J-11 FY20 CHG-1 NWRMC LOCAL STANDARD ITEM 099-09NW.pdf

PDF 26 KB Posted

Attached to
Carrier Engineering Maintenance Assist Team (CEMAT)
Solicitation number
N0002419R4304
Issued by

About this file

This document contains a local standard item and a related federal contract opportunity. The local standard item outlines requirements for contractors to prepare and manage a production schedule for availabilities nine weeks or less. Contractors must submit an initial schedule prior to start, revise it weekly, and chair a weekly progress meeting. The federal contract opportunity is a request for proposals from the Naval Sea Systems Command to provide Carrier Engineering Maintenance Assist Team and Surface Engineering Maintenance Assist Team services globally in support of aircraft carriers and surface vessels. Services include repairs, maintenance training, and technical support. The requirement is solicited as a cost plus fixed fee indefinite delivery/indefinite quantity contract for a five year ordering period.

View the file

Other files

File Type Posted
N00024-19-R-4304-0004 Conformed.pdf PDF
CEMAT Q and A - 04SEP20.pdf PDF
N00024-19-R-4304-0004.pdf PDF
CEMAT Q and A - 27AUG20.pdf PDF
N00024-19-R-4304-0003 Conformed.pdf PDF
N00024-19-R-4304-0003.pdf PDF
N00024-19-R-4304-0002 Conformed.pdf PDF
N00024-19-R-4304-0002.pdf PDF
CEMAT Q and A - 14AUG20.pdf PDF
N00024-19-R-4304-0001 Conformed.pdf PDF
N00024-19-R-4304-0001.pdf PDF
CEMAT SEMAT Q and A - 11AUG20.pdf PDF
J-22 Contractor Badging and Access Requirements Solicitation (HL).pdf PDF
J-13 FY20 CHG-1 NWRMC LOCAL STANDARD ITEM 099-11NW.pdf PDF
EXHIBIT A-DD 1423 GLOSSARY.pdf PDF
J-17 042-007 Security Requirements for Work Within Norfolk Naval Shipyard.pdf PDF
J-14 FY20 CHG-1 NWRMC LOCAL STANDARD ITEM 099-12NW.pdf PDF
J-5 FY20 CHG-1 NWRMC LOCAL STANDARD ITEM 099-04NW.pdf PDF
J-8 FY20 CHG-1 NWRMC LOCAL STANDARD ITEM 099-06NW.pdf PDF
J-24 Non-Key Reference Guide.pdf PDF
J-25 DD 254.pdf PDF
J-15 042-005 NNSY Work Authorization Form (WAF) Requirements.pdf PDF
J-16 042-006 General Occupational Safety Health and Environment (OSHE) Requirements for Work Within Norfolk Naval Shipyard.pdf PDF
J-2 FY20 CHG-1 NWRMC LOCAL STANDARD ITEM 099-01NW.pdf PDF
J-12 FY20 CHG-1 NWRMC LOCAL STANDARD ITEM 099-10NW.pdf PDF
N00024-19-R-4304 RFP - CEMAT SEMAT.pdf PDF
J-1 TAM.pdf PDF
J-7 FY20 CHG-1 NWRMC LOCAL STANDARD ITEM 099-05NW.pdf PDF
EXHIBIT A-CEMAT CDRLs 6.16.2020 signed.pdf PDF
J-3 FY20 CHG-1 NWRMC LOCAL STANDARD ITEM 099-02NW.pdf PDF
J-18 042-010 Nuclear Powered Ships-Nuclear Support Ships.pdf PDF
J-6 FY20 099-05PH MISC.pdf PDF
J-9 FY20 CHG-1 NWRMC LOCAL STANDARD ITEM 099-07NW.pdf PDF
J-4 FY20 CHG-1 NWRMC LOCAL STANDARD ITEM 099-03NW.pdf PDF
J-23 Attachment Key Personnel List.pdf PDF
L-1 Bidder Question Submittal Form CEMAT.xlsx XLSX spreadsheet
J-19 042-037 General Requirements for Work Within Naval Station Norfolk.pdf PDF
J-10 FY20 CHG-1 NWRMC LOCAL STANDARD ITEM 099-08NW.pdf PDF
J-21 NAVSEA INST 5100.3E.pdf PDF
L-2 RIS Past Performance Questionnaire (PPQ) CEMAT.docx DOCX document
L-3 Cost Proposal Format CEMAT.xlsx XLSX spreadsheet
J-20 077-001 Hazardous Waste Produced on Naval Vessels.pdf PDF
Show all 42

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1 of 3 ITEM NO: 099-09NW

FY-2020

EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.

International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.

NWRMC

LOCAL STANDARD ITEM

ITEM NO: 099-09NW

DATE: 24 JUN 2018

CATEGORY: I

1. SCOPE:

1.1 Title: Schedule and Associated Reports for Availabilities 9 Weeks or Less in Duration; provide and manage

1.2 Location of Work:

1.2.1 None

1.3 Identification:

1.3.1 Not Applicable

2. REFERENCES:

2.1 None

3. REQUIREMENTS:

3.1 For work packages 9 weeks or less in duration, Firm Fixed Price (FFP) or Multi-Ship/Multi-Option (MS/MO), Chief of Naval Operations (CNO), Continuous Maintenance (CM), or Emergent Maintenance (EM) work as determined by the SUPERVISOR to be routine or standard repair: Prepare and manage a Production Schedule for each Work Item of the Job Order, including milestones identified by the SUPERVISOR. The Production Schedule shall list:

3.1.1 Schedule each Work Item to the activity level listing the start and completion dates for each activity. Each activity shall be displayed to reflect its relevancy to the applicable key events and milestones.

3.1.1.1 Assign each activity in the Production Schedule a short title to describe the nature of the activity, system and equipment or machinery involved.

3.1.1.2 Each activity shall be scheduled by location, system and integrated into the schedule for each activity.

3.1.2 The latest allowable receipt date for contractor and

government furnished material to maintain schedule.

3.1.3 Scheduled key events/milestones.

3.1.4 Critical path and controlling Work Items.

3.1.5 Scheduled start and completion dates of tests.

3.1.6 Submit one legible copy, in approved transferrable media, of the Production schedule to the SUPERVISOR no later than 5 days prior to the availability start date.

3.2 Revise Production Schedule weekly to reflect the addition, deletion, or modification of Work Items, and changes made by the contractor for work packages identified in 3.1.

2 of 3 ITEM NO: 099-09NW

EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.

International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative,

3.2.1 Submit one legible copy, in approved transferrable media, of the revised Production Schedule to the SUPERVISOR one day prior to weekly progress meeting of 3.3.

3.3 Chair and lead a weekly progress meeting to be held at a time and place mutually agreeable to all parties for work packages identified in 3.1.

3.3.1 Address critical path, controlling work and offer reasonable solutions to problems which may have impact on scheduled milestones or completion date.

3.3.2 Provide management representation to chair the weekly progress meeting, authorized to make management decisions relative to routine requirements of the Job Order which, in good faith, commit the contractor.

3.3.3 Submit one legible copy, in approved transferrable media, of an availability status report to the SUPERVISOR one working day prior to the weekly progress meeting that includes the revised Production Schedule for work packages identified in 3.2. Submit the following for each Work Item:

3.3.4 Percent of production work completed (Physical Progress).

3.3.5 Late contractor furnished material.

3.4 Coordinate and schedule subcontractor's performance with respect to work progress, material procurement, and interface to support the production schedule for work packages identified in 3.1.

3.4.1 Submit one legible copy, in approved transferrable media, of a complete list of subcontractors by Work Item to the SUPERVISOR at the same time the Production Schedule is submitted. The subcontractor list shall include:

3.4.1.1 Work Item paragraph number.

3.4.1.2 Specific work to be accomplished.

3.4.1.3 Subcontractor's business address.

3.4.2 Submit one legible copy, in approved transferrable media, of a report to the SUPERVISOR of any change to the original list prior to making the change, whenever any subcontractor is added or deleted.

3.4.3 Schedule daily meetings to resolve problems/unfinished work relating to work tied to milestones and key events. Meetings shall commence 2 weeks prior to the milestone or key event, and continue until completion of work.

3.4.4 Revise the list of unfinished work, including machinery and systems discrepancies, daily.

4. NOTES:

4.1 Definitions.

4.1.1 Production Schedule: The schedule used by contractor and subcontractor personnel as a means of planning, tracking, and coordinating the accomplishment of contract work.

EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.

International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative,

4.1.2 Activity: A portion of an individual Work Item which is a logical subdivision of the Work Item representing a manageable unit of work which must be accomplished at a specific period of time in relation to other activities of the Job Order.

4.1.3 Key Event: An event which cannot slip without impacting or delaying the overall schedule. Key events may be identified by either the contractor or the SUPERVISOR.

4.1.4 Milestone: A significant event identified by the Maintenance Team. Milestones may be identified by either the contractor or the

SUPERVISOR.

4.1.5 Critical Path: That sequence of activities which forms the longest duration, and directly affects the completion of the availability. Factors in determining critical path are: time duration required for the activity, space limitations, manpower available, and the interface between Work Item activities.

4.1.6 Controlling Work Items: Those Work Items which are on the critical path of the Job Order and/or those Work Items which, by virtue of scope, material requirements, complexity, or other considerations, have the potential for impact on the scheduled project key events or completion of the availability.

4.1.7 Float: The amount of time an event can be delayed without delaying the start of subsequent or follow-on activities.

3 of 3 ITEM NO: 099-09NW

EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.

International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative,

File details come from the government source that posted it. Updated .