This document contains a series of questions and answers related to a federal contract opportunity for the MT FLAP BOR 2980(1) Sun River Bridge Replacement project. The project involves constructing a new 3-span, 462-foot long precast-post-tensioned girder bridge with precast concrete deck approximately 200 feet downstream of the existing steel truss bridge. Additional work includes building new approaches on embankments and MSE walls, with final surfacing of gravel for the approaches and concrete on the bridge. The prospective contractor inquired about the use of cast-in-place concrete deck in lieu of prestressed deck panels, access to construction specifications, availability of geotechnical data, and the potential to add a turnaround area outside the construction limits. The government provided responses addressing these inquiries and noted that some project details would be amended or clarified. The contract opportunity is a sealed bid, firm-fixed-price solicitation with an estimated value between $10 million and $20 million, and a tentative completion date of Fall 2026.
View the file
Other files for this federal contract opportunity
Show all 45
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MT FLAP BOR 2980(1)
Sun River Bridge Replacement
# General Technical Question Answer Date
1 X
I see the preliminary plans have been posted and have reviewed them.
Would cast in place bridge deck be acceptable in lieu of the prestressed deck panels in the plans?
The preliminary documents posted on sam.gov have been posted to aid prospective bidders in identifying the location and type of work for this project. Please monitor the SAM site for the actual date of solicitation release (https://sam.gov/), and the duration of the advertisement period; and submit your questions during the advertisement period for the project. To receive automatic notification through SAM, you must login and select “Follow” feature and follow the steps as indicated.
8/15/2024
2 X I’m having a hard time finding the construction specifications. Can you point me to the right direction for sun river road replacement.
Please see page A-1 Notice to bidders of the IFB. You will find a link to the FP-14. see below:
THIS PROJECT IS BEING SOLICITED AND AWARDED UNDER FP-14.
The FP-14 is FLH’s Standard Specifications for Construction of Roads and Bridges on Federal Highway
Projects. To view the FP-14 electronically go to: https://highways.dot.gov/federal-lands/specs.
10/18/2024
3 X Is there a Geotech report for this project?
Yes, go to https://sam.gov/opp/44a9c9db98dc4caabf4f6507242c87d3/view
SAM: Update 10/18/2024: Due to technical error, some physical data files did not upload when the solicitation was initially posted. The remaining physical data files are available under Physical
Data_2.zip.
10/18/2024
4 X
I had a question regarding project MT FLAP BOR 2980(1). Attached is a kml file of the corner turn of the roadway to the existing bridge that’s outside the construction limits. Would we be able to disturb an area and add gravel for a turn-around for semi-trucks beginning at option X? The turn currently is too tight for equipment to turn around.
This will be addressed under Amendment A002 10/18/2024
5 X SCR 104.03(s) states “Optional cast-in-place concrete deck plan details and design calculations”.
Will there be a bid item added for this option?
Bid as shown. No bid item will be added for this options. If a Cast-in-Place deck alternative is proposed this would be evalutated under FP-14 SubSection 103.03 10/22/2024
6 X Given the logistical complexity and remote location of the project, we respectfully request a one-month extension to the bid.
The Government will not be extending the Bid Opening date. 10/22/2024