01 31 00 44 Project Meetings.doc

DOC document 38 KB Posted

Attached to
Repair Structural Components, Bldg 1374 Federal contract opportunity
Solicitation number
JBSF_15-0006
Issued by
Department of the Air Force Air Education and Training Command

About this file

Appendices - Attachment 2 FA3047-15-R-0078

View the file

Other files for this federal contract opportunity

Other files attached to Repair Structural Components, Bldg 1374, newest first.
File Type Posted
QUESTIONS_AND_ANSWERS_-_FA304715R0078.pdf PDF
01 35 29 Occupational Safety and Health.doc DOC document
01 45 00.10 20 Contractor Quality Control.doc DOC document
request to use radioactive material.pdf PDF
01 35 13.01 44 Special Project Procedures for JBSA-FSH CB 08 April 2014.pdf PDF
01 35 35 Environmental Protection Oct30.doc DOC document
01 72 00.00 44 Alterations to Existing Facilities.doc DOC document
Attach 2 - Contractor HAZMAT Usage Report_Mar2015.docx DOCX document
Application for Installation Access Credential 12 .pdf PDF
01 74 19.00 Construction Waste Management.doc DOC document
FSH Historical Bldg Maintenance and Repair Plan.pdf PDF
01 78 23- OPERATION AND MAINTENANCE DATA.doc DOC document
CEPT Work Request Form Editable.pdf PDF
01 78 36.00 Warranty of Construction.doc DOC document
Rad permit company request letter template.pdf PDF
01 33 16_Design_After_Award.docx DOCX document
01 35 13 30 Special Project Proceedures - GIS rev6.pdf PDF
01 78 00 Closeout Submittals.doc DOC document
JBSA_FSH_NDA_Use Authorization.pdf PDF
01 77 00.00 20 Contract Closeout.doc DOC document
502CES ACM LBP spec requirements.pdf PDF
01 71 23.16 Cutting and Patching.doc DOC document
01 35 13 03 44 Technical_Supplement_to_the_Design_Guide_for_FSH_02-14-2013.doc DOC document
01 35 13.20 00 Special Project Proceedures - CAD rev6.pdf PDF
01 32 01 00 10 Project Schedule.doc DOC document
01 56 00.00 44 Dust Control.doc DOC document
01 35 13 10 00 Special Project Proceedures - Survey Revision5.pdf PDF
As-Builts.pdf PDF
01 52 13.00 Temporary Facilities and Controls.doc DOC document
Army Installation Design Guide.pdf PDF
Installation Access Credential —
01 35 30 Safety Health and Emergency Response.doc DOC document
AFI 31-113 Installation Access Control.pdf PDF
DIGGING PERMIT 4Jan12.pdf PDF
01 33 00 Submittal Procedures.doc DOC document
01 00 00 00 General Requirements.doc DOC document
Cover_Page-Attch2.docx DOCX document
FA304715R0078.pdf PDF
Wage_Determinations_TX150016_TX150280.pdf PDF
Attch5-AETC47.pdf PDF
Attch1-SOW_JBSF150006.pdf PDF
Attch4-MATSUB.xlsx XLSX spreadsheet
Attch3Construction_Cost_Estimate_Breakdown.xls XLS spreadsheet
11_-_Draft_DD_Form_1354_H_3_16_42_Doors.pdf PDF
Show all 44

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

JBSF150006

SECTION 01 31 00.00 44

PROJECT MEETINGS

PART 1

GENERAL

1.1 Preconstruction Conference

Prior to start of construction, a pre-construction conference will be scheduled by the authorized representative of the Contracting Officer. The Contractor's Project Manager, Superintendent, and Quality Control Manager will attend this meeting. The Contractor is encouraged to have an officer of his company and representation from his sub-contractors at this conference. This conference will be held at the location specified by the Contracting Officer's authorized representative. Minutes of the meeting will be prepared by the Government and signed by both the Contractor and the Contracting Officer. The minutes shall become a part of the contract file.

1.1.1 Start of Task Order Work

If the Contractor has submitted the Accident Prevention (Safety) Plan, Quality Control Plan, Environmental Protection Plan, and the Storm Water Pollution Prevention Plan for review prior to this meeting, these may be accepted in total or accepted with comments at the conference. Task order work will not proceed until after this meeting has been held, these plans noted above have been accepted and the Notice to Proceed has been received and acknowledged by the Contractor.

1.2 Other Meetings

Construction Quality Control meetings and conferences are specified in Section 01 45 00.10 20 CONTRACTOR QUALITY CONTROL. Other meetings are specified in various Division 1 and technical sections.

PART 2

PRODUCTS – NOT USED

PART 3

EXECUTION – NOT USED

---END OF SECTION 01 31 00 44---

PROJECT MEETINGS