M6700425R0007 MCPP II DRAFT RFP 23 MAY 25.pdf

PDF 3 MB Posted

Attached to
Marine Corps Prepositioning Program (MCPP) II RFP Notification M6700426R0007
Solicitation number
M6700425R1301
Issued by

About this file

This document is a Draft Request for Proposal (RFP) for the Marine Corps Prepositioning Program (MCPP) Logistics Services Contract. The solicitation seeks a contractor to provide comprehensive logistics support services for Marine Corps prepositioned equipment and supplies across multiple global locations, including Maritime Prepositioning Ships (MPS), Norway, and the Philippines. The contract is an Indefinite Delivery/Indefinite Quantity (IDIQ) hybrid contract with a base period of five years and five optional years, allowing for task orders with various pricing structures including Cost Plus Fixed Fee (CPFF), Firm Fixed Price (FFP), and cost reimbursable elements.

Key services include maintenance management, supply chain management, inventory control, equipment preservation, transportation, container management, and support for military exercises and contingency operations. The contract will cover approximately 11,000 national stock numbered items totaling over 36 million pieces of equipment. The draft RFP indicates the government will issue a final solicitation on 19 May 2025, with an Industry Day scheduled for 24 June 2025 at Blount Island Command in Jacksonville, Florida. Interested contractors are encouraged to review the draft RFP and provide feedback by 3 July to the Contracting Officer, Timothy L. Rivers.

View the file

Other files

File Type Posted
Solicitation Amendment - M6700426R00070006.pdf PDF
Solicitation Amendment M6700426R00070006 SF 30.pdf PDF
ATCH J-5 Statement of Work SOW - Updtd Amd 0006.docx DOCX document
Solicitation Amendment - M6700426R00070005.pdf PDF
Solicitation Amendment M6700426R00070005 SF 30.pdf PDF
J_3_CBA_Wage_Rates_July_2026.pdf PDF
Solicitation Amendment - M6700426R00070004.pdf PDF
Solicitation Amendment M6700426R00070004 SF 30.pdf PDF
Solicitation Amendment M6700426R00070003 SF 30.pdf PDF
ATCH S-5 MCPP II RFP Q_A - Updtd Amd 0003.pdf PDF
ATCH J-7 MCPP Cost Model Workbook - Updtd Amd 0003.xlsx XLSX spreadsheet
Solicitation Amendment - M6700426R00070003.pdf PDF
ATCH J-5 Statement of Work SOW - Updtd Amd 0003.docx DOCX document
Solicitation Amendment - M6700426R00070002.pdf PDF
ATCH S-5 MCPP II RFP Q_A.pdf PDF
Solicitation Amendment M6700426R00070002 SF 30.pdf PDF
ATCH J-5 Statement of Work SOW Amend 2.docx DOCX document
Exh A-4 CDRL 2008-7010 MCPP NORWAY - Amend 1.pdf PDF
Exh A-3 CDRL 2003-11004 MCPP PHIL - Amend 1.pdf PDF
Solicitation Amendment - M6700426R00070001.pdf PDF
ATCH J-4 - DD Form 254 Amend 1.pdf PDF
ATCH J-5 Statement of Work SOW - Amend 1.docx DOCX document
Section J. Exh A - CDRLs List by CLIN - Amendment 1.xlsx XLSX spreadsheet
Exh A-13 CDRL 2004-11004 MCPP AUS and MCPP PALAU.pdf PDF
Solicitation Amendment M6700426R00070001 SF 30.pdf PDF
ATCH J-7 MCPP Cost Model Workbook - Amend 1.xlsx XLSX spreadsheet
ATCH S-2 MCPP II - NOTIONAL ORGANIZATION STRUCTURE - Amend 1.pdf PDF
MCPP Questions and Answers Part 2 dated 9.24.25.pdf PDF
MCPP Question and Answers Part 1 dtd 8.22.25.pdf PDF
MCPP II Industry Day Brief.pdf PDF
Industry DAY Questions dtd 7.25.25 Final.pdf PDF
MCPP II GOVT TO INDUSTRY QUESTIONS.xlsx XLSX spreadsheet
ATCH S-2 - RFP_INDUSTRY DAY QUESTION FORMAT.xlsx XLSX spreadsheet
Show all 33

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CODE

(Hour)

PAGE(S)

until 03:00 PM local t ime 24 Jun 2026

X

A X B X C X D

EX

X

G F 374 - 382

383 - 402 X H 403 - 408 timothy .l.rivers@usmc.mil

RATING PAGE OF PAGES

7. ISSUED BY

(Date)

IMPORTANT - Award will be made on this Form, or on Standard Form 26, or by other authorized official written notice.

Previous Edition is Unusable 33-134 STANDARD FORM 33 (REV. 9-97)

1 408

(If other than Item 7)

15A. NAME 16. NAME AND TITLE OF PERSON AUTHORIZED TO

AND

ADDRESS SIGN OFFER (Type or print)

OF

OFFEROR

AMENDMENT NO. DATE

15B. TELEPHONE NO (Include area code) 17. SIGNATURE15C. CHECK IF REMITTANCE ADDRESS

IS DIFFERENT FROM ABOVE - ENTER

SUCH ADDRESS IN SCHEDULE.

18. OFFER DATE

1. THIS CONTRACT IS A RATED ORDER

UNDER DPAS (15 CFR 700)

2. CONTRACT NO.

M67004 8. ADDRESS OFFER TO

See Item 7

9. Sealed offers in original and 7 copies for furnishing the supplies or services in the Schedule will be received at the place specified in Item 8, or if handcarried, in the depository located in

CAUTION - LATE Submissions, Modifications, and Withdrawals: See Section L, Provision No. 52.214-7 or 52.215-1. All offers are subject to all terms and

5880 Channel View Blvd.

conditions contained in this solicitation.

10. FOR INFORMATION

CALL:

A. NAME (NO COLLECT CALLS)

TIMOTHY RIVERS 906 696 5360

11. TABLE OF CONTENTS

SOLICITATION/ CONTRACT FORM

SUPPLIES OR SERVICES AND PRICES/ COSTS

1 - 2 3 - 36

X I CONTRACT CLAUSES

DESCRIPTION/ SPECS./ WORK STATEMENT X

PACKAGING AND MARKING

37 - 300 301 - 308

J LIST OF ATTACHMENTS

INSPECTION AND ACCEPTANCE

DELIVERIES OR PERFORMANCE

309 - 312

313 - 317 X K REPRESENTATIONS, CERTIFICATIONS AND

OTHER STATEMENTS OF OFFERORS

CONTRACT ADMINISTRATION DATA 318 - 324 X

SPECIAL CONTRACT REQUIREMENTS

OFFER (Must be fully completed by offeror) 325 - 335 X M

L INSTRS., CONDS., AND NOTICES TO OFFERORS

EVALUATION FACTORS FOR AWARD

NOTE: Item 12 does not apply if the solicitation includes the provisions at 52.214-16, Minimum Bid Acceptance Period.

is inserted by the offeror) from the date for receipt of offers specified above, to furnish any or all items upon which prices are offered at the price set opposite each item, delivered at the designated point(s), within the time specified in the schedule.

13. DISCOUNT FOR PROMPT PAYMENT

(See Section I, Clause No. 52.232-8)

14. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments

AMENDMENT NO. DATE

to the SOLICITATION for offerors and related documents numbered and dated):

FACILITY

12. In compliance with the above, the undersigned agrees, if this offer is accepted within calendar days (60 calendar days unless a different period

SOLICITATION, OFFER AND AWARD

X

(X) SEC. DESCRIPTION (X) SEC. DESCRIPTION PAGE(S)

PART I - THE SCHEDULE

26. NAME OF CONTRACTING OFFICER (Type or print) 27. UNITED STATES OF AMERICA 28. AWARD DATE

EMAIL:TEL: (Signature of Contracting Officer)

CODE CODE

B. TELEPHONE (Include area code) C. E-MAIL ADDRESS

AWARD (To be completed by Government)

19. ACCEPTED AS TO ITEMS NUMBERED 20. AMOUNT 21. ACCOUNTING AND APPROPRIATION

22. AUTHORITY FOR USING OTHER THAN FULL AND OPEN COMPETITION:

10 U.S.C. 2304(c)( ) 41 U.S.C. 253(c)( ) (4 copies unless otherwise specified)

23. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

24. ADMINISTERED BY (If other than Item 7) CODE 25. PAYMENT WILL BE MADE BY CODE

PART IV - REPRESENTATIO NS AND INSTRUCTIO NS

PART III - LIST O F DO CUMENTS, EXHIBITS AND O THER ATTACHMENTS

336 - 365

PART II - CO NTRACT CLAUSES

USMC BLOUNT ISLAND COMMAND

ATTN: TIMOTHY RIVERS

5880 CHANNEL VIEW BLVD

JACKSONVILLE FL 32226 904-696-5360

FAX:

TEL:

FAX:

TEL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

SOLICITATION

366 - 373

6. REQUISITION/PURCHASE NO.5. DATE ISSUED

26 Feb 2026

4. TYPE OF SOLICITATION

SEALED BID (IFB)

NEGOTIATED (RFP)

[ X ]

3. SOLICITATION NO.

M6700425R0007

DRAFT RFP

Section A - Solicitation/Contract Form

CLAUSES INCORPORATED BY REFERENCE

This draft Request for Proposal (RFP) is being issued solely to solicit feedback from industry. Interested parties are encouraged to review the questions posted to SAM.GOV and provide responses by 3 July, along with any comments on the draft RFP, to the Contracting Officer, Timothy L. Rivers, at timothy.l.rivers@usmc.mil. Please note that this is not a request for proposals at this time, and no submissions will be considered as such. Only the formal solicitation, once released, should be relied upon for the Government’s official requirements.

A-1 TYPE OF CONTRACT. This is a single award hybrid Indefinite Delivery Indefinite Quanty (IDIQ) contract with the flexibility to award task orders on a CPFF, FFP, and Cost Reimbursable (for Materials and Travel) basis as defined by the respective Contract Line Item Number/Sub Line Item Number (CLINs/SLINs) against which Task Orders will be issued.

A-2 ORDERING PERIODS AND CLIN NUMBERS

Base Ordering Period Year One (CLINs 0001-0007) Base Ordering Period Year Two (CLINs 1001-1007) Base Ordering Period Year Three (CLINs 2001-2007) Base Ordering Period Year Four (CLINs 3001-3007) Base Ordering Period Year Five (CLINs 4001-4007) Opt I Ordering Period Year Six (CLINs 5001-5007) Opt I Ordering Period Year Seven (CLINs 6001-6007) Opt I Ordering Period Year Eight (CLINs 7001-7007) Opt I Ordering Period Year Nine (CLINs 8001-8007) Opt I Ordering Period Year Ten (CLINs 9001-9007) 52.217-8 Ordering Period

Note: “X001” is used throughout the SOW where “X” indicates the ordering period 0 through 9 to correlate with the ordering periods as identified in paragraph 3 above.

Section B - Supplies or Services and Prices

Minimum and Maximum IDIQ Amounts

a. Minimum guarantee, base year award only: $10,000.00

b. Maximum: TBD at time of award based on total evaluated price. The maximum represents the potential cumulative total of all task orders issued under this contract under all ordering periods.

Funds shall be obligated by issuance of Task Orders for precise quantities.

CLIN # SOW Section Cost Constraint

CLIN TITLE Qty Unit Proposed or Govt Provided

X0001 C.1, C.2.A, C.2.B, C.2.C, and C.2.D.

Phase-Out (H-21)

FFP Program Management

12 Months Proposed

X0002 All of the SOW except for the sections identified in CLIN X001

CPFF LOE Maintenance Production

(CONUS)

To be provided by the Government

Hours *Government to provide labor category and hour breakdown.

Contractor to provide ceiling, labor and indirect rates.

X0003 All of the SOW except for the sections identified in CLIN X001

CPFF LOE Maintenance Production

(OCONUS)

To be provided by the Government

Hours *Government to provide labor category and hour breakdown.

Contractor to provide ceiling, labor and indirect rates.

X0004 All of the SOW except for the sections identified in CLIN X001

CPFF LOE Other logistics Support

To be provided by the Government

Hours Govt Provided

X0005 H.10 CPFF LOE Travel * Lot Govt Provided X0006 CPFF LOE Other Direct Cost * Lot Govt Provided X0007 Section J Not Separately

Priced CDRLS NSP Govt Provided

00008 H-21 FFP Transition Period 3 Months Proposed

*Estimated hours for purpose of draft RFP, subject to change.

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 12 Months Program Management

FFP

Base Ordering Period One- The MCMC shall provide Program and Risk Management support in accordance with Section C.1, C.2.A, C.2.B, C.2.C, and C.2.D of the attached Statement of Work. Phase-Out (H-21) requirements shall also be captured under this FFP CLIN.

FOB: Destination

PSC CD: R706

NET AMT

ITEM NO SUPPLIES/SERVICES MAX

QUANTITY

UNIT UNIT PRICE MAX AMOUNT

0002 Hours Maintenance Production (CONUS)

CPFF

Base Ordering Period One - The MCMC shall provide all necessary resources to execute all tasks and responsibilities to the established standards in accordance with and all Maintenance Activities of the attached Statement of Work.

CPFF Level of Effort IAW FAR 16.306(d)(2)

MAX COST

FIXED FEE

TOTAL MAX COST + FEE

UNIT UNIT PRICE MAX AMOUNT

0003 Hours Maintenance Production (OCONUS)

CPFF

Base Ordering Period One - The MCMC shall provide all necessary resources to execute all tasks and responsibilities to the established standards in accordance with all Maintenance Activities of the attached Statement of Work.

CPFF Level of Effort IAW FAR 16.306(d)(2)

UNIT UNIT PRICE MAX AMOUNT

0004 Hours Other Logistics Support

CPFF

Base Ordering Period One - The MCMC shall provide Contingency/Exercise/Emerging Requirements support in accordance with the attached Statement of Work.

CPFF Level of Effort IAW FAR 16.306(d)(2)

Overtime Premium shall not be subject to fee. Contingency/Exercise/Emerging Requirements Fixed Fee will be determined upon authorization of work in accordance with Section H-8.3: "The same ratio of fee awarded in the initial contract award will be used in any task orders issued."FOB: Destination

UNIT UNIT PRICE MAX AMOUNT

0005 Task Travel

COST

Base Ordering Period One – Fee or any markups shall not be applied to Travel.

UNIT UNIT PRICE MAX AMOUNT

0006 Unit Other Direct Costs

COST

Base Ordering Period Year One – Fee shall not be applied to Other Direct Costs.

UNIT UNIT PRICE MAX AMOUNT

0007 Unit Data Requirements / CDRLs

NSP

Base Ordering Period Year One-The MCMC shall provide all data requirements, reports, and submittals using DD Form 1423-1 as established in the SOW. (SEE Contract Attachment #9) Data Requirements are Not Separately Priced.

0008 Hours Contract Transition

FFP

For Phase-in services

1001 12 Months Program Management

FFP

Base Ordering Period One- The MCMC shall provide Program and Risk Management support in accordance with Section C.1, C.2.A, C.2.B, C.2.C, and C.2.D of the attached Statement of Work. Phase-Out (H-21) requirements shall also be captured under this FFP CLIN.

UNIT UNIT PRICE MAX AMOUNT

1002 Hours Maintenance Production (CONUS)

CPFF

Base Ordering Period One - The MCMC shall provide all necessary resources to execute all tasks and responsibilities to the established standards in accordance with and all Maintenance Activities of the attached Statement of Work.

CPFF Level of Effort IAW FAR 16.306(d)(2)

UNIT UNIT PRICE MAX AMOUNT

1003 Hours Maintenance Production (OCONUS)

CPFF

Base Ordering Period One - The MCMC shall provide all necessary resources to execute all tasks and responsibilities to the established standards in accordance with all Maintenance Activities of the attached Statement of Work.

CPFF Level of Effort IAW FAR 16.306(d)(2)

UNIT UNIT PRICE MAX AMOUNT

1004 Hours Other Logistics Support

CPFF

Base Ordering Period One - The MCMC shall provide Contingency/Exercise/Emerging Requirements support in accordance with the attached Statement of Work.

CPFF Level of Effort IAW FAR 16.306(d)(2)

Overtime Premium shall not be subject to fee. Contingency/Exercise/Emerging Requirements Fixed Fee will be determined upon authorization of work in accordance with Section H-8.3: "The same ratio of fee awarded in the initial

UNIT UNIT PRICE MAX AMOUNT

1005 Task Travel

COST

Base Ordering Period One – Fee or any markups shall not be applied to Travel.

UNIT UNIT PRICE MAX AMOUNT

1006 Unit Other Direct Costs

COST

Base Ordering Period Year One – Fee shall not be applied to Other Direct Costs.

UNIT UNIT PRICE MAX AMOUNT

1007 Unit Data Requirements / CDRLs

NSP

Base Ordering Period Year One-The MCMC shall provide all data requirements, reports, and submittals using DD Form 1423-1 as established in the SOW. (SEE Contract Attachment #9) Data Requirements are Not Separately Priced.

2001 12 Months Program Management

FFP

Base Ordering Period One- The MCMC shall provide Program and Risk Management support in accordance with Section C.1, C.2.A, C.2.B, C.2.C, and C.2.D of the attached Statement of Work. Phase-Out (H-21) requirements shall also be captured under this FFP CLIN.

UNIT UNIT PRICE MAX AMOUNT

2002 Hours Maintenance Production (CONUS)

CPFF

Base Ordering Period One - The MCMC shall provide all necessary resources to execute all tasks and responsibilities to the established standards in accordance with and all Maintenance Activities of the attached Statement of Work.

CPFF Level of Effort IAW FAR 16.306(d)(2)

UNIT UNIT PRICE MAX AMOUNT

2003 Hours Maintenance Production (OCONUS)

CPFF

Base Ordering Period One - The MCMC shall provide all necessary resources to execute all tasks and responsibilities to the established standards in accordance with all Maintenance Activities of the attached Statement of Work.

CPFF Level of Effort IAW FAR 16.306(d)(2)

UNIT UNIT PRICE MAX AMOUNT

2004 Hours Other Logistics Support

CPFF

Base Ordering Period One - The MCMC shall provide Contingency/Exercise/Emerging Requirements support in accordance with the attached Statement of Work.

CPFF Level of Effort IAW FAR 16.306(d)(2)

Overtime Premium shall not be subject to fee. Contingency/Exercise/Emerging Requirements Fixed Fee will be determined upon authorization of work in accordance with Section H-8.3: "The same ratio of fee awarded in the initial

UNIT UNIT PRICE MAX AMOUNT

2005 Task Travel

COST

Base Ordering Period One – Fee or any markups shall not be applied to Travel.

UNIT UNIT PRICE MAX AMOUNT

2006 Unit Other Direct Costs

COST

Base Ordering Period Year One – Fee shall not be applied to Other Direct Costs.

UNIT UNIT PRICE MAX AMOUNT

2007 Unit Data Requirements / CDRLs

NSP

Base Ordering Period Year One-The MCMC shall provide all data requirements, reports, and submittals using DD Form 1423-1 as established in the SOW. (SEE Contract Attachment #9) Data Requirements are Not Separately Priced.

3001 12 Months Program Management

FFP

Base Ordering Period One- The MCMC shall provide Program and Risk Management support in accordance with Section C.1, C.2.A, C.2.B, C.2.C, and C.2.D of the attached Statement of Work. Phase-Out (H-21) requirements shall also be captured under this FFP CLIN.

UNIT UNIT PRICE MAX AMOUNT

3002 Hours Maintenance Production (CONUS)

CPFF

Base Ordering Period One - The MCMC shall provide all necessary resources to execute all tasks and responsibilities to the established standards in accordance with and all Maintenance Activities of the attached Statement of Work.

CPFF Level of Effort IAW FAR 16.306(d)(2)

UNIT UNIT PRICE MAX AMOUNT

3003 Hours Maintenance Production (OCONUS)

CPFF

Base Ordering Period One - The MCMC shall provide all necessary resources to execute all tasks and responsibilities to the established standards in accordance with all Maintenance Activities of the attached Statement of Work.

CPFF Level of Effort IAW FAR 16.306(d)(2)

UNIT UNIT PRICE MAX AMOUNT

3004 Hours Other Logistics Support

CPFF

Base Ordering Period One - The MCMC shall provide Contingency/Exercise/Emerging Requirements support in accordance with the attached Statement of Work.

CPFF Level of Effort IAW FAR 16.306(d)(2)

Overtime Premium shall not be subject to fee. Contingency/Exercise/Emerging Requirements Fixed Fee will be determined upon authorization of work in accordance with Section H-8.3: "The same ratio of fee awarded in the initial

UNIT UNIT PRICE MAX AMOUNT

3005 Task Travel

COST

Base Ordering Period One – Fee or any markups shall not be applied to Travel.

UNIT UNIT PRICE MAX AMOUNT

3006 Unit Other Direct Costs

COST

Base Ordering Period Year One – Fee shall not be applied to Other Direct Costs.

UNIT UNIT PRICE MAX AMOUNT

3007 Unit Data Requirements / CDRLs

NSP

Base Ordering Period Year One-The MCMC shall provide all data requirements, reports, and submittals using DD Form 1423-1 as established in the SOW. (SEE Contract Attachment #9) Data Requirements are Not Separately Priced.

4001 12 Months Program Management

FFP

Base Ordering Period One- The MCMC shall provide Program and Risk Management support in accordance with Section C.1, C.2.A, C.2.B, C.2.C, and C.2.D of the attached Statement of Work. Phase-Out (H-21) requirements shall also be captured under this FFP CLIN.

UNIT UNIT PRICE MAX AMOUNT

4002 Hours Maintenance Production (CONUS)

CPFF

Base Ordering Period One - The MCMC shall provide all necessary resources to execute all tasks and responsibilities to the established standards in accordance with and all Maintenance Activities of the attached Statement of Work.

CPFF Level of Effort IAW FAR 16.306(d)(2)

UNIT UNIT PRICE MAX AMOUNT

4003 Hours Maintenance Production (OCONUS)

CPFF

Base Ordering Period One - The MCMC shall provide all necessary resources to execute all tasks and responsibilities to the established standards in accordance with all Maintenance Activities of the attached Statement of Work.

CPFF Level of Effort IAW FAR 16.306(d)(2)

UNIT UNIT PRICE MAX AMOUNT

4004 Hours Other Logistics Support

CPFF

Base Ordering Period One - The MCMC shall provide Contingency/Exercise/Emerging Requirements support in accordance with the attached Statement of Work.

CPFF Level of Effort IAW FAR 16.306(d)(2)

Overtime Premium shall not be subject to fee. Contingency/Exercise/Emerging Requirements Fixed Fee will be determined upon authorization of work in accordance with Section H-8.3: "The same ratio of fee awarded in the initial

UNIT UNIT PRICE MAX AMOUNT

4005 Task Travel

COST

Base Ordering Period One – Fee or any markups shall not be applied to Travel.

UNIT UNIT PRICE MAX AMOUNT

4006 Unit Other Direct Costs

COST

Base Ordering Period Year One – Fee shall not be applied to Other Direct Costs.

UNIT UNIT PRICE MAX AMOUNT

4007 Unit Data Requirements / CDRLs

NSP

Base Ordering Period Year One-The MCMC shall provide all data requirements, reports, and submittals using DD Form 1423-1 as established in the SOW. (SEE Contract Attachment #9) Data Requirements are Not Separately Priced.

5001 12 Months OPTION Program Management

FFP

Base Ordering Period Two- The MCMC shall provide Program and Risk Management support in accordance with Section C.1, C.2.A, C.2.B, C.2.C, and C.2.D of the attached Statement of Work. Phase-Out (H-21) requirements shall also be captured under this FFP CLIN.

UNIT UNIT PRICE MAX AMOUNT

5002 Hours OPTION Maintenance Production (CONUS)

CPFF

Base Ordering Period Two - The MCMC shall provide all necessary resources to execute all tasks and responsibilities to the established standards in accordance with and all Maintenance Activities of the attached Statement of Work.

CPFF Level of Effort IAW FAR 16.306(d)(2)

UNIT UNIT PRICE MAX AMOUNT

5003 Hours OPTION Maintenance Production (OCONUS)

CPFF

Base Ordering Period Two - The MCMC shall provide all necessary resources to execute all tasks and responsibilities to the established standards in accordance with all Maintenance Activities of the attached Statement of Work.

CPFF Level of Effort IAW FAR 16.306(d)(2)

UNIT UNIT PRICE MAX AMOUNT

5004 Hours OPTION Other Logistics Support

CPFF

Base Ordering Period Two - The MCMC shall provide Contingency/Exercise/Emerging Requirements support in accordance with the attached Statement of Work.

CPFF Level of Effort IAW FAR 16.306(d)(2)

Overtime Premium shall not be subject to fee. Contingency/Exercise/Emerging Requirements Fixed Fee will be determined upon authorization of work in accordance with Section H-8.3: "The same ratio of fee awarded in the initial

UNIT UNIT PRICE MAX AMOUNT

5005 Task OPTION Travel

COST

Base Ordering Period Two – Fee or any markups shall not be applied to Travel.

UNIT UNIT PRICE MAX AMOUNT

5006 Unit OPTION Other Direct Costs

COST

Base Ordering Period Year Two – Fee shall not be applied to Other Direct Costs.

UNIT UNIT PRICE MAX AMOUNT

5007 Unit OPTION Data Requirements / CDRLs

NSP

Base Ordering Period Year Two-The MCMC shall provide all data requirements, reports, and submittals using DD Form 1423-1 as established in the SOW. (SEE Contract Attachment #9) Data Requirements are Not Separately Priced.

6001 12 Months OPTION Program Management

FFP

Base Ordering Period Two- The MCMC shall provide Program and Risk Management support in accordance with Section C.1, C.2.A, C.2.B, C.2.C, and C.2.D of the attached Statement of Work. Phase-Out (H-21) requirements shall also be captured under this FFP CLIN.

UNIT UNIT PRICE MAX AMOUNT

6002 Hours OPTION Maintenance Production (CONUS)

CPFF

Base Ordering Period Two - The MCMC shall provide all necessary resources to execute all tasks and responsibilities to the established standards in accordance with and all Maintenance Activities of the attached Statement of Work.

CPFF Level of Effort IAW FAR 16.306(d)(2)

UNIT UNIT PRICE MAX AMOUNT

6003 Hours OPTION Maintenance Production (OCONUS)

CPFF

Base Ordering Period Two - The MCMC shall provide all necessary resources to execute all tasks and responsibilities to the established standards in accordance with all Maintenance Activities of the attached Statement of Work.

CPFF Level of Effort IAW FAR 16.306(d)(2)

UNIT UNIT PRICE MAX AMOUNT

6004 Hours OPTION Other Logistics Support

CPFF

Base Ordering Period Two - The MCMC shall provide Contingency/Exercise/Emerging Requirements support in accordance with the attached Statement of Work.

CPFF Level of Effort IAW FAR 16.306(d)(2)

Overtime Premium shall not be subject to fee. Contingency/Exercise/Emerging Requirements Fixed Fee will be determined upon authorization of work in accordance with Section H-8.3: "The same ratio of fee awarded in the initial

UNIT UNIT PRICE MAX AMOUNT

6005 Task OPTION Travel

COST

Base Ordering Period Two – Fee or any markups shall not be applied to Travel.

UNIT UNIT PRICE MAX AMOUNT

6006 Unit OPTION Other Direct Costs

COST

Base Ordering Period Year Two – Fee shall not be applied to Other Direct Costs.

UNIT UNIT PRICE MAX AMOUNT

6007 Unit OPTION Data Requirements / CDRLs

NSP

Base Ordering Period Year Two-The MCMC shall provide all data requirements, reports, and submittals using DD Form 1423-1 as established in the SOW. (SEE Contract Attachment #9) Data Requirements are Not Separately Priced.

7001 12 Months OPTION Program Management

FFP

Base Ordering Period Two- The MCMC shall provide Program and Risk Management support in accordance with Section C.1, C.2.A, C.2.B, C.2.C, and C.2.D of the attached Statement of Work. Phase-Out (H-21) requirements shall also be captured under this FFP CLIN.

UNIT UNIT PRICE MAX AMOUNT

7002 Hours OPTION Maintenance Production (CONUS)

CPFF

Base Ordering Period Two - The MCMC shall provide all necessary resources to execute all tasks and responsibilities to the established standards in accordance with and all Maintenance Activities of the attached Statement of Work.

CPFF Level of Effort IAW FAR 16.306(d)(2)

UNIT UNIT PRICE MAX AMOUNT

7003 Hours OPTION Maintenance Production (OCONUS)

CPFF

Base Ordering Period Two - The MCMC shall provide all necessary resources to execute all tasks and responsibilities to the established standards in accordance with all Maintenance Activities of the attached Statement of Work.

CPFF Level of Effort IAW FAR 16.306(d)(2)

UNIT UNIT PRICE MAX AMOUNT

7004 Hours OPTION Other Logistics Support

CPFF

Base Ordering Period Two - The MCMC shall provide Contingency/Exercise/Emerging Requirements support in accordance with the attached Statement of Work.

CPFF Level of Effort IAW FAR 16.306(d)(2)

Overtime Premium shall not be subject to fee. Contingency/Exercise/Emerging Requirements Fixed Fee will be determined upon authorization of work in accordance with Section H-8.3: "The same ratio of fee awarded in the initial

UNIT UNIT PRICE MAX AMOUNT

7005 Task OPTION Travel

COST

Base Ordering Period Two – Fee or any markups shall not be applied to Travel.

UNIT UNIT PRICE MAX AMOUNT

7006 Unit OPTION Other Direct Costs

COST

Base Ordering Period Year Two – Fee shall not be applied to Other Direct Costs.

UNIT UNIT PRICE MAX AMOUNT

7007 Unit OPTION Data Requirements / CDRLs

NSP

Base Ordering Period Year Two-The MCMC shall provide all data requirements, reports, and submittals using DD Form 1423-1 as established in the SOW. (SEE Contract Attachment #9) Data Requirements are Not Separately Priced.

8001 12 Months OPTION Program Management

FFP

Base Ordering Period Two- The MCMC shall provide Program and Risk Management support in accordance with Section C.1, C.2.A, C.2.B, C.2.C, and C.2.D of the attached Statement of Work. Phase-Out (H-21) requirements shall also be captured under this FFP CLIN.

UNIT UNIT PRICE MAX AMOUNT

8002 Hours OPTION Maintenance Production (CONUS)

CPFF

Base Ordering Period Two - The MCMC shall provide all necessary resources to execute all tasks and responsibilities to the established standards in accordance with and all Maintenance Activities of the attached Statement of Work.

CPFF Level of Effort IAW FAR 16.306(d)(2)

UNIT UNIT PRICE MAX AMOUNT

8003 Hours OPTION Maintenance Production (OCONUS)

CPFF

Base Ordering Period Two - The MCMC shall provide all necessary resources to execute all tasks and responsibilities to the established standards in accordance with all Maintenance Activities of the attached Statement of Work.

CPFF Level of Effort IAW FAR 16.306(d)(2)

UNIT UNIT PRICE MAX AMOUNT

8004 Hours OPTION Other Logistics Support

CPFF

Base Ordering Period Two - The MCMC shall provide Contingency/Exercise/Emerging Requirements support in accordance with the attached Statement of Work.

CPFF Level of Effort IAW FAR 16.306(d)(2)

Overtime Premium shall not be subject to fee. Contingency/Exercise/Emerging Requirements Fixed Fee will be determined upon authorization of work in accordance with Section H-8.3: "The same ratio of fee awarded in the initial

UNIT UNIT PRICE MAX AMOUNT

8005 Task OPTION Travel

COST

Base Ordering Period Two – Fee or any markups shall not be applied to Travel.

UNIT UNIT PRICE MAX AMOUNT

8006 Unit OPTION Other Direct Costs

COST

Base Ordering Period Year Two – Fee shall not be applied to Other Direct Costs.

UNIT UNIT PRICE MAX AMOUNT

8007 Unit OPTION Data Requirements / CDRLs

NSP

Base Ordering Period Year Two-The MCMC shall provide all data requirements, reports, and submittals using DD Form 1423-1 as established in the SOW. (SEE Contract Attachment #9) Data Requirements are Not Separately Priced.

9001 12 Months OPTION Program Management

FFP

Base Ordering Period Two- The MCMC shall provide Program and Risk Management support in accordance with Section C.1, C.2.A, C.2.B, C.2.C, and C.2.D of the attached Statement of Work. Phase-Out (H-21) requirements shall also be captured under this FFP CLIN.

UNIT UNIT PRICE MAX AMOUNT

9002 Hours OPTION Maintenance Production (CONUS)

CPFF

Base Ordering Period Two - The MCMC shall provide all necessary resources to execute all tasks and responsibilities to the established standards in accordance with and all Maintenance Activities of the attached Statement of Work.

CPFF Level of Effort IAW FAR 16.306(d)(2)

UNIT UNIT PRICE MAX AMOUNT

9003 Hours OPTION Maintenance Production (OCONUS)

CPFF

Base Ordering Period Two - The MCMC shall provide all necessary resources to execute all tasks and responsibilities to the established standards in accordance with all Maintenance Activities of the attached Statement of Work.

CPFF Level of Effort IAW FAR 16.306(d)(2)

UNIT UNIT PRICE MAX AMOUNT

9004 Hours OPTION Other Logistics Support

CPFF

Base Ordering Period Two - The MCMC shall provide Contingency/Exercise/Emerging Requirements support in accordance with the attached Statement of Work.

CPFF Level of Effort IAW FAR 16.306(d)(2)

Overtime Premium shall not be subject to fee. Contingency/Exercise/Emerging Requirements Fixed Fee will be determined upon authorization of work in accordance with Section H-8.3: "The same ratio of fee awarded in the initial

UNIT UNIT PRICE MAX AMOUNT

9005 Task OPTION Travel

COST

Base Ordering Period Two – Fee or any markups shall not be applied to Travel.

UNIT UNIT PRICE MAX AMOUNT

9006 Unit OPTION Other Direct Costs

COST

Base Ordering Period Year Two – Fee shall not be applied to Other Direct Costs.

UNIT UNIT PRICE MAX AMOUNT

9007 Unit OPTION Data Requirements / CDRLs

NSP

Base Ordering Period Year Two-The MCMC shall provide all data requirements, reports, and submittals using DD Form 1423-1 as established in the SOW. (SEE Contract Attachment #9) Data Requirements are Not Separately Priced.

Section C - Descriptions and Specifications-

UNITED STATES MARINE CORPS

BLOUNT ISLAND COMMAND

STATEMENT OF WORK (SOW)

FOR THE

MARINE CORPS PREPOSITIONING PROGRAM

LOGISTICS SERVICES CONTRACT

STATEMENT OF WORK

CONSTRUCT

1.0 MCPP PROGRAM REQUIREMENTS OVERVIEW

1.A Background 1.B Overall MCPP Scope 1.C Work Requirements 1.D Program Complexity 1.E Program Operational Objective 1.F Organizational Responsibility 1.G Contract Authority 1.H Personnel 1.I Equipment and Materiel Accountability 1.J Government Furnished Property (GFP) and Services 1.K References, Publications, Forms and Reports 1.L Rights in Data 1.M Applicable Publications/Source Documents 1.N Acronyms

2.0 PROGRAM AND RISK MANAGEMENT

2.A MPS Plans and Data 2.B Maintenance Management 2.C Business Intelligence and Key Performance Indicators (KPI’s) 2.D Risk and Performance

3.0 MAINTENANCE ACTIVITIES

4.0 SUPPLY

4.A Supply Demand Planning & Monitoring of Materiel Requirements/ Shortfalls 4.B Procurement and Sourcing 4.C Inventory Management 4.D MMC Supply Production Operations 4.E T-AKE Supply Operations 4.F ISO Freight Container Inventory and Maintenance 4.G Transportation and Distribution Management Operations (TMO/DMO) 4.H Supply Fiscal Requirements 4.I Exemptions and Waivers

5.0 MEDICAL

6.0 NAVY

6.A Navy Services 6.B Navy Fiscal Requirements

6.C Navy Supply Chain, Logistics, and Warehousing 6.D Navy Containerized CAPSET Production 6.E Navy Civil Engineering Support Equipment (CESE) 6.F Navy Watercraft (Lighterage) Ashore (Phase Bravo, Charlie & Delta) 6.G External Contracts Support 6.H Navy Watercraft Controls System Support (CSS) 6.I Navy Exemptions, Deviations and Waivers 6.J Navy Shipboard Support 6.K Navy MPS Plans and Data 6.L Navy Exercise and Surge Support 6.M Navy MPS Embarkation/Debarkation Support 6.N Navy Organic Ground Support Equipment (GSE) Maintenance 6.O Navy Business and Performance Requirements 6.P Navy Mobile Load Requirements 6.Q Navy Weight Handling Equipment (WHE) Program 6.R Navy Planning & Estimating Requirements 6.S Navy Safety Requirements 6.T Navy Environmental Requirements

7.0 SHIPBOARD

8.0 KEY MANAGEMENT INFRASTRUCTURE

8.A Administrative Requirements 8.B Inventory and Accountability 8.C Storage, Handling, and Transportation 8.D Maintenance 8.E Training

9.0 PORT OPERATIONS SUPPORT

9.A Port Operations and Embarkation Support 9.B Fuel Level Requirements 9.C Vehicles and Equipment

10.0 INSTALLATION SUPPORT SERVICES

10.A Equipment Support and Management 10.B Safety Requirements 10.C Environmental

11.0 COMMUNICATION SUPPORT SYSTEMS

SECTION C.1 MCPP PROGRAM REQUIREMENT OVERVIEW

1.A BACKGROUND

1.A.1 The Maritime Prepositioning Ships (MPS) program was initiated by the Secretary of Defense in August 1979 creating a new option for increasing the responsiveness of Marine Corps operating forces requiring immediate and rapid deployment. The program requires the prepositioning of equipment and supplies aboard nine Navy owned ships strategically located around the world. Seven of the ships are located in the Indian and Pacific Oceans and two ships are located in Jacksonville, FL. Maritime Prepositioning Force (MPF) is a term utilized to describe the combat capability derived when combining a Marine operating force and associated fly-in echelon (FIE) with the assets loaded aboard the MPSs. Combined, these ships carry equipment and supplies to support approximately 18000 Marines and Sailors for up to 30 days of sustained combat. Equipment and supplies include, but are not limited to; trucks, trailers, generators, watercraft, radios, ordnance equipment, tool kits, crew-served weapons, ammunition, rations, medical supplies, fuel, and water. Smaller prepositioned sets of equipment and supplies (E/S) are maintained in six caves in central Norway as part of the Marine Corps Prepositioning Program – Norway (MCPP-N). A new Program of Record (POR) consisting of a humanitarian assistance/disaster relief (HA/DR) equipment is prepositioned in the Philippines, known as Marine Corps Prepositioning Program – Philippines (MCPP-PHIL). MCPP-PHIL contains specific USMC designed equipment and supplies to provide operating forces with equipment required to conduct various training exercises and contingency operations. Equipment is maintained and issued/recovered, at the direction of Headquarters Marine Corps by Blount Island Command (BIC). Additional prepositioning sites are being considered in Australia and Palau and are undergoing review at HQMC. Continental United States (CONUS) based support for this entire program is conducted at Blount Island, Jacksonville, Florida.

1.A.2 The breadth and depth of the E/S prepositioned (over 11,000 national stock numbered items totaling slightly over 36 million pieces) provides significant capability and flexibility, enabling the combatant commander to conduct numerous crisis response missions. The concept of combining the speed of strategic airlift with the storage capacity of prepositioned sealift has greatly reduced force closure times in response to contingency scenarios. Under the MPS concept, the ships will be staged, in advance, near the vicinity of a possible crisis area. If deployment is ordered, the ships would move to a rendezvous point to link up with Marine Corps personnel flown to the area by the U. S. Air Force’s Air Mobility Command. The equipment would be quickly downloaded and assigned to combat and support units which then would proceed to the objective area. On 12 March 1983, the Commandant of the Marine Corps (CMC) directed the Marine Corps Support Base, Atlantic, hereinafter referred to in its present name, the Marine Corps Logistics Command (LOGCOM), to contract for logistics services in support of prepositioned assets. Therefore, a contracted civilian maintenance crew living aboard the ships and at a CONUS industrial facility, would be responsible for performing a wide range and depth of logistics functions such as preventative and intermediate level corrective maintenance, limited depot level repair (up to 4th echelon depot-level maintenance), equipment modifications, stock rotation, calibration, inventory management, management of support systems, supply support, asset visibility and transportation management to include in-transit visibility. The MPS program requires logistics efforts to be accomplished aboard ship, in port areas around the world, and at an industrial facility located on Marine Corps Support Facility Blount Island (MCSF-BI), Jacksonville, Florida during the MPF Maintenance Cycle (MMC). The Statement of Work (SOW) is applicable to both port areas and shipboard activities. Each ship E/S set is tailored to maximize combat capability and disaster relief options for the combatant commanders.

1.A.3 In 1981, the United States and the Kingdom of Norway signed a bilateral agreement establishing the Norway Air-Landed Marine Expeditionary Brigade (NALMEB) prepositioning program. The NALMEB program reached initial operating capability (IOC) in January 1990 with the prepositioning of E/S in three equipment caves, three ammunition caves, and two above ground storage hangars. Shortly thereafter, the collapse of the Soviet Union lessened the military threat to the North Atlantic Treaty Organization (NATO) northern flank and the program’s relevance in its intended role became less critical. Subsequently, the program's role and importance to Norway continued to grow and in 1995, Norway assumed a 50% cost sharing arrangement with the Marine Corps. Throughout the 1990’s the program was used to support NATO out of area missions in support of operations in the Balkans and the first Gulf War.

NALMEB assets were withdrawn beginning in 2003 through 2005 in support of Operation Iraqi Freedom, MPS reconstitution, and to address home station shortfalls for garrison-based Marine forces. In January 2005, the Commandant announced that a prepositioning program would remain in Norway, continue to maintain support to defend Norway, and be capable of deploying globally. The approved name was changed to the Marine Corps Prepositioning Program – Norway (MCPP-N). The Secretary of Defense and the Norwegian Minister of Defense signed a new Memorandum of Understanding Governing Pre-stockage and Reinforcement of Norway on 8 June 2005. MCPP-N serves multiple activities and missions capable of global support to all Geographic Combatant Commanders (GCCs). E/S are stored for selective withdrawal and movement and can be tailored to meet multiple tasks. Logistics services conducted in Norway are performed by Norwegian Ministry of Defense (MOD) personnel from the Norwegian Defense Logistics Organization / Marine Expeditionary Brigade (NDLO/MEB) with one exception. Section C.8 details Marine Corps Maintenance Contractor (MCMC) support for Key Management Infrastructure (KMI) stored in Norway. The MCMC also provides inventory management, and shipping and receiving services in support of assets being shipped to or returned from Norway. Maintenance services are provided on the Norway assets stored on or passing through MCSF-BI. In addition, the MCMC may be tasked to provide specialized equipment expertise to and/or assist in increased maintenance or supply requirements in support of the NDLO/MEB personnel.

1.A.4 In order to meet emerging crisis response and theater engagement requirements worldwide, the Marine Corps may explore options to initiate other land-based prepositioning programs overseas. The MCMC may be tasked to provide logistics services in support of these initiatives, such as maintenance, supply/inventory management, and transportation/distribution.

1.A.5 In 1990, all 13 prepositioning ships existing at the time were downloaded in preparation for the first Gulf War in Saudi Arabia. The downloads in Southwest Asia left the workforce at Blount Island idle, which resulted substantial reduction of the MCMC CONUS support requirements and subsequent Partial Termination for Convenience. Upon conclusion of the conflict, approximately 45% of the skilled workforce did not return to the program resulting in several adverse consequences and extended the recovery time of the program by several years.

In an effort to mitigate that situation from recurring, all subsequent contracts including this procurement contain provisions for the MCMC to provide Other Logistics Services to the Marine Corps.

1.A.6 In 2022 DON and HQMC made the decision to reduce the number of Full Operating Status (FOS) ships from twelve to the current seven ships, with two ships in a Reduced Operating Status (ROS). As a result, ships in excess of the FOS requirement were rotated back to BICmd where their stocks were downloaded and either utilized for other prepositioning requirements, held for potential future prepositioning requirements, or redistributed to other units or locations. The term Global Positioning Network (GPN) was introduced during this period and refers to an overarching umbrella of the combination of prepositioning stocks, fleet operating stocks, and the maritime and aerial connectors to connect the nodes.

1.A.7 In 2024, HQMC directed the establishment of the Marine Corps Prepositioning Program Philippines (MCPP-PHIL). The new ashore site, located in the Subic Bay Metropolitan Authority (SBMA) Freeport zone within the Republic of the Philippines, includes communication radio systems, engineer equipment systems, and light, medium and heavy trucks.

The MCPP-PHIL PO aims to create operationally relevant capabilities supporting FMF campaigning and provide support to Commander, INDOPACIFIC theater campaign objectives.

MCPP-PHIL PO establishment consisted of a phased and incremental approach that aligned service-wide actions with resources and host nation authorizations. A portion of the PO supports humanitarian assistance/disaster relief (HA/DR) as an equipment set with associated sustainment was shipped to Subic Bay Philippines after the coordinating all necessary host nation agreements in December of 2024. The equipment arrived at SBMA in February of 2025, and the first PO equipment withdrawal occurred in March 2025.

1.A.8 The primary effort of all work shall be accomplished at the Marine Corps Support Facility Blount Island (MCSF-BI), Jacksonville, Florida utilizing Government provided facilities, Government-furnished equipment/materials (GFE/M), and MCMC employee provided common hand tools (reference Collective Bargining Agreement (CBA) Contract attachment (10) The MMC facilities are Government Furnished Facilities (GFF) and are located at MCSF-BI, Jacksonville, Florida. Facility maintenance of the acreage and buildings is the responsibility of the MCSF-BI which has contracted through the Navy Region Southeast service provider for roads, grounds, and building support. The Commanding Officer (CO), Blount Island Command (BICmd) is also the CO, MCSF-BI. The MCMC performs Government Furnished Equipment (GFE) maintenance, repair and self-help efforts as delineated in this SOW. The MCMC shall not use Prepositioning Objective (PO) equipment and supplies for the purpose of organic support without prior government approval. The list of GFE is in Contract Attachment 6.a. The list of GFF is in Contract Attachment 6.b. The MCMC is responsible for the efficient and economical use of the facilities and equipment provided by the Marine Corps in the performance of contractual tasks. The MCMC shall coordinate new requirements for space, modifications to existing assigned space, changes to the facilities and/or equipment with the Facility Planning Committee, BICmd/MCSF-BI. The MCMC is responsible for operations which provide support to all organizations on the Installation, e.g., wash rack and fueling, and will be required to share, with Government coordination, some facilities with other Installation organizations, e.g., Corrosion Repair Facility and some staging areas. MCMC is expected to exhibit workplace organization and hygiene in the appearance of their assigned workspaces and is responsible for maintaining professional workplace appearance commensurate with that expected on a United States Marine Corps (USMC) installation. Additionally, the MCMC is responsible for user level maintenance in those facilities where they operate which includes pickup of trash/debris and placement in appropriate receptacles, emptying of most receptacles in industrial areas, and occasional dusting, sweeping, wiping, and cleaning of industrial workspace floors, walls, and other surfaces. Sweeping, mopping, and trash receptacle pickup for administrative areas are provided by the Government.

1.A.8.A. Most of the MCPP-N services shall be provided in the Trondelog region of Norway utilizing Government provided facilities, Government-furnished equipment/materials (GFE/M), and Government provided common hand tools.

1.A.8.B. Most of the MCPP-PHIL services shall be provided in Subic Bay Philippines utilizing Government provided facilities, Government-furnished equipment/materials (GFE/M), and Government provided common hand tools. The facilities are Government Furnished Facilities (GFF) and are located in the Republic of the Philippines. The MCMC shall have the primary responsibility for coordinating import/export clearances, hiring labor to work in the Philippines for maintenance, and ensuring operations remain in accordance with Philippine law and SBMA regulations. MCMC shall register with the Philippine Security and Exchange Commission and SBMA, obtaining all necessary licensure and credentials to attain status as a licensed commercial importer/exporter of all MCPP-PHIL equipment, supplies, and consumables, which includes obtaining and maintaining a Philippine Certificate of Registration and Tax Exemption (CRTE).

Further, the MCMC shall comply with U.S. laws and regulations, including International Traffic in Arms Regulations compliance and obtain a licensure from the U. S. Directorate of Defense Trade Controls for the permanent export of unclassified defense articles, termed a DSP-5 License. MCMC Shall submit a copy of its DSP-5 application to the Government and provide the Government with its nine-digit case number within 30 days of contract award.

1.B OVERALL MCPP SCOPE. The MCMC shall provide a full range of logistics services in support of the three Marine Corps’ Prepositioning Program efforts: the MPS Program, MCPP-N and MCPP-PHIL. The number of ships and land based sites may increase or decrease based on Marine Corps operational needs. The MCMC shall provide all management, supervision, administrative/clerical equipment, supplies, consumables, and personal protective equipment required for all personnel performing under this effort (except GFP); cost associated with administrative/clerical equipment, supplies, consumables, and personal protective equipment shall be included in CLIN X001. This SOW delineates work to be performed by the MCMC for maintenance of equipment and materiel management such that required assets are attained, preserved, packaged, identified accurately in the Business Operating Systems/Accountable Property Systems of Record identified in paragraph 2.C.1, and available in support of the Marine Corps Prepositioning Programs (MCPP) and deployed forces world-wide.

In addition to prepositioning support, the MCMC shall provide operational logistics services to engaged Marine Corps and Department of Defense (DoD) operating forces. These services shall enable the operating forces to rapidly and successfully conduct and quickly recover from assigned missions across the full spectrum of expeditionary warfare. SOW Attachment C.1-3 (MMC Notional Plan of Action & Milestones (POA&M) defines the phasing of MMC operations conducted separately and jointly by the MCMC and Government for both Marine Corps and Navy equipment. Tasks assigned to the MCMC are not limited to materiel management and maintenance as there are specific support activities necessary for sustainment of this program (e.g. wash rack operations, fuel station, etc. as described in this SOW). This SOW also defines some tasks performed by the Government. Government tasks described are provided to ensure a clear understanding of the total program and to help define the division of responsibilities and necessary interfaces between the Government, other contractors and the MCMC in this unique program. BICmd has been designated as Executive Agent for the MCPP by the Marine Corps and as such shall be the organization, which shall provide all guidance, direction, oversight, and liaison required for the prepositioning programs. The maintenance level to be accomplished at the MMC facility or to equipment prepositioned aboard ship is dependent upon availability of special tools, proximity of established facilities (Marine Corps/Navy maintenance facilities), and the availability of funds. Further scope specifics are provided as follows:

1.B.1 MMC. The MPS rotations are scheduled to meet American Bureau of Shipping (ABS) requirements for hull inspections and ship certifications. As such, ship schedules and MMC time frames are generally available several years in advance and are tied to dry dock periods (see SOW Attachments C.1-8 MMC-14 schedule and proposed MMC-15 schedule, and C.1-9 Navy Watercraft Plan. The MCMC work effort is extremely time sensitive for several reasons. First, the MMC effort shall be accomplished during the ship's dry dock period and secondly, when the ship is out of its area of responsibility (AOR) the squadron is in a degraded status, i.e., one seventh of the squadron's capability is not available to the regional GCC. Determination of logistics requirements is an ongoing process which shall be conducted in accordance with this document. MCMC shall provide logistics services in support of the program directives found throughout this SOW. MCMC shall, primarily in government owned CONUS-based facilities, perform equipment maintenance and materiel management operations required to accomplish up to and including intermediate level maintenance of ground combat support equipment.

1.B.2 Program Sustainment. MCMC shall provide logistics services in support of the program directives found throughout this SOW. MCMC shall perform primarily in government owned CONUS based facilities, those materiel management operations required to sustain MPS, MCPP- N and MCPP-PHIL operations. Toward this end, these materiel management operations are described throughout the SOW and include; but are not limited to quality control, organic supply, and environmental and safety compliance. The MCMC shall plan for materiel management of government assets in a Care of Supplies in Storage (COSIS) status against the current ship’s/MCPP-PHIL Production Cycle/embarkation period of performance. COSIS services include preventive and corrective maintenance, application of equipment modifications, and equipment preservation and corrective maintenance.

1.B.3 Shipboard Operations. Shipboard work performance required by this SOW shall be accomplished aboard deployed MPS and Layberthed ROS ship(s). In addition, maintenance may be required ashore at the off-load site during exercises and contingencies . Shipboard logistics requirements are specified in Section C.7. The MCMC shall place necessary personnel aboard each FOS and ROS ship to perform COSIS on the embarked equipment and materiel.

1.B.4 Navy Support Requirements. The Navy effort includes the Navy Support Element (NSE) and Naval Construction Element (NCE) equipment outlined in their respective Tables of Allowance (TOA) assigned to support the MPF Program, including rotational spares and Navy organic equipment. The MCMC provides the maintenance, repair and logistical services for the Navy mission as detailed in the SOW. The MCMC’s Navy support organization shall provide optimal equipment readiness while meeting limitations associated with cost and funding, production requirements and schedule timelines. The MCMC shall deliver Navy products and services in accordance with standards identified in Section C.6 of the SOW and all applicable Navy and Marine Corps orders and directives.

1.B.5 OCONUS Operations

1.B.5.a MCPP-N. The USMC has prepositioned equipment in Norway for MCPP-N that contains all classes of supply to include communications security materiel/controlled cryptographic items (COMSEC/CCI) used to provide cryptographic security of US Department of the Navy communications. Due to the sensitivity of COMSEC/CCI, this equipment requires U. S. personnel to account and maintain the equipment while it is prepositioned in Norway.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .