J-13 FY20 CHG-1 NWRMC LOCAL STANDARD ITEM 099-11NW.pdf
PDF 24 KB Posted
- Solicitation number
- N0002419R4304
About this file
This document contains a local standard item and related federal contract opportunity. The local standard item provides requirements for compartment closeout to be accomplished by contractors working aboard Navy vessels. It specifies acceptance criteria for contractor work, requirements for inspections and reports, and turnover of accepted compartments.
The related federal contract opportunity is a request for proposals from the Naval Sea Systems Command to provide Carrier Engineering Maintenance Assist Team and Surface Engineering Maintenance Assist Team services. It will be a cost-plus-fixed-fee, indefinite delivery/indefinite quantity contract with a five-year ordering period. The services provided under this contract will support repairs and maintenance training for equipment operators and technicians aboard aircraft carriers and surface vessels located around the world, including major locations in Norfolk, Newport News, Portsmouth, San Diego, Bremerton, Everett, and Yokosuka.
View the file
Other files
Show all 42
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1 of 2 ITEM NO: 099-11NW
FY-2020
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
NWRMC
LOCAL STANDARD ITEM
ITEM NO: 099-11NW
DATE: 24 JUN 2018
CATEGORY: I
1. SCOPE:
1.1 Title: Compartment Closeout; accomplish
1.2 Location of Work:
1.2.1 None
1.3 Identification:
1.3.1 Not Applicable
2. REFERENCES:
2.1 Standard Items
3. REQUIREMENTS:
(V)(G) "COMPARTMENT INSPECTION"
3.1 Accomplish a joint inspection with the SUPERVISOR and the Commanding Officer's designated representative upon completion, inspection, and acceptance, by the contractor, of work within each compartment.
3.1.1 Acceptance criteria is completion of all contractor work within the compartment inclusive of associated Work Items, settled changes to associated Work Items, restoration of removals under "Interference; remove and install" of 2.1, removal of temporary blanks under "Authorization, Control, Isolation, Blanking, Tagging and Cleanliness; accomplish" of 2.1, as well as insulation, paint, and floor covering restoration required as a result of contractor work. Incomplete work is cause for rejection. Minor cleanliness deficiencies shall be promptly corrected by the contractor within one shift of the closeout inspection. Minor cleanliness deficiencies or outstanding work by Ship’s Force, AIT, FMA, or other Third Party Maintenance providers shall not be cause for rejection. “FINAL CONTAMINATION/DAMAGE INSPECTION” in accordance with "Maintaining Protection and Cleanliness from Non-Radioactive Operations;
accomplish" of 2.1 will normally be accomplished for all work within the compartment prior to, or in conjunction with compartment closeout, but may be delayed to facilitate ongoing equipment protection with SUPERVISOR approval.
3.1.1.1 Provide a listing of all contractor work applicable to the compartment for use in evaluating the status of contractor’s work completion during the inspection.
3.1.2 Submit one legible copy, in approved transferrable media, of a report to the SUPERVISOR after each compartment inspection, listing any incomplete work or discrepancies preventing compartment turnover, and recommendation for disposition.
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative,
3.1.3 Turn over each compartment accepted in accordance with 3.1.1 to Ship's Force for maintenance/use.
4. NOTES:
4.1 For purposes of this item, the term compartment includes
compartments, tanks, and voids. The terms "space/spaces", "room/rooms", and "compartment/compartments" are synonymous.
4.2 Interface conflicts in the closeout schedule will be resolved as they occur.
4.3 Integrated Production Schedule and Production Schedule are prescribed by 099-08NW and 099-09NW of 2.1.
4.4 The term “contractor work” is inclusive of any service or product subcontracted by the contractor.
4.5 When invoked, the following Standard Items interface with this Standard Item: 009-04, 009-06 or 099-10NW, 009-24, 009-43, 009-60 or 099- 08NW , 009-67, 009-111 or 099-09NW, and 009-117.
4.6 Coordination with 009-43 and 009-117. These Standard Items provide direction for the completion of work and processes to ensure the ship’s crew can conduct downstream operations. In contrast, 099-11NW is a final closeout of contractor work accomplished in a compartment and marks the end of contractor work in that compartment.
2 of 2 ITEM NO: 099-11NW
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative,
File details come from the government source that posted it. Updated .