This document is a Performance Work Statement (PWS) for a Management and Administration specification item covering services to be provided under a federal contract with the Navy/NAVFAC.

The PWS establishes comprehensive management, administrative, safety, environmental, and personnel requirements for contractor operations. Key management requirements include staffing a Project Manager, Quality Manager, Site Safety and Health Officer (SSHO), and Environmental/Energy Manager, with specified minimum experience levels (5 years for PM and Quality Manager; 5 years or 3 years with CSP certification for SSHO). The contractor must maintain a Quality Management System with documented inspections and surveillance, develop and implement an Accident Prevention Plan (APP) and Activity Hazard Analyses (AHAs), and establish security protocols including DBIDS enrollment for personnel, background screening, and access controls. Administrative deliverables include monthly on-site labor reports, safety inspection reports, quality inspection and surveillance reports, and various compliance documentation. Government working hours are 0700-1600, Monday-Friday, with certain annexes requiring 24/7 operations. The contractor must procure and maintain minimum insurance coverage including $500,000 comprehensive general liability, $200,000-$500,000 automobile liability, and workers' compensation as required by law. Environmental and sustainability requirements mandate compliance with installation Environmental Management System goals, energy conservation, water conservation planning, hazardous materials management, waste disposal (regulated and non-regulated), spill prevention and reporting, and use of environmentally preferable products. Safety program requirements reference EM 385-1-1 and OSHA standards, with specific compliance plans for confined spaces, fall protection, critical lifts, lockout/tagout, and pathogen exposure. The PWS also addresses recurring and non-recurring work procedures, with recurring work priced using Unit Priced Tasks (UPTs) and non-recurring work utilizing Unit Priced Labor (UPL) with detailed cost estimating requirements based on industry standards such as R.S. Means.

View the file

Other files

File Type Posted
N4008025R4580 8A GROUNDS RFI Sheet w Answers.pdf PDF
N4008025R4580 8a Grounds Solicitation Synopsis Revised.pdf PDF
J-1503050-08 Washington Revised.xlsx XLSX spreadsheet
Leumas CBA (Signed by the Union and Companies) 2023.pdf PDF
J-1503050-08 Quantico Revised.xlsx XLSX spreadsheet
N4008025R4580 8A GROUNDS RFI Sheet w Answers.pdf PDF
J-1503050-17(h4) SN_SWPPP_2022.pdf PDF
J-1503050-17(h2) Stump Neck Map.pdf PDF
J-1503050-17(h1) Indian Head Map.pdf PDF
J-1503050-08 Indian Head Final.xlsx XLSX spreadsheet
J-1503050-17(h3) IH_SWPPP_2022.pdf PDF
J-1503050-16(g2) Dahlgren_HerbicideApp_Oct2024.pdf PDF
J-1503050-16(g1) Dahlgren_GroundMaint_Dec2024.pdf PDF
J-1503050-8 Dahlgren Final Inventory KDC 20241101.xlsx XLSX spreadsheet
J-1503050-16(g3) PumpkinNeck_GroundMaint_Oct2024.pdf PDF
New Attach J-2000000-10 Blank ELIN 8a Regional Grounds Rewrite.xlsx XLSX spreadsheet
J Attach 5.2 WD 15-4329 Rev 32.pdf PDF
J Attach 5.0 WD 15-4269 Rev 31.pdf PDF
J Attach 4.0 secnav5512.pdf PDF
Section J 1503060 All Maps.pdf PDF
Section J 1503060-10 Maps and Excel Sheet List.pdf PDF
J-1503050-11(a) Washington SWD Systems Inventory.xlsx XLSX spreadsheet
J-1503050-09(a) Irrigation System Inventory.xlsx XLSX spreadsheet
J Attach 2.2 - 1503060 F Pvmt Clear v2.4 20240701 KDC.pdf PDF
N4008025R4580 Exhibits A-E.pdf PDF
J-1503060-05 Bethesda.xlsx XLSX spreadsheet
J Attach 3.2 - 1503060 J Pvmt Clear v2.5.pdf PDF
J-1503050 13(a1 a4 a10 f1 f2) and excel sheets list.pdf PDF
J-1503050-11(f) Bethesda SWD Systems Inventory.xlsx XLSX spreadsheet
J-0200000-05(i) Contractor Incident Report System (CIRS).pdf PDF
J Attach 1.0 - 0100000 C General Info v2.4 rev 20200311 KDC 20240701.pdf PDF
J Attach 6.0 Perform Assess Plan - v3.3 Regional Grnds Maint & Pvmt Clear Serv.pdf PDF
J Attach 5.3 DSA CBA.pdf PDF
Section J 1503050-14 Maps Attachment List.pdf PDF
J-1503050-08 Quantico.xlsx XLSX spreadsheet
J-1503050-08 Bethesda.xlsx XLSX spreadsheet
J-0200000-08(e) MBQ Spill Emergency Notification Response Proced.pdf PDF
J Attach 2.0 - 0200000 F Mngmt & Admin v2.9 20240701 (1).pdf PDF
J Attach 5.1 WD 15-4281 Rev 35.pdf PDF
J-1503060-05 Washington.xlsx XLSX spreadsheet
Section J 1503050-15 Maps Consolidated.pdf PDF
J-1503050-08 Washington.xlsx XLSX spreadsheet
J Attach 3.1 - 1503050 J Grounds Maint & Landscaping v2.7.pdf PDF
J-0200000-08(f) Bethesda (NSAB)- Spill Contingency Plan.pdf PDF
Updated Attchment J-2000000-10 Blank ELIN Regional Grounds Rewrite Revised KDC.xlsx XLSX spreadsheet
J Attach 3.0 - 0200000 J Mngmt & Admin v2.7.pdf PDF
J Attach 2.1 - 1503050 F Grounds Maint & Landscape v2.4 20240701 KDC.pdf PDF
J Attach 1.3 - 1503060 C Pvmt Clear v2.5 20240701 KDC.pdf PDF
J Attach 1.2 - 1503050 C Grounds Maint & Landscape v2.7 20240701 KDC.pdf PDF
N4008025R4580 8a Grounds Solicitation Synopsis.pdf PDF
Show all 50

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

0200000 – Management and Administration

Spec Item Title

2 Management and Administration

2.1 Definitions and Acronyms

2.2 General Information

2.2.1 Government Regular Working Hours

2.2.1.1 Observed Federal Holidays

2.2.1.2 Restriction to Contractor Working Hours

2.2.2 Wage Determinations

2.2.3 Requirements Hierarchy

2.3 General Administrative Requirements

2.3.1 Required Conferences and Meetings

2.3.2 Training for Maintenance and Operation of New and Replacement Systems and Equipment

2.3.3 Partnering

2.3.3.1 Informal Partnering

2.3.3.2 Contract Partnering Administration

2.3.3.3 Contract Partnering Session Attendees

2.3.4 Permits and Licenses

2.3.5 Insurance

2.3.5.1 Certificate of Insurance

2.3.5.2 Minimum Insurance Amounts

2.3.6 Protection of Government Property

2.3.7 Directives, Instructions, and References

2.3.8 Invoicing Procedures

2.3.9 Forms

2.4 Government-Furnished Items

2.4.1 Government-Furnished Property (GFP)

2.4.2 Government-Furnished Facilities

2.4.3 Government-Furnished Vehicles and Equipment

2.4.4 Government-Furnished Utilities

2.5 Contractor-Furnished Items

2.6 Management

2.6.1 Safeguarding Information

2.6.2 Dissemination of Information

2.6.3 Work Reception

2.6.4 Work Control

2.6.5 Work Schedule

2.6.6 Deliverables

2.6.7 Service Interruptions

2.6.8 NAVFAC Maximo- Not Used

2.6.8.1 NAVFAC Maximo Data- Not Used

2.6.8.2 NAVFAC Maximo Method of Data Entry- Not Used

2.6.8.3 NAVFAC Maximo Access- Not Used

2.6.8.4 NAVFAC Maximo Training- Not Used

2.6.9 Quality Management System (QMS)

2.6.9.1 Quality Management (QM) Plan

2.6.9.2 Quality Inspection and Surveillance

2.6.9.3 Quality Inspection and Surveillance Report

2.6.10 Property Management Plan

2.6.11 System and Equipment Replacement

2.7 Personnel Requirements

2.7.1 Key Personnel

2.7.1.1 Project Manager (PM)

2.7.1.2 Quality Manager

2.7.1.2.1 Quality Control Personnel

2.7.1.3 Site Safety and Health Officer (SSHO)

2.7.1.4 Environmental/Energy Manager

2.7.2 Employee Requirements

2.7.2.1 Employee Certification and Training

2.7.2.2 Employee Appearance

2.7.2.3 Employee Conduct

2.7.2.4 Identification as Contractor Employee

2.7.2.5 Removal of Employees

2.7.2.6 Proof of Legal Residency

2.7.3 Service Contract Reporting (SCR)

2.8 Security Requirements

2.8.1 Employee Listing

2.8.2 Vehicles

2.8.3 Passes and Badges

2.8.4 Access to Installation

2.8.4.1 DBIDS Program

2.8.4.2 DBIDS Credentials

2.8.5 Access to Buildings

2.8.6 Access Arrangements

2.8.6.1 Escort Arrangement for Secured Areas

2.8.7 Security Clearances

2.8.8 Access to Controlled Unclassified Information

2.8.9 Access to Government Information Technology (IT), Operating Technology (OT), and Facility

Related Control Systems (FRCS)

2.8.10 Access to Navy Marine Corps Intranet (NMCI)

2.8.11 Employee Status

2.9 Contractor Safety Program

2.9.1 Contractor Safety Requirements

2.9.1.1 Experience Modification Rate (EMR)

2.9.1.2 OSHA Days Away From Work, Restricted Duty, or Job Transfer (DART) Rate

2.9.2 Accident Prevention Plan (APP)

2.9.3 Activity Hazard Analysis (AHA)

2.9.4 Safety and Occupational Health (SOH) Risks and Compliance Plans

2.9.4.1 Alcohol and Drug Abuse Prevention Plan

2.9.4.2 Chemical Hazard Communication Program

2.9.4.3 Confined Space Program

2.9.4.4 Critical Lift Plan

2.9.4.5 Fall Prevention and Protection Plan

2.9.4.6 Pathogen Exposure

2.9.4.7 Control of Hazardous Energy (lockout/tag out)

2.9.5 Crane Operations

2.9.5.1 Crane Inspections

2.9.5.2 Rigging Gear

2.9.5.3 Crane Operators

2.9.6 Accident and Damage Reporting

2.9.6.1 Accident Reporting and Notification Criteria

2.9.7 Fire Protection

2.9.8 Monthly On-Site Labor Report

2.9.9 OSHA Citations and Violations

2.9.10 Safety Inspections and Monitoring

2.9.11 Safety Certification

2.9.12 Safety Apparel on Jobsites

2.9.13 Emergency Medical Treatment

2.9.14 Excavations

2.10 Environmental Management and Sustainability

2.10.1 Energy Management Program

2.10.1.1 Water Conservation Plan

2.10.1.2 Energy Efficient Products

2.10.2 Environmental Protection

2.10.2.1 Sampling, Testing and Laboratory Services

2.10.2.2 ODS Requirements for Refrigerant Recycling- Not Applicable

2.10.2.3 Solid Waste Management and Recycling

2.10.2.4 Non-Regulated Waste Disposal

2.10.2.5 Regulated Waste Disposal

2.10.2.6 Universal Waste

2.10.2.7 Spill Prevention, Containment, and Clean-up

2.10.2.8 Hazardous Material Management

2.10.2.9 Protection of Endangered and Threatened Species (Flora and Fauna)

2.10.2.10 Noise Control

2.10.2.11 Salvage

2.10.2.12 Asbestos Containing Material (ACM)

2.10.2.13 Clean Air Act (CAA)

2.10.3 Sustainable Procurement and Practices

2.10.3.1 Environmentally Preferable Products

2.10.3.2 Use of Recovered Materials

2.10.3.3 Use of Bio-based Products

2.11 Disaster Preparedness

2.12 Technical Library

2.13 Warranty Management

2.14 Recurring Work Procedures

2.14.1 Recurring Work Preparation of Proposals

2.14.2 Notification to the Government for Work Above the Recurring Work Limitations

2.14.3 Recurring Work Exhibit Line Item Numbers (ELINs)

2.15 Non-Recurring Work

2.15.1 Unit Priced Task (UPT) Work (Non-Negotiated)

2.15.1.1 Acceptance and Performance

2.15.1.2 Invoicing and Receiving Payment

2.15.2 Unit Priced Labor (UPL)Work (Negotiated)

2.15.2.1 Non-recurring Work Preparation of Proposals

2.15.2.1.1 Labor Requirements

2.15.2.1.2 Direct Material and Construction Equipment Requirements

2.15.2.2 Issuance of Final Task Order

2.15.3 Non-Recurring Work ELINS

0200000 - Management and Administration

Spec Item Title Description

2 Management and

Administration

2.1 Definitions and

Acronyms

Definitions and Acronyms are listed in J-0200000-01.

2.2 General

Information

2.2.1 Government

Regular Working

Hours

The Government's regular working hours are from 0700-1600, five days per week, Monday through Friday, except observed Federal holidays. Exceptions to the regular hours of operation are detailed in subsequent sections of this

PWS. Work in certain annexes or sub-annexes require Contractor continuous operations, 24 hours a day, every day of the year including holidays. The performance of other work requirements shall be accomplished within the

Government’s regular working hours unless the specific work requirement specified herein necessitates otherwise. Any other work outside Government regular working hours must be authorized by the KO prior to commencement of work.

2.2.1.1 Observed Federal

Holidays

The Government observes the following holidays: New Year’s Day, Martin

Luther King Jr.’s Birthday, President’s Day, Memorial Day, Juneteenth

National Independence Day, Independence Day, Labor Day, Columbus Day, Veterans’ Day, Thanksgiving Day, and Christmas Day.

2.2.1.2 Restriction to

Contractor

Working Hours

If the Contractor wishes to work outside of the Government's regular working hours for the Contractor’s convenience, the Contractor shall submit a written

Request to Work Outside Government’s Regular Working Hours per Section

F. Excludes work to be performed during specified hours.

2.2.2 Wage

Determinations

Wage Determinations are included in J-0200000-02.

2.2.3 Requirements

Hierarchy

Requirements or definitions specified in each spec item of this contract apply to subordinate paragraphs. For example, requirements shown in spec item 3.1 would apply to spec items 3.1.1, 3.1.2, 3.1.2.1 and so on.

Likewise, Performance Standards specified at a lower digit level (i.e. spec item 3.1.1, 3.1.2, 3.1.2.1) apply when performance is assessed at a higher tier

(i.e., spec item 3.1) based on the composite work requirements.

2.3 General

Administrative

Requirements

2.3.1 Required

Conferences and

Meetings

The Contractor shall attend administrative and coordination meetings. The

Contractor shall provide sign-in sheets and prepare minutes of all meetings and submit per Section F for review and comments. Comments received within two working days shall be incorporated into the minutes and a copy of the final revision shall be submitted per Section F for concurrence.

Historically, there has been approximately one meeting per month.

2.3.2 Training for

Maintenance and

Operation of New and Replacement

Systems and

Equipment

When construction, renovation, or repair work is performed by means other than this contract, the Contractor shall attend Government provided training, as applicable, for maintenance and operation of new and replacement systems and equipment at no additional cost to the Government.

2.3.3 Partnering The Government requires cohesive partnerships with its Contractors and subcontractors. Key stakeholders, including the supported commands who may receive services, principal individuals from NAVFAC, the performance assessment team, and representative(s) of the installation(s) will be invited to participate in the partnering process. Key members of the prime and sub-contractor teams, including senior management personnel must participate.

The partnership will draw on the strength of each organization in an effort to achieve quality contract services done right the first time, within the contract price, as scheduled, and without any safety mishaps.

The goal of Partnering is to develop a cohesive team with common purpose, commitment and established communication processes.

2.3.3.1 Informal Partnering The Contracting Officer shall organize the initial Partnering Meeting with key personnel of the project team, including Contractor's personnel and

Government personnel. The initial session will be scheduled concurrent with the Pre-Performance Conference and held no later than 30 days after award and will be held at a Government provided facility as designated by the KO.

The Initial Informal Partnering Session will be conducted and facilitated using electronic media (a video and accompanying forms) provided by

Contracting Officer. The senior Government stakeholder present will lead the meeting, however, the Contractor’s PM or senior representative is encouraged to participate as co-lead.

The Partners will determine the frequency of the follow-on sessions.

2.3.3.2 Contract Partnering

Administration

Upon award, the ACO will contact the Contractor, supported command(s), Region, and Installation(s) stakeholders, and the performance assessment team to discuss implementation of partnering. A partnership agreement, The

Charter, should be in place as early as possible so issues arising, even before work begins, can be resolved using the issues resolution process.

Replacement of Core Management Team members (stakeholders who attended the initial session and manage the contract work day-to-day) is discouraged since it will disrupt the synergy that has been developed. If replacement of a team member proves to be unavoidable, a follow-on partnering session must be held to officially turn the responsibilities of the position over to the new member.

The Core Management Team consisting of the attendees below must be present during the initial and all follow-on partnering sessions. These are the core mandatory attendees. Other stakeholders may attend if they desire or as recommended by the partners.

2.3.3.3 Contract Partnering

Session Attendees

The Contractor shall bring the necessary personnel to successfully partner on this contract. Asterisk indicates mandatory personnel.

President/Vice President

* Project Manager

* Quality Manager

Site Safety and Health Officer

2.3.4 Permits and

Licenses

The Contractor shall obtain all required permits, licenses, and authorizations to perform work under this contract and comply with all the applicable

Federal, state and local laws and regulations. The Contractor shall submit copies of Permits and Licenses per Section F.

2.3.5 Insurance The Contractor shall submit a Certificate of Insurance per Section F as evidence of the existence of the following insurance coverage in amounts not less than the amounts specified below in accordance with the FAR Clause

52.228-5, INSURANCE – WORK ON A GOVERNMENT

INSTALLATION. This insurance must be maintained during the performance period.

2.3.5.1 Certificate of

Insurance

The Certificate of Insurance shall provide for at least 30 calendar days written notice to the KO by the insurance company prior to cancellation or material change in policy coverage. Other requirements and information are contained in the aforementioned insurance clause.

2.3.5.2 Minimum

Insurance Amounts

The Contractor shall procure and maintain, during the entire period of performance under this contract, the following minimum insurance coverage:

Comprehensive General Liability: $500,000 per occurrence

Automobile Liability: $200,000 per person, $500,000 per occurrence, $20,000 per occurrence for property damage

Workmen's Compensation: As required by Federal and state worker's compensation and occupational disease statutes

Employer's Liability coverage: $100,000, except in states where worker's compensation may not be written by private carriers

Other as required by state law

2.3.6 Protection of

Government

Property

During execution of the work, the Contractor shall protect Government property. The Contractor shall return areas damaged as a result of Contractor negligence under this contract to their original condition at no cost to the

Government.

2.3.7 Directives, Instructions, and

References

Department of Defense (DoD), Secretary of the Navy (SECNAV), Chief of

Naval Operations (OPNAV), and other applicable Directives, Instructions, and References are listed in J-0200000-03. The Contractor shall comply with the most current version of directives, instructions, and references including versions published during the term of the contract.

2.3.8 Invoicing

Procedures

Refer to Section G for invoicing instructions. Refer to Invoice Form in J-

0200000-04 for sample.

Invoices shall be submitted in a format compatible with the most recent

Government installed Microsoft Office Version (currently 2016). Invoice data shall be capable of being sorted by CLIN, annex/sub-annex, spec item, spec item title, and ELIN/Sub-ELIN.

2.3.9 Forms Forms referenced in this Annex, e.g. accident reporting, and damage reporting are included among the Forms in J-0200000-05.

2.4 Government-

Furnished Items

Except for items identified below as Government-Furnished, the Contractor shall furnish all labor, supervision, management, tools, materials, equipment, facilities, transportation, incidental engineering, and other items necessary to provide the services described in this Performance Work Statement (PWS).

2.4.1 Government-

Furnished Property

(GFP)

Government- Furnished Property is not provided.

2.4.2 Government-

Furnished Facilities

Government- Furnished Facilities are not provided.

2.4.3 Government-

Furnished Vehicles and Equipment

Government- Furnished Vehicles and Equipment are not provided.

2.4.4 Government-

Furnished Utilities

The Government will furnish water and electricity at existing outlets required for the work to be performed under the contract. The Contractor shall provide and maintain, at its expense, the necessary service lines from the existing

Government outlets to the work site. Provide and maintain backflow prevention devices on connections to domestic water lines and electrical transformer provisions on connections to electric lines. Meet all Federal, State, local, and installation codes and regulations for backflow prevention devices and electrical transformer provisions. Services required by the

Contractor, for which there are no available Government outlets, shall be provided by the Contractor at no cost to the Government.

2.5 Contractor-

Furnished Items

Except for items identified as Government Furnished, the Contractor shall provide all equipment, materials, parts, supplies, components, and facilities to perform the requirements of this contract. The KO may inspect Contractor-furnished items for adequacy and compliance with contract requirements.

Inadequate or unsafe items shall be removed and replaced by the Contractor at no cost to the Government. Materials containing asbestos, lead, and polychlorinated biphenyls (PCBs) shall not be brought onsite. Energy efficient tools and equipment shall be used when available. The KO may at any time require Samples, Safety Data Sheets (SDS) or Manufacturer’s Data

Cut Sheets of Materials used in this contract.

2.6 Management The Contractor shall manage the total work effort associated with the services required herein to meet the performance objectives and standards. Such management includes but is not limited to planning, scheduling, cost accounting, report preparation, establishing and maintaining records, and quality assurance. The Contractor shall provide a staff with the necessary management expertise to ensure performance objectives and standards are met.

2.6.1 Safeguarding

Information

The Contractor shall safeguard controlled unclassified information and information associated with Government property in accordance with the latest revision of CNSSI 1253, DoDI 8582.01, NIST SP 800-53, NIST SP

800-171, SECNAV Defense Industrial Base (DIB) Memo, and applicable contract clauses. At a minimum, this information shall be protected at the moderate confidentiality level as defined in NIST SP 800-171.

Contractor information and data systems that contain information associated with Government property shall comply with DoD Risk Management

Framework (RMF).

The Contractor shall develop Plans of Action and Milestones (POA&Ms) per

NIST SP 800-171, track accomplishment, and submit to the Government per

Section F.

If a cybersecurity incident is encountered or suspected related to any

(Contractor or Government) Information Technology (IT) or Operating

Technology (OT) systems, including Monitoring and Control Systems, the

Contractor shall notify the Government per Section F.

2.6.2 Dissemination of

Information

DoD policy limits the dissemination of certain information. Instructions, Directives, and References not releasable to the public, e.g., Floor Plans, Maps, Post Orders, and Standard Operating Procedures, will be made available after contract award to the successful offeror with appropriate credentials and a need to know.

2.6.3 Work Reception The Contractor shall provide the capability to receive, prioritize, correspond, and respond to trouble/service calls and task orders during Government regular working hours and provide a point of contact at a local or toll free number who can perform the above function during other than Government regular working hours.

2.6.4 Work Control The Contractor shall implement all necessary work control procedures to ensure timely accomplishment of work requirements, as well as to permit tracking and reporting of work in progress. The Contractor shall plan and schedule work to assure material, labor, and equipment are available to complete work requirements within the specified time limits and in conformance with the quality standards established herein. Verbal scheduling and work status updates shall be provided when requested by the

Government. A status update of any item of work must be provided within two hours of the inquiry during regular working hours, and by 0800 the following work day for inquiries after regular working hours.

The Contractor shall provide work schedules for both Recurring and Non-

Recurring Work per Section F. At a minimum, work schedules shall include:

Description of service(s) to be accomplished

Location

Date service(s) are scheduled to be accomplished

2.6.5 Work Schedule The Contractor's work shall not interfere with normal Government business.

In those cases where some interference is unavoidable, the Contractor shall minimize the impact and effects of the interference. The Contractor shall provide advance access of all of its work schedules to the Government. The

Contractor shall provide written notification of any difficulty in scheduling work due to Government controls, per Section F. At a minimum, the notification shall include the following:

The date and time the work was initially coordinated.

The name and phone number of the Government person with whom the work was initially coordinated.

The name and phone number of the Government person who prevented the work from being performed as previously coordinated.

The alternative date and time, the Government person requested the work be accomplished.

2.6.6 Deliverables Except where otherwise stated, deliverable requirements are specified in

Sections C, F, H, I, J, and within the Directives, Instructions, and References.

The Contractor shall submit accurate and complete documents within the specified timeframes. The Contractor shall revise/modify deliverables, as directed by the KO, at no additional cost to the Government.

Except where otherwise specified, all deliverables shall be submitted electronically in a Microsoft Office Version 2010 compatible format.

Deliverables shall include the company name, contract number, contract title, date, and shall be unprotected and capable of being sorted by CLIN, work order number, asset number, section, annex/sub-annex, spec item and

ELIN/Sub-ELIN or clause. All formulas shall be traceable.

Government acceptance of deliverables shall not relieve the Contractor of the responsibility for any error or omission which may exist in the deliverable, as the Contractor is responsible for all requirements of this contract.

The Contractor shall establish and maintain a secure website for posting an electronic copy of all deliverables listed in Section F. The Contractor shall allow only authorized Government and Contractor personnel to access the website. Government personnel access shall be limited to viewing and downloading of deliverables, but restricted from posting to the website. The

Contractor shall notify the Government by email whenever there are new or updated deliverables posted to the website. Each deliverable posting on the website and each email notification shall include the title of the deliverable, the spec item requiring the deliverable, and the date and time the deliverable was posted. All deliverables shall be available to authorized Government personnel 24 hours/day and 365 days/year for the duration of the contract.

2.6.7 Service

Interruptions

If any utilities or other services must be discontinued (even temporarily) due to scheduled contract work, the Contractor shall notify the KO, COR, affected tenants, and customers in accordance with Section F local procedures. If the discontinued service is due to an emergency breakdown the Contractor shall notify the KO, COR, affected tenants, and customers as soon as practicable and provide the status of repairs, as directed by the KO, until normal operation is restored.

Scheduled utility outages and interruptions to equipment, system(s) operation, or other services shall be scheduled after hours of operation.

The Contractor shall shutdown, restart, and perform operational checks on all equipment affected by both scheduled and unscheduled utility outages and service interruptions, at no additional cost to the Government.

2.6.8 NAVFAC

Maximo- Not Used

NAVFAC Maximo is the Computerized Maintenance Management System

(CMMS) used by the Government for work order history, asset management, and condition assessment. The Contractor shall provide all required data for

NAVFAC MAXIMO as identified below:

Informational Note:

Not all supported commands’ assets are included in NAVFAC Maximo. Not all of the modules available within the Maximo application are utilized by

NAVFAC and the modules utilized may not be fully implemented.

NAVFAC Maximo does not include a detailed inventory of all assets, components, and equipment that the Contractor is required to service under this contract and may include inaccuracies, omissions, and redundancies.

2.6.8.1 NAVFAC Maximo

Data- Not Used

2.6.8.2 NAVFAC Maximo

Method of Data

Entry- Not Used

2.6.8.3 NAVFAC Maximo

Access- Not Used

2.6.8.4 NAVFAC Maximo

Training- Not Used

2.6.9 Quality

Management

System (QMS)

The Contractor shall establish and maintain a complete QMS program in accordance with the provisions specified herein. The Contractor’s QMS program shall provide an effective and efficient means of identifying and correcting problems throughout the entire scope of operations. The

Contractor's QMS program shall address:

Accurate documentation of work processes, procedures, and output measures.

A systematic procedure for assessing compliance with performance objectives and standards.

Accurate documentation of quality inspections and surveillance conducted throughout the execution of work.

Assessment-driven corrective actions and process adjustments as appropriate in a timely manner.

2.6.9.1 Quality

Management (QM)

Plan

The Contractor shall develop and submit a QM Plan per Section F. The QM

Plan shall describe the QMS methodology and approaches used under this contract. If any changes are made during the period of performance, the

Contractor shall submit the revised QM Plan for acceptance, per Section F.

The Contractor’s QM Plan shall include, at a minimum, the following:

• Policy and objectives of Quality Management System (QMS)

• Quality organization o List of personnel o Responsibilities & lines of authority o Training and qualifications

• Approach to assuring quality of services provided and conformance with performance objectives and standards

• Methods and procedures for effective planning, operation and control of processes and performance of work

• Procedures for inspection and surveillance of services to include all contractual requirements.

o Scheduling and performance of inspection and surveillance o Measurement, data collection and analysis o Corrective action, preventive action, and continuous improvement o Oversight of subcontracted work

• Documentation and records management

• Communication with government (customers)

2.6.9.2 Quality Inspection

and Surveillance

The Contractor shall establish and maintain an inspection and surveillance system in accordance with the FAR Clause 52.246-4, INSPECTION OF

SERVICES – FIXED PRICE, to ensure that the work performed conforms to the contract requirements. The Contractor shall document and maintain a file of all scheduled and performed inspections and surveillances, inspection and surveillance results, and dates and details of corrective and preventive actions. The quality inspection and surveillance file shall be the property of the Government and made available during the Government’s regular working hours. The file shall be submitted to the COR after completion/termination of the contract per Section F.

2.6.9.3 Quality Inspection

and Surveillance

Report

The Contractor shall submit a copy of the Contractor Quality Inspection and

Surveillance Report per Section F. The Contractor Quality Inspection and

Surveillance Report shall include a narrative of events, a tabulated summary and results of the quality inspection and surveillance events performed, inspection-driven corrective actions taken and the results attained, and management process adjustments during the previous month. The

Government may adjust the frequency of the submittal based on the

Contractor’s quality of performance.

2.6.10 Property

Management Plan-

Not Used

2.6.11 System and

Equipment

Replacement-Not

Used

2.7 Personnel

Requirements

The Contractor shall comply with the personnel requirements stated below:

2.7.1 Key Personnel The Contractor shall submit a List of Key Personnel and Qualifications per

Section F. The Contractor shall provide any additional information requested by the KO or COR necessary to validate their qualifications.

The Contractor shall submit an Organizational Chart per Section F showing lines of authority of the key personnel and on-site supervisor(s) for this contract. The chart shall include names of personnel and their position title in this contract. As a minimum, include the PM, Quality Manager, SSHO, and on-site supervisor(s) and who they will report directly to for this contract.

The key personnel shall be revised as applicable for the contract.

The Contractor shall provide complete resumes for proposed substitutes and any additional information requested by the KO. Proposed substitutes shall have comparable qualifications to those of the persons being replaced. The

KO will notify the Contractor within 15 calendar days after receipt of all required information of the consent on substitutions. No change in fixed unit prices may occur as a result of key personnel substitutions.

2.7.1.1 Project Manager

(PM)

The Contractor shall provide a PM and designated alternate, as applicable, who shall have full authority to act for the Contractor on all contract matters relating to this contract. The PM or alternate shall be on-site during the

Government's regular working hours and shall be available on-site within one hour after the Government's regular working hours.

The PM shall have at least five years of experience in managing a workforce providing services on contracts of similar size, scope and complexity.

2.7.1.2 Quality Manager The Contractor shall provide a Quality Manager or designated alternate who shall be on-site at all times when the Contractor is performing work during the Government's regular working hours and shall be available on-site within two hours after the Government’s regular working hours. The Quality

Manager or designated alternate shall report directly to a senior corporate official and shall not report directly to the Project Manager.

The Quality Manager or designated alternate shall have fulfilled the following pre-requisite training and experiences before being hired as the Quality

Manager under this contract:

The Quality Manager or designated alternate shall have at least five years of experience in preparing and enforcing QMS programs on contracts of similar size, scope and complexity. The Quality Manager or designated alternate shall not be the same person as the SSHO.

2.7.1.2.1 Quality Control

Personnel

The Contractor shall provide Quality Control personnel whose primary duty and responsibility is to enforce the Contractor’s Quality Management System on this contract. The Quality Control personnel shall be on-site at all times when the Contractor is performing work during the Government's regular working hours. The Quality Control personnel shall report directly to the

Quality Manager and shall not report directly to the Project Manager.

Quality Control personnel shall have fulfilled the following pre-requisite training and experiences before being hired as Quality Control under this contract:

Quality Control personnel shall meet or exceed the qualifications, technical knowledge and experience requirements specified for the personnel performing the work, which they will be inspecting, and have at least three years of experience in enforcing QMS programs on contracts of similar size, scope and complexity.

2.7.1.3 Site Safety and

Health Officer

(SSHO)

The SSHO must meet the requirements of EM 385-1-1 Section 1 and ensure that the requirements of 29 CFR 1926.16 are met for the project. Provide a

Safety oversight team that includes a minimum of one Competent Person at each project site to function as the Site Safety and Health Officer (SSHO).

The SSHO or an equally-qualified Designated Representative/alternate shall be on-site at all times when work is being performed to implement and administer the Contractor's safety program and government-accepted

Accident Prevention Plan. The SSHO's training, experience, and qualifications shall be as required by EM 385-1-1 paragraph 01.A.17, entitled

SITE SAFETY AND HEALTH OFFICER (SSHO), and all associated sub-paragraphs.

A Competent Person shall be provided for all of the hazards identified in the

Contractor's Safety and Health Program in accordance with the accepted

Accident Prevention Plan, and shall be on-site at all times when the work that presents the hazards associated with their professional expertise is being performed. Provide the credentials of the Competent Persons(s) to the

Contracting Officer for acceptance in consultation with the Safety Office.

The Contractor shall provide a SSHO whose primary duty and responsibility is to prepare and enforce the Contractor’s safety program on this contract.

The SSHO shall have fulfilled the following pre-requisite training and experiences before being hired as the SSHO under this contract:

The SSHO shall have completed five years of satisfactory experience in preparing and enforcing safety programs on contracts of similar size and complexity in the past or three years’ experience if he possesses a Certified

Safety Professional (CSP) or safety and health degree. The SSHO shall have completed the OSHA 30-hour construction safety class or equivalent and maintain competency through 24 hours of formal safety and health related coursework every four years. The SSHO shall not be the same person as the project manager.

2.7.1.4 Environmental/

Energy Manager

The Contractor shall provide an Environmental/Energy Manager whose primary duty and responsibility is to ensure Contractor operations adhere to the goals and policies of the Environmental Management System, the

Installation Energy Plan, and other specified Sustainability requirements affecting this contract. The Environmental/Energy Manager shall develop, implement and monitor environmental strategies, policies and programs that promote sustainable development and examine the contract activities to establish where improvements can be made and ensure compliance with environmental legislation and energy policy.

The Environmental/Energy Manager shall have a minimum two years’ experience with environmental procedures similar to those of this contract;

familiarity with Environmental Management Systems (EMSs); and knowledge of environmental regulations and federal energy laws and policy

(including energy and water reduction requirements and renewable energy requirements) that are applicable to operations similar to those of this contract.

2.7.2 Employee

Requirements

The Contractor shall provide experienced, qualified, and capable personnel to perform the work in this contract. Personnel shall be fully knowledgeable of all safety, environmental, and energy requirements associated with the work they perform. Personnel shall speak, read, and comprehend English to the extent that they can perform the contract requirements and comply with installation emergency procedures.

2.7.2.1 Employee

Certification and

Training

The Contractor shall maintain personnel certification, training, and licensing records for employee requirements specified herein and within all technical annexes/sub-annexes. Certification, training, and licensing records shall be kept current and on file for the duration of the contract including all option periods. Records shall be made available for Government review within 4 hours of request.

The Contractor shall ensure that all Contractor personnel have received proper safety training, appropriate to their respective jobs. At a minimum, all

Contractor personnel shall have attended the OSHA 10-hour safety course, or equivalent. The Contractor shall implement an ongoing training program that refreshes the safety skills, qualifications and awareness of the Contractor workforce on a regular, periodic basis. The details of the Contractor’s safety training program shall be included as part of the Contractor’s Accident

Prevention Plan, as required in Spec Item 2.9.2 below.

2.7.2.2 Employee

Appearance

The Contractor shall ensure that all employees present a professional appearance that is appropriate for their position. The KO reserves the right to determine the acceptability of any clothing worn. All

Contractor/subcontractor employees working under this contract shall be identified by a distinctive nameplate, emblem, or patch attached in a prominent place on an outer garment. Employee identification shall not be substituted for station required passes or badges.

2.7.2.3 Employee Conduct Contractor employees shall conduct themselves in a proper, efficient, courteous and businesslike manner.

2.7.2.4 Identification as

Contractor

Employee

Contractor employees shall identify themselves as Contractor personnel by introducing themselves or being introduced as Contractor personnel and displaying distinguishing badges or other visible identification for meetings with Government personnel. All Contractor employees shall appropriately identify themselves as contractor employees in both verbal communication and electronic or written correspondence.

2.7.2.5 Removal of

Employees

The Contractor shall remove from the site any individual whose continued employment is deemed by the KO to be contrary to the public interest or inconsistent with the best interests of National Security.

2.7.2.6 Proof of Legal

Residency

No employee or representative of the Contractor will be admitted to the site of work unless satisfactory Proof of Legal Residency is submitted per Section

F.

2.7.3 Service Contract

Reporting (SCR)

The Contractor shall report total dollar amount invoiced and all contractor labor hours (including subcontractor labor hours) required for performance of services provided under this contract via a secure data collection site. The contractor is required to completely fill in all required data fields using the following web address: https://www.sam.gov.

Per Section F, reporting inputs will be for the labor executed during the period of performance during each Government fiscal year (FY), which runs

October 1 through September 30. While inputs may be reported any time during the FY, all data shall be reported no later than October 31 of each calendar year. Contractors may direct questions to the help desk, linked at https://www.sam.gov.

2.8 Security

Requirements

The Contractor shall comply with all Federal, state, and local security statutes, regulations, and requirements. The Contractor shall become https://www.sam.gov/ acquainted with and comply with all Government regulations as posted, or as requested by the KO when required to enter a Government site. The

Contractor shall ensure that all security/entrance clearances are obtained.

The Contractor shall ensure that Contractor personnel do not present a risk to security. By entering the installation, Contractor personnel are subject to installation, state, local and federal regulations and laws, including but not limited to debarment and criminal prosecution.

2.8.1 Employee Listing The Contractor shall maintain a current Employee List and submit per Section

F. The list shall include employee’s name, supervisor, company, and level of security clearance.

2.8.2 Vehicles The company name shall be displayed on each of the Contractor's vehicles in a manner and size that is clearly visible. All vehicles shall display a valid state license plate that complies with State Vehicle Code. Vehicles shall meet all other requirement of the State Vehicle Code, such as safety standards, and shall carry proof of insurance and state registration, if applicable.

2.8.3 Passes and Badges All Contractor employees shall obtain the required employee and vehicle passes. The Contractor employees must be able to obtain Common Access

Cards (CAC) in accordance with security requirements. Each employee shall wear the Government issued badge over the front of the outer clothing. When an employee leaves the Contractor's service, the employee's Passes and

Badges shall be confiscated by the Contractor immediately and returned within 10 calendar days.

2.8.4 Access to

Installation

All Contractor personnel shall obtain access to the installation through enrollment and registration into the Defense Biometric Identification System

(DBIDS).

The Contractor shall provide the KO with the name of their designated

Service Contractor Administrator (SCA) for enrollment in DBIDS. Once enrolled, the Contractor must provide the DBIDS Registrar with an approved employee list and then direct their employees to register into DBIDS.

2.8.4.1 DBIDS Program DBIDS is an enterprise identity management and perimeter installation access control solution in which Contractor personnel who enroll, and are approved, are subsequently granted access to the installation for a period up to three years, or the length of the contract, whichever is less, and are not required to obtain a new pass from the Base Pass and Identification Office for each visit.

There are no fees associated with obtaining a DBIDS credential.

The Government performs background screening and credentialing.

Throughout the year, the Contractor employee must continue to meet background screening standards. Periodic background screenings are conducted to verify continued DBIDS participation and installation access privileges. DBIDS access privileges will be immediately suspended or revoked if at any time a Contractor employee becomes ineligible.

2.8.4.2 DBIDS Credentials Contractor employees shall furnish a completed copy of the SECNAV 5512/1 form to obtain the required background check and visit the local Navy

Installation Visitor Control Center to obtain a DBIDS credential once approved. The SECNAV 5512/1 form and additional information about

DBIDS can be found at: https://www.cnic.navy.mil/om/dbids.html.

The Contractor may initiate the adjudication process when a background screen failure results in disqualification from participation in DBIDS and the

Contractor employees do not agree with the reason for disqualification. The

Contractor may also apply for a waiver when a background screening failure results in disqualification from participation in DBIDS. The Commanding

Officer will be the final waiver determination authority.

The Contractor shall immediately collect employee DBIDS credentials and notify the KO in writing:

(1) That an employee has departed the company without having properly returned or surrendered their DBIDS credentials.

(2) That there is a reasonable basis to conclude that an employee, or former employee, might pose a risk, compromise, or threat to the safety or security of the installation or anyone therein.

2.8.5 Access to

Buildings

The Contractor shall monitor and control access into restricted areas under their responsibility, allowing only those individuals who have been properly cleared into restricted areas or other controlled access areas. The Contractor shall comply with security requirements, plus those imposed by the installation Commander at all times. Personnel with access to restricted areas shall have the appropriate screening, and shall wear special badges authorizing access for those areas. Contractor personnel shall not enter restricted or controlled areas or installation facilities unless specifically authorized in performance of their duties. The Contractor shall secure all buildings and facilities entered during non-duty hours and will secure all building and facilities under the Contractor’s cognizance at the end of each work day or shift period.

2.8.6 Access

Arrangements

The Contractor shall make all arrangements through the appropriate office necessary to obtain access to buildings, facilities and other work areas, and when necessary, arrange for them to be opened and closed by the controlling authority. The Government may issue keys to the Contractor. The

Contractor shall use due diligence and be responsible for compromised security systems to include replacement costs that result from its action or inaction.

2.8.6.1 Escort

Arrangement for

Secured Areas

The Contractor shall make arrangements for Government escort into secured areas requiring escort. The KO will provide information on applicable buildings, spaces and the appropriate point of contact.

The Contractor may experience delays while waiting for escorts. The

Government estimates the wait period can be up to 15 minutes. The

Contractor shall notify the Government Performance Assessment

Representative (PAR) and appropriate point of contract if an escort is not available after 15 minutes and access to accomplish the work is denied.

Unscheduled requirements, e.g., trouble calls, may require a longer wait for an escort.

2.8.7 Security

Clearances

The Contractor shall obtain all required corporate and personnel Security

Clearances, prior to commencement of work, at no additional cost to the

Government. The Contractor shall ensure that a list of all personnel with

Security Clearances is maintained current, including clearances that are pending.

2.8.8 Access to

Controlled

Unclassified

Information

The Contractor personnel whose work involves access to controlled unclassified information shall undergo a Tier 3 Investigation to verify their trustworthiness. If the Contractor personnel currently have a favorably adjudicated Tier 3 Investigation the Contractor shall notify the Government

Command Security Manager who will validate this in the Joint Personnel

Adjudication System (JPAS).

The Contractor shall request from the Government for access to the E-QIP

Direct program for the Contractor employees to complete the SF-86 form on line for a Tier 3 Investigation. The Security Manager will determine suitability. Upon a favorable Tier 3 Investigation, the Contractor personnel shall submit the original signed release statements, and an OF-306

Declaration for Federal Employment to the Security Manager per Section F.

Upon submission of the necessary documentation through E-QIP, the

Contractor Employee shall provide digital fingerprints. The Contractor’s

Security POC shall notify the COR and the Security Manager when

Contractor Employees have submitted their fingerprints.

The request shall be renewed annually or for the duration of the contract if less than one year.

2.8.9 Access to

Government

Information

Technology (IT), Operation

Technology (OT), and Facility

Related Control

Systems (FRCS)

Personnel accessing Government IT and OT systems to include but not limited to Maximo, DMLSS, DDC, and SCADA are in positions considered

Non-Critical Sensitive/IT-II and require a Tier 3 investigation to verify their trustworthiness.

Prior to being granted access to Government IT, OT, and FRCS systems, personnel shall have a favorably adjudicated Tier 3 Investigation, obtain a

CAC in accordance with security requirements, successfully complete required training, submit a Systems Authorization Access Request (SAAR)

Form, and meet all eligibility requirements.

Personnel accessing Government IT, OT, and FRCS systems shall complete annual required training such as cyber assurance awareness, information security (INFOSEC) awareness, and operations security (OPSEC) awareness.

The Contractor shall submit a list of personnel requiring access to

Government IT, OT, and FRCS systems per Section F.

2.8.10 Access to Navy

Marine Corps

Intranet (NMCI)

The Contractor may be required to access Navy Marine Corps Intranet

(NMCI). Prior to being granted access to NMCI, Contractor employees shall obtain a CAC in accordance with security requirements, successfully complete required training, submit a Systems Authorization Access Request

(SAAR) Form, and meet all eligibility requirements.

2.8.11 Employee Status The Contractor shall notify the KO of any changes to any employee’s status to include, but not limited to, termination, convictions/arrests, adverse actions taken on the job for any reason or any other documented misbehavior that may affect, or have the potential to affect, security standing in terms of access to federal facilities or IT systems.

2.9 Contractor Safety

Program

The Contractor shall develop and implement a Safety Program detailing how the Contractor plans, staffs, performs, and controls all safety practices while delivering best value services to the Government without any accidents or mishaps. The Contractor’s safety program shall comply with all safety standards identified in the U.S. Army Corps of Engineers Safety and Health

Requirements Manual, EM 385-1-1, UFC 3-560-01 Operation and

Maintenance Electrical Safety, and Public Law 91-596, Occupational Safety and Health Act.

Any reference to “USACE" facilities, property, or equipment specified in EM

385-1-1 should be interpreted as Government facilities, property, and equipment.

2.9.1 Contractor Safety

Requirements

Neither Contractor nor any subcontractor may enter into contract with any subcontractor that fails to meet the below requirements. The term subcontractor in this and the following paragraphs means any entity holding a contract with the Contractor or with a subcontractor at any tier.

2.9.1.1 Experience

Modification Rate

(EMR)

Subcontractors on this contract must have an effective EMR less than or equal to 1.10, as computed by the National Council on Compensation

Insurance (NCCI) or if not available, as computed by the state agency's rating bureau in the state where the subcontractor is registered, when entering into a subcontract agreement with the Prime Contractor or a subcontractor at any tier.

The Prime Contractor may submit a written request for additional consideration to the Contracting Officer where the specified acceptable EMR range cannot be achieved. Relaxation of the EMR range will only be considered for approval on a case-by-case basis for special conditions and must not be anticipated as tacit approval. Contractor's Site Safety and Health

Officer (SSHO) must collect and maintain the certified EMR ratings for all subcontractors on the project and make them available to the Government at the Government's request.

2.9.1.2 OSHA Days Away

From Work, Restricted Duty, or

Job Transfer

(DART) Rate

Subcontractors on this contract must have a DART rate, calculated from the most recent, complete calendar year, less than or equal to 3.4 when entering into a subcontract agreement with the Prime Contractor or a subcontractor at any tier.

The Prime Contractor may submit a written request for additional consideration to the Contracting Officer where the specified acceptable

OSHA Dart rate range cannot be achieved for a particular subcontractor.

Relaxation of the OSHA DART rate range will only be considered for approval on a case-by-case basis for special conditions and must not be anticipated as tacit approval. Contractor's Site Safety and Health Officer

(SSHO) must collect and maintain self-certified OSHA DART rates for all subcontractors on the project and make them available to the Government at the Government's request.

2.9.2 Accident

Prevention Plan

(APP)

The Contractor shall develop and implement a site Accident Prevention Plan

(APP). The APP shall be prepared by the Contractor’s SSHO and shall be followed by all Contractor employees, subcontractors, and vendors at each service site.

The APP shall follow the abbreviated format and include, as a minimum,…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .