The provided document is an Inadvertent Discovery Plan for the Sun River Bridge Replacement Project. The plan outlines the procedures to be followed if suspected archaeological material is encountered during construction. Key details include:

If archaeological material is discovered, the construction supervisor must halt work within 100 feet of the find, secure and protect the site, and notify the FHWA archaeologist. The FHWA archaeologist will then notify the land manager and the State Historic Preservation Office (SHPO). The SHPO may require a professional archaeologist to examine the find. If confirmed as archaeological, the appropriate course of action will be determined through consultation with the SHPO and Tribal Governments, and construction will not resume until this consultation is complete.

View the file

Other files for this federal contract opportunity

Other files attached to MT FLAP BOR 2980(1), Sun River Bridge Replacement, newest first.
File Type Posted
Tabulation of Bids.pdf PDF
BidSum.pdf PDF
QA_11-13-2024.pdf PDF
Amendment A008.pdf PDF
QA_11-08-2024.pdf PDF
Amendment A007.pdf PDF
QA_11-07-2024.pdf PDF
Amendment A006.pdf PDF
QA_11-06-2024.pdf PDF
QA_11-05-2024 part 2.pdf PDF
QA_11-05-2024.pdf PDF
Siphon Construction Narrative.pdf PDF
Pages from D-1771-D0000 Construction Documents 1944.pdf PDF
Amendment A005.pdf PDF
QA_11-04-2024.pdf PDF
QA_11-01-2024.pdf PDF
QA_10-31-2024.pdf PDF
QA_10-24-2024.pdf PDF
Amendment A004.pdf PDF
QA_10-22-2024.pdf PDF
Amendment A003.pdf PDF
Amendment A002.pdf PDF
QA_10-18-2024.pdf PDF
Physical Data_2.zip ZIP file
Amendment A001.pdf PDF
mta-bor298001_ALI_APPR_APPR-01.pdf PDF
mta-bor298001_SuperelevationReport.xlsx XLSX spreadsheet
mta-bor298001_SUR_ControlPoints.xlsx XLSX spreadsheet
mta-bor298001_Plans Sun River Bridge Replacement.pdf PDF
Physical Data.zip ZIP file
FY21_GPMT0311_Rtn-FC InspRpt.pdf PDF
mta-bor298001_CompiledSWPPP_Signed.pdf PDF
mta-bor298001_ALI_APPR_APPR-02.pdf PDF
mta-bor298001_PRO_APPR_APPR-02.pdf PDF
mta-bor298001_ALI_MAIN_MAIN-01.pdf PDF
mta-bor2980-1_SunRiverBridge_HaulRoadAssessment.pdf PDF
mta-bor2980-1_Combined Asbestos Report 999-5098.pdf PDF
mta-bor298001_QTY_EARTHWORK_Mainline.xlsx XLSX spreadsheet
mta-bor298001_FinalHydraulicMemo.pdf PDF
mta-bor2980-1_SunRiverBridge_SiphonInspectionReport.pdf PDF
mta-bor298001_QTY_EARTHWORK_Mainline.pdf PDF
mta-bor298001_PRO_APPR_APPR-01.pdf PDF
mta-bor298001_PRO_MAIN_MAIN-01.pdf PDF
mta-bor298001_QTY_EARTHWORK_Approaches.xlsx XLSX spreadsheet
IFB Sun River Bridge Replacement.pdf PDF
Show all 45

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Cultural Resources Survey for the Sun River Bridge Replacement Project C-1

Inadvertent Discovery Plan

1. If suspected archaeological material is observed, the Construction supervisor will halt work in the vicinity of the objects. No new ground disturbance should be carried out within 100 ft of the find.

Archaeological material may include objects, foundations, wells, privies that are more than 50 years old; stone, bone, wood, or antler tools or artifacts;

deposits of midden sediments; clusters of fire-modified rock, charcoal, or other evidence of fire-related activities; and faunal remains in association with stone chips or tools.

2. The Construction supervisor will secure and protect the find from damage or removal.

3. The Construction supervisor will notify the FHWA archaeologist. The FHWA archaeologist will notify the land manager and the State Historic Preservation Office (SHPO).

Contacts for the Discovery of Archaeological Material.

Organization Name Phone Numbers

FHWA Mike Schurke Office: (360) 619-7636

Montana State Historic Preservation Office (SHPO), State Archaeologist

Jessica Bush Office: (406) 444-0388

4. The SHPO may require the FHWA to have a professional archaeologist, one that meets the definition of a secretary qualified archaeologist, examine the find.

5. If the archaeologist determines the find is not archaeological in nature, work can resume. If the archaeologist confirms the find is archaeological, they will provide information about it to the FHWA and the SHPO. The appropriate course of action will be determined through consultation with the SHPO and appropriate Tribal Governments.

6. Construction will not resume until consultation with the SHPO and appropriate Tribal

Governments has completed.

File details come from the government source that posted it. Updated .