This is a Request for Proposal (RFP 124469 O5) issued by the State of Nebraska Department of Administrative Services, Materiel Division, State Purchasing Bureau, seeking qualified contractors to provide comprehensive technical services and personnel support for Disaster Mitigation, Preparedness, Response, and Recovery Programs administered under the Stafford Act and National Flood Insurance Act. The solicitation targets knowledgeable and experienced personnel across three primary FEMA program areas: Public Assistance (PA), Individual Assistance (IA), and Hazard Mitigation Assistance (HMA). Required services include project review and eligibility determinations, post-obligation compliance monitoring, payment verification, project closeout support, and disaster recovery expertise delivered to sub-recipients. The contract will operate as an indefinite delivery and indefinite quantity agreement with no guaranteed minimum work or retainer fees, with task orders issued as needed following declared disasters. Contractors must respond within 30 days of receiving signed task orders. Written questions are due by February 8, 2026, and electronic proposal responses must be submitted by March 3, 2026, at 2:00 p.m. Central Time, with the State expected to post an Intent to Award on March 20, 2026. The contract term is two years from notice to proceed with options to renew for three additional one-year periods upon mutual agreement.
Contractors must submit not-to-exceed hourly rates for fifteen mandatory personnel categories including Project Manager, Senior Advisors, Program Liaisons, Technical Liaisons, Appeals Specialists, Debris Specialists, Benefit-Cost Analysis Specialists, Individual Assistance Specialists, Closeout Specialists, Disaster Recovery Specialists, and Accounting Analysts, with rates remaining fixed for the first two contract years and any subsequent increases capped at five percent. Evaluation will be conducted on a 100-point scale with Corporate Overview accounting for 30 points and Technical Response for 70 points, prioritizing technical capability. The State indicates a preference for resident disabled veterans or businesses located in designated enterprise zones under Nebraska Revised Statute 73-107 if all other factors are equal. No incumbent vendors or award budget ranges are specified, with pricing determined through individual task orders that factor travel costs separately from hourly labor rates. Contractors must maintain comprehensive insurance coverage including Workers' Compensation, Commercial General Liability with a $2,000,000 aggregate limit, Commercial Automobile Liability with $1,000,000 combined single limit, and Professional Liability with $1,000,000 per claim. Personnel assigned to contract positions must submit resumes for State approval prior to work commencement, and all assigned staff must comply with employee work eligibility verification and all applicable federal and state regulations governing disaster recovery programs. Monthly invoicing will be based on submitted weekly timesheets and approved deliverables.
View the file
Other files
Show all 39
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Jacobs Program Management Co.
222 South 15th St, Suite 1408-S
Omaha, NE 68102 T +1.402.342.9765 www.jacobs.com
March 3, 2026
Attn: Craig Palik and Clinton Paul Procurement Contract Officers State of Nebraska Purchasing Bureau 1526 K Street, Suite 13, Lincoln, NE 68508 as.materielpurchasing@nebraska.gov
Subject: Disaster Mitigation, Preparedness, Response, and Recovery Programs for the State of Nebraska (Solicitation no: 123919 O5)
Dear Evaluation Committee, We are grateful for the opportunity to stand alongside Nebraska as a long‑term partner in community resilience. Our commitment is simple:
bring local faces and 4 decades of national Federal Emergency Management Agency (FEMA) expertise, including in Nebraska, to help Nebraska lead a lifecycle program—from mitigation and preparedness to response and recovery—built on strong governance, transparent reporting, and audit‑ready delivery aligned to your state needs.
Technical Expertise & FEMA Experience—Applied to Nebraska’s Needs. Jacobs brings proven FEMA program delivery across Public Assistance (PA), Individual Assistance (IA), and Hazard Mitigation Assistance (HMA), with repeatable methods for eligibility, documentation, inspections, cost estimation, and closeout that protect funding and accelerate recovery. We pair that experience with Nebraska‑specific field knowledge and FEMA program delivery—from southeast sandy‑loam road conditions to culvert hydraulics and construction oversight—so every site decision is both locally informed and federally compliant. Our teams have earned positive applicant feedback on Nebraska recovery assignments and maintain a disciplined reporting culture that keeps progress visible. Our team has also supported FEMA in developing Version 5.0 of the Public Assistance Program and Policy Guide (PAPPG) including expanding mitigation measures in Appendix J. What this means for Nebraska: faster, cleaner recoveries;
fewer reworks and deobligations; and competent and efficient application of FEMA-approved tools and policies for applicants and sub-recipients to navigate policy and documentation at pace.
Local Experience, Presence, & Relationships—Community Dedication in Action. Our approach centers on local people and community engagement. Jacobs’ Omaha office and Nebraska staff provide familiar leadership and on‑the‑ground coordination with cities, districts, and local authorities. We reinforce this with community participation and reporting under the city’s Economic Equity & Inclusion Program, reflecting a sustained commitment to Nebraska’s social value goals.
What this means for Nebraska: trusted local relationships, faster applicant support, and resilience planning rooted in the needs of Nebraska communities by meeting applicants where they are when dealing with a devastating disaster.
Resource Reach Back & Subcontractor Teaming Strength—Flexible Capacity, Strong Governance. In addition to our existing depth of experienced and qualified FEMA resources, our subcontractors are established partners who have worked with us on FEMA response and recovery assignments and provide immediate surge capacity. We have the flexibility to add qualified firms as needs evolve, supported by our internal systems that accelerate onboarding while confirming Health, Safety, Proposal Key:
Follow Jacobs Strength Signals – To make our differentiators easy to spot, we use three icons as “wayfinding” markers throughout our proposal. When you see an icon, you’re looking at a section where we demonstrate Jacobs’ core strengths:
Technical Expertise & FEMA Experience—Applied to Nebraska’s Needs
Local Experience, Presence, & Relationships—Community Dedication in Action
Resource Reach Back & Subcontractor Teaming Strength—Flexible Capacity, Strong Governance
Appendix B contains information to directly address evaluation criteria a-e.
March 3, 2026
Subject: Disaster Mitigation, Preparedness, Response, and Recovery Programs for the State of Nebraska (Solicitation no: 123919 O5)
Security, and Environmental (HSSE) compliance; quality; and small‑business participation. What this means for Nebraska: scalable capacity (that pulls from a deployment-ready roster of 1000+ disaster-experienced professionals) with clear controls, transparent utilization reporting, and mentoring that gets you what you need when you need it.
We’re invested in Nebraska’s communities and stand ready to set the right resources, governance, and support in place—so the state can lead disaster mitigation, preparedness, response, and recovery with confidence. Please do not hesitate to contact Marshall Sanders with any questions (contact information in signature line).
Regards, Jacobs Program Management Co.
Marshall Sanders Project Manager
+1.202.341.9778 Marshall.Sanders@jacobs.com
Jason Glasgow, P.E.
Manager of Projects
+1.770.330.9365 Jason.Glasgow@jacobs.com
Our Partnership Promise to Nebraska Communities With Omaha‑based staff and deep relationships across the state, we work shoulder‑to‑shoulder with Nebraska Emergency Management Agency (NEMA) and sub-recipients to simplify complex federal requirements, support applicants, and keep communities informed. Our Omaha presence, FEMA experience, and track record of engaging with city programs and local stakeholders means faster coordination, familiar points of contact, and trusted delivery. We align our program cadence to your task-order (TO) framework and reporting expectations, including weekly time summaries and monthly status reports, bringing clarity for decision-makers and confidence for auditors.
Nebraska Disaster Mitigation, Preparedness, Response, & Recovery Services Prepared for Nebraska – Department of Administrative Services (DAS), Materiel Division, State Purchasing Bureau (SPB)
Solicitation Number: 123919 O5 | March 3, 2026
Contents Attachment A Bidder Questionnaire RFP 124469 O5
Corporate Overview
Technical Proposal Hourly Rates
Appendices Appendix A. Financial Statements – Jacobs 2025 10k Report Appendix B. Evaluation Criteria Supplemental Content
Evaluation Criteria Letter a. Ability, Capacity, and Skill ..........................................................................................A-1 Evaluation Criteria Letter b. Character, Integrity, Reputation, Judgment, Experience, and Efficiency .........A-3
Evaluation Criteria Letter c. Performing the Contract Within the Specified Time Frame .................................A-4
Evaluation Criteria Letter d. Jacobs’ Disaster Mitigation, Preparedness, Response, & Recovery Services .A-6
Evaluation Criteria Letter e. Other Information: Jacobs Differentiators ............................................................. A-7
Appendix C. Contractual Agreement Form & Completed Sections II through IV
Attachment A Bidder Questionnaire
RFP 124469 O5
Bidder Name: Jacobs Project Management Co.___________________________
Bidder should provide a response to all questions in this attachment to meet the requirements of the RFP.
CORPORATE OVERVIEW
1.1
a. BIDDER IDENTIFICATION AND INFORMATION
b. The bidder should provide the full company or corporate name, address of the company's headquarters, entity organization (corporation, partnership, proprietorship), state in which the bidder is incorporated or otherwise organized to do business, year in which the bidder first organized to do business and whether the name and form of organization has changed since first organized.
Response:
Full company or corporate name: Jacobs
Project Management Co., a wholly owned subsidiary of Jacobs Engineering Group Inc.
Headquarters: 1999 Bryan Street, Ste. 3500 Dallas TX, 75201 USA
Entity organization: Corporation State of Incorporation: Delaware Year Established: 1947
1.2
c. FINANCIAL STATEMENTS The bidder should provide financial statements applicable to the firm. If publicly held, the bidder should provide a copy of the corporation's most recent audited financial reports and statements, and the name, address, and telephone number of the fiscally responsible representative of the bidder’s financial or banking organization.
If the bidder is not a publicly held corporation, either the reports and statements required of a publicly held corporation, or a description of the organization, including size, longevity, client base, areas of specialization and expertise, and any other pertinent information, should be submitted in such a manner that solicitation evaluators may reasonably formulate a determination about the stability and financial strength of the organization. Additionally, a non-publicly held firm should provide a banking reference.
The bidder must disclose any and all judgments, pending or expected litigation, or other real or potential financial reversals, which might materially affect the viability or stability of the organization, or state that no such condition is known to exist.
d. The State may elect to use a third party to conduct credit checks as part of the corporate overview evaluation.
Response:
Jacobs most recent financial reports are provided in Appendix A.
Jacobs Fiscally Responsible Representative:
Mike Hsu, Treasurer Phone: 213.228.8219 Address: 555 South Flower Street, Suite 3200, Los Angeles, CA 90071
No judgments, pending or expected litigation, or other real or potential financial reversals, which might materially affect the Jacobs viability or stability is known to exist.
1.3
CHANGE OF OWNERSHIP
e. If any change in ownership or control of the company is anticipated during the twelve (12) months following the solicitation response due date, the bidder should describe the circumstances of such change and indicate when the change will likely occur. Any change of ownership to an awarded bidder(s) will require notification to the State.
Response:
No change in ownership or control of the company is anticipated during the 12 months following the solicitation response due date stated on the cover letter.
1.4
OFFICE LOCATION
f. The bidder’s office location responsible for performance pursuant to an award of a contract with the State of Nebraska should be identified.
Response:
Jacobs Nebraska Office 2111 South 67th Street, Suite 300 Omaha, NE 68106
1.5
RELATIONSHIPS WITH THE STATE
g. The bidder should describe any dealings with the State over the previous ten (10) years. If the organization, its predecessor, or any Party named in the bidder’s solicitation response has contracted with the State, the bidder should identify the contract number(s) and/or any other information available to identify such contract(s). If no such contracts exist, so declare.
Response:
The table below provides a list of our teams contracts with the state of Nebraska in the past 10 years.
Exhibit A. Nebraska State Contracts in the Past 10 Years Firm Contract Date Client Name Agreement # Project Name
Jacobs 10/Jan/2019 NDOT VH1901 Nebraska Department of Transportation (NDOT)
Jacobs 18/Jun/2019 NDOT XK1923 Preliminary, Functional and Final Design, Environmental and Bridge Repair Services
Jacobs 04/Feb/2020 NDOT XK2010 US-138 West Roadway Design, Bridge Repair, Environmental and Public Involvement Services
Jacobs 04/Feb/2020 NDOT XK2011 Chappell East Roadway Design and Environmental Services
Jacobs 29/Apr/2020 NDOT XK2038 Highway 77 Princeton to N33 Project No. NH-77-2(166)
Jacobs 24/Jul/2020 NDOT VH2007 State & Local Federal-AID Projects Contract – Revised Fees & Payment Exhibits
Jacobs 27/Jul/2020 NDOT VH2019 State & Local Federal-AID Projects Contract – Revised Fees & Payment Exhibits
Jacobs 27/Jul/2021 NDOT XK2131 Funk-E JCT N-44 Environmental, Roadway Design, Public Involvement, ROW Services
Jacobs 01/Dec/2021 NDOT VK2144 NDOT COZAD Viaduct
Jacobs 28/Mar/2022 NDOT VK2210 State & LPA On-Call Environmental Services (NEPA)
Jacobs 18/Apr/2022 NDOT VK2220 Noise Training and Threatened and Endangered Species (T&E) Training
Jacobs 14/Dec/2023 NDOT VK2361 State & LPA On-Call Environmental Services (NEPA) Studies
Jacobs 11/Jun/2025 NDOT VK2300 Multi-Service Profesional Services On-Call – Spring 2025
Jacobs 26/Aug/2025 NDOT XK2527 Broken Bow South Environmental and Survey
1.6
h. BIDDER'S EMPLOYEE RELATIONS TO STATE If any Party named in the bidder’s solicitation response is or was an employee of the State within the past twelve (12) months, identify the individual(s) by name, State agency with whom employed, job title or position held with the State, and separation date. If no such relationship exists or has existed, so declare.
i. If any employee of any agency of the State of Nebraska is employed by the bidder or is a subcontractor to the bidder, as of the due date for solicitation response submission, identify all such persons by name, position held with the bidder, and position held with the State (including job title and agency). Describe the responsibilities of such persons within the proposing organization. If, after review of this information by the State, it is determined that a conflict of interest exists or may exist, the bidder may be disqualified from further consideration in this solicitation. If no such relationship exists, so declare.
Response:
Jacobs confirms that none of our intended team members that would support roles and tasks listed in our response to your solicitation were employees of the state within the past 12 months.
1.7
j. CONTRACT PERFORMANCE If the bidder or any proposed subcontractor has had a contract terminated for default during the past ten (10) years, all such instances must be described as required below. Termination for default is defined as a notice to stop performance delivery due to the bidder’s non-performance or poor performance, and the issue was either not litigated due to inaction on the part of the bidder or litigated and such litigation determined the bidder to be in default.
It is mandatory that the bidder submit full details of all termination for default experienced during the past ten (10) years, including the other Party's name, address, and telephone number. The response to this section must present the bidder’s position on the matter. The State will evaluate the facts and will score the bidder’s solicitation response accordingly. If no such termination for default has been experienced by the bidder in the past ten (10) years, so declare.
k. If at any time during the past five (5) years, the bidder has had a contract terminated for convenience, non-performance, non-allocation of funds, or any other reason, describe fully all circumstances surrounding such termination, including the name and address of the other contracting Party.
Response:
Jacobs Engineering Group Inc. was terminated for default in August 2020 by the Procurement Office of the Arizona Department of Transportation (ADOT). The basis for the termination was a dispute over a real estate license requirement.
In August 2020, the Procurement Office of ADOT notified Jacobs Engineering Group Inc. (Jacobs) of its intent to terminate On-Call Acquisition and Relocation Services contracts (CTR049970 and CTR049971) for default due to a disputed real estate brokerage licensing requirement. Jacobs has been in the process with ADOT of correcting this administrative default and securing rescission of the notice. No TOs had been requested or issued under the subject On-Call.
Jacobs has delivered world-class engineering services with ADOT for more than 30 years and continues to win new contracts and deliver many projects with ADOT. This termination is not expected to have a material adverse effect on Jacobs Engineering Group Inc.
or on the business, financial condition, results of operations, or cash flows for the company.
Our proposed subcontractors declare they have not had a contract terminated for default in the past 10 years.
1.8
l. SUMMARY OF BIDDER’S CORPORATE EXPERIENCE The bidder should provide a summary matrix listing the bidder’s previous projects similar to this Solicitation in size, scope, and complexity. The State will use no more than three (3) narrative project descriptions submitted by the bidder during its evaluation of the solicitation response.
The bidder should address the following:
i. Provide narrative descriptions to highlight the similarities between the bidder’s experience and this Solicitation.
These descriptions should include:
a) The time period of the project,
b) The scheduled and actual completion dates,
c) The bidder’s responsibilities,
d) For reference purposes, a customer name (including the name of a contact person, a current telephone number, a facsimile number, and e-mail address); and
e) Each project description should identify whether the work was performed as the prime Vendor or as a subcontractor. If a bidder performed as the prime Vendor, the description should provide the originally scheduled completion date and budget, as well as the actual (or currently planned) completion date and actual (or currently planned) budget.
ii. Bidder and Subcontractor(s) experience should be listed separately. Narrative descriptions submitted for Subcontractors should be specifically identified as subcontractor projects.
iii. If the work was performed as a subcontractor, the narrative description should identify the same information as requested for the bidders above. In addition, subcontractors should identify what share of contract costs, project responsibilities, and time period were performed as a subcontractor.
m.
Response:
Jacobs’ Technical Expertise & FEMA Experience, including our PA, IA, and HMA experience, aligns to Nebraska’s recovery needs and is supported by our established Local Experience, Presence, & Relationships and local experience.
As summarized in Exhibit B, which includes two Nebraska‑based projects, and detailed in the three narrative projects that follow, we combine repeatable, federally compliant delivery with on‑the‑ground leadership from our Omaha office, Nebraska staff, and Resource Reach Back & Subcontractor Teaming Strength to accelerate recoveries, strengthen applicant support through trusted local relationships, and deliver resilient solutions rooted in the needs of Nebraska communities.
Exhibit B. Jacobs Relevant FEMA Project Summary Matrix
Project Names
Relevant Scope
FEMA
PA
FEMA
IA
FEMA
HMA
FEMA
Grants
Program Management
Located in Nebraska
Local Experience, Presence, & Relationships
Contractor Performance Assessment Reporting System
(CPARS)
Surge Staff Deployed
Resource Reach Back & Subcontractor Teaming Strength
Ke y P ro je ct s
PATAC V Region VII Multiple Disasters Task Order x x x x x Project in progress – CPARS not issued yet
90+
Florida Technical Support Services (TSS) 23-46 FL DR x x x x Exceptional 80+
LOGHOUSE (fka IA-TAC), supporting Regions I, II, III, IV, V
- DR-4559\4570-LA
x x Satisfactory 25+
PATAC IV: PA Disaster Operations Support for the Severe Winter x x Very Good 700+
Storm, Straight Line Winds and Flooding -DR-4420-NE
IASC COVID-19 Vaccination Sites Non-Clinical Staffing Mission x x Very
Good/Satisfactory 25+
PATAC III x x x Exceptional/Very Good
300+
Kentucky Community Planning Capacity Building - TSS 22-143 x x x Exceptional/Very
Good
Jacobs Key Project 1: PATAC V, Region VII Multiple Disasters Task Order | FEMA
Time Period: October 30, 2024, to June 17, 2025 Completion Date: June 17, 2025 Budget Award amount/actual (time & materials): $64,565,547/$23,878,343 Responsibilities: PA; HMA; grants Client Reference: Rachel Woods, FEMA Contracting Officer (CO) Phone: 256.454.1197 | Fax: N/A | Email: Rachel.Woods@fema.dhs.gov Our Role: Prime (managing partner for joint venture CH2M HILL (now Jacobs) – CDM PATAC Recovery Services (CCPRS)
Project Description and Services Provided
Under Public AssistanceTechnical Assistance Contract (PATAC) V, Jacobs supports FEMA’s PA program, which provides supplemental federal disaster grant assistance for emergency protective measures, and the repair, replacement, and restoration of disaster-damaged, publicly owned facilities and facilities of certain private nonprofit organizations. The program also encourages protecting damaged facilities from future events by providing assistance for hazard mitigation measures during the recovery process. CCPRS (Jacobs) leveraged our Resource Reach Back & Subcontractor Teaming Strength to assemble a team of 157 resources to respond to disasters in FEMA Region VII (Nebraska, Iowa, Missouri, and Kansas) as requested. The team assembled included construction managers, management analysts, construction/building inspectors, civil engineers, structural engineers, mechanical engineers, electrical engineers, soil/geotechnical engineers, hydrologists, project managers for 406 mitigation, project managers for environmental and historic preservation (EHP), architectural historians, biologists, archaeologists, environmental planners, certified floodplain managers, and technical assistance coordinators (TAC). Under this TO, Jacobs provided Technical Expertise & FEMA Experience consisting of comprehensive technical and operational support for directly delivering FEMA’s PA program, including site inspections, field technical services, and program delivery managers. FEMA requested 157 resources, we presented 157 resources but only 95 were deployed due to workload needs shifting. Jacobs provided staff to both Lincoln and North Platt. Throughout the performance period, we consistently received positive feedback from FEMA Task Force Leaders (TFLs) and applicants. FEMA requested TACs to extend beyond their scheduled demobilization because of exceptional performance. Multiple TFLs and applicants recognized the high-quality technical support provided, and FEMA noted that our personnel integrated effectively into FEMA teams;
demonstrated strong technical competence; and consistently showed dedication, flexibility, and mission focus in supporting disaster-impacted communities across FEMA Region VII.
Relevance to Nebraska
Proven Nebraska delivery with the same subcontractors included in our proposal (Arcus, Flux, National Disaster Recovery Technical Assistance Consultants, Inc. [NDRtac])—providing successful workflow continuity, trusted communication channels, and reliable staffing models that Nebraska can depend on
Local Experience, Presence, & Relationships: Firsthand experience with Nebraska’s disaster patterns, applicant needs, and regional FEMA/federal expectations
Surge capability for Nebraska events via our Resource Reach Back & Subcontractor Teaming Strength, proving the ability to scale up rapidly when Nebraska faces concurrent flooding, severe storms, or infrastructure impacts
Exceptional performance—evidence of reliable, compliant, and trusted delivery Nebraska can depend on for PA mission support Technical Expertise & FEMA Experience: Full lifecycle disaster grants capability with established partners whose longstanding subcontractor relationships make sure Nebraska receives a fully integrated team experienced across all service requirements-standing subcontractor relationships mailto:Rachel.Woods@fema.dhs.gov
Experience supporting rural, urban, and infrastructure-heavy communities (inspections, technical services, and program delivery across diverse community types)—mirroring the mix of rural towns, agricultural assets, and urban centers like Omaha and Lincoln that Nebraska supports during disasters
Jacobs Key Project 2: Florida TSS 23-46 FL DR | FEMA
Time Period: April 13, 2023 to October 12, 2024 Completion Date(s): October 12, 2024 Budget Award amount/actual (time & materials): $5,417,162/ $5,166,317.85 Responsibilities: PA; HMA; grants Client Reference: Gretchen Carreiro, FEMA Contracting Officer Representative (COR) Phone: 202. 646.2615 | Fax: N/A | Email:
Gretchen.Carreiro@fema.dhs.gov Our Role: Co-prime with Cadmus Consulting, through a General Services Administration (GSA) Contractor Teaming Arrangement (CTA)
Project Description and Services Provided
Jacobs, as part of the Cadmus/Jacobs CTA, leveraged our Technical Expertise & FEMA Experience to support FEMA’s Community Assistance (CA) program after Hurricane Ian and Tropical Storm Nicole, which resulted in federal disaster declarations across 26 Florida counties. Many impacted communities faced severe socioeconomic challenges, understaffing, and significant operational disruption. Jacobs leveraged our Resource Reach Back & Subcontractor Teaming Strength to deploy more than 80 staff to multiple locations in Florida, delivering analysis, planning, technical assistance, and community engagement to help these jurisdictions accelerate long‑term recovery and build resilience. The scope of services we delivered included:
Program Support
Operational planning for the Interagency Recovery Coordination (IRC) mission Subject matter expert (SME)‑level technical assistance for recovery planning, project development, and implementation Data analytics to support informed decision‑making across federal partners
Targeted Local Government Support
Jacobs provided embedded staff and on‑site planning expertise to six priority communities, including services listed in the Exhibit below.
Exhibit C. Services Delivered to Priority Communities Category Combined Services Delivered Operational & Technical Program Support
Operational planning for the IRC mission SME level technical assistance for recovery planning, project development, and implementation-level technical assistance for recovery planning, project development, and implementation Data analytics to support informed, multi-agency decision-making
Community & Stakeholder Engagement
Public workshops, stakeholder meetings, and community engagement sessions Public surveys (including large-scale efforts such as 300+ responses) Community driven recovery prioritization processes-driven recovery prioritization processes
Long-Term Recovery Planning Long-term recovery plans and planning workbooks development Funding pathways Identification and alignment with federal, state, and regional partners
Technical Assessments & Feasibility Studies
Environmental, housing, and solar feasibility studies Wastewater infrastructure feasibility studies Economic impact studies to support grant applications
Fort Meyers Beach Pier Post Hurricane Ian, a priority recovery project.
mailto:Gretchen.Carreiro@fema.dhs.gov
Interagency & Multi-Jurisdictional Coordination
Coordination across municipalities, counties, state, and federal agencies (EPA, USACE, DOI, FEMA) Multi-jurisdictional engagement facilitation
Prioritization, Tools, & Decision Frameworks
Prioritization frameworks for recovery projects (including 37 projects and 68 project scopes) ArcGIS StoryMaps Long-term decision-making and prioritization tools
Embedded Staffing & Technical Surge Capacity
Embedded planners, engineers, and SME staff supporting jurisdictions on-site Technical surge support to address backlogs (e.g., 590 permit applications)
Permitting, Grant, & Funding Support
Assistance with permitting identification and resolution Funding strategy development Grant support, including FEMA PA and HMA programs
Outcomes Delivered Across All Communities
Accelerated recovery timelines Strengthened local capacity and governance Streamlined permitting, funding alignment, and long-term resilience building
Together, this work delivered measurable, community-driven results across six jurisdictions—each equipped with a customized long-term recovery plan and the tools needed to sustain progress well beyond the period of performance. By coordinating seamlessly across city, county, state, and federal partners, the team strengthened local capacity, streamlined permitting and funding alignment, and enabled data informed decision-making for years to come. Through embedded staff and targeted technical expertise, we accelerated recovery timelines and positioned each community to rebuild stronger, safer, and more resilient for the future.
Relevance to Nebraska
Experience performing key competencies at the state and local level including stakeholder engagement, long-term recovery planning, funding and grant support, public outreach, permit identification, technical assessments, all of which demonstrate Jacobs’ Technical Expertise & FEMA Experience
Accelerating recovery timelines through on-location embedded staff and specialized technical support leveraging our Resource Reach Back & Subcontractor Teaming Strength
Proven delivery of long‑term recovery plans tailored to local needs Facilitating multi-jurisdictional coordination across city, county, state, and federal partners Equipping communities with tools for prioritization, permitting, funding alignment, and long-term decision-making
Jacobs Key Project 3: LOGHOUSE I | FEMA
Time Period: April 3, 2018, to January 30, 2025 Completion Date: January 30, 2025 Budget actual (Indefinite Delivery, Indefinite Quantity Contract): $49,271,482 Responsibilities: IA Client Reference: Derek Reaves, FEMA Contracting Officer Representative Phone: 202.304.9516 | Fax: N/A | Email: Derek.Reaves@fema.dhs.gov Our Role: Prime
Project Description and Services Provided
Jacobs supported FEMA with Logistics Housing Operations Unit Installation, Maintenance, and Deactivation (LOGHOUSE) in response to DR-4559\4570-LA Hurricane Laura/Delta Housing Recovery Mission. Our team executed comprehensive site inspections, completing 1,213 private and 27 commercial feasibility reports out of 1,259 FEMA-issued work orders. Under the Haul and Install Performance Area, we managed permitting, transporting, and installing 1,800 temporary transportable housing units (TTHUs), placing 1,061 modular housing units and 571 travel trailers across private and commercial sites. Jacobs completed on a total of 541 modular housing units and 384 travel trailers which included cleaning and making the units ready for reuse. The remainder of the units were still in service when the work transitioned to a small business closeout contractor. Jacobs also delivered extensive maintenance support, recording and resolving
Tornado Recovery in Kansas and Texas We turned a 66-acre wheat field into site capable of housing two-thirds of the town’s population.
mailto:Derek.Reaves@fema.dhs.gov
15,413 maintenance issues and completing 22,782 preventive maintenance inspections. Our call center implemented a mass communication text messaging system for communicatin with all applicants for emergencies. For example, during Hurricane Ida’s landfall, which impacted the project area, a mass text message was sent to all occupants about staff availability for responding to maintenance issues during the storm. After the storm, we quickly prioritized issues and responded accordingly while keeping staff safe and out of harm's way.
Jacobs assigned a full-time operations manager (FTOM) for continued operations who coordinated with the FEMA COR to identify and work through numerous challenges during this disaster. Through TO management, the FTOM collaborated closely with FEMA to resolve applicant issues, support Hurricane Ida response, and complete authorized additional out‑of‑scope tasks, earning feedback such as “The guys did a fantastic job! Thank you all for the assistance.” and “Thanks for all your hard work!”
Contracts management focused on maintaining compliance with the contract and verifying our responses to FEMA’s requests were accurate, complete, and timely. Our contracts manager maintained open communication and an excellent working relationship with FEMA COs and CORs, resolving contract/TO matters in a way that benefited both FEMA and Jacobs. FEMA’s Quality Assurance Surveillance Plan (QASP) rated us “Outstanding,” and applicants praised the team, including: “Applicant’s mother said that FEMA has the best maintenance staff that anyone could ask for!”
Contract management maintained 24/7 coordination with FEMA COs to confirm compliance, timely responses, and successful contract extensions, while customer satisfaction surveys—over 225 completed—yielded a 99.03% average rating, with applicants, noting “Passionate worker who takes the time to listen. Gets things done,” “Really blessed to have this mobile home to keep my family warm and safe,” and “Very impressed with maintenance. Very pleased with all you do.”
Relevance to Nebraska
Demonstrated Technical Expertise & FEMA Experience via project staffing depth across IA and technical housing roles Proven ability to leverage our Resource Reach Back & Subcontractor Teaming Strength to rapidly mobilize and operate within required timelines Strong contract compliance and performance, matching evaluation criteria and requiring integrity, efficiency, and historical success Illustrates capability to manage high‑volume, multi‑county disaster operations Includes extensive applicant support and customer communication, emphasizing community‑focused service delivery Coordination with FEMA leadership and CORs, demonstrating partnership and communication Provides evidence of quality assurance (QA) through FEMA QASP positive ratings and 99% customer satisfaction
Subcontractor Experience
Exhibit D. Subcontractor Relevant Project Summary Matrix
Subcontractor Name Project Name Client Role
Relevant Scope
PA IA HMA Grants
Arcus PATAC III, IV, and V FEMA Subcontractor X X
Flux PATAC IV and V FEMA Subcontractor X X
NDRtac PATAC III, IV, and V FEMA Subcontractor X X X
Arcus Key Project: PATAC III, IV, and V | FEMA
Time Period: PATAC III – 3/2014 to 12/2019; PATAC IV – 4/2019 to 11/2025; PATAC V – 4/2024 to Ongoing Completion Date(s): PATAC III – 2014; PATAC IV – 2025; PATAC V – Ongoing
Responsibilities: PA – construction management and project management grants Client Reference: Julia Ripley, CCPRS Resourcing Manager | Phone: 678.458.3975 | Fax: N/A | Email: Julia.Ripley@jacobs.com Our Role: Subcontractor to Jacobs (CCPRS) and NISTAC+ (PATAC V only) Share of Contract Cost: PATAC III 11%% | PATAC IV 9% | PATAC V 2%
Project Description and Services Provided
Arcus Consulting Group, LLC, provided comprehensive technical assistance in support of CCPRS and the FEMA PA program to help eligible applicants and FEMA staff throughout the disaster recovery lifecycle, delivering Technical Expertise & FEMA Experience.
The scope of work included 19 major disasters, 123 TOs, and 69 staff deployed across 18 states and territories (CA, NM, TX, MO, IA, NE, LA, NC, TN, PA, WI, FL, VA, DC, NJ, NY, Puerto Rico [PR], and the U.S. Virgin Islands [USVI]); delivering subject matter expertise in PA policy, regulations, and guidance; supporting applicant outreach, training, and technical briefings; assisting with project formulation, documentation, and eligibility determinations; and supporting development, review, and validation of project worksheets or equivalent documentation.
Arcus brought deep hazard mitigation expertise across critical infrastructure systems—including water/wastewater, power, schools, housing, hospitals, and marine structures—verifying that Nebraska projects met applicable technical and regulatory standards while aligning with FEMA mitigation policy and cost-effectiveness requirements.
Arcus also supported grants management activities; confirmed compliance with federal requirements (including environmental, historic preservation, and procurement standards); and performed QA activities to promote accuracy, consistency, and timeliness.
Services were performed in support of response, recovery, mitigation, and closeout activities and were delivered on-site, remotely, or in hybrid environments as required by FEMA. Exemplifying our Resource Reach Back & Subcontractor Teaming Strength, in total, Arcus deployed 30+ staff within 2 weeks and 50+ staff within 1 month.
Arcus staff conducted comprehensive site inspections to validate infrastructure damage caused by springtime snowmelt and heavy rains that resulted in widespread flooding across Nebraska. Roads, bridges, and culverts were washed out, disrupting rural livelihoods and critical transportation networks used to move agricultural commodities. The team traveled extensively to reach remote, heavily impacted communities where hundreds of roadway systems in some counties needed repair or replacement. Inspectors worked closely with local highway departments and applicants to verify all damaged sites were accurately identified and documented to fully restore transportation infrastructure.
During site inspections, the team quantified and documented disaster-related damage, including debris impacts, and prepared detailed damage descriptions that included photographs and site sketches. They developed scopes of work and cost estimates for large projects, complying with applicable laws, regulations, policies, and relevant codes and standards while also identifying special consideration issues. Inspectors coordinated with other PA staff, obtained applicant concurrence on documented damages, and delivered completed inspection packages to the Site Inspection Task Force Leader and Program Delivery Manager in a timely manner.
All site inspections and cost estimates were completed within 8 months to support recovery and rebuilding efforts across the affected regions.
Relevance to Nebraska
Deep hazard mitigation expertise across critical infrastructure systems—including water/wastewater, power, schools, housing, hospitals, and marine structures—verifying Nebraska projects meet technical and regulatory standards
Advanced cost‑estimating tools and methodologies that speed project formulation while improving accuracy and reducing the risk of FEMA eligibility issues
Proven ability to operate across technical, operational, and public‑facing dimensions of disaster recovery, including policy interpretation, compliance, documentation, and coordination with oversight bodies such as the Office of Inspector General and Government Accountability Office
Demonstrated Nebraska field performance, including rural transportation infrastructure inspections, accurate damage documentation, and timely project packages that support faster obligations mailto:Julia.Ripley@jacobs.com
Rapid surge capacity to supplement NEMA during overlapping or high‑volume disasters, maintaining continuous service delivery Experience communicating with diverse stakeholders, preparing briefings and summaries that support state leadership decision‑making and strengthen transparency during recovery operations
FLUX Key Project: PATAC IV, V, | FEMA (CCPRS )
Time Period: PATAC IV – 4/2019 to 11/2025; PATAC V – 2024 to Ongoing Completion Date(s): PATAC IV – 2025; PATAC V – Ongoing Responsibilities: PA – construction management and project management; grants Client Reference: Julia Ripley, CCPRS Resourcing Manager | Phone: 678.458.3975 | Fax: N/A | Email: Julia.Ripley@jacobs.com Our Role: Subcontractor to Jacobs (CCPRS), Share of Contract Cost: PATAC IV 1% | PATAC V 4%
Project Description and Services Provided
Between April and June 2025, Flux Resources, LLC, supported Jacobs (CCPRS) on PATAC IV and V providing assistance for FEMA disasters across the U.S. with 406 mitigation, hydrology, soil/geotech engineer, program delivery management, and historical architecture. This included Local Experience, Presence, & Relationships through three federally declared disasters in the state of Nebraska—DR‑4778‑NE, DR‑4786‑NE, and DR‑4808‑NE. These events brought widespread severe storms, straight‑line winds, tornado activity, and flooding across multiple counties. Impacts included rural roadway washouts, damage to water control facilities, power infrastructure disruptions, structural damage to public buildings, and significant debris generation affecting local jurisdictions already resource‑constrained from previous events in the region. Leveraging Technical Expertise & FEMA Experience, Flux deployed experienced specialists across PA, IA, HMA, and grants management functions. Our work supported local applicants and the state, maintaining accurate documentation, rapid mobilization, and compliance with FEMA requirements under the Stafford Act.
Relevance to Nebraska
In-state experience bringing direct familiarity with Nebraska-specific disaster conditions; FEMA Region VII processes; and coordination with state, local, and federal stakeholders
Previous experience working directly with Jacobs leverages Resource Reach Back & Subcontractor Teaming Strength and enables immediate, lockstep integration into our reporting and quality systems—eliminating onboarding lag and delivering day-one efficiency for Nebraska
Technical Expertise & FEMA Experience: Expert PA staff who know how to apply advanced regulatory knowledge, integrate 406 mitigation during formulation, and manage Grants Manager efficiently—providing Nebraska’s rural and resource-constrained applicants with faster funding decisions, clean documentation, and resilient “build back better” solutions
IA specialists with deep Individuals and Households Program (IHP) Unified Guidance expertise and advanced National Emergency Management Information System proficiency deliver accurate eligibility decisions, reduce appeals and improper payments, and deliver faster, compassionate help for Nebraska disaster survivors.
Combining 404 and 406 strategy, expert-level benefit-cost analysis (BCA) development, and full lifecycle grants management, our team increases Nebraska’s rate of obligated mitigation funds by confirming every sub-application is FEMA-compliant, technically defensible, and resilience-focused.
NDRtac Key Project: PATAC III, IV, and V | FEMA Time Period: PATAC III – 2013 to 2018; PATAC IV – 2018 to 2024; PATAC V – 2024 to Ongoing Completion Date(s): PATAC III – 1/2021; PATAC IV – 1/2024; PATAC V – Ongoing Responsibilities: PA, IA, HMA
Client Reference: Julia Ripley, CCPRS Resourcing Manager | Phone: 678.458.3975 | Fax: N/A | Email: Julia.Ripley@jacobs.com Our Role: Subcontractor to Jacobs (CCPRS) Share of Contract Cost: PATAC III 6% | PATAC IV 4% | PATAC V 9%
Project Description and Services Provided
NDRtac successfully supported FEMA’s PA, IA, and Hazard Mitigation Grant Program (HMGP) programs by deploying qualified consultants and managing multiple TOs through closeout. Under PATAC III and IV, they provided disaster recovery services across 10 states and territories—including NE, IA, MO, TX, FL, NM, NY, NJ, PR, and USVI—following major events such as severe flooding and Hurricanes Sandy, Harvey, and Irma. Leveraging their Technical Expertise & FEMA Experience, their teams supported every stage of the recovery process, from preliminary damage assessments through closeout, leveraging a diverse cadre of FEMA‑experienced specialists trained in both technical requirements and customer service. All personnel were fully vetted through background checks and security‑clearance badging and equipped with the tools needed to deliver compliant recovery support quickly. During the 2017 sequence of Hurricanes Harvey, Irma, and Maria, NDRtac’s continuous recruiting pipeline enabled rapid mobilization—filling hundreds of resource needs across TX, FL, PR, and USVI within days.
To deliver comprehensive, end‑to‑end disaster recovery support, our team worked with Jacobs to deliver Resource Reach Back & Subcontractor Teaming Strength by deploying a diverse group of specialized professionals whose combined expertise provided technical accuracy, regulatory compliance, and efficient project execution. This included financial and analytical specialists who strengthened documentation and grant compliance, architects and civil and electrical engineers who provided technical assessments and design‑level support, and environmental and EHP experts who maintained alignment with federal standards. Our recovery personnel—including disaster recovery specialists, IA, and hazard mitigation professionals, program delivery managers (PDMGs), PA liaisons, and site inspectors—worked directly with applicants to assess damages, formulate eligible projects, and guide sub‑recipients through the full FEMA lifecycle. Closeout and auditing experts contributed to clean, defensible files and expedited obligations, while project managers and Consolidated Resource Center (CRC) staff maintained coordinated communication, proactive issue resolution, and streamlined workflows. Together, this multidisciplinary team delivered a high‑value, integrated approach that improved accuracy, accelerated timelines, and made sure applicants received the full benefits of FEMA programs with confidence and clarity.
Relevance to Nebraska
In-state experience includes DR-4420-NE and DR-4321-NE—deployed 20 Disaster Recovery FEMA PA consultants to Nebraska for severe winter storm, straight line winds, and flooding spanning May 2019 to January 2021. We successfully closed out on January 2021.
Direct partnership for Resource Reach Back & Subcontractor Teaming Strength, delivering seamless, lockstep alignment with Jacobs through CCPRS’ rigorous compliance guidance, proven QA/quality control (QC) processes, and surge-ready staffing model—driving efficient project delivery, transparent performance monitoring, and faster closeout approvals supported by strong CPARS and client feedback
Technical Expertise & FEMA Experience: 12+ years of PA expertise working directly with Jacobs across hurricanes, floods, fires, tornadoes, and earthquakes—applying Sandy Recovery Improvement Act (2013), Disaster Recovery Reform Act (2018), and FEMA’s PA Program and Policy Guide (2025) to use simplified procedures, document management costs, confirm eligibility for facilities like schools, and support state-led PA—backed by on-hand subject matter guidance and a QA/QC matrix that streamlines approvals and accelerates obligation and audit-ready closeout for the state
Experience supporting disasters’ most vulnerable applicants by guiding homeowners through the full IA process—helping them register for assistance, document damages accurately, and submit complete applications—making faster eligibility decisions, reducing administrative burden on NEMA, and accelerating recovery for communities that may have limited staff or disaster experience
1.9
n. SUBCONTRACTORS If the awarded bidder(s) intends to subcontract any part of its performance hereunder, the awarded bidder(s) should provide:
i. name, address, and telephone number of the subcontractor(s),
ii. specific tasks for each subcontractor(s),
iii. percentage of performance hours intended for each subcontract; and
iv. total percentage of subcontractor(s) performance hours.
No Response Required:
We’ve teamed with three subcontractors (summary information provided in Exhibit D below)to provide additional surge support and capability to respond to any disaster support needs. This approach has been very effective for the FEMA PATAC contract—we’ve been extremely successful in fulfilling large staffing requirements with rapid deployments.
Our subcontractor partners include Arcus (veteran-owned small business [VOSB]), Flux, and NDRtac. We’ve successfully partnered with Arcus and NDRtac since 2012 and with Flux since 2019 in delivering FEMA PA disaster recovery work. As a result of our longstanding relationships and partnerships, we can efficiently ramp up to meet staffing needs with no learning curve. All three of our subcontractors have the staff capacity and capabilities to fill required roles. We’re not constrained by a specific number of hours per subcontractor but will work with the team to identify and deploy the best resources to meet disaster response needs.
As an example, in response to March 2019 floods in Nebraska (DR-4420-NE), Arcus and NDRtac provided staff to support the Jacobs PA team and all three subcontractors provided staff for the Region VII PA response that included the April–June 2025 floods in Nebraska Declared Disasters (DR-4778, DR-4786, and DR-4808-NE).
Exhibit D. Subcontractor Key Information Summary Key Information Subcontractor Name
Arcus Flux NDRtac
Address 2001 L St. NW, Suite 500 Washington, DC 20036
6950 SW Hampton St., Suite 338 Tigard, OR 97223
59 Court St., Suite 202 Binghamton, NY 13901
Phone 512.791.6036 563.723.1947 607.321.1088
Specific Task Support
PA, HMA PA, IA, HMA PA, IA, HMA
% of Performance Hours Intended
To be determined by TO and scope requirements
Total % of Performance Hours
We do not allocate fixed hours to any subcontractor; instead, we flexibly assign the right resources as needs evolve to make sure the state receives best-fit support for every preparedness and recovery need.
# Staff 75+disaster professionals 400+ disaster professionals 50+ disaster professionals
Nebraska- Specific Experience
FEMA-DR-4420-NE
FEMA-DR-4778-NE, DR-4786-NE,
and DR-4808-NE
FEMA-DR-4420-NE and DR-4321-
NE
TECHNICAL RESPONSE
2.1
Describe bidder’s process for providing PA technical services.
The bidder should address the following:
i. Bidder’s process for reviewing projects for sub-recipients not yet obligated by FEMA
ii. Bidder’s process for reviewing projects for sub-recipient(s) after obligation to ensure eligible payments made to sub-recipient(s) and smooth closeout process
• Bidder’s process for working with sub-recipients to ensure needs of project are met (Please provide at least one narrative description of previous work with a sub-recipient)
Response:
Disaster planning, response, and recovery environments are complex and have compressed timelines and increasingly expanding intergovernmental roles. While federal disaster programs such as FEMA’s PA framework continue to provide critical guidance and funding pathways, states are increasingly assuming greater operational responsibility, making faster decisions, and managing heightened compliance risk amid uncertainty. In this context, Nebraska’s ability to deliver timely, accurate, and defensible recovery outcomes depends on scalable capacity, technical rigor, and adaptable delivery models that are effective regardless of the level or structure of federal involvement—this is the core of our expertise.
Jacobs’ approach to PA and recovery support is intentionally designed to strengthen NEMA’s ability to lead, coordinate, and execute recovery activities across response, recovery, and planning phases. Rather than relying on rigid, dependent processes, Jacobs provides integrated technical, financial, and policy support that aligns with current federal requirements while remaining flexible enough to operate in state-led or hybrid delivery environments.