N00024-13-R-5100_Bidder's_Questions_Set_5.pdf
PDF 39 KB Posted
- Solicitation number
- N0002413R5100
About this file
Set 5 of Bidder's Questions and Answers
View the file
Other files
Show 40 more
Latest 50 of 74 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SI&T - Question 01 RFP Section:
Section L
Page:
357-359
RFP Para., Clause, or Other Definitive Citation:
Cost Volume, Section 1.1 Cost Summaries
Document Name:
Final RFP
Document Date:
09/05/13
Question: There are a number of inconsistencies between the RFP and the actual Attachment J-
25. For example, the RFP describes five (5) summary spreadsheets but the attachment contains nine (9) summary tabs.
Is it NAVSEA’s intention to reconcile these instances and provide consistent direction by updating Section L, 1.1 or Attachment J-25?
Answer: The language in Section L, 1.1 Cost Summary is consistent with the instructions contained within Attachment J-25. Attachment J-25 contains five summary tabs. The five summary tabs are to be populated and instructions are given to the completion of those specific tabs. The instructions also direct offerors, where applicable, to complete lower level detailed tabs to populate the summary tabs, e.g. detailed calendar year tabs in the “2a” series. The Government will provide a revised Attachment J-25 in a forthcoming amendment; however the revised attachment will not revise the number of summary or detailed tabs.
SI&T - Question 07
Section J
Page:
314-315
RFP Para., Clause, or Other Definitive Citation:
Attachment J-25
Document Name:
Final RFP
09/05/2013
Question: Attachment J-25 specifies that 168,497 hours are allocated to the Program Management Labor Category in CLIN 0001. This Labor Category has a single Job Title (Program Manager, Senior Grade Level). The CLIN 0001 scope (as defined in RFP Section C, Part 1, paragraph 3.1) requires a mix of Program Managers and support personnel.
Was it NAVSEA’s intention to have only the Program Management labor category hours included in J-25 CLIN 0001 section?
Answer: No, that is not the intention. The Government has modified the CLIN 0001 labor mix in the revised Attachment J-25 provided as an enclosure to this response.
It should be noted that the revised Attachment J-25 includes numerous other changes beyond the modified CLIN 0001 labor mix. The revised Attachment J-25 will be formally incorporated via a forthcoming solicitation amendment.
Question: The RFP states in Section F that, for proposal purposes, the estimated date of award is 15 January 2015.
Attachment J-25, Tab 1 (“Government Estimate”), however, contains hours in CY 2014 through
CY 2023.
Will the Government update Attachment J-25 periods of performance to match the estimated start date contained in Section F?
Answer: The Government will amend the solicitation to provide consistency with the estimated award date cited in Section F. This will include revisions to Section B, Attachment J-15 and Attachment J-25.
SI&T – Question 26
Section F and Attachment J-25
Page:
RFP Para., Clause, or Other Definitive Citation:
Section F, Part 1
Document Name:
Final RFP
Question: In Section B the summation of all Level of Effort hours total 2,895,431 and Section B Table 3 totals 2,851,994 hours.
In Section H of the RFP, the LOE clause states, “The total level of effort for the performance of this contract shall be 2,895,429 total man-hours of direct labor, including subcontractor direct labor for those subcontractors specifically identified in the Contractor's proposal as having hours included in the proposed level of effort.”
In J-25 Cost Evaluation Workbook, the total hours listed in the spreadsheet total 2,851,995.
(1) Will the Government please provide direction as to which number is correct?
(2) Should the total hours not agree with the J-25 provided, will the Government provide an updated J-25 to match the corrected total?
Answer: The Government has provided a revised Attachment J-25 that will be formally incorporated in a forthcoming amendment. In this amendment, the total LOE will be consistent in Section B, Section H and Attachment J-25.
SI&T – Question 28
B, H, and Attachment J-
Page:
277 (Sec. H)
RFP Para., Clause, or Other Definitive Citation:
Level Of Effort – Alternate I (May 2010)
Document Name:
Final RFP
Question: There are differences in the hours that have been allocated for LOE CLINs stated in the RFP, Schedule B and Attachment J-25. It is requested the Government provide a consistent set of LOE hours between Section B and J-25.
Also, Attachment J-25 does not contain whole hours for labor. It contains fractions of hours in individual years. Comparing the sums containing fractions of hours to sums of whole number hourly totals results in minor discrepancies.
It is requested that the government update J-25 to utilize only whole numbers for labor hours.
Answer: Please see the response to Question 28 regarding consistent of the required LOE.
Attachment J-25 has been revised and will be incorporated in a forthcoming amendment to cite only whole labor hours.
SI&T – Question 41
B, J
Page:
2-190
RFP Para., Clause, or Other Definitive Citation:
Section B (Supplies or Services and Prices Attachment) and Attachment J-25 (Cost Evaluation Workbook)
Document Name:
Final RFP
Question: CLIN’s 0019, 0020, and 0024 are missing from Worksheets 2b and 2c in Attachment J- 25.
It is requested that the government add the CLIN information to Worksheets 2b and 2c of Attachment J-25 Cost Evaluation Workbook.
Answer: CLINs 0019, 0020, and 0024 have been included in the revised Attachment J-25.
SI&T – Question 45
J
Page:
RFP Para., Clause, or Other Definitive Citation:
Attachment J-25 (Cost Evaluation Workbook)
Document Name:
Final RFP
Question: Worksheet 1 Government Estimate combines Systems/Electrical/Mechanical Engineers into one line, yet Worksheets 2b (Proposed Mix) and 2c (Gov-Ktr Matrix) have Systems, Electrical and Mechanical labor categories separated.
Request that the government to clarify Worksheets 2b and 2c with a single labor category “Systems/Electrical/Mechanical” to be consistent with Worksheet 1 Government Estimate.
Answer: Attachment J-25 Worksheet 2b and 2c have been revised to reflect a single labor category “Systems/Electrical/Mechanical” to be consistent with Worksheet 1.
SI&T – Question 46
J
Page:
RFP Para., Clause, or Other Definitive Citation:
Attachment J-25 (Cost Evaluation Workbook), Worksheet 1 – Government Estimate
Document Name:
Final RFP
Question: Attachment J-23 Staffing Plan Definitions lists ILS as a labor category and agrees with J-25 Worksheet 1. However, J-25 Cost Evaluation Worksheet 2b and 2c contain two different labor categories (ILS Manager and ILS Management Support).
It is recommended that the government clarify Worksheets 2b and 2c with the single labor category of ILS to be consistent with J-23 and J-25 Worksheet 1 Government Estimate.
Answer: Attachment J-25 Worksheet 2b and 2c has been revised to reflect a single labor category “ILS” to be consistent with Worksheet 1.
SI&T – Question 47
J
Page:
RFP Para., Clause, or Other Definitive Citation:
Attachments J-25 (Cost Evaluation Worksheet) and J-23 (Staffing Plan Definitions)
Document Name:
Final RFP
Question: In RFP Section F, Part 1, page 262, it states that the estimated AEGIS SI&T award date is January 15, 2015. However, per Attachment J-25 (Cost Evaluation Workbook _0005+0006+0019+0020+0024 LOE_8-28-2013.xlsx) a start date in CY 2014 is indicated.
It is requested that NAVSEA update Section F, Part 1, page 262 to provide clarification to the Offeror that the start date occurs in CY 2014 and the specific start month that should be used in our proposal?
Answer: The Government will amend the solicitation to provide consistency with the estimated award date cited in Section F. This will include revisions to Section B, Attachment J-15 and Attachment J-25.
SI&T – Question 68
F
Page:
RFP Para., Clause, or Other Definitive Citation:
Section F – Deliverables or Performance
Document Name:
Final RFP
File details come from the government source that posted it. Updated .