Fort Garland - Advertisement - Appendix O - Code Compliance Notice.pdf
PDF 207 KB Posted
- Attached to
- Fort Garland 7+1 Bay VSF
- Solicitation number
- 23704
- Issued by
- Custer County, Colorado
About this file
This document is a comprehensive Plan Review Report and Compliance Notice for the Colorado Department of Transportation's Ft. Garland Vehicle Storage Facility project, prepared by Code Consultants International. The project involves constructing a new vehicle storage facility with a total area of 8,250 square feet plus a 970 square foot mezzanine, located at 29152 Hwy. 159. The facility is classified as Type VB construction with B and S-1 occupancy classifications, designed to accommodate 49 total occupants (12 in business areas, 37 in storage areas). The project was reviewed against 2021 International Building, Fire, Mechanical, and Plumbing Codes, and the 2023 National Electrical Code, with the design team including Vega Architecture, Portis Structural Design, D. Keller Electrical Design, and MEC Inc.
The review process involved multiple stages of technical review across building, mechanical, plumbing, and electrical disciplines, with comments and corrections systematically addressed by the design team. Key technical aspects include provisions for helical piers, life safety systems, underground utilities, electrical panel clearances, and mechanical ventilation. The project includes infrastructure for propane tanks, sand/oil interceptors, and specific site requirements such as bollard placement, accessible parking, and exterior landings. The compliance notice, dated August 8, 2025, indicates that all initial comments were successfully addressed and the project is deemed compliant with applicable codes and standards, pending final field verification of the recommended inspection points.
View the file
Other files
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
COMPLIANCE NOTICE
CO Department of Transportation Ft. Garland Vehicle Storage Facility
#23704
August 8, 2025
Dear Rob, After reviewing the plans and specifications for the above project we found the design to be in compliance with the SBP codes and standards in effect at the time of review.
All comments were successfully addressed by the design team and will be verified in the field for code compliance. Please see attachment for inspection recommendations.
Respectfully Submitted, Michael Abruzzi, CBO Vice President
I certify that all comments from the plan review have been properly addressed:
Project Manager
Building (Consultant) Date Comments or Corrections X Footings/Foundations
Concrete Slab / Under-Floor
X Framing (after rough elec/mech/plumb)
X Lath and Gypsum Board
Fire-Resistant Penetrations
X Mechanical/Energy Efficiency
X Roofing
Other
X Final
Special (Consultant) Date Comments or Corrections
X Steel
X Concrete
Masonry
Wood
X Soils/Foundations
Spray-Applied Fireproofing
Smoke Control Systems
Other: Helical Piers
Elevator Inspection (State) Date Comments or Corrections
Final Electrical (Co. St. Electrical Bd.) Date Comments or Corrections
X Underground X Rough Walls X Rough Ceilings X Final
Plumbing (Co. Ex. Bd. of Plumbers) Date Comments or Corrections X Underground X Gas X Inside Water X Final
Fire Department Inspection (Local) Date Comments or Corrections Fire Sprinkler System
Fire Alarm System
X Other: Life safety
Final
Health Dept. Inspection (Local) Date Comments or Corrections
Boiler Inspection (State) Date Comments or Corrections
New Installation Repair or Alteration
PLAN REVIEW REPORT
CO Department of Transportation CDOT25-0525 Permit #: CDOT25-0525 / 29152 Hwy. 159 / Ft. Garland Vehicle Storage Commercial New
Code Criteria
Governing Codes & Standards: 2021 IBC,2021
IFC,2021 IMC,2021 IPC,2023 NEC
Type of Construction: VB Occupancy Class: B ,S-1
Fire Suppression System: Use: Allowable Area: VSF: 27’-0” and 8,250 SF + 970 SF Mezz.
# of Exits Required: 1 Accessibility: Max Travel Distance: 200'
Max Common Path: 100' Max Dead End: 50' Occupant Load: B: 12 occupants; S-1: 37 occupants; Total: 49
Design Team
Architect: Vega Architecture Contact Name: David Grooms Address: 495 W. Cedar Ave., Denver, CO 80223 Phone: (303) 872-0487 Email: david@vegaarchitecture.com
Structural Engineer: Portis Structural Design Contact Name: Jon Eldridge Phone: (720) 501-4900 Email: jon@portisdesign.com
Electrical Engineer: D. Keller Electrical Design Contact Name: Dawn Keller Phone: (303) 918-9475 Email: dawn@dkellereng.com
Mechanical Engineer: MEC Inc.
Contact Name: Joe Wittenberg Phone: (914) 860-6507 Email: jwittenberg@mecengr.com
Building CD Comments
Item Date Approved Approval Final Comments
CD Review 08/07/25 Deferred 07/21/25 - Julie Whitmire - Rejected 08/07/25 - Julie Whitmire - Approved 08/07/25 - Julie Whitmire - Deferred
Mechanical CD Comments
Item Date Approved Approval Final Comments
CD Review 08/07/25 Approved 07/21/25 - Julie Whitmire - Rejected 08/07/25 - Julie Whitmire - Approved
Plumbing CD Comments
Item Date Approved Approval Final Comments
CD Review 08/07/25 Approved 07/21/25 - Julie Whitmire - Rejected 08/07/25 - Julie Whitmire - Approved
Electrical CD Comments
Item Date Approved Approval Final Comments
CD Review 08/07/25 Approved 07/21/25 - Julie Whitmire - Rejected 08/07/25 - Julie Whitmire - Approved
BUILDING CD COMMENTS
Permit #: CDOT25-0525 / 29152 Hwy. 159 / Ft. Garland Vehicle Storage
B-1: Civil Sheets - Civil engineer of record shall stamp and sign these sheets prior to final approval.
Response: Stamp and signature added to all Civil Sheets.
CCI: Accepted.
B-2: WW Sheets - Septic engineer of record shall stamp and sign all waste water and water treatment sheets prior to final approval.
Response: Stamp and signature added to all Waste Water Sheets. Water Treatment is not in contract and is being provided for information only.
CCI: Accepted.
B-3: A Sheets - Architect of record shall stamp and sign all architectural sheets prior to final approval.
Response: Stamp and signature added to all Architectural Sheets.
CCI: Accepted.
B-4: Soils Report - Geotechnical engineer or geologist of record shall stamp and sign the first sheet of the submitted geotechnical report prior to final approval.
Response: Noted.
CCI: Accepted.
B-5: M & P Sheets - Mechanical engineer of record shall stamp and sign all mechanical and plumbing sheets prior to final approval.
Response: Stamp and signature added to all Mechanical and Plumbing Sheets.
CCI: Accepted.
B-6: E Sheets - Electrical engineer of record shall stamp and sign all electrical sheets prior to final approval.
Response: Stamp and signature added to all Electrical Sheets.
CCI: Accepted.
B-7: S Sheets - Structural engineer of record shall stamp and sign all structural sheets prior to final approval.
Response: Stamp and signature added to all Structural Sheets.
CCI: Accepted.
B-8: Calcs - Structural calculations stamped & signed by the structural engineer of record shall be provided for the proposed construction of the new vehicle storage facility and were no included in this submittal. Comments may follow upon review.
Response: Until we have final column reactions from the pre-engineered metal building (PEMB) manufacturer, there is nothing to calculate. Structural calculations for the foundations can be provided once we have that information.
CCI: Accepted, this will be a deferred submittal.
B-9: Cover Sheet - Specify PIN for this site as part of the Code Summary table information.
Response: We were not able to determine the PIN for this site.
CCI: Accepted.
B-10: Cover Sheet - Specify total lot area as part of the Code Summary table information.
Response: Lot area has been added to the Code Summary table.
CCI: Accepted.
B-11: Cover Sheet - Revise 2020 NEC to 2023 NEC and 2009 ICC A117.1 to 2017 ICC A117.1.
Response: The codes have been updated.
CCI: Accepted.
B-12: Cover Sheet - Add geotechnical engineer's information (Terracon) to the Design Team.
Response: Geotechnical Engineer's information has been added to the Design Team.
CCI: Accepted.
B-13: Cover Sheet - Add land surveyor's information to the Design Team.
Response: Land Surveyor's information has been added to the Design Team.
CCI: Accepted.
B-14: WTS.1 - Sheet WTS.1 is included in the sheet index but was not submitted as part of this submittal. Please provide for review.
Response: Sheet WTS-1 has been added to the set. NOTE: It is not in this contract and is being provided for information only.
CCI: Accepted.
B-15: Cover Sheet - Coordinate occupant load provided in Occupancy Tabulation with the values listed for the business area on the Code Plan (12 vs 13 total B-occupants).
Response: The occupancies on the code plan have been rounded up to the nearest whole number; the Occupancy Tabulation is based on aggregate occupancies (we have a note under the tabulation clarifying this). Business area on the first floor = 5.16 (rounded to 6); business area on the mezzanine = 6.44 (rounded to 7).
Total Occupancy = 11.60 (rounded to 12).
CCI: Accepted.
B-16: Cover Sheet - Coordinate the total proposed areas listed on the Code Plan and used for occupancy calculation with the areas listed in the Code Summary table. Maintain consistency.
Response: The Occupancy Tabulation has been corrected.
CCI: Accepted.
B-17: C101 - Specify the height and material type of all existing and proposed site walls and/or fences on the proposed site plan. Please note, fences over 7'-0†in height shall be supported with structural calculations and an appropriate assembly detail.
Response: All fencing will be 6' chainlink with barbed wire as previously noted. A note has been added to the concrete wall around the sand filter treatment area, max height 2.5'.
CCI: Accepted.
B-18: C101 - Provide a direct reference to bollard detail 5/C500 or the details on A4.0, for all areas equipped with bollards for impact protection IFC 312 Response: A general note has been added to sheet C101.
CCI: Accepted.
B-19: C101 - Dimension the spacing of all called-out bollards @ 4'-0†on center and located not less than 3'-0†from the protected object. IFC 312 Response: Typical bollard spacing dimensions have been added to Sheet C101 CCI: Accepted.
B-20: C101 - Identify the location of the main electrical service panel, water meter, gas meter (if any), and ground-mounted HVAC/Heat Pump equipment on the proposed site plan.
Response: Electrical service panel, water meter and heat pump notes added to sheet C400, Utility Plan. A gas meter is not required for the project as it is on propane with tanks on-site.
CCI: Accepted.
B-21: C101 - Provide enlarged accessible parking layout, fully dimensioned, per the requirements of section 502 ICC A117.1.
Response: An expanded site plan with dimensions included has been added to sheet C101.
CCI: Accepted.
B-22: A2.0 - Specify the ceiling height within each room, space, or area on proposed floor plans.
Response: The ceiling height of each room is noted within Finish Schedule on sheet A0.1 and indicated in the Reflected Ceiling Plans on sheet A2.1. We avoid duplicating information within the drawing set to avoid conflict and error.
CCI: Accepted.
B-23: A2.0 - First floor plan refers to sheet A1.0 for architectural site plan, however sheet A1.0 is not part of this submittal. Please verify.
Response: Architectural Site Plan was unnecessary and removed from the set. The note has been updated to reference the Civil Site Plan.
CCI: Accepted.
B-24: A2.0 - Provide a minimum 44†deep exterior landing to serve exterior doors 105A and 101D. IBC 1010.1.5 Response: Slab at door 101D is identified and dimensioned on the Floor Slab Plan on sheet A2.2; the note has been clarified to reference Civil drawings and the note has been added to door 105A.
CCI: Accepted.
B-25: A2.0 - Demonstrate the mezzanine shall be open and unobstructed to the room in which the mezzaine is located and equipped with 42†high guardrails.
IBC 505.2.3
Response: From our Code Analysis on the Cover Sheet: 505.2.3. Exception 1: Mezzanines or portions thereof are not required to be open to the room in which the mezzanines are located, provided that the occupant load of the aggregate area of the enclosed space is not greater than 10. Occupant load of the mezzanine is 7.
CCI: Accepted.
B-26: A2.1 - Per section 808.1.1.1 of the 2021 IBC, provide a typical suspended ceiling system detail and include manufacturer's specifications complying with ASTM C635 and ASTM C636. IBC 808.1.1.1 Response: The specifications require compliance with ASTM C635 and stipulates requirements of C636. A note has been added to the Reflected Ceiling Legend to further clarify installation requirements.
CCI: Accepted.
B-27: A2.2 - Identify gutters, downspouts, and/or scuppers to serve the new roof. IBC 1502 Response: CDOT has requested no gutters and downspouts in Climate Zone 6. IBC 1502 does not require roof drainage systems but stipulates requirements for any roof drainage systems provided.
CCI: Accepted.
B-28: Structural - Structural review is incomplete without structural calculations. Comments may follow upon resubmittal and review.
Response: Noted.
CCI: Accepted, this will be a deferred submittal.
B-29: Provide a written response letter indicating how each comment or correction has been addressed.
Response: Noted.
CCI: Accepted.
MECHANICAL CD COMMENTS
Permit #: CDOT25-0525 / 29152 Hwy. 159 / Ft. Garland Vehicle Storage
M-1: All mechanical plan sheets: The mechanical plans must bear the seal of a registered design professional. (OSA, Exhibit A, 107.1) Response: The plans are now stamped.
CCI: Accepted.
M-2: M4.0 - Provide installation details for infrared systems to include clearances and venting.
Response: Venting and combustion air and all clearances are now described in keynote 4 on M2.0 with sizes noted in the radiant heater schedule on M3.1.
CCI: Accepted.
M-3: Provide mechanical ventilation calculations. (IMC Sec. 403) Response: These calculations are shown on M3.
CCI: Accepted.
M-4: Provide a site plan indicating the placement of the propane tank with clearances measured from the building and property line and the LP container capacity.
(IMC General) Response: This work is shown on the civil site plan, C101. Clearances have been added to the civil sheet (25' clearances to building and property lines per the IFC and NFPA 58) as requested.
PLUMBING CD COMMENTS
Permit #: CDOT25-0525 / 29152 Hwy. 159 / Ft. Garland Vehicle Storage
P-1: The plumbing plans must bear the seal of a registered design professional. (ASA, Exhibit A, 107.1) Response: The plans are now stamped.
CCI: Accepted.
P-2: P4.1 - Detail installation for backflow and cross contamination prevention for Sand/Oil Interceptor and water system recycling. (IPC 1301) Response: This is described in keynote 10 on P2.0 CCI: Accepted.
P-3: P4.1 - Provide Drawings showing routing of drainage to Sand/Oil Interceptor. (IPC 1301) Response. This waste piping to the sand/oil interceptor is shown on keynote 8 on P2.0.
ELECTRICAL CD COMMENTS
Permit #: CDOT25-0525 / 29152 Hwy. 159 / Ft. Garland Vehicle Storage
E-1: Electrical plans must bear the seal of a registered design professional, (OSA, Exhibit A, 107.1) Response: The electrical plans have been signed and sealed as required.
CCI: Accepted.
E-2: Cover - Plans should indicate the 2023 National Electric Code. (Currently indicate 2021).
Response: The plans do indicate and comply with the 2023 National Electrical Code, as stated in the Code Compliance Statement on Sheet E0.0.
CCI: Accepted.
E-3: E1.0 - Please provide scale drawings indicating equipment clearance per power plan note #8. ART 110 Response: Details 3 and 4 added to Sheet E1.0 for NEC 110 Working Clearance at Electrical Panel, Top-View and Front-View.