SSSB RFP Q&A - 20 Nov 2019.pdf
PDF 411 KB Posted
- Attached to
- Surface Ship Support Barge (SSSB) Dismantlement and Disposal Federal contract opportunity
- Solicitation number
- N00024-18-R-4339
About this file
This document contains questions and answers related to a request for proposals for the Surface Ship Support Barge Dismantlement and Disposal project. The Navy seeks proposals to dismantle and dispose of the Surface Ship Support Barge, with work to include characterization of radioactive and hazardous materials. An industry day was held on November 6, 2018 for interested parties to learn more about the project scope, which includes dismantlement phases and transportation options. Questions submitted by October 29, 2018 were addressed during the presentation. Site visits are available from November 20 to December 13, 2019, with no visits allowed from November 25 to 29th or December 9th. Proposers must request site visits at least 30 days in advance.
View the file
Other files for this federal contract opportunity
Show all 50
Surface Ship Support Barge (SSSB) Dismantlement and Disposal has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Question
Number
Question
Source
Pg. or
Paragraph Question Answer
1 Attachment
S-6
Is there a list of available dates for site visits? Available dates are 20 Nov 2019 through 20 Dec 2019 with NO visits on
25-29 Nov or 9 Dec 2019.
2 S-2 and J-14 There are multiple J-14s posted on beta.sam.gov. Please check Section J in the RFP for the correct title of each attachment. Additionally, you can verify by date. The RFP and corresponding attachments were all posted on November 5th, 2019.
3 Sec. L L-237-
7001 (b), and 1.0
(pg. 69)
L-237-7001(b) states: "Offerors who plan to attend shall submit a visit request at least 30 days in advance prior to the visit", however, Sec. L, 1.0
Instructions states: "Offerors shall allow up to five business days for scheduling a visit with
SUPSHIPNN". Which requirement is correct?
SUPSHIPNN needs thirty (30) days to get the badge paperwork processed.The five (5) days is for scheduling the actual visit after all badge paperwork and dosimetry requests have been approved. To summarize - one time frame is for paperwork while the other is the actual visit scheduling effort.
4 S-3 What is the last day a request for site visit can be emailed to SUPSHIPNN?
13 December 2019 to meet the five business days.