This document is a Tabulation of Bids for the MT FLAP BOR 2980(1), Sun River Bridge Replacement project. The project involves building a new 462-foot long precast-post-tensioned girder bridge with precast concrete deck, new approach embankments and MSE walls. An optional item is demolition of the existing steel truss bridge. The solicitation was offered for full and open competition. The project is located 50 miles northwest of Augusta, MT, with a tentative completion date of Fall 2026. The estimated price range is between $10-$20 million. The document provides a detailed tabulation of bids received from 5 contractors for the base bid schedule and optional schedule, including unit prices and total bid amounts. The lowest base bid was $16,391,289 from Hamilton Construction Co. The lowest option bid was $329,475 from Missouri River Contractors LLC.

View the file

Other files for this federal contract opportunity

Other files attached to MT FLAP BOR 2980(1), Sun River Bridge Replacement, newest first.
File Type Posted
BidSum.pdf PDF
QA_11-13-2024.pdf PDF
Amendment A008.pdf PDF
QA_11-08-2024.pdf PDF
Amendment A007.pdf PDF
QA_11-07-2024.pdf PDF
Amendment A006.pdf PDF
QA_11-06-2024.pdf PDF
QA_11-05-2024 part 2.pdf PDF
QA_11-05-2024.pdf PDF
Siphon Construction Narrative.pdf PDF
Pages from D-1771-D0000 Construction Documents 1944.pdf PDF
Amendment A005.pdf PDF
QA_11-04-2024.pdf PDF
QA_11-01-2024.pdf PDF
QA_10-31-2024.pdf PDF
QA_10-24-2024.pdf PDF
Amendment A004.pdf PDF
QA_10-22-2024.pdf PDF
Amendment A003.pdf PDF
Amendment A002.pdf PDF
QA_10-18-2024.pdf PDF
Physical Data_2.zip ZIP file
Amendment A001.pdf PDF
mta-bor298001_ALI_APPR_APPR-01.pdf PDF
mta-bor298001_SuperelevationReport.xlsx XLSX spreadsheet
mta-bor298001_SUR_ControlPoints.xlsx XLSX spreadsheet
mta-bor298001_Plans Sun River Bridge Replacement.pdf PDF
Physical Data.zip ZIP file
FY21_GPMT0311_Rtn-FC InspRpt.pdf PDF
mta-bor298001_CompiledSWPPP_Signed.pdf PDF
mta-bor298001_ALI_APPR_APPR-02.pdf PDF
mta-bor298001_PRO_APPR_APPR-02.pdf PDF
mta-bor298001_ALI_MAIN_MAIN-01.pdf PDF
mta-bor298001_FinalHydraulicMemo.pdf PDF
mta-bor2980-1_SunRiverBridge_SiphonInspectionReport.pdf PDF
mta-bor298001_QTY_EARTHWORK_Mainline.pdf PDF
mta-bor298001_PRO_APPR_APPR-01.pdf PDF
mta-bor298001_PRO_MAIN_MAIN-01.pdf PDF
mta-bor298001_QTY_EARTHWORK_Approaches.xlsx XLSX spreadsheet
IFB Sun River Bridge Replacement.pdf PDF
mta-bor2980-1_SunRiverBridge_HaulRoadAssessment.pdf PDF
mta-bor2980-1_Combined Asbestos Report 999-5098.pdf PDF
mta-bor2980-1_SunRiverBridge_InadvertentDiscoveryPlan.pdf PDF
mta-bor298001_QTY_EARTHWORK_Mainline.xlsx XLSX spreadsheet
Show all 45

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Tabulation of Bids Report Date: 11/21/24

1 out of 19Source Selection Information - See FAR 2.101 & 3.104

Project No: MT FLAP BOR 2980(1)

Project Name: Sun River Bridge Replacement

Contractor Responsive?

Engineer's Estimate

CK May Excavating, Inc.

Hamilton Construction Co.

McMillen, Inc.

Missouri River Contractors LLC

SLETTEN CONSTRUCTION COMPANY

Base Schedule A

$11,983,050.00

$18,537,785.00

$16,391,289.00

$29,069,850.00

$18,378,302.00

$17,053,150.00

Option: X

$523,850.00

$993,150.00

$442,818.60

$717,150.00

$329,475.00

$588,310.00

Contractor Responsive?

Engineer's Estimate

CK May Excavating, Inc.

Hamilton Construction Co.

McMillen, Inc.

Missouri River Contractors LLC

SLETTEN CONSTRUCTION COMPANY

Total Base Schedule A and Option(s): X

$12,506,900.00

$19,530,935.00

$16,834,107.60

$29,787,000.00

$18,707,777.00

$17,641,460.00

2 out of 19Source Selection Information - See FAR 2.101 & 3.104

Project No: MT FLAP BOR 2980(1)

Project Name: Sun River Bridge Replacement

Schedule: A

Schedule Type: Base

Solcitation No:

Division: Western Federal Lands

State: MT County: Lewis And Clark

Federal Land: USFS, BLM, BOR Opened at: Vancouver WA

Opened by: Robert Kolln

Date: 11/21/24

I certify that this Bid Tabulation accurately reflects the offers received for this solicitation.

Signed: _______________________________

Title: _______________________________

Date: _______________________________

Contract Awarded to: ____________________ Award Date: ____________________

Contractor Comment Bid Amount Responsive

Hamilton Construction Co. $16,391,289.00

PO BOX 659

Springfield, OR 97477

SLETTEN CONSTRUCTION COMPANY $17,053,150.00

PO Box 2467 Great Falls, MT 59403

Missouri River Contractors LLC $18,378,302.00 1500 Baine Street Helena, MT 59601

CK May Excavating, Inc. $18,537,785.00 PO Box 1426 Belgrade, MT 59714

McMillen, Inc. $29,069,850.00 1471 Shoreline Dr., Suite 100 Boise, ID 83702

Engineer's Estimate $11,983,050.00

Contract Officer 11/21/2024

3 out of 19Source Selection Information - See FAR 2.101 & 3.104

Project No: MT FLAP BOR 2980(1)

Project Name: Sun River Bridge Replacement

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0020 15101-0000 MOBILIZATION

Hamilton Construction Co. Lump Sum $1,600,000.00 SLETTEN CONSTRUCTION COMPANY Lump Sum $2,810,000.00 Missouri River Contractors LLC Lump Sum $1,900,000.00 CK May Excavating, Inc. Lump Sum $2,000,000.00 McMillen, Inc. Lump Sum $2,975,000.00 Engineer's Estimate ALL LPSM Lump Sum $1,280,000.00

A0040 15201-0000 CONSTRUCTION SURVEY AND STAKING

Hamilton Construction Co. Lump Sum $45,000.00 SLETTEN CONSTRUCTION COMPANY Lump Sum $145,400.00 Missouri River Contractors LLC Lump Sum $145,000.00 CK May Excavating, Inc. Lump Sum $35,000.00 McMillen, Inc. Lump Sum $750,000.00 Engineer's Estimate ALL LPSM Lump Sum $200,000.00

A0060 15301-0000 CONTRACTOR QUALITY CONTROL

Hamilton Construction Co. Lump Sum $250,000.00 SLETTEN CONSTRUCTION COMPANY Lump Sum $750,000.00 Missouri River Contractors LLC Lump Sum $795,000.00 CK May Excavating, Inc. Lump Sum $300,000.00 McMillen, Inc. Lump Sum $1,497,600.00 Engineer's Estimate ALL LPSM Lump Sum $200,000.00

A0080 15401-0000 CONTRACTOR TESTING

Hamilton Construction Co. Lump Sum $100,000.00 SLETTEN CONSTRUCTION COMPANY Lump Sum $150,000.00 Missouri River Contractors LLC Lump Sum $315,000.00 CK May Excavating, Inc. Lump Sum $150,000.00 McMillen, Inc. Lump Sum $690,000.00 Engineer's Estimate ALL LPSM Lump Sum $200,000.00

A0100 15501-0000 CONSTRUCTION SCHEDULE

Hamilton Construction Co. Lump Sum $16,000.00 SLETTEN CONSTRUCTION COMPANY Lump Sum $70,000.00 Missouri River Contractors LLC Lump Sum $65,000.00 CK May Excavating, Inc. Lump Sum $30,000.00 McMillen, Inc. Lump Sum $245,000.00 Engineer's Estimate ALL LPSM Lump Sum $50,000.00

4 out of 19Source Selection Information - See FAR 2.101 & 3.104

Project No: MT FLAP BOR 2980(1)

Project Name: Sun River Bridge Replacement

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0120 15702-5000 SOIL EROSION CONTROL, TEMPORARY DIVERSION BERM

Hamilton Construction Co. Lump Sum $45,000.00 SLETTEN CONSTRUCTION COMPANY Lump Sum $1.00 Missouri River Contractors LLC Lump Sum $488,312.00 CK May Excavating, Inc. Lump Sum $1,825,000.00 McMillen, Inc. Lump Sum $2,116,600.00 Engineer's Estimate ALL LPSM Lump Sum $158,000.00

A0140 15705-1400 SOIL EROSION CONTROL, FIBER ROLL

Hamilton Construction Co. $10.00 $28,000.00

SLETTEN CONSTRUCTION COMPANY $31.00 $86,800.00

Missouri River Contractors LLC $30.00 $84,000.00 CK May Excavating, Inc. $15.00 $42,000.00 McMillen, Inc. $23.00 $64,400.00 Engineer's Estimate 2,800 LNFT $10.00 $28,000.00

A0160 15706-0200 SOIL EROSION CONTROL, CHECK DAM (FILTER ROCK)

Hamilton Construction Co. $1,250.00 $8,750.00

SLETTEN CONSTRUCTION COMPANY $4,900.00 $34,300.00

Missouri River Contractors LLC $850.00 $5,950.00 CK May Excavating, Inc. $1,000.00 $7,000.00 McMillen, Inc. $4,950.00 $34,650.00 Engineer's Estimate 7 EACH $275.00 $1,925.00

A0180 15802-0000 WATERING FOR DUST CONTROL

Hamilton Construction Co. Lump Sum $39,000.00 SLETTEN CONSTRUCTION COMPANY Lump Sum $151,280.00 Missouri River Contractors LLC Lump Sum $175,000.00 CK May Excavating, Inc. Lump Sum $55,000.00 McMillen, Inc. Lump Sum $500,000.00 Engineer's Estimate ALL LPSM Lump Sum $10,000.00

A0200 20101-0000 CLEARING AND GRUBBING

Hamilton Construction Co. $3,000.00 $7,500.00

SLETTEN CONSTRUCTION COMPANY $22,356.00 $55,890.00

Missouri River Contractors LLC $75,000.00 $187,500.00 CK May Excavating, Inc. $30,000.00 $75,000.00 McMillen, Inc. $30,325.00 $75,812.50 Engineer's Estimate 2.5 ACRE $17,500.00 $43,750.00

5 out of 19Source Selection Information - See FAR 2.101 & 3.104

Project No: MT FLAP BOR 2980(1)

Project Name: Sun River Bridge Replacement

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0220 20301-0600 REMOVAL OF CATTLE GUARD

Hamilton Construction Co. $500.00 $500.00

SLETTEN CONSTRUCTION COMPANY $500.00 $500.00

Missouri River Contractors LLC $2,000.00 $2,000.00 CK May Excavating, Inc. $4,000.00 $4,000.00 McMillen, Inc. $6,000.00 $6,000.00 Engineer's Estimate 1 EACH $2,700.00 $2,700.00

A0240 20301-1100 REMOVAL OF GATE

Hamilton Construction Co. $500.00 $1,000.00

SLETTEN CONSTRUCTION COMPANY $500.00 $1,000.00

Missouri River Contractors LLC $1,500.00 $3,000.00 CK May Excavating, Inc. $2,000.00 $4,000.00 McMillen, Inc. $3,000.00 $6,000.00 Engineer's Estimate 2 EACH $815.00 $1,630.00

A0260 20301-2400 REMOVAL OF SIGN

Hamilton Construction Co. $150.00 $600.00

SLETTEN CONSTRUCTION COMPANY $200.00 $800.00

Missouri River Contractors LLC $500.00 $2,000.00 CK May Excavating, Inc. $175.00 $700.00 McMillen, Inc. $1,500.00 $6,000.00 Engineer's Estimate 4 EACH $300.00 $1,200.00

A0280 20302-0700 REMOVAL OF FENCE

Hamilton Construction Co. $10.00 $2,150.00

SLETTEN CONSTRUCTION COMPANY $10.00 $2,150.00

Missouri River Contractors LLC $10.00 $2,150.00 CK May Excavating, Inc. $32.00 $6,880.00 McMillen, Inc. $28.00 $6,020.00 Engineer's Estimate 215 LNFT $14.00 $3,010.00

A0300 20401-0000 ROADWAY EXCAVATION

Hamilton Construction Co. $45.00 $135,000.00

SLETTEN CONSTRUCTION COMPANY $50.00 $150,000.00

Missouri River Contractors LLC $40.00 $120,000.00 CK May Excavating, Inc. $35.00 $105,000.00 McMillen, Inc. $106.15 $318,450.00 Engineer's Estimate 3,000 CUYD $50.00 $150,000.00

6 out of 19Source Selection Information - See FAR 2.101 & 3.104

Project No: MT FLAP BOR 2980(1)

Project Name: Sun River Bridge Replacement

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0320 20403-0000 UNCLASSIFIED BORROW

Hamilton Construction Co. $100.00 $800,000.00

SLETTEN CONSTRUCTION COMPANY $110.00 $880,000.00

Missouri River Contractors LLC $35.00 $280,000.00 CK May Excavating, Inc. $85.00 $680,000.00 McMillen, Inc. $55.29 $442,320.00 Engineer's Estimate 8,000 CUYD $37.00 $296,000.00

A0340 20801-0000 STRUCTURE EXCAVATION

Hamilton Construction Co. $75.00 $20,250.00

SLETTEN CONSTRUCTION COMPANY $83.00 $22,410.00

Missouri River Contractors LLC $350.00 $94,500.00 CK May Excavating, Inc. $200.00 $54,000.00 McMillen, Inc. $150.00 $40,500.00 Engineer's Estimate 270 CUYD $945.00 $255,150.00

A0360 25120-0100 RIPRAP DITCH, METHOD A, CLASS 1

Hamilton Construction Co. $120.00 $78,000.00

SLETTEN CONSTRUCTION COMPANY $129.00 $83,850.00

Missouri River Contractors LLC $75.00 $48,750.00 CK May Excavating, Inc. $250.00 $162,500.00 McMillen, Inc. $148.00 $96,200.00 Engineer's Estimate 650 LNFT $97.00 $63,050.00

A0380 25501-1000 MECHANICALLY STABILIZED EARTH WALL, WELDED WIRE FACE

Hamilton Construction Co. $140.00 $588,000.00

SLETTEN CONSTRUCTION COMPANY $168.00 $705,600.00

Missouri River Contractors LLC $85.00 $357,000.00 CK May Excavating, Inc. $215.00 $903,000.00 McMillen, Inc. $137.00 $575,400.00 Engineer's Estimate 4,200 SQFT $140.00 $588,000.00

A0400 25701-0200 CONTRACTOR FURNISHED MECHANICALLY STABILIZED EARTH WALL DESIGN

Hamilton Construction Co. Lump Sum $5,750.00 SLETTEN CONSTRUCTION COMPANY Lump Sum $6,325.00 Missouri River Contractors LLC Lump Sum $45,000.00 CK May Excavating, Inc. Lump Sum $15,000.00 McMillen, Inc. Lump Sum $15,100.00 Engineer's Estimate ALL LPSM Lump Sum $25,000.00

7 out of 19Source Selection Information - See FAR 2.101 & 3.104

Project No: MT FLAP BOR 2980(1)

Project Name: Sun River Bridge Replacement

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0420 30202-2000 ROADWAY AGGREGATE, METHOD 2

Hamilton Construction Co. $90.00 $405,000.00

SLETTEN CONSTRUCTION COMPANY $98.00 $441,000.00

Missouri River Contractors LLC $70.00 $315,000.00 CK May Excavating, Inc. $60.00 $270,000.00 McMillen, Inc. $77.00 $346,500.00 Engineer's Estimate 4,500 TON $26.00 $117,000.00

A0440 55101-2100 STEEL H-PILE, 14X 117, IN PLACE (ROCK SOCKET)

Hamilton Construction Co. $625.00 $275,000.00

SLETTEN CONSTRUCTION COMPANY $861.00 $378,840.00

Missouri River Contractors LLC $1,250.00 $550,000.00 CK May Excavating, Inc. $425.00 $187,000.00 McMillen, Inc. $939.00 $413,160.00 Engineer's Estimate 440 LNFT $600.00 $264,000.00

A0460 55201-0200 STRUCTURAL CONCRETE, CLASS A (AE)

Hamilton Construction Co. $2,200.00 $1,621,400.00

SLETTEN CONSTRUCTION COMPANY $2,332.00 $1,718,684.00

Missouri River Contractors LLC $2,950.00 $2,174,150.00 CK May Excavating, Inc. $4,050.00 $2,984,850.00 McMillen, Inc. $2,700.00 $1,989,900.00 Engineer's Estimate 737 CUYD $2,750.00 $2,026,750.00

A0480 55301-3500 PRECAST, PRESTRESSED CONCRETE SLAB (DECK PANEL)

Hamilton Construction Co. $27,500.00 $2,530,000.00

SLETTEN CONSTRUCTION COMPANY $18,755.00 $1,725,460.00

Missouri River Contractors LLC $17,750.00 $1,633,000.00 CK May Excavating, Inc. $28,000.00 $2,576,000.00 McMillen, Inc. $45,000.00 $4,140,000.00 Engineer's Estimate 92 EACH $20,500.00 $1,886,000.00

A0500 55302-2100 PRECAST, PRESTRESSED CONCRETE BULB TEE GIRDER, 74-INCH (SPLICED)

Hamilton Construction Co. $1,900.00 $2,603,000.00

SLETTEN CONSTRUCTION COMPANY $1,971.00 $2,700,270.00

Missouri River Contractors LLC $3,500.00 $4,795,000.00 CK May Excavating, Inc. $2,000.00 $2,740,000.00 McMillen, Inc. $2,295.00 $3,144,150.00 Engineer's Estimate 1,370 LNFT $1,200.00 $1,644,000.00

8 out of 19Source Selection Information - See FAR 2.101 & 3.104

Project No: MT FLAP BOR 2980(1)

Project Name: Sun River Bridge Replacement

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0520 55401-1000 REINFORCING STEEL

Hamilton Construction Co. $2.50 $389,750.00

SLETTEN CONSTRUCTION COMPANY $3.00 $467,700.00

Missouri River Contractors LLC $3.50 $545,650.00 CK May Excavating, Inc. $3.40 $530,060.00 McMillen, Inc. $3.50 $545,650.00 Engineer's Estimate 155,900 LB $2.75 $428,725.00

A0540 55401-2000 REINFORCING STEEL, EPOXY COATED

Hamilton Construction Co. $1.50 $36,900.00

SLETTEN CONSTRUCTION COMPANY $3.50 $86,100.00

Missouri River Contractors LLC $5.00 $123,000.00 CK May Excavating, Inc. $4.20 $103,320.00 McMillen, Inc. $3.50 $86,100.00 Engineer's Estimate 24,600 LB $3.80 $93,480.00

A0560 55601-1200 BRIDGE RAILING, STEEL, THREE RAIL (WEATHERING STEEL)

Hamilton Construction Co. $280.00 $270,200.00

SLETTEN CONSTRUCTION COMPANY $340.00 $328,100.00

Missouri River Contractors LLC $495.00 $477,675.00 CK May Excavating, Inc. $315.00 $303,975.00 McMillen, Inc. $400.00 $386,000.00 Engineer's Estimate 965 LNFT $325.00 $313,625.00

A0580 56401-1000 BEARING DEVICE, ELASTOMERIC

Hamilton Construction Co. $2,250.00 $13,500.00

SLETTEN CONSTRUCTION COMPANY $1,500.00 $9,000.00

Missouri River Contractors LLC $3,500.00 $21,000.00 CK May Excavating, Inc. $4,500.00 $27,000.00 McMillen, Inc. $5,025.00 $30,150.00 Engineer's Estimate 6 EACH $7,250.00 $43,500.00

A0600 56501-0000 DRILLED SHAFT (120-INCH DIAMETER)

Hamilton Construction Co. $11,000.00 $583,000.00

SLETTEN CONSTRUCTION COMPANY $11,082.00 $587,346.00

Missouri River Contractors LLC $19,000.00 $1,007,000.00 CK May Excavating, Inc. $8,250.00 $437,250.00 McMillen, Inc. $17,400.00 $922,200.00 Engineer's Estimate 53 LNFT $10,000.00 $530,000.00

9 out of 19Source Selection Information - See FAR 2.101 & 3.104

Project No: MT FLAP BOR 2980(1)

Project Name: Sun River Bridge Replacement

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0620 57502-0000 TEMPORARY BRIDGE

Hamilton Construction Co. Lump Sum $2,842,500.00 SLETTEN CONSTRUCTION COMPANY Lump Sum $1,382,852.00 Missouri River Contractors LLC Lump Sum $380,000.00 CK May Excavating, Inc. Lump Sum $750,000.00 McMillen, Inc. Lump Sum $5,450,000.00 Engineer's Estimate ALL LPSM Lump Sum $42,000.00

A0640 58501-0000 ULTRA HIGH PERFORMANCE CONCRETE

Hamilton Construction Co. $12,750.00 $714,000.00

SLETTEN CONSTRUCTION COMPANY $13,848.00 $775,488.00

Missouri River Contractors LLC $13,900.00 $778,400.00 CK May Excavating, Inc. $12,000.00 $672,000.00 McMillen, Inc. $11,360.00 $636,160.00 Engineer's Estimate 56 CUYD $10,000.00 $560,000.00

A0660 60201-0800 24-INCH PIPE CULVERT

Hamilton Construction Co. $100.00 $11,000.00

SLETTEN CONSTRUCTION COMPANY $110.00 $12,100.00

Missouri River Contractors LLC $250.00 $27,500.00 CK May Excavating, Inc. $250.00 $27,500.00 McMillen, Inc. $767.00 $84,370.00 Engineer's Estimate 110 LNFT $285.00 $31,350.00

A0680 60202-0400 24-INCH EQUIVALENT DIAMETER ARCH OR ELLIPTICAL PIPE CULVERT

Hamilton Construction Co. $100.00 $13,000.00

SLETTEN CONSTRUCTION COMPANY $110.00 $14,300.00

Missouri River Contractors LLC $275.00 $35,750.00 CK May Excavating, Inc. $300.00 $39,000.00 McMillen, Inc. $826.00 $107,380.00 Engineer's Estimate 130 LNFT $215.00 $27,950.00

A0700 61701-5150 GUARDRAIL SYSTEM MGS, TYPE 4, CLASS B WOOD POSTS

Hamilton Construction Co. $100.00 $17,500.00

SLETTEN CONSTRUCTION COMPANY $104.50 $18,287.50

Missouri River Contractors LLC $120.00 $21,000.00 CK May Excavating, Inc. $105.00 $18,375.00 McMillen, Inc. $105.00 $18,375.00 Engineer's Estimate 175 LNFT $60.00 $10,500.00

10 out of 19Source Selection Information - See FAR 2.101 & 3.104

Project No: MT FLAP BOR 2980(1)

Project Name: Sun River Bridge Replacement

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0720 61702-1500 TERMINAL SECTION, TYPE MGS TANGENT (WEATHERING STEEL)

Hamilton Construction Co. $6,500.00 $26,000.00

SLETTEN CONSTRUCTION COMPANY $7,150.00 $28,600.00

Missouri River Contractors LLC $5,000.00 $20,000.00 CK May Excavating, Inc. $7,000.00 $28,000.00 McMillen, Inc. $4,710.00 $18,840.00 Engineer's Estimate 4 EACH $5,900.00 $23,600.00

A0740 61707-4000 STRUCTURE TRANSITION RAILING, MGS SYSTEM (WEATHERING STEEL)

Hamilton Construction Co. $500.00 $42,000.00

SLETTEN CONSTRUCTION COMPANY $495.00 $41,580.00

Missouri River Contractors LLC $160.00 $13,440.00 CK May Excavating, Inc. $500.00 $42,000.00 McMillen, Inc. $260.00 $21,840.00 Engineer's Estimate 84 LNFT $240.00 $20,160.00

A0760 61901-0000 FENCE (WILDLIFE-FRIENDLY)

Hamilton Construction Co. $45.00 $9,900.00

SLETTEN CONSTRUCTION COMPANY $11.00 $2,420.00

Missouri River Contractors LLC $9.50 $2,090.00 CK May Excavating, Inc. $80.00 $17,600.00 McMillen, Inc. $96.00 $21,120.00 Engineer's Estimate 220 LNFT $82.00 $18,040.00

A0780 61902-0000 GATE

Hamilton Construction Co. $22,500.00 $22,500.00

SLETTEN CONSTRUCTION COMPANY $16,500.00 $16,500.00

Missouri River Contractors LLC $5,000.00 $5,000.00 CK May Excavating, Inc. $2,750.00 $2,750.00 McMillen, Inc. $4,850.00 $4,850.00 Engineer's Estimate 1 EACH $16,000.00 $16,000.00

A0800 61902-1400 GATE, METAL, 16 FEET WIDTH

Hamilton Construction Co. $1,400.00 $1,400.00

SLETTEN CONSTRUCTION COMPANY $10,450.00 $10,450.00

Missouri River Contractors LLC $13,900.00 $13,900.00 CK May Excavating, Inc. $8,250.00 $8,250.00 McMillen, Inc. $5,008.00 $5,008.00 Engineer's Estimate 1 EACH $10,000.00 $10,000.00

11 out of 19Source Selection Information - See FAR 2.101 & 3.104

Project No: MT FLAP BOR 2980(1)

Project Name: Sun River Bridge Replacement

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0820 62201-0250 DUMP TRUCK, 10 CUBIC YARD MINIMUM CAPACITY

Hamilton Construction Co. $175.00 $7,000.00

SLETTEN CONSTRUCTION COMPANY $175.00 $7,000.00

Missouri River Contractors LLC $175.00 $7,000.00 CK May Excavating, Inc. $265.00 $10,600.00 McMillen, Inc. $205.00 $8,200.00 Engineer's Estimate 40 HOUR $215.00 $8,600.00

A0840 62201-0550 BACKHOE LOADER, 6 CUBIC FOOT MINIMUM RATED CAPACITY BUCKET, 24-INCH WIDTH

Hamilton Construction Co. $175.00 $7,000.00

SLETTEN CONSTRUCTION COMPANY $175.00 $7,000.00

Missouri River Contractors LLC $215.00 $8,600.00 CK May Excavating, Inc. $350.00 $14,000.00 McMillen, Inc. $160.00 $6,400.00 Engineer's Estimate 40 HOUR $200.00 $8,000.00

A0860 62201-2850 MOTOR GRADER, 12 FOOT MINIMUM BLADE

Hamilton Construction Co. $175.00 $7,000.00

SLETTEN CONSTRUCTION COMPANY $175.00 $7,000.00

Missouri River Contractors LLC $225.00 $9,000.00 CK May Excavating, Inc. $400.00 $16,000.00 McMillen, Inc. $185.00 $7,400.00 Engineer's Estimate 40 HOUR $250.00 $10,000.00

A0880 62201-3400 HYDRAULIC EXCAVATOR, 1 CUBIC YARD MINIMUM CAPACITY WITH THUMB ATTACHMENT

Hamilton Construction Co. $200.00 $8,000.00

SLETTEN CONSTRUCTION COMPANY $200.00 $8,000.00

Missouri River Contractors LLC $225.00 $9,000.00 CK May Excavating, Inc. $400.00 $16,000.00 McMillen, Inc. $210.00 $8,400.00 Engineer's Estimate 40 HOUR $250.00 $10,000.00

A0900 62301-0000 GENERAL LABOR

Hamilton Construction Co. $140.00 $5,600.00

SLETTEN CONSTRUCTION COMPANY $110.00 $4,400.00

Missouri River Contractors LLC $90.00 $3,600.00 CK May Excavating, Inc. $250.00 $10,000.00 McMillen, Inc. $71.00 $2,840.00 Engineer's Estimate 40 HOUR $100.00 $4,000.00

12 out of 19Source Selection Information - See FAR 2.101 & 3.104

Project No: MT FLAP BOR 2980(1)

Project Name: Sun River Bridge Replacement

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0920 62406-0300 PLACING CONSERVED TOPSOIL, 4-INCH DEPTH

Hamilton Construction Co. $3,000.00 $6,000.00

SLETTEN CONSTRUCTION COMPANY $3,000.00 $6,000.00

Missouri River Contractors LLC $39,000.00 $78,000.00 CK May Excavating, Inc. $35,000.00 $70,000.00 McMillen, Inc. $18,565.00 $37,130.00 Engineer's Estimate 2.0 ACRE $27,000.00 $54,000.00

A0940 62501-0000 TURF ESTABLISHMENT (HYDRAULIC METHOD)

Hamilton Construction Co. $2,500.00 $5,000.00

SLETTEN CONSTRUCTION COMPANY $5,500.00 $11,000.00

Missouri River Contractors LLC $22,000.00 $44,000.00 CK May Excavating, Inc. $11,000.00 $22,000.00 McMillen, Inc. $10,000.00 $20,000.00 Engineer's Estimate 2.0 ACRE $9,500.00 $19,000.00

A0960 63302-0000 SIGN SYSTEM

Hamilton Construction Co. $165.00 $6,765.00

SLETTEN CONSTRUCTION COMPANY $181.50 $7,441.50

Missouri River Contractors LLC $25.00 $1,025.00 CK May Excavating, Inc. $180.00 $7,380.00 McMillen, Inc. $158.00 $6,478.00 Engineer's Estimate 41 SQFT $140.00 $5,740.00

A0980 63302-0000 SIGN SYSTEM (TRAIL MARKER)

Hamilton Construction Co. $250.00 $250.00

SLETTEN CONSTRUCTION COMPANY $275.00 $275.00

Missouri River Contractors LLC $500.00 $500.00 CK May Excavating, Inc. $275.00 $275.00 McMillen, Inc. $80.50 $80.50 Engineer's Estimate 1 SQFT $500.00 $500.00

A1000 63502-0600 TEMPORARY TRAFFIC CONTROL, BARRICADE TYPE 3

Hamilton Construction Co. $500.00 $1,500.00

SLETTEN CONSTRUCTION COMPANY $550.00 $1,650.00

Missouri River Contractors LLC $600.00 $1,800.00 CK May Excavating, Inc. $550.00 $1,650.00 McMillen, Inc. $500.00 $1,500.00 Engineer's Estimate 3 EACH $545.00 $1,635.00

13 out of 19Source Selection Information - See FAR 2.101 & 3.104

Project No: MT FLAP BOR 2980(1)

Project Name: Sun River Bridge Replacement

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A1020 63502-1250 TEMPORARY TRAFFIC CONTROL, TUBULAR MARKER, TYPE 42-INCH

Hamilton Construction Co. $35.00 $3,500.00

SLETTEN CONSTRUCTION COMPANY $38.50 $3,850.00

Missouri River Contractors LLC $12.00 $1,200.00 CK May Excavating, Inc. $35.00 $3,500.00 McMillen, Inc. $55.00 $5,500.00 Engineer's Estimate 100 EACH $34.00 $3,400.00

A1040 63502-1700 TEMPORARY TRAFFIC CONTROL, WARNING LIGHT TYPE C

Hamilton Construction Co. $50.00 $300.00

SLETTEN CONSTRUCTION COMPANY $55.00 $330.00

Missouri River Contractors LLC $750.00 $4,500.00 CK May Excavating, Inc. $55.00 $330.00 McMillen, Inc. $150.00 $900.00 Engineer's Estimate 6 EACH $90.00 $540.00

A1060 63503-1000 TEMPORARY TRAFFIC CONTROL, PLASTIC FENCE

Hamilton Construction Co. $18.00 $5,040.00

SLETTEN CONSTRUCTION COMPANY $21.00 $5,880.00

Missouri River Contractors LLC $15.00 $4,200.00 CK May Excavating, Inc. $20.00 $5,600.00 McMillen, Inc. $8.00 $2,240.00 Engineer's Estimate 280 LNFT $11.50 $3,220.00

A1080 63504-1000 TEMPORARY TRAFFIC CONTROL, CONSTRUCTION SIGN

Hamilton Construction Co. $59.00 $16,284.00

SLETTEN CONSTRUCTION COMPANY $65.00 $17,940.00

Missouri River Contractors LLC $35.00 $9,660.00 CK May Excavating, Inc. $65.00 $17,940.00 McMillen, Inc. $51.00 $14,076.00 Engineer's Estimate 276 SQFT $70.00 $19,320.00

A1100 63506-0500 TEMPORARY TRAFFIC CONTROL, FLAGGER

Hamilton Construction Co. $60.00 $114,000.00

SLETTEN CONSTRUCTION COMPANY $60.00 $114,000.00

Missouri River Contractors LLC $75.00 $142,500.00 CK May Excavating, Inc. $65.00 $123,500.00 McMillen, Inc. $61.00 $115,900.00 Engineer's Estimate 1,900 HOUR $90.00 $171,000.00

14 out of 19Source Selection Information - See FAR 2.101 & 3.104

Project No: MT FLAP BOR 2980(1)

Project Name: Sun River Bridge Replacement

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

Total Schedule - All Items

Hamilton Construction Co. $16,391,289.00

SLETTEN CONSTRUCTION COMPANY $17,053,150.00

Missouri River Contractors LLC $18,378,302.00 CK May Excavating, Inc. $18,537,785.00 McMillen, Inc. $29,069,850.00 Engineer's Estimate $11,983,050.00

15 out of 19Source Selection Information - See FAR 2.101 & 3.104

Project No: MT FLAP BOR 2980(1)

Project Name: Sun River Bridge Replacement

Schedule: X

Schedule Type: Options

Solcitation No:

Division: Western Federal Lands

State: MT County: Lewis And Clark

Federal Land: USFS, BLM, BOR Opened at: Vancouver WA

Opened by: Robert Kolln

Date: 11/21/24

I certify that this Bid Tabulation accurately reflects the offers received for this solicitation.

Signed: _______________________________

Title: _______________________________

Date: _______________________________

Contract Awarded to: ____________________ Award Date: ____________________

Contractor Comment Bid Amount Responsive

Missouri River Contractors LLC $329,475.00 1500 Baine Street Helena, MT 59601

Hamilton Construction Co. $442,818.60

PO BOX 659

Springfield, OR 97477

SLETTEN CONSTRUCTION COMPANY $588,310.00

PO Box 2467 Great Falls, MT 59403

McMillen, Inc. $717,150.00 1471 Shoreline Dr., Suite 100 Boise, ID 83702

CK May Excavating, Inc. $993,150.00 PO Box 1426 Belgrade, MT 59714

Engineer's Estimate $523,850.00

16 out of 19Source Selection Information - See FAR 2.101 & 3.104

Project No: MT FLAP BOR 2980(1)

Project Name: Sun River Bridge Replacement

Schedule: X

Schedule Type: Options

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

X0020 15101-0000 MOBILIZATION

Missouri River Contractors LLC Lump Sum $33,000.00 Hamilton Construction Co. Lump Sum $44,000.00 SLETTEN CONSTRUCTION COMPANY Lump Sum $154,800.00 McMillen, Inc. Lump Sum $85,000.00 CK May Excavating, Inc. Lump Sum $200,000.00 Engineer's Estimate ALL LPSM Lump Sum $55,000.00

X0040 15201-0000 CONSTRUCTION SURVEY AND STAKING

Missouri River Contractors LLC Lump Sum $5,000.00 Hamilton Construction Co. Lump Sum $5,000.00 SLETTEN CONSTRUCTION COMPANY Lump Sum $10,400.00 McMillen, Inc. Lump Sum $36,000.00 CK May Excavating, Inc. Lump Sum $15,000.00 Engineer's Estimate ALL LPSM Lump Sum $8,800.00

X0060 15301-0000 CONTRACTOR QUALITY CONTROL

Missouri River Contractors LLC Lump Sum $14,700.00 Hamilton Construction Co. Lump Sum $20,000.00 SLETTEN CONSTRUCTION COMPANY Lump Sum $40,000.00 McMillen, Inc. Lump Sum $45,000.00 CK May Excavating, Inc. Lump Sum $50,000.00 Engineer's Estimate ALL LPSM Lump Sum $8,800.00

X0080 15401-0000 CONTRACTOR TESTING

Missouri River Contractors LLC Lump Sum $16,500.00 Hamilton Construction Co. Lump Sum $1,168.60 SLETTEN CONSTRUCTION COMPANY Lump Sum $20,000.00 McMillen, Inc. Lump Sum $21,500.00 CK May Excavating, Inc. Lump Sum $5,000.00 Engineer's Estimate ALL LPSM Lump Sum $8,800.00

X0100 15501-0000 CONSTRUCTION SCHEDULE

Missouri River Contractors LLC Lump Sum $15,000.00 Hamilton Construction Co. Lump Sum $5,000.00 SLETTEN CONSTRUCTION COMPANY Lump Sum $6,500.00 McMillen, Inc. Lump Sum $9,900.00 CK May Excavating, Inc. Lump Sum $10,000.00 Engineer's Estimate ALL LPSM Lump Sum $2,200.00

17 out of 19Source Selection Information - See FAR 2.101 & 3.104

Project No: MT FLAP BOR 2980(1)

Project Name: Sun River Bridge Replacement

Schedule: X

Schedule Type: Options

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

X0120 15705-1400 SOIL EROSION CONTROL, FIBER ROLL

Missouri River Contractors LLC $30.00 $39,000.00 Hamilton Construction Co. $10.00 $13,000.00

SLETTEN CONSTRUCTION COMPANY $31.00 $40,300.00

McMillen, Inc. $23.00 $29,900.00 CK May Excavating, Inc. $15.00 $19,500.00 Engineer's Estimate 1,300 LNFT $10.00 $13,000.00

X0140 20301-0400 REMOVAL OF BRIDGE

Missouri River Contractors LLC $115,000.00 $115,000.00 Hamilton Construction Co. $275,000.00 $275,000.00

SLETTEN CONSTRUCTION COMPANY $222,760.00 $222,760.00

McMillen, Inc. $425,000.00 $425,000.00 CK May Excavating, Inc. $500,000.00 $500,000.00 Engineer's Estimate 1 EACH $300,000.00 $300,000.00

X0160 21101-2000 ROADWAY OBLITERATION, METHOD 2

Missouri River Contractors LLC $4.25 $15,725.00 Hamilton Construction Co. $15.00 $55,500.00

SLETTEN CONSTRUCTION COMPANY $15.00 $55,500.00

McMillen, Inc. $4.50 $16,650.00 CK May Excavating, Inc. $25.00 $92,500.00 Engineer's Estimate 3,700 SQYD $18.00 $66,600.00

X0180 25125-0000 BOULDER

Missouri River Contractors LLC $500.00 $7,500.00 Hamilton Construction Co. $300.00 $4,500.00

SLETTEN CONSTRUCTION COMPANY $300.00 $4,500.00

McMillen, Inc. $895.00 $13,425.00 CK May Excavating, Inc. $2,500.00 $37,500.00 Engineer's Estimate 15 EACH $1,100.00 $16,500.00

X0200 62201-0250 DUMP TRUCK, 10 CUBIC YARD MINIMUM CAPACITY

Missouri River Contractors LLC $175.00 $1,750.00 Hamilton Construction Co. $175.00 $1,750.00

SLETTEN CONSTRUCTION COMPANY $175.00 $1,750.00

McMillen, Inc. $205.00 $2,050.00 CK May Excavating, Inc. $265.00 $2,650.00 Engineer's Estimate 10 HOUR $215.00 $2,150.00

18 out of 19Source Selection Information - See FAR 2.101 & 3.104

Project No: MT FLAP BOR 2980(1)

Project Name: Sun River Bridge Replacement

Schedule: X

Schedule Type: Options

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

X0220 62201-0550 BACKHOE LOADER, 6 CUBIC FOOT MINIMUM RATED CAPACITY BUCKET, 24-INCH WIDTH

Missouri River Contractors LLC $215.00 $2,150.00 Hamilton Construction Co. $175.00 $1,750.00

SLETTEN CONSTRUCTION COMPANY $175.00 $1,750.00

McMillen, Inc. $160.00 $1,600.00 CK May Excavating, Inc. $350.00 $3,500.00 Engineer's Estimate 10 HOUR $200.00 $2,000.00

X0240 62201-2850 MOTOR GRADER, 12 FOOT MINIMUM BLADE

Missouri River Contractors LLC $225.00 $2,250.00 Hamilton Construction Co. $175.00 $1,750.00

SLETTEN CONSTRUCTION COMPANY $175.00 $1,750.00

McMillen, Inc. $185.00 $1,850.00 CK May Excavating, Inc. $400.00 $4,000.00 Engineer's Estimate 10 HOUR $250.00 $2,500.00

X0260 62301-0000 GENERAL LABOR

Missouri River Contractors LLC $90.00 $900.00 Hamilton Construction Co. $140.00 $1,400.00

SLETTEN CONSTRUCTION COMPANY $110.00 $1,100.00

McMillen, Inc. $71.00 $710.00 CK May Excavating, Inc. $250.00 $2,500.00 Engineer's Estimate 10 HOUR $100.00 $1,000.00

X0280 62406-0300 PLACING CONSERVED TOPSOIL, 4-INCH DEPTH

Missouri River Contractors LLC $39,000.00 $39,000.00 Hamilton Construction Co. $3,000.00 $3,000.00

SLETTEN CONSTRUCTION COMPANY $22,200.00 $22,200.00

McMillen, Inc. $18,565.00 $18,565.00 CK May Excavating, Inc. $40,000.00 $40,000.00 Engineer's Estimate 1.0 ACRE $27,000.00 $27,000.00

X0300 62501-0000 TURF ESTABLISHMENT (HYDRAULIC METHOD)

Missouri River Contractors LLC $22,000.00 $22,000.00 Hamilton Construction Co. $10,000.00 $10,000.00

SLETTEN CONSTRUCTION COMPANY $5,000.00 $5,000.00

McMillen, Inc. $10,000.00 $10,000.00 CK May Excavating, Inc. $11,000.00 $11,000.00 Engineer's Estimate 1.0 ACRE $9,500.00 $9,500.00

19 out of 19Source Selection Information - See FAR 2.101 & 3.104

Project No: MT FLAP BOR 2980(1)

Project Name: Sun River Bridge Replacement

Schedule: X

Schedule Type: Options

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

Total Schedule - All Items

Missouri River Contractors LLC $329,475.00 Hamilton Construction Co. $442,818.60

SLETTEN CONSTRUCTION COMPANY $588,310.00

McMillen, Inc. $717,150.00 CK May Excavating, Inc. $993,150.00 Engineer's Estimate $523,850.00