Amendment 0009 USS LAKE ERIE (CG-70) FY21 Selected Restricted Availability (SRA)
Solicitation number
N00024-20-R-4401
Issued by

About this file

This document provides details for solicitation N00024-20-R-4401 regarding the USS LAKE ERIE (CG 70) FY21 Selected Restricted Availability. The solicitation is for the execution of maintenance, modernization, and repair work for the USS LAKE ERIE, requiring facilities and resources capable of coordinating multiple areas of ship maintenance and repair. Interested parties must monitor beta.SAM.gov for solicitation release and amendments. The Navy will not release Attachments J-1, J-2, J-3, J-4, and J-9 on beta.SAM.gov and they are available by written request. Companies must submit a signed letter to receive Government Furnished Information. The work will not be set aside for small businesses. The Navy anticipates a single award by August 2020 for an availability start in November 2020 at the contractor's facility on the West Coast.

View the file

Other files

File Type Posted
N0002420R4401_A0009_CONFORMED.pdf PDF
N0002420R4401_A0009.pdf PDF
N0002420R4401_A0008_CONFORMED.pdf PDF
N0002420R4401_A0008.pdf PDF
Bidder Question Nos. 81 - 101.pdf PDF
N0002420R4401_A0007_CONFORMED.pdf PDF
N0002420R4401_A0007.pdf PDF
N0002420R4401_A0006.pdf PDF
Bidder Question Nos. 72 - 80.pdf PDF
N0002420R4401_A0006_CONFORMED.pdf PDF
TPPC-CG70-SWRMC21-CN01 - ERRATA 5 Rev 1.pdf PDF
N0002420R4401_A0005.pdf PDF
N0002420R4401_A0005_CONFORMED.pdf PDF
TPPC-CG70-SWRMC21-CN01 - ERRATA 4 rev 1.pdf PDF
Bidder Question Nos. 47 - 71.pdf PDF
N0002420R4401_A0004_CONFORMED.pdf PDF
Bidder Question Nos. 39 - 46.pdf PDF
N0002420R4401_A0004.pdf PDF
Bidder Questions Nos. 31 - 38.pdf PDF
N0002420R4401_A0003.pdf PDF
Bidders Questions Nos. 18 - 30.xlsx XLSX spreadsheet
N0002420R4401_A0002_Conformed.pdf PDF
Bidders Questions Nos. 18 - 30.pdf PDF
N0002420R4401_A0002.pdf PDF
N0002420R4401_A0001.docx DOCX document
Bidder Questions Nos. 1-17.xlsx XLSX spreadsheet
N0002420R4401_A0001 Conformed.docx DOCX document
Attachment J-8 GFM LIST CG70_FY21_SRA.xlsx XLSX spreadsheet
Attachment S-3 PPI Form CG70_FY21_SRA.docx DOCX document
Attachment S-5 Eligibility Criteria Data Sheet CG70_FY21_SRA.docx DOCX document
Attachment S-7 Proposal Assessment 21_SRA_CG_70.xlsx XLSX spreadsheet
Attachment J-5 QASP CG70_FY21_SRA.pdf PDF
CDRLs.zip ZIP file
Attachment J-7 Schedule Model Review CG70_FY21_SRA.pdf PDF
N00024-20-R-4401.pdf PDF
Show all 35

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation #: N00024-20-R-4401 USS LAKE ERIE (CG 70) SRA NAVSEA POC: Dan Magrino, daniel.magrino@navy.mil, (202) 781-3544

Jackie Black, jacqueline.black@navy.mil, (202) 781-1088

Master # Question Area Para # Date Received Contractor Question Government Response

J-1, Numerous WIs; J-

2-Apr-20 Contractor requests references cited in J-1, however, omitted from J-2.

Please refer to Tab 2, 'Restricted References,' for a complete list of all references omitted due to dissemination restrictions. In order to access these documents, please contact the SWRMC technical library for access: POC: Sonia Moran Email: sonia.moran@navy.mil Phone number: (619) 556-3158 3755 Brinser Street BLDG 36 San Diego, CA 92136

For non-restricted drawings identified as missing, please contact Jacqueline Black at jacqueline.black@navy.mil:

Work Item # Document # 524-11-002 _2.3 541-6646262-E 630-90-001 _2.7 512-8799681 772-21-001 _2.4 77221-3-093-D

992-21-001 _2.2 S9086-SN-STM-010/CH-541R10

19 J-1, WI No. 438-90-

3.1.3, 4.1 7-Apr-20

Work item 438-90-001: ShipAlt CG-47 92593K Enterprise Remote Monitoring (ERM) Hardware Installation; accomplish. Para 4.1 states “This ShipAlt will be accomplished in conjunction with SA 73856K” which is work item 438-90-002. Work item 438-90-002 ShipAlt CG47-73856K, Integrated Ship Console; accomplish. Para 4.1 states “AIT is doing all of the electrical, fiber, and equipment mounting. Q.(A): Since the AIT is accomplishing all of the electrical, fiber and equipment mounting on work item 438-90-002 and it is being worked in conjunction with 438-90-001, will the AIT also be accomplishing all electrical, fiber and equipment mounting on work item 438-90-001? Q(B): Para 3.1.3 of work item 438-90-001 states to “accomplish the requirements of 009-123 for each fiber optic cable impacted by this ShipAlt” Will the requirement of 3.1.3 be accomplished by the AIT IAW para 4.1 on work item 438-90-001 and 438-90-002? Q.(C): Unless otherwise stated no fiber optic requirements including para 3.1.3 of 438-90-001 will be estimated and will be subject to a change order at the time of production.

(A): No; The contractor is required to complete the requirements of Work Item No. 438-90-001. (B): No; The contractor is required to complete the requirements of Work Item No. 438-90-001. (C): The contractor shall bid work as required per SID.

20 J-1, Numerous WIs; J-

N/A 7-Apr-20 Contractor identified 12 missing references.

Duplicate - Please refer to #2 for access to restricted references. For non-restricted drawings identified as missing, please contact Jacqueline Black at jacqueline.black@navy.mil:

Work Item # Document # 772-21-001 _2.4 77221-3-093-D 993-31-005 S9086-HK-STM-010/CH-241 Rev 4

21 J-1, WI No. 513-10-

3.1 8-Apr-20

Work Item 513-10-001, Emergency Air Damper/Louver and Remote Operating Assembly; replace. Paragraph 3.1 states, “Remove existing and install new each emergency air damper/louver including each associated remote operating assembly and stuffing box listed in 1.3 and located in 1.2, using 2.2 through 2.5 for guidance, and material provided in 5.1”. Contractor note that paragraph 5.1 through 5.3 does not list any GOVERNMENT FURNISHED MATERIAL (GFM). Is the Customer providing any GFM or is the bidder to provide new emergency air damper/louver including each associated remote operating assembly and stuffing box listed in 1.3 and will an Errata specification be issue?

The contractor must procure material referenced in paragraph 3.1.

No GFM will be provided. Errata No. 2 will be provided.

J-1, WI No. 992-21-

3.1 - 3.3 8-Apr-20

Work Item 992-21-001, Defuel Ship; accomplish: Contractor has reviewed the RFP, specification, and all identified references noting that, the intent of this items work scope appears to be for out of home port (San Diego) bidders. Historically in the port of San Diego naval vessels are typically defueled prior to arrival at the Contractors facility and are typically refueled after departing the Contractor facility. Contractor note Attachment J-4 Pricing Workbook identifies this Specification as part of the Basic package and not as an Option. Can the Customer provided clarification as to why the J-4 Pricing Workbook lists this specification as a Basic and not as an Option and is this work item to be priced only by OUT of homeport (San Diego) bidders and accomplished only if the contract is awarded outside of San Diego?

Work Item No. 992-21-001 is a basic requirement. The contractor is responsible for defueling the ship upon arrival at its facility irrespective of whether the contractor is located within the ship's homeport of San Diego or out of homeport.

23 RFP, Section C; J-3 N/A 8-Apr-20

Section C - Descriptions and Specifications, SCOPE OF WORK.Paragraph 2.1 states, "The required place of performance for the Availabilities shall be the contractor’s facility" additionally, attachments J-3 Execution Milestones and Key Event Date documents also identify the first milestone as, "Avail Start at KTR Facility" and appear to be generalized statements prepared for a coast wide bid for out of homeport (San Diego) bidders. The contractor has reviewed previously awarded contracts, both Coast wide and SDMAC, and notes that availabilities accomplished in the Port of San Diego start pier side at NAVSTA 32nd Street for the first 14 Calendar days. This allows the customer and ship's force time to prepare the ship to enter contractor’s facility. Activities listed are not all inclusive: Ship's Force movement to Berthing Barge and Ship's Force off-load of stores, material, and portable equipment. This also allows the contractor an opportunity to set-up temporary services; installation of staging, drain, disposal, and dewatering of specific water systems; installation of the AN/SPY-1D Antenna Protective Covers and installation of deck protection prior to arrival in the contractor’s facility. Can bidder's assume that if the contract is awarded to a bidder for accomplishment in the Port of San Diego CA, than the first 14 Calendar days will be accomplished pier side at NAVSTA 32nd Street prior to movement of the ship and berthing barge to the contractors facility?

No. The place of performance is the contractor's facility for the duration of the availability.

24 RFP, Section C N/A 10-Apr-20

RFP, Section C - Descriptions and Specifications, CLAUSES INCORPORATED BY FULL TEXT, C-211-H016 SPECIFICATIONS AND STANDARDS (NAVSEA) (OCT 2018). Contractor notes the Governments inclusion of the following: (a) Definitions. (i) A "zero-tier reference" is a specification, standard, or drawing that is cited in the contract (including its attachments). (ii) A "first-tier reference" is either: (1) a specification, standard, or drawing cited in a zero-tier reference, or (2) a specification cited in a first-tier drawing. (b) Requirements. All zero-tier and first-tier references, as defined above, are mandatory for use. All lower tier references shall be used for guidance only unless specifically identified below. None. It is the Contractors understanding that all required references listed in paragraph 2 of a zero-tier specification (work item) are "first tier" references.

However, when a zero-tier specification directs to use a first-tier reference as "guidance", bidders should not estimate the reference and only use it to aid in the development of an estimate of references that are to be accomplished. Can the Customer concur or advise on this interpretation.

All zero-tier and first-tier references are mandatory for use in accordance with C-211-H016. The contractor is responsible for ensuring compliance with mandatory references.

25 J-1, WI No. 343-12-

3.3 10-Apr-20

Work Item 343-12-001, Generator Exhaust Duct Ship Service Gas Turbine Generator (SSGTG) 2; repair”: Paragraph 3.3 states, “Accomplish repair of the equipment located in

1.3 and located in 1.2 using 2.2 through 2.6 and the report submitted in 3.1.1 for guidance, as designated by SUPERVISOR.” Contractor notes that 3.1.1 states, “Protect, blank, wrap, cover, or mask equipment and openings to preclude damage and prevent entry of foreign material into gas turbine exhaust duct, trunk, bleed air and discharge piping at the location listed in 1.2, prior to accomplishing this repair” and appears to be incorrect and it is believed that paragraph 3.2.1 that states, “Submit one legible copy, in hard copy or approved transferrable media, of a report listing results of the requirements of 3.1 to the SUPERVISOR” are applicable for 3.3. Can the Customer provide clarification the disparities identified between 3.3, 3.1.1 and 3.2.1 and will an Errata be issued revising this specification? Typo in 3.3 correct 3.1.1 to 3.2.1. Errata No. 2 provides clarification.

26 RFP, Section C C-217-H0005 15-Apr-20

Clause C-217-H0005 Growth and New Work: paragraph d found on page 61 of 130 states, “The Government will NOT negotiate modification to increase the contract price to address errors or omissions to the contract package which were reasonably apparent prior to proposal submission.” Please define what is the test (or criteria) for reasonably apparent errors or omissions, and cite examples.

The Government will not respond to requests for blanket assertions or a catch-all 'test' for reasonably apparent errors or omissions which will necessarily need to be addressed on a case-by-case basis during contract execution.

27 RFP, Section L N/A 15-Apr-20 Due to the ongoing COVID 19 situation, vendors and subcontractors are slow to respond. In order to afford all contractors ample time to prepare an accurate proposal that will be most beneficial to the Government, it is requested that the PPI due date be extended by two weeks to 1 May 2020 vice 17 APR 2020.

The Government hereby extends the PPI deadline from April 17, 2020, to April 24, 2020. Please refer to Amendment 002.

28 RFP, Section B N/A 15-Apr-20

Section B: Note A.1.a found on page 35 of 130 states, “37,021 direct labor hours (labor hours) and $784,582 ($TBD fully burdened) materials to complete expected, within scope growth work on the USS LAKE ERIE (CG-70) FY21 SRA work package under CLINS 0016-0033.” Contractor notes that these values are for new work and not for CLINS 0016- 0033. Contractor believes 65,190 labor hours (labor hours) and $1,653,833 ($TBD fully burdened) materials cover CLINS 0016-0033. Please review values, make corrections as necessary and redistribute. Section B, Note A is revised. Please refer to Amendment 002.

29 RFP, J-4 N/A 15-Apr-20

J-4 Pricing Workbook: (1) Missing subtotal line at the bottom of Work Items Tab. (2) Total of Work Items Tab does not link to cell B4 of Total Proposed Evaluated Price Tab for “Total Work Item Price”.(3) Daily Extension Rates does not link to any cell in Total Proposed Evaluated Price Tab. (4) “Value Adjusted Trade Off schedule acceleration adjustment (if applicable as derived in Section M)” in Total Proposed Evaluated Price Tab is not found in Section M. (5) “Inter-port Differential Reduction for “Days Completed Early” in Total Proposed Evaluated Price Tab is not found in Section M and the J-3 Milestones does not allow for days completed early. Please review, make corrections as necessary and redistribute J_4 Pricing Workbook ith revised file name.

Please refer to Amendment 001 and Attachment J-4, Rev1, posted to beta.SAM on April 13, 2020, with regard to VATEP and link revisions within the J-4. Please review Sections L &M and note 'VATEP' and 'IPD Reduction for Days Completed Early' are not part of this solicitation. Daily Extension Rates are to be priced for evaluation purposes only. Please refer to Amendment 002 for update regarding Daily Extension Rates.

30 RFP, J-4 N/A 15-Apr-20

Attachment J-4 Pricing Workbook, Upon review of the Pricing Workbook the follow functional issues have been identified: Contractor notes the “Labor&Material Rates” worksheet contractor has identified that cell D27 is not formulated $B$3, to reflect the Labor Rate entered by the bidder in cell B3. Contractor notes the “Total Proposed Evaluated Price” worksheet, the Total Work Item Price, cell B4 appears to have an invalid formula, as it should reflect the sum of the work items from the Work Item worksheet. Contractor notes the “Total Proposed Evaluated Price” worksheet, the Total Evaluated Price cell B10 only provides a Sum Total of cells B4 through B8 and does not include data from the Daily Extension Rate worksheet, which should be included as part of the Total Evaluated Price (TEP). Can the Customer in an Amendment provide a revised J-4 Pricing Workbook correcting the “Labor&Material Rates worksheet formula for cell D27, and the “Total Proposed Evaluated Price” worksheet formula for cells B4 and B10 to all bidders?

Please refer to RFP, Section M, para (B)(2). New Work is for evaluation purposes only and is not a component of the Total Evaluated Price. Please refer to Amendment 0002 for update regarding Daily Extension Rates.