L-3 Cost Proposal Format CEMAT.xlsx

XLSX spreadsheet 69 KB Posted

Attached to
Carrier Engineering Maintenance Assist Team (CEMAT) Federal contract opportunity
Solicitation number
N0002419R4304
Issued by
Department of the Navy Naval Sea Systems Command

About this file

This document contains a cost proposal template for a carrier engineering maintenance assistance team contract opportunity issued by the Naval Sea Systems Command. The template includes tabs for direct labor costs by labor category and year, labor and indirect rates, subcontractor details, consultant details, and other direct costs including materials and supplies, equipment, travel, and miscellaneous expenses. Offerors are instructed to complete the template to provide a detailed cost breakdown for the contract by cost element and year. The template requires supporting documentation to substantiate proposed costs and rates. The related federal contract opportunity notice provides additional context, describing the requirement as a cost plus fixed fee indefinite delivery/indefinite quantity contract for carrier and surface ship maintenance assistance teams over a five year ordering period. Offerors should contact the identified contracting officer for further details.

View the file

Other files for this federal contract opportunity

Other files attached to Carrier Engineering Maintenance Assist Team (CEMAT), newest first.
File Type Posted
N00024-19-R-4304-0004.pdf PDF
N00024-19-R-4304-0004 Conformed.pdf PDF
CEMAT Q and A - 04SEP20.pdf PDF
N00024-19-R-4304-0003 Conformed.pdf PDF
N00024-19-R-4304-0003.pdf PDF
CEMAT Q and A - 27AUG20.pdf PDF
N00024-19-R-4304-0002 Conformed.pdf PDF
CEMAT Q and A - 14AUG20.pdf PDF
N00024-19-R-4304-0002.pdf PDF
N00024-19-R-4304-0001 Conformed.pdf PDF
CEMAT SEMAT Q and A - 11AUG20.pdf PDF
N00024-19-R-4304-0001.pdf PDF
J-5 FY20 CHG-1 NWRMC LOCAL STANDARD ITEM 099-04NW.pdf PDF
J-14 FY20 CHG-1 NWRMC LOCAL STANDARD ITEM 099-12NW.pdf PDF
J-8 FY20 CHG-1 NWRMC LOCAL STANDARD ITEM 099-06NW.pdf PDF
EXHIBIT A-CEMAT CDRLs 6.16.2020 signed.pdf PDF
J-25 DD 254.pdf PDF
J-3 FY20 CHG-1 NWRMC LOCAL STANDARD ITEM 099-02NW.pdf PDF
J-21 NAVSEA INST 5100.3E.pdf PDF
L-2 RIS Past Performance Questionnaire (PPQ) CEMAT.docx DOCX document
J-19 042-037 General Requirements for Work Within Naval Station Norfolk.pdf PDF
J-20 077-001 Hazardous Waste Produced on Naval Vessels.pdf PDF
J-10 FY20 CHG-1 NWRMC LOCAL STANDARD ITEM 099-08NW.pdf PDF
J-13 FY20 CHG-1 NWRMC LOCAL STANDARD ITEM 099-11NW.pdf PDF
J-2 FY20 CHG-1 NWRMC LOCAL STANDARD ITEM 099-01NW.pdf PDF
J-9 FY20 CHG-1 NWRMC LOCAL STANDARD ITEM 099-07NW.pdf PDF
J-6 FY20 099-05PH MISC.pdf PDF
J-11 FY20 CHG-1 NWRMC LOCAL STANDARD ITEM 099-09NW.pdf PDF
L-1 Bidder Question Submittal Form CEMAT.xlsx XLSX spreadsheet
J-16 042-006 General Occupational Safety Health and Environment (OSHE) Requirements for Work Within Norfolk Naval Shipyard.pdf PDF
J-22 Contractor Badging and Access Requirements Solicitation (HL).pdf PDF
J-18 042-010 Nuclear Powered Ships-Nuclear Support Ships.pdf PDF
J-15 042-005 NNSY Work Authorization Form (WAF) Requirements.pdf PDF
J-1 TAM.pdf PDF
EXHIBIT A-DD 1423 GLOSSARY.pdf PDF
J-12 FY20 CHG-1 NWRMC LOCAL STANDARD ITEM 099-10NW.pdf PDF
J-7 FY20 CHG-1 NWRMC LOCAL STANDARD ITEM 099-05NW.pdf PDF
J-23 Attachment Key Personnel List.pdf PDF
J-17 042-007 Security Requirements for Work Within Norfolk Naval Shipyard.pdf PDF
J-24 Non-Key Reference Guide.pdf PDF
J-4 FY20 CHG-1 NWRMC LOCAL STANDARD ITEM 099-03NW.pdf PDF
N00024-19-R-4304 RFP - CEMAT SEMAT.pdf PDF
Show all 42

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CLIN Detail (Template)

Name of Project: CARRIER ENGINEERING MAINTENANCE ASSIST TEAM (CEMAT)
SOLICITATION NO. N00024-19-R-4304
ATTACHMENT L-3
Document Template dtd 28 May 20
Cost Proposal for CLIN XXXX (include Purpose/Description of CLIN)
Prime / Offeror:
(Note 1)Year AYear BYear CYear DYear EYear FTotal (Note 3)
Direct Labor (DL)MM/YR to MM/YRMM/YR to MM/YRMM/YR to MM/YRMM/YR to MM/YRMM/YR to MM/YRMM/YR to MM/YR
Labor Category (Note 2)Name (Last, First)HoursRateExtended $HoursRateExtended $HoursRateExtended $HoursRateExtended $HoursRateExtended $HoursRateExtended $HoursExtended $
Sample: ENG, Level IISmith, John20$56.00$1,120.00100$57.40$5,740.00100$58.84$5,884.0080$60.31$4,824.80$0.00$0.00300$17,568.80
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
Total Direct Labor20$1,120.00100$5,740.00100$5,884.0080$4,824.800$0.000$0.00300$17,568.80
Subcontracts/Interorganizational Transfer (Note 4)
Sample: Acme Anvils$50,000.00$0.00$0.00$0.00$0.00$0.00$50,000.00
$0.00$0.00$0.00$0.00$0.00$0.00$0.00
$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Total Subcontract Costs$50,000.00$0.00$0.00$0.00$0.00$0.00$50,000.00
Consultants (Note 4)
Sample: Trusted Ex-Employee52$10,214.72209$40,881.11$0.00$0.00$0.00$0.00261$51,095.83
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
$0.00$0.00$0.00$0.00$0.00$0.000$0.00
Total Consultants Costs52$10,214.72209$40,881.11$0.00$0.00$0.00$0.00261$51,095.83
Other Direct Costs (Note 4)
Sample: Materials and Supplies$1,647.50$0.00$0.00$0.00$0.00$0.00$1,647.50
Sample: Equipment$560.00$0.00$0.00$0.00$0.00$0.00$560.00
Sample: Travel$0.00$8,060.00$0.00$0.00$0.00$0.00$8,060.00
Sample: Miscellaneous$0.00$0.00$5,000.00$0.00$0.00$0.00$5,000.00
$0.00$0.00$0.00$0.00$0.00$0.00$0.00
$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Total ODCs$2,207.50$8,060.00$5,000.00$0.00$0.00$0.00$15,267.50

Total Direct Costs $63,542.22 $54,681.11 $10,884.00 $4,824.80 $0.00 $0.00 561 $133,932.13

Indirect Costs (Note 5)BaseRateExtended $BaseRateExtended $BaseRateExtended $BaseRateExtended $BaseRateExtended $BaseRateExtended $
Sample: Labor and Material Overhead$2,767.5090.20%$2,496.29$5,740.0090.20%$5,177.48$5,884.0090.20%$5,307.37$4,824.8090.20%$4,351.97$0.00$0.00$17,333.11
Sample: Material G&A$1,647.5016.30%$268.54$0.0016.30%$0.00$0.0016.30%$0.00$0.0016.30%$0.00$0.00$0.00$268.54
Sample: Cost of Money (CoM)$66,307.050.05400%$35.81$59,858.590.05400%$32.32$16,191.370.05400%$8.74$9,176.770.05400%$4.96$0.00$0.00$81.83
$0.00$0.00$0.00$0.00$0.00$0.00$0.00
$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Total Indirect Costs$2,800.64$5,209.80$5,316.11$4,356.93$0.00$0.00$17,683.48

Total Total Estimated Costs $66,342.86 $59,890.91 $16,200.11 $9,181.73 $0.00 $0.00 $151,615.61

Fee / Profit (Note 6) $65,747.05 5.00% $3,287.35 $59,858.59 5.00% $2,992.93 $16,191.37 5.00% $809.57 $9,176.77 5.00% $458.84 $0.00 5.00% $0.00 $0.00 5.00% $0.00 $7,548.69

Total Price / Costs Plus Fixed Fee $69,630.21 $62,883.84 $17,009.68 $9,640.57 $0.00 $0.00 $159,164.30

Instructions: • Add a separate tab for each separately priced CLIN in the proposal and indicate the CLIN number / Description as the name of the tab. If more than one CLIN tab is used, an additional tab shall be inserted as the first tab taht summarizes subsequent CLIN specific tabs. The summay tab shall be linked to the CLIN specific tabs for the formulas for any rate or dollar value. The CLIN specific tabs shall be linked directly to the detailed tabs for labor and indirect rates, subcontractors, consultants, materials-supplies, equipment, travel, and misc.ODCs. Remember that the total of all Base and Option worksheets should equal the total of the summary worksheet.

• A sample is included in all tabs to demonstrate how to properly complete this worksheet (noted in blue font). Delete all sample entries when completing the worksheets to avoid erroneous cost enteries in you final submission.

Note 1: Indicate whether the Offeror'sContractor's accounting system is based on a calendar year or fiscal year. Indicate the months during the period of performance that these rates apply.

Note 2: Any proposed personnel in the technical proposal should be identified with their labor category. List Principal Investigator and Key Personnel (as appropriate) working on the project even if they receive no salary support.

Note 3: The values under Total Direct Labor "hours/base" column indicate the total for the effort for the project for each cost category.

Note 4: The Offeror/Contractor shall link to associated tab for the details. Indicate when submission is from a prime, subcontractor or consultant.

Note 5: The Offeror/Contractor shall include all indirect costs applied and identified in the Labor & Indirect Rates tab and shall specify and enumerate the basis in which those rates apply. This may include, but is not limited to Fringe Benefits, Labor Overhead, Material Handling, General and Administrative, and Facilities Cost of Money.

Note 6: Profit or fee is not allowed on direct costs for equipment, Government entities, facilities capital cost of money or cost share contracts. In addition, a DD Fom 1547 (DFARS 215.404-70) will be utilized in calculating the Government objective for fee.

&"Arial,Bold"&12&A

Labor & Indirect Rates LABOR Rate Information

(Note 2)Year AYear BYear CYear DBasis of Labor Rate
(Note 3)MM/YR to MM/YRMM/YR to MM/YRMM/YR to MM/YRMM/YR to MM/YR
Labor Category (Note 1)Employee NameRateRateRateRate
Sample: ENG, Level IISmith, John$56.00$57.40$58.84$60.31Individual Pay Rate with 2.5% annual escalation
Indirect Rate Information
Year AYear BYear CYear DBasis of Indirect Rate (Note 5)Applied Against (Note 6)
Rate Category (Note 4)RateRateRateRate
Sample: Labor and Material Overhead90.20%90.20%90.20%90.20%FPRA Approved by DCMA/DCAA on 2/13/20Direct Labor and Material, not Subcontracts or ODC
Sample: Material G&A16.30%16.30%16.30%16.30%FPRA Approved by DCMA/DCAA on 2/13/20Direct Material, excludes material overhead
Sample: Cost of Money (CoM)0.05400%0.05400%0.05400%0.05400%FPRA Approved by DCMA/DCAA on 2/13/20Total cost (not fee)

Instructions: • If the rates have been approved/negotiated by a Government agency, provide a copy of the memorandum/agreement.

• If the rates have not been approved/negotiated, provide sufficient detail to enable a determination of allowability, allocability and reasonableness of the allocation bases and how the rates are calculated.

• If composite rates are used, provide the calculations used in deriving the composite rates.

• Example Basis of Estimates for Direct Labor include Individual Payrate, Average for Job Category, etc. Examle Basis of Indirect Rate include FPRA, FPRP, Estimate, etc.

Note 1: Add additional labor categories if needed.

Note 2: Add additional years if needed (unless specifically authorized, this shall not exceed 5 years).

Note 3: Identify the month and year tied to when rates change according with the Contractor's accounting system, not tied to the year after contract award. It is understood that a contractor's fiscal year may not align with the contract year of performance or the Government Fiscal Year.

Note 4: Categories of indirect rates may include, but not be limited to, labor and material overheads, fringe benefits, approved materials escalations, general and administrative (G&A) costs applied to labor/material/total/etc., scrap, warranty (if requested), material handling, facility capital cost of money applied to various elements, etc. Include all distinctions between on and off site rates.

Note 5:Add additional indirect rates as needed.
If the offeror does not have a Forward Pricing Rate Agreement (FPRA), Forward Pricing Rate Recommendation (FPRR), or provisional billing rates; in order to assist the Government in evaluating the reasonableness of your proposed indirect rates, please provide the following information:
1. Proforma data used to develop your proposed indirect rates. This typically consists of pool costs and base costs that demonstrate how the indirect rates were derived.
2. Information regarding your projections for out years, including your assumptions and method for developing these estimates.

Note 6: Indicate what the base is that the rate on which the rate is applied, or if it applied to multiple cost elements each should be identified.

Subcontractors

SUBCONTRACTOR DATA
Name
(Note 1)SubcontractorCAGE
CodeYear AppliedTotal CostCompetitive/ Sole SourceCost/Price analysis included (Y/N)Type of Subcontract (i.e., Fixed Price, Time and Materials, etc.)Competitive Quotes or Sole Source Documentation Included (Y/N)Total amount exceeds $2M (Y/N)
CLIN 0001
1Sample: Acme Anvils1YES1Year A$50,000.00CompetitiveNoFixed PriceYesNo

Option X

Instructions: Subcontracts/Interorganizational Transfers – A fully disclosed cost proposal as detailed as the Offeror’s cost proposal including support documentation will be required to be submitted by all proposed subcontractors and for all interorganizational transfers over $150,000. For subcontracts and interorganizational transfers under $150,000, only a cost proposal with cost categories broken out must be provided. If options are proposed, the option periods should be separately priced. The subcontract or interorganizational transfer proposal, along with supporting documentation, must be provided either in a sealed envelope with the prime’s proposal or via email directly to the Program Officer or Contract Specialist upon request. The email should identify the prime Offeror, proposal title, and that the attached proposal is a subcontract. The subcontractor and interorganizational transfer proposals with supporting documentation must be received and reviewed before the Government can complete its cost analysis of the proposal and enter negotiations.

The prime contractor should perform and provide a cost/price analysis of each subcontractor’s cost proposal. Offerors are required to obtain competition to the maximum extent practicable when selecting subcontractors; if the offeror has obtained competitive quotes, copies should be provided. If the Offeror has selected other than the low bid for inclusion in their proposal or intends to award the subcontract on a sole-source basis, the offeror should provide rationale for their decision. For sole-sourced subcontracts, the prime contractor must provide a short sole-source justification.

Certified cost or pricing data may be required for subcontractor proposals over $2,000,000.

*Note: Federal Acquisition Regulation provision 52.215-22 (Limitations on Pass-Through Charges--Identification of Subcontract Effort) may be incorporated into this solicitation by reference. The offeror is to exclude excessive pass-through charges from subcontractors. The offeror must identify in its proposal the percentage of effort it intends to perform and the percentage to be performed by each of its proposed subcontractors. If more than 70 percent of the total effort will be performed through subcontractors, the offeror must include the additional information required by the above-cited clause.

&"Arial,Bold"&12&A

Consultants

CONSULTANTS

Name
(Note 1)Description of effort to be performed by the Consultant or attach Consultant Statement of Work (Note 2)Year AppliedNumber of Labor HoursLabor Hourly RateLabor CostTravel costsOther CostsTotal CostBasis of EstimateIncluded copy of Consulting Agreement or other documentation supporting the proposed rate (Y/N)Supporting Documentation Reference Number
CLIN 0001
1Sample: Trusted Ex-Employee. Selection criteria: only source of knowledge on how things get done here.Year A52.3$190.53$9,964.72$200.00$50.00$10,214.72QuoteYesMr. Taylor Quote #3
2Sample: Trusted Ex-Employee. Selection criteria: only source of knowledge on how things get done here.Year B208.6$194.78$40,631.11$200.00$50.00$40,881.11QuoteYesMr. Taylor Quote #3
$0.00$0.00
$0.00$0.00
SubTotal:$51,095.83
Option X
Sample: Not Applicable$0.00$0.00
$0.00$0.00
$0.00$0.00
$0.00$0.00
SubTotal:$0.00
TOTAL$51,095.83

Instructions: • Indicate “Not Applicable” in column B if there is no information to include for the Base and Options.

• Fill out all columns on the Consultants Tab for each item.

Note 1:Include a separate section in the above table for the Base and each Option.
Note 2:Describe how and why the consultant was selected.

ODC Materials-Supplies MATERIALS - SUPPLIES (Note 1)

Item
(Note 2)Description of MaterialQtyUnit of IssueUnit PriceTotal PriceYear AppliedCompetitive /Sole SourceCommercial Off The Shelf (COTS) item (Y/N)Vendor/Source (If known)Basis of Estimate (Note 3)Supporting documentation has been provided (Y/N) (Note 3)Supporting Documentation Reference Number
CLIN 0001
1Sample: Wing nut50Boxes$32.95$1,647.50Year ACompetitionYesHome DepotInternetYesAttachment 3 web page
20$0.00$0.00
30$0.00$0.00
40$0.00$0.00
50$0.00$0.00
60$0.00$0.00
70$0.00$0.00
80$0.00$0.00
90$0.00$0.00
100$0.00$0.00
SubTotal:$1,648
Option X
1Sample: Not Applicable0$0.00$0.00
20$0.00$0.00
30$0.00$0.00
40$0.00$0.00
50$0.00$0.00
SubTotal:$0

TOTAL $1,647.50

Instructions: • Indicate “Not Applicable” in column B if there is no information to include for the Base and Options.

• Fill out all columns on the Materials/Supplies Tab for each item.

• Add additional lines if needed.

• Include backup for each entry. Backup may consist of a vendor quote, information from a website, or a detailed explanation of labor and material costs for custom made items.

• Clearly label Materials/Supplies backup with a Supporting Documentation Reference Number and place the Supporting Documentation Reference Number in the upper right hand side of the supporting document. If there are several lines supported on a single page, make sure each desired item has a separate reference number placed to the left of the item on the backup page.

• Ensure that descriptions and vendors listed on the Materials/Supplies worksheet match information provided in the backup.

• Number Supporting Documentation Reference Number so they match the Item number in column M.

Note 1: Material is property that may be incorporated into or attached to a deliverable end item or that may be consumed or expended in performing a contract. It includes assemblies, components, parts, raw and processed materials, and small tools and supplies that may be consumed in normal use in performing a contract. Material should be proposed separately from Equipment (see Equipment tab for definitions).

Note 2: Include a separate section in the above table for each CLIN, including any Options. Add additional lines labeled with the CLIN number and Options if needed.

Note 3: In an attachment, provide all supporting documentation to support your price basis, e.g. copy of quote, page from catalog, or method used for deriving engineering estimates.

ODC Equipment EQUIPMENT (Note 1)

Item
(Note 2)Description of Equipment (Note 1)Justification for why the equipment is neededWill the equipment be included as part of a deliverable item under the award? (Y/N)Type of Equipment (special test equipment, special tooling, general purpose equipment, or plant equipment)
(Note 3)QtyUnit of IssueUnit PriceTotal PriceYear AppliedVendor/SourceBasis of Estimate (Note 4)Supporting documentation has been provided (Y/N)
(Note 4)Supporting Documentation Reference Number
CLIN 0001
1Sample: Drill PressTo drill holesNoSpecial Tooling1Each$560.00$560.00Year ASearsCatalogYesCatalog 123 page 6
$0.00
SubTotal:$560.00
Option X
Sample: Not applicable$0.00
SubTotal:$0.00
TOTAL$560.00

Instructions: • Indicate “Not Applicable” in column A if there is no information to include for the Base and Options.

• Fill out all columns on the Equipment Tab for each item.

• Add additional lines if needed.

• Provide justification for equipment. Be sure to indicate the benefit(s) to the Government. Expand on any statements along the lines of “It is needed to support the project deliverables”. Link the justification to the type of equipment purchase, i.e. special test equipment, special tooling, or plant equipment.

• Include backup for each entry. Backup may consist of a vendor quote, information from a website, or a detailed explanation of labor and material costs for custom made items.

• Label equipment backup clearly with a Supporting Documentation Reference Number and place the Supporting Documentation Reference Number in the upper right hand side of the supporting document. If there are several lines supported on a single page, make sure each desired item has a separate reference number placed to the left of the item on the backup page.

• Ensure that descriptions and vendors listed on the Equipment worksheet match information provided in the backup.

• Number Supporting Documentation Reference Number so they match the Item number in column M.

Note 1: Contractors are normally required to furnish all equipment and/or facilities necessary to perform Government contracts (see FAR 45.102(a)). The Government may allow equipment and/or facilities only under special circumstances. If equipment and/or facilities are proposed, the specific description should identify the component, nomenclature, and configuration of the equipment/hardware that it proposes to purchase for this effort. The purchase on a direct reimbursement basis of equipment that is not included in a deliverable item will be evaluated for allowability on a case-by-case basis.

Note 2: Include a separate section in the above table for each CLIN, including any Options. Add additional lines labeled with the CLIN number and Options if needed.

Note 3: Definitions:

Special Test Equipment is defined as either single or multipurpose integrated test units engineered, designed, fabricated, or modified to accomplish special purpose testing in performing a contract. It consists of items or assemblies of equipment including standard or general purpose items or components that are interconnected and interdependent so as to become a new functional entity for special testing purposes.

Special tooling is defined as jigs, dies, fixtures, molds, patterns, taps, gauges, and all components of these items, including foundations and similar improvements necessary for installing special test equipment, and which are of such a specialized nature that without substantial modification or alteration their use is limited to the development or production of particular supplies or parts thereof or to the performance of particular services.

Plant equipment means personal property of a capital nature (including equipment, machine tools, test equipment, furniture, vehicles, and accessory and auxiliary items) for use in manufacturing supplies, in performing services, or for any administrative or general plant purpose. It does not include special tooling or special test equipment.

Note 4: In an attachment, provide all supporting documentation to support your price basis, e.g. copy of quote, page from catalog, or method used for deriving engineering estimates.

ODC Travel

TRAVEL

CLINTripNumberNumberNumberNumberAir/RailPer DiemPer DiemCarParkingMileageTaxiOther
City, StateWhen: MM/YR to MM/YRPurposeof TripsTravelersof Daysof NightsFareMealsLODGINGRentalMisc.TOTALRationale
From:Sample City A0001AALearn something new2432Fare Base:$350$45$210$50$20$0$0$50Commercially available airfare, Gov't per diem, parking at hotel, other is hotel tax
To:Sample City B04/Year B to 05/Year BTrip Cost:$2,800$1,080$3,360$300$120$0$0$400$8,060
From:Fare Base:
To:Trip Cost:$0$0$0$0$0$0$0$0$0
From:Fare Base:
To:Trip Cost:$0$0$0$0$0$0$0$0$0
From:Fare Base:
To:Trip Cost:$0$0$0$0$0$0$0$0$0
From:Fare Base:
To:Trip Cost:$0$0$0$0$0$0$0$0$0
From:Fare Base:
To:Trip Cost:$0$0$0$0$0$0$0$0$0
From:Fare Base:
To:Trip Cost:$0$0$0$0$0$0$0$0$0
From:Fare Base:
To:Trip Cost:$0$0$0$0$0$0$0$0$0
TOTAL$0

Instructions: • When completing the “From” and “To” information, enter the city and state where travel will originate and end. For example, from Seattle WA to Washington DC. Do not list airport codes.

• Ordinarily, you cannot stay overnight the same number of days that you travel. There will usually be one more day than night.

• Do not combine any categories.

• For lodging and M&IE, use federal Per Diem Rates found at http://www.gsa.gov.

• Submit backup for airfare and rental cars. Price airfare at economy rates; indicate if the airfare is refundable.

Note 1: If there are miscellaneous expenses associated with the trip, provide description and rationale.

Misc ODC Details MISCELLANEOUS OTHER DIRECT COSTS (Note 1)

Description
(Note 2)QtyUnit of IssueUnit PriceTotal PriceYear AppliedBasis of Estimate (Note 3)Supporting documentation has been provided (Y/N) (Note 3)Supporting Documentation Reference Number
CLIN 0001
Sample: FOB Destination Shipping1Each$5,000.00$5,000.00Year CQuoteYesQ#23456
$0.00
SubTotal:$5,000.00
Option X
Sample: Not Applicable$0.00
$0.00
$0.00
SubTotal:$0.00
TOTAL$5,000.00

Instructions: • Indicate “Not Applicable” in column A if there is no information to include.

• If you have any ODC entries, be sure to fill out all columns.

• Label ODC backup clearly with a Supporting Documentation Reference Number and place the Supporting Documentation Reference Number in the upper right hand side of the supporting document. If there are several lines supported on a single page, make sure each desired item has a separate reference number placed to the left of the item on the backup page.

• Ensure that descriptions and vendors listed on the ODC Details worksheet match information provided in the backup.

Note 1: Examples include rental fees, shipping costs, license fees

Note 2: Include a separate section in the above table for each CLIN, including any Options. Add additional lines labeled with the CLIN number and Options if needed.

Note 3: In an attachment, provide all supporting documentation to support your price basis, e.g. copy of quote, page from catalog, or method used for deriving engineering estimates.

File details come from the government source that posted it. Updated .