Bidder's Questions and Answers Set 8
View the file
Other files
Show 40 more
Latest 50 of 74 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions: Section L 4.3.1 c. Events: states “The Management Plan and Integrated Master Schedule (IMS) must support Government established schedule requirements for the prime and subcontractors integrated baseline review (IBR), the plan to meet new construction and modernization milestones as follows:
For new construction, milestones to be met are:
i. Preliminary Design
ii. Contract Design
iii. Detail Design
iv. Zonal Design
v. Preliminary TDP
vi. Ship Check
vii. SIDs Release
viii. AEGIS Light-Off
ix. Crew Move Aboard
x. Builder’s Trials
xi. Final Contract Trials
xii. Post Shakedown Availability
For modernization, milestones to be met are:
i. Production completion Date
ii. AEGIS Light-Off
iii. Crew Move Aboard
iv. Dock Trials
v. HM&E Sea Trials
vi. Combat System Sea Trials
vii. End of Availability”
It is requested that at least one of the listed events for new construction and one of the listed events for modernization be defined relative to one or all of the other events (e.g., months after PDR or months after production completion date). In this way, all bidders will follow a similar schedule baseline for the purposes of bidding the completion CLINs.
Answer: Offerors shall use the following relative milestone timeline for proposal purposes:
For new construction, milestones to be met are in months where Aegis Light Off is day zero (0).
Ship Check and SIDs release milestones for new construction will be removed:
i. Preliminary Design (Ship Design Agent) ALO - 45 months
ii. Contract Design (SI&T Contract) ALO – 23 months
iii. Detail Design (Ship Design Agent) ALO – 39 months
SI&T – Question 58 RFP Section:
L
Page:
RFP Para., Clause, or Other Definitive Citation:
Section L 4.3.1.c Events
Document Name:
Final RFP
Document Date:
09/05/13
iv. Zonal Design (Ship Design Agent) ALO – 30 months
v. Preliminary TDP (SI&T Contract) ALO – 57 months
viii. AEGIS Light-Off ALO = 0
ix. Crew Move Aboard ALO + 13 months
x. Builder’s Trials A + 8 months
xi. Final Contract Trials ALO + 23 months
xii. Post Shakedown Availability ALO + 22 month
For a DDG modernization, milestones to be met are in days where Availability start is A = 0:
i. Production completion Date A+190
ii. AEGIS Light-Off A+176
iii. Crew Move Aboard A+170
iv. Dock Trials A+241
v. HM&E Sea Trials A+245
vi. Combat System Sea Trials A+ 325
vii. End of Availability A+365
This clarification will be incorporated into the solicitation in a forthcoming amendment.
Question: SOW Section 3.3.1 (ACB-16/TI-16 New Construction Test Execution), Section
3.3.2 (Future ACB/Future TI New Construction Test Execution), Section 3.7.1 (ACB-16/TI-16 Aegis Modernization Test Execution – One DDG 51 Class Ship) and Section 3.7.2 (Future ACB/Future AMOD Test Execution) each contain the following statements: “The Contractor shall document all equipment or ship discrepancies via Test Observation Reports (TOR), Computer Program Change Requests (CPCR) or Trial Cards to the ATO/ATM.”
TORs, CPCRs and Trial Cards are not listed as CDRLs in Exhibit A.
Is it the government’s intention to specify these items as CDRLs and if so will the format and acceptance criteria for the CDRLs be specified?
Answer: No, it is not the Government’s intention for TORs, CPCRs or Trial Cards to be delivered as CDRLs.
SI&T – Question 85 RFP Section:
J
Page:
RFP Para., Clause, or Other Definitive Citation:
Exhibit A_-_CDRLs_DD_Form_1423
Document Name:
Final RFP
Document Date:
09/05/13