J-1503060.pdf
PDF 143 KB Posted
- Solicitation number
- N62470-22-R-0006
About this file
This document provides attachments to a solicitation for base operations support services. The solicitation seeks proposals to provide services such as snow and ice removal, street sweeping, and landscaping at the Russell Knox Building, a secure facility at Marine Corps Base Quantico in Virginia. Attachment J-1503060-03 defines four service levels for different types of paved surfaces, with requirements for snow and ice removal and deicing ranging from within two hours to within 72 hours of a snow event, depending on the priority and type of area. Attachment J-1503060-04 lists two priority areas covering around 27 acres that must be kept clear of snow accumulations exceeding one to two inches. The Naval Facilities Engineering Command is the contracting agency.
View the file
Other files
Show 40 more
Latest 50 of 54 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION J – 1503060
PAVEMENT CLEARANCE
DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS
TABLE OF CONTENTS
ATTACHMENT NUMBER ATTACHMENT TITLE
J-1503060-01 DEFINITIONS AND ACRONYMS
J-1503060-02 REFERENCES AND TECHNICAL DOCUMENTS
J-1503060-03 SERVICE LEVELS
J-1503060-04 SNOW REMOVAL PRIORITIES AND AREAS DESCRIPTION
J-1503060-05 SITE MAPS AND LOCATIONS
ATTACHMENT J-1503060-01
DEFINITIONS AND ACRONYMS
DEFINITION/ACRONYM DESCRIPTION
Air Operations (Air Ops) The department responsible for all ground and air traffic on the airfield side of Naval
Air Station.
Air Snow King Person or persons designated by the Government to act as the overall responsible party for all airfield snow and ice operations. The Air Snow King has no authority to change, alter, or modify the contract.
Bare Pavement Free of frozen precipitation down to the surface of the pavement. Bare pavement does not mean completely dry and may still have frozen and/or liquid precipitation in the holes, pores, divots, seams and cracks.
Clear Free of debris, as defined below.
DOT U.S. Department of Transportation Debris Includes, but is not limited to, paper, cans, bottles, limbs and branches, pine straw and pinecones, leaves, sand, soil, aggregates, grass, metals, and other similar items.
End of Cleanup Defined as when the Contractor has met all performance objectives.
End of Precipitation The end of the hour during which the Contractor and the KO or designated representative mutually agree the precipitation has ended EPA Environmental Protection Agency FAA Federal Aviation Administration Finished Street, Road, or Parking Lot
A paved or improved area in which the following conditions are met:
Clear, Dry Area – The entire area of responsibility is as close as possible to clear and dry. Not more than one inch of snow shall remain on the area, including hard packed snow.
Full Width – Snow is from the full width of the paved and improved area of the streets, roads, or parking lots. The snow is removed to at least the outer edge of the entire area of responsibility, so that the outer edge is exposed, unless otherwise specified.
Obstructions – Where obstructions such as utility poles, sign posts, fire hydrants, and trees exist between or in the midst of the streets, roads or parking area: snow shall be cleared around these objects down to the required finished depth (by hand if necessary) so that streets, roads, or parking areas are blocked with snow.
Foreign Object Debris
(FOD)
Any foreign object external to an aircraft that can cause damage. Examples include nuts, bolts, safety wire, baggage tags, misplaced tools, sand, rocks, asphalt chunks, birds, snakes and, rodents. Any item(s) on a runway that may be picked up by any aircraft and potentially cause damage to any part of the aircraft.
Ice (Taken from FAA AC 150/5200-30C)
The solid form of water consisting of a characteristic hexagonal symmetry of water molecules. The density of pure ice is 57 lb/ft3 (913 kg/m3), which is 9 percent less dense than water. Compacted snow becomes ice when the air passages become discontinuous at a density of about 50 lb/ft3 (800 kg/m3).
Initiation of Work The Contractor shall initiate work as required to maintain streets, roads, and parking lots within the performance standard for snow removal and sanding.
NAS Naval Air Station New Storm Any precipitation occurring after the “End of Precipitation” defined above.
Passage The movement of persons or vehicles across paved surfaces.
Primary Runway (Taken from FAA AC 150/5200-30C)
A runway expected to be used under the existing atmospheric and storm event conditions where most of the takeoff and landing operations will take place.
ATTACHMENT J-1503060-01
DEFINITIONS AND ACRONYMS
DEFINITION/ACRONYM DESCRIPTION
Secondary Runway (Taken from FAA AC 150/5200-30C)
A runway that supports a primary runway. Takeoff and landing operations on such a runway are generally less frequent than on a primary runway.
Snow (on the ground).
(Taken from FAA AC 150/5200-30C)
A porous, permeable aggregate of ice grains, which can be predominately single crystals or close groupings of several crystals.
Snow Event Any occurrence of frozen precipitation that results in visible accumulation of snow or ice on paved surfaces.
Snow King Person or persons designated by the Government to act as the overall responsible party for all snow and ice operations. The Snow King has no authority to change, alter, or modify the contract.
Twenty-Four (24) Hour Lot Parking Lots that have to be cleared during designated shift changes or maintained during the course of an intense storm.
ATTACHMENT J-1503060-02
REFERENCES AND TECHNICAL DOCUMENTS
The Contractor shall adhere to the applicable portions of the current edition of the following publications and directives in performing the services required under this contract. This list shall not be considered all-inclusive and does not release the Contractor from all obligations that must be fulfilled in the observance and execution of this contract.
When multiple directives, instructions and industry standards are applicable to the work to be performed under this contract, the most stringent directives, instructions and industry standards shall govern.
TITLE REFERENCE
U.S. Army Corps of Engineers Safety and Health Requirements EM 385-1-1
ATTACHMENT J-1503060-03
SERVICE LEVELS
SERVICE
LEVEL
TYPE OF
PAVED
SURFACE
STREET
SWEEPING
SNOW AND ICE
REMOVAL DEICING
Primary Roads Monthly Within 2 Hours of notification by
Facility Manager
Prior to Expected Snow Event
Service Level 1 Secondary Roads Monthly Within 2 Hours of notification by
Facility Manager
Prior to Expected Snow Event
Parking Lots
Sidewalks
Perimeter Fence
Monthly Within 2 Hours of notification by
Facility Manager
Prior to Expected
Service Level 2
Primary Roads
Secondary Roads
Monthly
Within 12 Hours of Snow Event
Within 36 Hours of Snow Event
Within 24 Hours
Prior to Expected
None
At start of Snow Event
Service Level 3 Secondary Roads Monthly Within 48 Hours
Service Level 4
Secondary Roads
Within 24 Hours of Snow Event
Within 72 Hours of Snow Event
ATTACHMENT J-1503060-04
SNOW REMOVAL PRIORITIES AND AREAS DESCRIPTION
AREA GENERAL AREA
DESCRIPTION
APPROXIMATE
AREA SIZE
SNOW
ACCUMULATION
Priority 1 Russell Knox Building 27130
Areas surrounding Bldg 27130 along with Parking Garage
20 Acres Not to Exceed 1”
Sidewalks 7,000 LF Priority 2 Perimeter Fence Patrol Path
Fence Line 1 Mile Not to Exceed 2”
ATTACHMENT J-1503060-05
SITE MAPS AND LOCATIONS
Site Maps and Locations are provided as a separate attachment. Refer to PDF file “J-1503060-05 Site Maps and Locations”