N00024-13-R-5100_0002.doc

DOC document 101 KB Posted

Attached to
AEGIS Combat System (ACS) Ship Integration and Test (SI&T) efforts – Final Solicitation
Solicitation number
N0002413R5100
Issued by

About this file

N00024-13-R-5100 Amendment 0002 of the Solicitation

View the file

Other files

File Type Posted
Attachment_17-__ACB_16_TI_16_AMT_Responsible_Test_List_(AWS).pdf PDF
N00024-13-R-5100_Bidder's_Question_Set_19.pdf PDF
N00024-13-R-5100_Amendment_0005.docx DOCX document
N00024-13-R-5100__conformed.doc DOC document
N00024-13-R-5100_Bidder's_Questions_Set_18.pdf PDF
N00024-13-R-5100_Bidder's_Question_Set_17.pdf PDF
N00024-13-R-5100_Bidder's_Questions_Set_16.pdf PDF
N00024-13-R-5100_Bidder's_Questions_Set_15.pdf PDF
Attachment_18_-_CLIN_0014_AWS_Element_Assessments_Pricing_Table.xls XLS spreadsheet
Attachment_16_-_ACB-16_TI-16_ATT_Responsible_Test_List_(AWS).pdf PDF
N00024-13-R-5100_Amendment_0004_Conformed.doc DOC document
N00024-13-R-5100_Amendment_0004.doc DOC document
Attachment_34_-_Key_Personnel_Positions_and_Definitions.pdf PDF
Attachment_23_-_Staffing_Plan_Definitions.pdf PDF
Attachment_17_-_ACB_16_TI_16_AMT_Responsible_Test_List_(AWS).pdf PDF
N00024-13-R-5100_Bidder's_Questions_Set_14.pdf PDF
N00024-13-R-5100__conformed.doc DOC document
N00024-13-R-5100_0003.doc DOC document
N00024-13-R-5100_0002_conformed.doc DOC document
Attachment_29_-_Cost_and_Software_Data_Reporting_(CSDR)_Plan.xls XLS spreadsheet
N00024-13-R-5100_Bidder's_Questions_Set_13.pdf PDF
N00024-13-R-5100_Bidder's_Questions_Set_12.pdf PDF
Exhibit_A_Contract_Data_Requirements_List_DD_Form_1423.pdf PDF
N00024-13-R-5100_Bidder's_Questions_Set_11.pdf PDF
Attachment_14_-_AMT_Standard_Operating_Procedures.pdf PDF
N00024-13-R-5100_0001_amended.doc DOC document
Attachment_25_-_Section_L_Attachment_Cost_Evaluation_Workbook.xlsx XLSX spreadsheet
Exhibit_A_Contract_Data_Requirements_List_DD_Form_1423.pdf PDF
Attachment_3_-_ICMP_Tasks_for_AWS_-_Element_Assessments.pdf PDF
N00024-13-R-5100_0001_conformed.doc DOC document
Attachment_20_-_Government_Furnished_Property.pdf PDF
Attachment_15_-_Performance_Incentive_Fee_Plan.pdf PDF
N00024-13-R-5100_Bidder's_Question_Set_10.pdf PDF
Exhibit_A_Contract_Data_Requirements_List_DD_Form_1423.pdf PDF
N00024-13-R-5100_Bidder's_Questions_Set_9.pdf PDF
N00024-13-R-5100_Bidder's_Questions_Set_8.pdf PDF
Attachment_25_-_Section_L_Attachment_Cost_Evaluation_Workbook.xlsx XLSX spreadsheet
N00024-13-R-5100_Bidder's_Questions_Set_7.pdf PDF
N00024-13-R-5100_Bidder's_Questions_Set_6.pdf PDF
N00024-13-R-5100_Bidder's_Questions_Set_5.pdf PDF
Attachment_25_-_Section_L_Attachment_Cost_Evaluation_Workbook.xlsx XLSX spreadsheet
Attachment_20_-_Government_Furnished_Property.pdf PDF
Attachment_3_-_ICMP_Tasks_for_AWS_-_Element_Assessments.pdf PDF
N00024-13-R-5100_Bidder's_Questions_Set_4.pdf PDF
N00024-13-R-5100_Bidder's_Questions_Set_3.pdf PDF
N0024-13-R-5100_Bidder's_Questions_Set_2.pdf PDF
N00024-13-R-5100_Bidders'_Questions_Set__1.pdf PDF
Exhibit_A_-_CDRLs_DD_Form_1423.pdf PDF
Bidders_Question_and_Answers_9_11_13.pdf PDF
N00024-13-R-5100.doc DOC document
Show 40 more

Latest 50 of 74 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

The following items are applicable to this modification:

NEW SUMMARY OF CHANGES

SECTION B - SUPPLIES OR SERVICES AND PRICES

The following CLINs and SUBCLINs have been modified to include the extended description that specifically aligns with: CLINs 3003, 3004, 3017, 3018, 4010, 4011, 4012, 4021, 4022, 4023, 5008FA, 5029FA, 5032FA, and 9037KA.

and:

The following SUBCLINs have been modified to incorporate reference to applicable CLINS in the extended description:

SUBCLIN 0016AA

The CLIN extended description has changed from Other Direct Costs (ODCs) in support of CLINs 0001-0015, Incidental Materials in support of CLINs 0001-0015(SEE NOTE D – OTHER DIRECT COSTS (ODC)) to Other Direct Costs (ODCs) in support of CLINs 0001-0015, Incidental Materials in support of CLINs 0001-0015 and CLINs 0019, 0020, and 0024(SEE NOTE D – OTHER DIRECT COSTS (ODC)).

SUBCLIN 1016BA

The CLIN extended description has changed from Other Direct Costs (ODCs) in support of CLINs 1001-1015, Incidental Materials in support of CLINs 1001-1015(SEE NOTE C – OPTION ITEM)(SEE NOTE D – OTHER DIRECT COSTS (ODC)) to Other Direct Costs (ODCs) in support of CLINs 1001-1015, Incidental Materials in support of CLINs 1001-1015 and CLINs 1019, 1020, and 1024(SEE NOTE C – OPTION ITEM)(SEE NOTE D – OTHER DIRECT COSTS (ODC)).

SUBCLIN 2016CA

The CLIN extended description has changed from Other Direct Costs (ODCs) in support of CLINs 2001-2015, Incidental Materials in support of CLINs 2001-2015(SEE NOTE C – OPTION ITEM)(SEE NOTE D – OTHER DIRECT COSTS (ODC)) to Other Direct Costs (ODCs) in support of CLINs 2001-2015, Incidental Materials in support of CLINs 2001-2015 and CLINs 2019, 2020, and 2024(SEE NOTE C – OPTION ITEM)(SEE NOTE D – OTHER DIRECT COSTS (ODC)).

SUBCLIN 3016DA

The CLIN extended description has changed from Other Direct Costs (ODCs) in support of CLINs 3001-3015, Incidental Materials in support of CLINs 3001-3015(SEE NOTE C – OPTION ITEM)(SEE NOTE D – OTHER DIRECT COSTS (ODC)) to Other Direct Costs (ODCs) in support of CLINs 3001-3015, Incidental Materials in support of CLINs 3001-3015 and CLINs 3019, 3020, and 3024(SEE NOTE C – OPTION ITEM)(SEE NOTE D – OTHER DIRECT COSTS (ODC)).

SUBCLIN 4016EA

The CLIN extended description has changed from Other Direct Costs (ODCs) in support of CLINs 4001-4015, Incidental Materials in support of CLINs 4001-4015(SEE NOTE C – OPTION ITEM)(SEE NOTE D – OTHER DIRECT COSTS (ODC)) to Other Direct Costs (ODCs) in support of CLINs 4001-4015, Incidental Materials in support of CLINs 4001-4015 and CLINs 4019, 4020, and 4024(SEE NOTE C – OPTION ITEM)(SEE NOTE D – OTHER DIRECT COSTS (ODC)).

SUBCLIN 5016FA

The CLIN extended description has changed from Other Direct Costs (ODCs) in support of CLINs 5001-5015, Incidental Materials in support of CLINs 5001-5015(SEE NOTE C – OPTION ITEM)(SEE NOTE D – OTHER DIRECT COSTS (ODC)) to Other Direct Costs (ODCs) in support of CLINs 5001-5015, Incidental Materials in support of CLINs 5001-5015 and CLINs 5019, 5020, and 5024(SEE NOTE C – OPTION ITEM)(SEE NOTE D – OTHER DIRECT COSTS (ODC)).

SUBCLIN 6016GA

The CLIN extended description has changed from Other Direct Costs (ODCs) in support of CLINs 6001-6015, Incidental Materials in support of CLINs 6001-6015(SEE NOTE C – OPTION ITEM)(SEE NOTE D – OTHER DIRECT COSTS (ODC)) to Other Direct Costs (ODCs) in support of CLINs 6001-6015, Incidental Materials in support of CLINs 6001-6015 and CLINs 6019, 6020, and 6024(SEE NOTE C – OPTION ITEM)(SEE NOTE D – OTHER DIRECT COSTS (ODC)).

SUBCLIN 7016HA

The CLIN extended description has changed from Other Direct Costs (ODCs) in support of CLINs 7001-7015, Incidental Materials in support of CLINs 7001-7015(SEE NOTE C – OPTION ITEM)(SEE NOTE D – OTHER DIRECT COSTS (ODC)) to Other Direct Costs (ODCs) in support of CLINs 7001-7015, Incidental Materials in support of CLINs 7001-7015 and CLINs 7019, 7020, and 7024(SEE NOTE C – OPTION ITEM)(SEE NOTE D – OTHER DIRECT COSTS (ODC)).

SUBCLIN 8016JA

The CLIN extended description has changed from Other Direct Costs (ODCs) in support of CLINs 8001-8015, Incidental Materials in support of CLINs 8001-8015(SEE NOTE C – OPTION ITEM)(SEE NOTE D – OTHER DIRECT COSTS (ODC)) to Other Direct Costs (ODCs) in support of CLINs 8001-8015, Incidental Materials in support of CLINs 8001-8015 and CLINs 8019, 8020, and 8024(SEE NOTE C – OPTION ITEM)(SEE NOTE D – OTHER DIRECT COSTS (ODC)).

SUBCLIN 9016KA

The CLIN extended description has changed from Other Direct Costs (ODCs) in support of CLINs 9001-9015, Incidental Materials in support of CLINs 9001-9015(SEE NOTE C – OPTION ITEM)(SEE NOTE D – OTHER DIRECT COSTS (ODC)) to Other Direct Costs (ODCs) in support of CLINs 9001-9015, Incidental Materials in support of CLINs 9001-9015 and CLINs 9019, 9020, and 9024(SEE NOTE C – OPTION ITEM)(SEE NOTE D – OTHER DIRECT COSTS (ODC)).

and:

The following has been modified to remove duplicate reference of 5005FA and replace with 5008FA:

NOTE C - Option item to which the option clause in SECTION I-2 (52.217-9 OPTION TO EXTEND THE TERM OF THE CONTRACT (MAR 2000)) applies and which is to be supplied only if and to the extent said option is exercised. As stated under Note A, the performance incentive CLINs 4017, 4018, 5017, 5018, 5021, 5022, 5023, 6017, 6018, 6021, 6022, 6023, 7017, 7018, 7021, 7022, 7023, 8017, 8018, 8021, 8022, 8023, 9017, 9018, 9021, 9022 and 9023 are only separated for administrative purposes. The latest option exercise date for performance incentive fee CLINs will be the same date as the primary CLIN. For example, the latest Option exercise date for CLIN 5003 is the latest Option exercise date for CLIN 5017. In addition, as stated under Note B, the award fee CLINs 0001AA, 0002AA, 0007AA, 0009AA, 0015AA; and if exercised Option SLINs 1001BA, 1002BA, 1007BA, 1009BA, 1015BA, 2001CA, 2002CA, 2007CA, 2009CA, 2015CA, 3001DA, 3002DA, 3007DA, 3009DA, 3015DA, 4001EA, 4002EA, 4007EA, 4009EA, 4015EA, 5001FA, 5002FA, 5005FA, 5007FA, 5008FA, 5009FA, 5015FA , 6001GA, 6002GA, 6005GA, 6007GA, 6008GA, 6009GA, 6015GA, 6019GA, 7001HA, 7002HA, 7006HA, 7007HA, 7008HA, 7009HA, 7015HA, 7019HA, 7020HA, 7024HA, 8001JA, 8002JA, 8007JA, 8008JA, 8009JA, 8015JA, 8019JA, 8020JA, 8024JA, 9001KA, 9002KA, 9007KA, 9008KA, 9009KA, 9015KA, 9019KA, 9020KA, 9024KA are separated for administrative purposes. The latest option exercise date for the award fee CLINs will be the same date as the primary CLIN. The latest option exercise dates are as follows:

CLIN/SLIN
Latest Option Exercise Date
0026
01/30/2024
1001BA
01/30/2016
1002BA
01/30/2016
1007BA
01/30/2016
1009BA
01/30/2016
1014
01/30/2016
1015BA
01/30/2016
1016BA
01/30/2016
2001CA
01/30/2017
2002CA
01/30/2017
2007CA
01/30/2017
2009CA
01/30/2017
2014
01/30/2017
2015CA
01/30/2017
2016CA
01/30/2017
3001DA
01/30/2018
3002DA
01/30/2018
3007DA
01/30/2018
3009DA
01/30/2018
3014
01/30/2018
3015DA
01/30/2018
3016DA
01/30/2018
4001EA
01/30/2019
4002EA
01/30/2019
4003
01/30/2019
4004
01/30/2019
4007EA
01/30/2019
4009EA
01/30/2019
4014
01/30/2019
4015EA
01/30/2019
4016EA
01/30/2019
5001FA
01/30/2020
5002FA
01/30/2020
5003
01/30/2020
5004
01/30/2020
5005FA
01/30/2020
5007FA
01/30/2020
5008FA
01/30/2020
5009FA
01/30/2020
5010
01/30/2020
5011
01/30/2020
5012
01/30/2020
5014
01/30/2020
5015FA
01/30/2020
5016FA
01/30/2020
6001GA
01/30/2021
6002GA
01/30/2021
6003
01/30/2021
6004
01/30/2021
6005GA
01/30/2021
6007GA
01/30/2021
6008GA
01/30/2021
6009GA
01/30/2021
6010
01/30/2021
6011
01/30/2021
6012
01/30/2021
6014
01/30/2021
6015GA
01/30/2021
6016GA
01/30/2021
6019GA
01/30/2021
7001HA
01/30/2022
7002HA
01/30/2022
7003
01/30/2022
7004
01/30/2022
7006HA
01/30/2022
7007HA
01/30/2022
7008HA
01/30/2022
7009HA
01/30/2022
7010
01/30/2022
7011
01/30/2022
7012
01/30/2022
7014
01/30/2022
7015HA
01/30/2022
7016HA
01/30/2022
7019HA
01/30/2022
7020HA
01/30/2022
7024HA
01/30/2022
8001JA
01/30/2023
8002JA
01/30/2023
8003
01/30/2023
8004
01/30/2023
8007JA
01/30/2023
8008JA
01/30/2023
8009JA
01/30/2023
8010
01/30/2023
8011
01/30/2023
8012
01/30/2023
8014
01/30/2023
8015JA
01/30/2023
8016JA
01/30/2023
8019JA
01/30/2023
8020JA
01/30/2023
8024JA
01/30/2023
9001KA
01/30/2024
9002KA
01/30/2024
9003
01/30/2024
9004
01/30/2024
9007KA
01/30/2024
9008KA
01/30/2024
9009KA
01/30/2024
9010
01/30/2024
9011
01/30/2024
9012
01/30/2024
9014
01/30/2024
9015KA
01/30/2024
9016KA
01/30/2024
9019KA
01/30/2024
9020KA
01/30/2024
9024KA
01/30/2024

and to remove duplicate reference of 3003 and replace with 3004:

“PAYMENTS OF FEE (S) (COMPLETION) (NAVSEA) (MAY 1993)

Applicable to Option CLINs 3003, 4003, 5003, 6003, 7003, 8003, 9003; 3004, 4004, 5004, 6004, 7004, 8004, 9004; 4010, 5010, 6010, 7010, 8010, 9010; 4011, 5011, 6011, 7011, 8011, 9011; 4012, 5012, 6012, 7012, 8012, and 9012

(a) For purposes of this contract, "fee" means "target fee" in cost-plus-incentive-fee type contracts, "base fee" in cost-plus-award-fee type contracts, "fixed fee" in cost-plus-fixed-fee type contracts for completion and phase type contracts.

(b) The Government shall make payments to the Contractor, subject to and in accordance with the clause in this contract entitled "FIXED FEE" (FAR 52.216-8) or "INCENTIVE FEE", (FAR 52.216-10), as applicable. Such payments shall be equal to TBD percent (TBD%) of the allowable cost of each invoice submitted by and payable to the Contractor pursuant to the clause of this contract entitled "ALLOWABLE COST AND PAYMENT" (FAR 52.216-7), subject to the withholding terms and conditions of the "FIXED FEE" or "INCENTIVE FEE" clause, as applicable (percentage of fee is based on fee dollars divided by estimated cost dollars, including facilities capital cost of money). Total fee(s) paid to the Contractor shall not exceed the fee amount(s) set forth in this contract.

(c) In the event of discontinuance of the work under this contract, or any specified phase of the contract, in accordance with the clause of this contract entitled "LIMITATION OF FUNDS" (FAR 52.232-22) or "LIMITATION OF COST" (FAR 52.232-20), as applicable, the fee shall be equitably adjusted by mutual agreement to reflect the diminution of work. If the adjusted fee is less than the sum of all fee payments made to the Contractor under this contract, the Contractor shall repay the excess amount to the Government. If the adjusted fee exceeds all payments made to the Contractor under this contract, the Contractor shall be paid the additional amount, subject to the availability of funds. In no event shall the Government be required to pay the Contractor any amount in excess of the funds obligated under this contract at the time of the discontinuance of work.

(d) Fee(s) withheld pursuant to the terms and conditions of this contract shall not be paid until the contract has been modified to reduce the fee(s) in accordance with paragraph (c) above, or until the Procuring Contracting Officer has advised the paying office in writing that no fee adjustment is required.”

SECTION I - CONTRACT CLAUSES

The following has been modified to remove 7025HA and replace with 7024HA:

“52.216-10 INCENTIVE FEE (JUN 2011)

Applicable Separately and Independently to Applicable to CLINs 0001AA, 0002AA, 0007AA, 0009AA, 0015AA; and if exercised Option CLINs 1001BA, 1002BA, 1007BA, 1009BA, 1015BA, 2001CA, 2002CA, 2007CA, 2009CA, 2015CA, 3001DA, 3002DA, 3007DA, 3009DA, 3015DA, 4001EA, 4002EA, 4007EA, 4009EA, 4015EA, 5001FA, 5002FA, 5005FA, 5007FA, 5008FA, 5009FA, 5015FA , 6001GA, 6002GA, 6005GA, 6007GA, 6008GA, 6009GA, 6015GA, 6019GA, 7001HA, 7002HA, 7006HA, 7007HA, 7008HA, 7009HA, 7015HA, 7019HA, 7020HA, 7024HA, 8001JA, 8002JA, 8007JA, 8008JA, 8009JA, 8015JA, 8019JA, 8020JA, 8024JA, 9001KA, 9002KA, 9007KA, 9008KA, 9009KA, and 9015KA, 9019KA, 9020KA, 9024KA.

(a) General. The Government shall pay the Contractor for performing this contract a fee determined as provided in this contract.

(b) Target cost and target fee. The target cost and target fee specified in the Schedule are subject to adjustment if the contract is modified in accordance with paragraph (d) below.

(1) "Target cost," as used in this contract, means the estimated cost of this contract as initially negotiated, adjusted in accordance with paragraph (d) below.

(2) "Target fee," as used in this contract, means the fee initially negotiated on the assumption that this contract would be performed for a cost equal to the estimated cost initially negotiated, adjusted in accordance with paragraph (d) below.

(c) Withholding of payment.

(1) Normally, the Government shall pay the fee to the Contractor as specified in the Schedule. However, when the Contracting Officer considers that performance or cost indicates that the Contractor will not achieve target, the Government shall pay on the basis of an appropriate lesser fee. When the Contractor demonstrates that performance or cost clearly indicates that the Contractor will earn a fee significantly above the target fee, the Government may, at the sole discretion of the Contracting Officer, pay on the basis of an appropriate higher fee.

(2) Payment of the incentive fee shall be made as specified in the Schedule; provided that the Contracting Officer withholds a reserve not to exceed 15 percent of the total incentive fee or $100,000, whichever is less, to protect the Government's interest. The Contracting Officer shall release 75 percent of all fee withholds under this contract after receipt of an adequate certified final indirect cost rate proposal covering the year of physical completion of this contract, provided the Contractor has satisfied all other contract terms and conditions, including the submission of the final patent and royalty reports, and is not delinquent in submitting final vouchers on prior years' settlements. The Contracting Officer may release up to 90 percent of the fee withholds under this contract based on the Contractor's past performance related to the submission and settlement of final indirect cost rate proposals.

(d) Equitable adjustments. When the work under this contract is increased or decreased by a modification to this contract or when any equitable adjustment in the target cost is authorized under any other clause, equitable adjustments in the target cost, target fee, minimum fee, and maximum fee, as appropriate, shall be stated in a supplemental agreement to this contract.

(e) Fee payable. (1) The fee payable under this contract shall be the target fee increased by sixty (60) cents for every dollar that the total allowable cost is less than the target cost or decreased by forty (40) cents for every dollar that the total allowable cost exceeds the target cost. In no event shall the fee be greater than TBD* percent or less than zero (0) percent of the target cost.

* Offeror to insert its proposed maximum fee payable.

(2) The fee shall be subject to adjustment, to the extent provided in paragraph (d) above, and within the minimum and maximum fee limitations in subparagraph (1) above, when the total allowable cost is increased or decreased as a consequence of (i) payments made under assignments or (ii) claims excepted from the release as required by paragraph (h)(2) of the Allowable Cost and Payment clause.

(3) If this contract is terminated in its entirety, the portion of the target fee payable shall not be subject to an increase or decrease as provided in this paragraph. The termination shall be accomplished in accordance with other applicable clauses of this contract.

(4) For the purpose of fee adjustment, "total allowable cost" shall not include allowable costs arising out of--

(i) Any of the causes covered by the Excusable Delays clause to the extent that they are beyond the control and without the fault or negligence of the Contractor or any subcontractor;

(ii) The taking effect, after negotiating the target cost, of a statute, court decision, written ruling, or regulation that results in the Contractor's being required to pay or bear the burden of any tax or duty or rate increase in a tax or duty;

(iii) Any direct cost attributed to the Contractor's involvement in litigation as required by the Contracting Officer pursuant to a clause of this contract, including furnishing evidence and information requested pursuant to the Notice and Assistance Regarding Patent and Copyright Infringement clause;

(iv) The purchase and maintenance of additional insurance not in the target cost and required by the Contracting Officer, or claims for reimbursement for liabilities to third persons pursuant to the Insurance Liability to Third Persons clause;

(v) Any claim, loss, or damage resulting from a risk for which the Contractor has been relieved of liability by the Government Property clause; or

(vi) Any claim, loss, or damage resulting from a risk defined in the contract as unusually hazardous or as a nuclear risk and against which the Government has expressly agreed to indemnify the Contractor.

(5) All other allowable costs are included in "total allowable cost" for fee adjustment in accordance with this paragraph (e), unless otherwise specifically provided in this contract.

(f) Contract modification. The total allowable cost and the adjusted fee determined as provided in this clause shall be evidenced by a modification to this contract signed by the Contractor and Contracting Officer.

(g) Inconsistencies. In the event of any language inconsistencies between this clause and provisioning documents or Government options under this contract, compensation for spare parts or other supplies and services ordered under such documents shall be determined in accordance with this clause.”

SECTION J – LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS

The following attachment has been revised to correct the SOW references in the Table of Contents (TOC):

Exhibit A: Contract Data Requirements List, DD Form 1423 – CDRLs Exhibit A, 75 pages and the following attachment has been modified to revise the submission dates to align with the award date:

J-29 Cost and Software Data Reporting (CSDR) Plan

(End of clause)

(End of Summary of Changes)

File details come from the government source that posted it. Updated .