Appendix G - CSTO Telecomm Shore Ties.pdf

PDF 366 KB Posted

Attached to
DESIGN/BUILD FRC HOMEPORTING SECTOR FIELD OFFICE (SFO) GALVESTON, GALVESTON, TX
Solicitation number
HSCG47-17-R-3EFK02
Issued by

About this file

Appendix G

View the file

Other files

File Type Posted
Wage_Determination_-_Building.pdf PDF
Amendment_No_0008.pdf PDF
HSCG4717R3EFK02_Amendment_No__0007.pdf PDF
Wage_Determination_-_Building.pdf PDF
Wage_Determination_-Heavy.pdf PDF
Amendment_No._0006.pdf PDF
Amendment_No._0005.pdf PDF
Industrial_Facility_and_Mobile_Boat_Hoist_-_PSI_Geotech_Report.pdf PDF
WAGE_DECISION_NO.__TX170067-_Heavy.pdf PDF
galveston085879sh29.pdf PDF
North_and_South_Pier.pdf PDF
WAGE_DECISION_NO._TX170298_-_Building.pdf PDF
Site_Visit_Attendance_Sheet.pdf PDF
Amendment_No._0004.pdf PDF
Amendment_No._0003.pdf PDF
AMENDMENT_001.pdf PDF
Appendix D - Design Narrative-Sept2012.pdf PDF
Attachment Y - SFO Galveston EA Mar 2017_Final e-signed.pdf PDF
Appendix H - CSTO Electrical Shore Ties.pdf PDF
GALV_FRC_COMBINED_DRAWINGS_5795615_23MAY17.pdf PDF
Appendix C -FDCC File Naming-SEP 2014.pdf PDF
Appendix I - Boat Data.pdf PDF
Appendix J - Hydrant Flow Test Report.PDF PDF
GALVESTON_INDUSTRIAL_BLDG_ARCH_ELEVATIONS.pdf PDF
Appendix M - 154 FRC Mooring Concept.pdf PDF
Attachment O&M Part 2 Equipment Enrollment Form.pdf PDF
Attachment O&M Part 3 SAM Job Plan.pdf PDF
Appendix B -ElectDeliv-Sept2012.pdf PDF
SFO_Galveston_FRC_Homeporting_Spec.pdf PDF
Attachment Z - USCG FONSI FRC Homeport at SFO Galveston.pdf PDF
Attachment X - 154-WPC_582_201_1_-_-MOORING AND TOWING A&D COMBINED.pdf PDF
RFP_HSCG47-17-R-3EFK02.pdf PDF
Appendix A-ComputerGenDrwgs-Sept2012.pdf PDF
Attachment O&M Part 1 Existing SAM Coast Guard Maintained Equipment.pdf PDF
Appendix E - Industry Standards for Const Docs-Sept2012.pdf PDF
Show all 35

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Configuration Standard Technical Order

C4&IT Shore Tie

X

COMDT (CG-64)

X

TISCOM (ENI PL)

64-CSTO-M2000.3D-20090930

Table of Contents

1. OVERVIEW ...................................................................................................................................... 1‐1

1.A. Intent .............................................................................................................................................. 1‐1 1.B. Referenced Directives .................................................................................................................... 1‐1

2. PURPOSE AND SCOPE ................................................................................................................... 2‐1 2.A. Purpose ........................................................................................................................................... 2‐1 2.B. Scope .............................................................................................................................................. 2‐1 2.C. Process Links ................................................................................................................................. 2‐1

3. STANDARD REFERENCES ............................................................................................................ 3‐1 3.A. Telecommunications Policy Manual, COMDTINST M2000.3D .................................................. 3‐1 3.B. Civil Engineering Manual, COMDTINST M11000.11 (series) .................................................... 3‐1 3.C. Naval Engineering Manual, COMDTINST M9000.6 (series) ....................................................... 3‐1

4. REQUIREMENTS ............................................................................................................................. 4‐1 4.A. General ........................................................................................................................................... 4‐1 4.B. Shipboard Configuration ................................................................................................................ 4‐1 4.C. Shoreside Configuration ................................................................................................................ 4‐1

5. GLOSSARY ...................................................................................................................................... 5‐1

1. OVERVIEW

1.A. Intent In conformance with logistics practices and to enhance operational home-porting interoperability, C4&IT shore ties shall be standard for each cutter. This Configuration Standard Technical Order (CSTO) establishes standards on C4&IT shore ties for cutters and shore facilities applications.

1.B. Referenced Directives

1.B.1. Telecommunication Manual, COMDTINST M2000.3D

2. PURPOSE AND SCOPE

2.A. Purpose This technical order informs facility managers of the requirements for providing acceptable standardized facility/vessel (cutters) C4&IT shore ties throughout the Coast Guard.

2.B. Scope

2.B.1. Who Performs C4IT-SC is responsible for the management of this technical order. TISCOM, the C4IT- SC Enterprise Network Infrastructure - Product Line (ENI PL) will be the Center of Excellence (CoE) responsible for the implementation of the standards outlined in this technical order.

2.B.2. Applicable Assets (and/or Services) All cutters and their homeport facilities will be covered under this technical order.

Homeport facilities will be coordinated with FD&CC to ensure all requirements are met and implemented.

2.B.3. When to Perform TISCOM is coordinating with C4ITSC the implementation in order to meet the standardization goal. Any new construction of pier mounds by FD&CC will be coordinated with the appropriate C4IT-SC product line to validate requirements. All new cutters will be delivered with a standard C4&IT shore tie.

2.B.4. To Whom (Customers) This technical order will apply to all cutters and shoreside facilities.

2.B.5. Suppliers ESU’s shall provide replacement shore ties when required. Cutters will not construct their own shore ties. ESU’s will be responsible for maintaining and replacing all pier mound shore tie connectors.

2.C. Process Links N/A

3. STANDARD REFERENCES

3.A. Telecommunication Manual, COMDTINST M2000.3D

3.B. Civil Engineering Manual, COMDTINST M11000.11 (series)

3.C. Naval Engineering Manual, COMDTINST M9000.6 (series)

4. REQUIREMENTS

4.A. General

4.A.1. C4&IT shore tie cables provide shipboard connectivity to the provided voice circuits and data circuit from the servicing shore facility. No other services (ie; CCTV, CATV etc.)

are considered part of the standard C4&IT shore tie. Space for vendor provided CATV will be allocated on the shoreside pier mound(s).

4.A.2. ESU’s shall be responsible for furnishing and maintaining C4&IT shoretie cables and plugs to ensure all cables maintain standard configuration.

4.A.3. ESU’s shall be responsible for maintaining shoreside pier mound receptacles and infrastructure.

4.A.4. All new cutters shall be delivered with a standard shore tie configuration as designated in this CSTO.

4.B. Shipboard Configuration

4.B.1. All vessels shall use the same configuration for plugs as follows: Plug 1 will consist of pins 1-8 as 4 dedicated voice circuits and pins 9-12 as the dedicated CGOne circuit. If required, Plug 2 will consist of pins 1-12 as 6 dedicated voice circuits for units requiring more than 4 dedicated voice lines. National Security Cutters (NSC) will utilize a third plug that will be unique to the NSC. Shipboard receptacles will be the RussellStoll

SKWR12XG.

4.B.2. All vessels shall use the designated standard shore tie cable, Belden’s 9389, 18 gauge, stranded 6 pair cable. All cable plugs will be the RussellStoll SKWP12XG.

4.B.3. Refer to enclosure (1) for the standard shoretie design practice.

4.C. Shoreside Configuration

4.C.1. Each shoreside pier mound will provide 4 dedicated copper C4&IT shoretie receptacles (RussellStoll SKWR12XG) and 2 future fiber optic receptacles (Delphi Hermaphroditic 12-CH receptacles).

4.C.2. Refer to enclosure (2) for recommended shoretie facility design practices.

4.C.3. Copper receptacles will be fed with 2 each 25 pair Category 5-E rated cables via dedicated 4 inch conduits. Conduits will be direct home-runs from the closest Telecommunications Closet with a maximum of 180 degrees of sweep between readily accessible pull boxes.

4.C.4. Each shoreside pier mound will provide for future fiber optic receptacles via dedicated 4 inch conduits, allowing for the mounting of the 2 each Delphi Hermaphroditic connectors. Conduits will be direct home-runs from the closest Telecommunications Closet with a maximum of 180 degrees of sweep between readily accessible pull boxes.

4.C.5. Refer to enclosure (3) for the fiber optic connector.

5. GLOSSARY

C4&IT Command, Control, Communications, Computers & Information Technology C4ITSC Command, Control, Communications, Computers & Information Technology

Service Center CG-6 Assistant Commandant for Command, Control, Communications, Computers &

IT

CG-64 Office of Enterprise Infrastructure Management CGOne Coast Guard One Data Network CoE Center of Excellence ESU Electronics Systems Support Unit FD&CC Facilities Design and Construction Center FY Fiscal Year NSC National Security Cutter STWG Shore Tie Working Group TISCOM Telecommunication and Information Systems Command TTY Teletype TVD&V Telephony Voice, Data & Video

CSTO C4&IT Shore Tie

Enclosure 1

Each connector will be the same configuration shown above.

A‐1

Enclosure 2

A‐2

Enclosure 3

A‐3

1. OVERVIEW
1.A. Intent
1.B. Referenced Directives
1.B.1. Telecommunication Manual, COMDTINST M2000.3D
2. PURPOSE AND SCOPE
2.A. Purpose
2.B. Scope
2.B.1. Who Performs
2.B.2. Applicable Assets (and/or Services)
2.B.3. When to Perform
2.B.4. To Whom (Customers)
2.B.5. Suppliers

2.C. Process Links

3. STANDARD REFERENCES
3.A. Telecommunication Manual, COMDTINST M2000.3D
3.B. Civil Engineering Manual, COMDTINST M11000.11 (series)
3.C. Naval Engineering Manual, COMDTINST M9000.6 (series)
4. REQUIREMENTS
4.A. General
4.A.1. C4&IT shore tie cables provide shipboard connectivity to the provided voice circuits and data circuit from the servicing shore facility. No other services (ie; CCTV, CATV etc.) are considered part of the standard C4&IT shore tie. Space for vendor provided CATV will be allocated on the shoreside pier mound(s).
4.A.2. ESU’s shall be responsible for furnishing and maintaining C4&IT shoretie cables and plugs to ensure all cables maintain standard configuration.
4.A.3. ESU’s shall be responsible for maintaining shoreside pier mound receptacles and infrastructure.
4.A.4. All new cutters shall be delivered with a standard shore tie configuration as designated in this CSTO.
4.B. Shipboard Configuration
4.B.1. All vessels shall use the same configuration for plugs as follows: Plug 1 will consist of pins 1-8 as 4 dedicated voice circuits and pins 9-12 as the dedicated CGOne circuit. If required, Plug 2 will consist of pins 1-12 as 6 dedicated voice circuits for units requiring more than 4 dedicated voice lines. National Security Cutters (NSC) will utilize a third plug that will be unique to the NSC. Shipboard receptacles will be the RussellStoll SKWR12XG.
4.B.2. All vessels shall use the designated standard shore tie cable, Belden’s 9389, 18 gauge, stranded 6 pair cable. All cable plugs will be the RussellStoll SKWP12XG.
4.B.3. Refer to enclosure (1) for the standard shoretie design practice.
4.C. Shoreside Configuration
4.C.1. Each shoreside pier mound will provide 4 dedicated copper C4&IT shoretie receptacles (RussellStoll SKWR12XG) and 2 future fiber optic receptacles (Delphi Hermaphroditic 12-CH receptacles).
4.C.2. Refer to enclosure (2) for recommended shoretie facility design practices.
4.C.3. Copper receptacles will be fed with 2 each 25 pair Category 5-E rated cables via dedicated 4 inch conduits. Conduits will be direct home-runs from the closest Telecommunications Closet with a maximum of 180 degrees of sweep between readily accessible pull boxes.
4.C.4. Each shoreside pier mound will provide for future fiber optic receptacles via dedicated 4 inch conduits, allowing for the mounting of the 2 each Delphi Hermaphroditic connectors. Conduits will be direct home-runs from the closest Telecommunications Closet with a maximum of 180 degrees of sweep between readily accessible pull boxes.
4.C.5. Refer to enclosure (3) for the fiber optic connector.

5. GLOSSARY

2011-05-24T08:18:02-0400