This document contains details regarding a federal solicitation for the USS Lake Erie (CG-70) FY21 Selected Restricted Availability. The Naval Sea Systems Command is seeking offers for the execution of maintenance, modernization, and repair of the USS Lake Erie. Offerors must have substantial facilities including a Ticonderoga-class capable pier and human resources to complete ship maintenance, repair, and modernization. The availability is open to all responsible sources on a coast-wide basis and will not be set aside for small businesses. Interested parties must register in SAM and monitor beta.SAM.gov for release of the solicitation and amendments. The solicitation includes specification packages, work item plans and drawings, milestones, and pricing workbook. Offers are due in August 2020 and a single award is anticipated in November 2020 for performance at the contractor's West Coast facility.
View the file
Other files
Show all 35
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
J-7 Schedule Model Review
USS LAKE ERIE (CG 70)
Purpose: At A-30 the LMA shall lead a Schedule Model Review of the Integrated Production Schedule (IPS) with all parties to validate integration requirements. The Schedule Model Review is intended to be a detailed review of all work items to ensure adequate integration into the master schedule and to de-conflict any overlapping activities. The anticipated duration of this meeting is 5-7 days. Hours for Day 1 is 0800-1600 and for Day2 and following is 0800-1130.
1. Required Attendees:
a. LMA management team
b. Government Project Management Team (NSA)
c. Turnkey Subcontractors
d. AIT On Site Installation Coordinators (OSIC)
e. Intermediate Maintenance Facility (IMF) Ship’s Superintendent, if applicable
f. Ship’s Force (one representative from each department, Ship’s Maintenance Officer)
2. Agenda:
Day 1 WPER (Government Facilitated)
a. Early Start Candidates (LMA)
b. WAF/Tag Out coordination (LMA)
c. Pier Laydown Plan (LMA)
d. First 100 Hour Plan (NSA)
e. Communications Plan (NSA)
f. Process Control Procedures (PCP) (LMA)
g. Access Cuts (LMA)
h. Fire Prevention and Fire Drill (8010) requirements (NSA)
i. Memorandum of Agreement (MOA) – AIT’s only (NSA)
Day 2 - 7
j. LMA to Present the IPS for review. The IPS shall include (but not limited to) all work associated with the
Lead Maintenance Activity (LMA), subcontractors, Alteration Installation Teams (AIT), Ship’s Force, and
Intermediate Maintenance Activity (IMA).
3. Deliverables:
a. Updated IPS with all maintenance activities fully integrated. (LMA)
b. Early start candidates submitted and approved by the NSA. (LMA)
c. WAF/Tag Out coordination plan established. (LMA)
d. First 100 Hour Plan established. (NSA)
e. Set schedule for all required meetings. (NSA)
f. Pier Laydown Plan submitted for approval by Naval Station Everett. (LMA)
g. List of Process Control Procedures with projected due dates. (LMA)
h. List of access cuts (if required). (LMA)
i. Fire drill execution date set. (NSA)
j. Detailed review of critical path and top three controlling path items. (LMA)