provided with the craft
APPROVED BY DIEGO E. KING, PMS325 DATA MANAGER PAGE | 32
BLOCK 1-DATA ITEM NO.: DI-016
BLOCK 2-DATA ITEM TITLE: NAVSEA HAZARDOUS MATERIAL WAIVER
REQUEST
BLOCK 3-REFERENCE: SOW C-3.077
1. A NAVSEA Hazardous Material Waiver Request shall be provided for each prohibited substance the Contractor finds necessary to incorporate in the design, construction, operation or maintenance of the craft. The request shall contain the following information:
a. Material to be used (identified by the name and Chemical Abstract Service (CAS) Number)
b. A copy of the Safety Data Sheet (SDS) and vendor technical (specification) data sheet showing 100% of the material/product constituents/ingredients. Note: When a supplier will not release to the Contractor an SDS that identifies 100% of the ingredients, the Contractor shall request the supplier enter into a non-disclosure agreement with the Government to release information directly to the Government.
c. Description of each specific craft location where the material will be used, including the quantity of material at each location.
d. The material’s intended use and justification for use in the requested application.
e. Measures taken to minimize or eliminate the prohibited substance. Include measures taken to identify substitute materials.
f. Personnel or environmental exposure potential during handling, installation, maintenance, and repair.
1) Identify the frequency that the system will require maintenance or replacement that will result in exposure to the material.
2) Include a description of personnel and/or environmental hazards associated with potential exposure.
g. Control and management measures that will be taken to minimize occupational and environmental exposure to the material prior to delivery of the vessels.
h. Recommend control and management measures to be taken to minimize occupational and environmental exposure to the material after delivery of the vessels while they are in service.
i. Description of ultimate disposal requirements and recommendations for both the material and any associated wastes.
j. Identification of regulations governing the material and associated waste’s distribution in commerce, transportation (including air, sea, and land), use and ultimate disposal.
k. Identification of the hazardous decomposition of off-gas products expected or anticipated during normal use in the material’s intended usage environment and from exposure to heat and fire, as identified by the SDS.
l. Identification of the specific training required by personnel handling, using, installing, packaging, transporting and disposing of the material.
BLOCK 5-APPROVAL/REVIEW REQ.:
Allow 14 days for Government review, comment and approval for content.
BLOCK 6-SUBMITTAL SCHEDULE:
30 DPT release for manufacture of related purchase specification material, or when the need to use a Government Prohibited Substance is identified for use during construction, operation, or maintenance; whichever is earlier. R/ASR 14
DARC.
APPROVED BY DIEGO E. KING, PMS325 DATA MANAGER PAGE | 33
BLOCK 1-DATA ITEM NO.: DI-017
BLOCK 2-DATA ITEM TITLE: SAFETY DATA SHEETS
BLOCK 3-REFERENCE: SOW C-3.077
1. All Safety Data Sheets for hazardous materials utilized in construction and for operation and maintenance shall be provided.
2. The Safety Data Sheets shall be included in a booklet at Craft Acceptance Trials.
BLOCK 6-SUBMITTAL SCHEDULE:
Individual Safety Data Sheets 3 days after receipt from vendor; R/ASR 14 DARC. Deliver booklet to the craft 3 DPT Craft Acceptance Trials.
BLOCK 7-DISTRIBUTION: Addressee QTY
PMS325IDE 1
Craft 1*
* Booklet only
APPROVED BY DIEGO E. KING, PMS325 DATA MANAGER PAGE | 34
BLOCK 1-DATA ITEM NO.: DI-018
BLOCK 2-DATA ITEM TITLE: INTEGRATED LOGISTICS SUPPORT
MANAGEMENT PLAN
BLOCK 3-REFERENCE: SOW C-3.080a
BLOCK 4-DESCRIPTION:
The Integrated Logistics Support Management Plan (ILSMP) shall identify how the Contractor intends to implement the ILS program to satisfy all logistics requirements and the processes to accomplish consistency between logistics products. The ILSMP shall identify, at a minimum, the processes and procedures to provide the integrated support of the craft, including Vendor Recommended Spares (VRS) listing requirements, procurement, receipt, storage, and loadout of the approved VRS, equipment and parts validation, Technical Manual development, review, validation and submission requirements, Crew Familiarization planning and execution, interface process between Purchasing, Engineering, Production, Contracts, and ILS departments (i.e. communication between all disciplines) to ensure ILS is kept up-to-date on all proposed engineering changes, documentation, and craft production progress.
The ILSMP shall identify contractor and subcontractor key personnel and support staff responsible for satisfying the contractual requirements of this program. The ILSMP shall also include an ILS Milestone Schedule indicating milestones, events, timeframes, etc. that have been established and/or are necessary to achieve the program’s logistics objectives in accordance with craft design and production schedules.
BLOCK 5-APPROVAL/REVIEW REQUIREMENTS:
Allow 14 days for Government review and approval for content.
BLOCK 6-SUBMITTAL SCHEDULE:
30 DAC; R/ASR 14 DARC or when the need for change is identified.
APPROVED BY DIEGO E. KING, PMS325 DATA MANAGER PAGE | 35