This document is a Design/Bid/Build Scope of Work for the Fort Garland 7+1-Bay Vehicle Storage Facility (VSF) project, issued by the Colorado Department of Transportation (CDOT) for a project located in Costilla County, Colorado. The project involves constructing an 8,000 gross square foot pre-engineered metal building with seven vehicle storage bays, two of which will be wash bays, and an administration area with a mezzanine. The facility will be built on undeveloped land adjacent to an existing CDOT maintenance yard and will include demolition of two existing maintenance garage buildings, construction of a concrete pad and utility rough-in for a new fuel island, and installation of a new septic system with a geotextile sand filter.

The project requires comprehensive site work including utility coordination, erosion control measures, asphalt paving, concrete work, fencing, electrical service installation, plumbing, and specialized equipment like a waste oil collection system and a propane gas-fired pressure washer. The contractor will be responsible for obtaining necessary permits, conducting environmental surveys for migratory birds and wildlife, and complying with the Buy Clean Colorado Act requirements for material global warming potential. The project involves coordination with multiple utility providers, including Monte Vista Co Op for propane, XCEL Energy for electricity, and Fort Garland Water & Sanitation District for water services. The scope of work details extensive technical specifications for building construction, mechanical systems, electrical infrastructure, and environmental compliance.

View the file

Other files

File Type Posted
Fort Garland - Advertisement - Appendix D - Applicable Prevailing Wage Rates (Building).pdf PDF
Fort Garland - Advertisement - Appendix D - Applicable Prevailing Wage Rates (Heavy).pdf PDF
Fort Garland - Advertisement - Appendix G - Labor and Material Bond.docx DOCX document
Fort Garland - Advertisement - Appendix L - Construction Specifications.pdf PDF
Fort Garland - Advertisement - Appendix M - Stormwater Management Plan.docx DOCX document
SBP-6.15 Award DBB_2025 (1).docx DOCX document
SBP-6.26 Notice Procd Const DBB_2025 (1).docx DOCX document
Fort Garland - Advertisement - Appendix A - Information for Bidders.pdf PDF
Fort Garland - Advertisement - Appendix H - Sample Contract.pdf PDF
SBP-070 SubCompletion-2025.docx DOCX document
SBP-7.3 Settlement_2025_0.docx DOCX document
SBP01 Notice Approval Occupncy Use R7-2022 (11).docx DOCX document
Fort Garland - Advertisement - Appendix B - Bid Form.pdf PDF
Fort Garland - Advertisement - Appendix E - Contract Wage Compliance Form.pdf PDF
Fort Garland - Advertisement - Appendix K - Construction Drawings.pdf PDF
Fort Garland - Advertisement - Appendix N - Buy Clean Colorado Form.xlsx XLSX spreadsheet
Fort Garland - Advertisement - Appendix O - Code Compliance Notice.pdf PDF
Fort Garland - Advertisement - Appendix B1 - Bid Bond.docx DOCX document
Fort Garland - Advertisement - Appendix C - Direct Labor Burden Calculation.docx DOCX document
Fort Garland - Advertisement - Appendix F - Performance Bond.docx DOCX document
Fort Garland - Advertisement.pdf PDF
SBP-6.27 Acceptance_2025.docx DOCX document
Show all 22

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Design/Bid/Build Scope of Work Fort Garland 7+1-Bay VSF

Project #23704

August 20, 2025

PROJECT LOCATION:

29152 Highway 159, Fort Garland, CO 81133

PROJECT DESCRIPTION:

Qualified contractors are invited to bid on the construction of a new 7+1-bay Vehicle Storage Facility (VSF) on undeveloped land adjacent to an existing CDOT maintenance yard in Costilla County.

The new VSF shall be a 8,000 gross square foot pre-engineered metal building (PEMB). The VSF will contain an administration bay with mezzanine and seven 20’-0” x 50’-0” bays used to store CDOT plow trucks, two of which shall be wash bays with waterproofed finishes and fixtures. The flooring shall be concrete slab-on-grade with a 20-foot concrete apron at the overhead doors.

The project will also include demolition of two existing maintenance garage buildings and construction of a concrete pad and utility rough-in for a new fuel island in the existing maintenance yard. CDOT will inspect for asbestos and lead-based paint in the structures to be demolished. CDOT will abate any materials that require disposal as special waste. This work should be scheduled to occur towards the end of the construction schedule to allow CDOT maintenance staff to use these facilities during the construction of the VSF. Additional structures in the existing maintenance yard include a sand shed, magnesium-chloride tanks with spill-containment structure and a lean-to shed in the NE corner of the yard. These structures are to remain operational and accessible to CDOT maintenance staff throughout the construction project.

Existing utilities on the adjacent site (inside the CDOT yard) include propane gas provided by Monte Vista Co Op, electric power provided by XCEL Energy, telecommunications fiber provided by CDOT ITS, and water provided by Fort Garland Water & Sanitation District. For sanitary sewer, a new septic system with a geotextile sand filter will be installed as part of this contract. The vehicle wash bays sewer lines will be connected to an on-site water recycling system that collects the melting snow from the plow trucks, filters the water through a treatment system that is buried outside the building, and then is available for re-use as supplementary supply water in the wash bays. The GC is responsible for purchasing and installing the concrete tanks and the piping and conduit for this treatment system, as well as the concrete pad that will hold the connex box housing the equipment; the equipment and final connections to the equipment is by others.

SCOPE OF SERVICES:

The following documents will be available on Bidnet and summarized at a mandatory pre-bid meeting: Drawings and Specifications by the contracted Architect Vega Architecture LLC, Civil Engineer Anderson & Hastings Consultants Inc., Structural Engineer Portis Structural Design, Mechanical and Plumbing Engineer MEC, Inc., Electrical Engineer D. Keller Electrical Design and

Septic Engineer Church Onsite Wastewater Consultants. Additionally, a geotechnical report prepared by the geotechnical engineer of record Terracon will be provided as part of the Specification.

The Scope of Work, Bid Drawings and Specification should all be referenced during bidding and any contradictory information should be brought to the attention of CDOT; misunderstanding of any of the Bid Drawings, Specification and/or Scope of Work will not be grounds for change orders after the bid question period. Requests for substitutions or evaluation of equivalent products or systems should also be made during the bidding period.

The Contractor is responsible for obtaining (and paying for) Permits from the State Electrical Inspector and State Plumbing Inspector. By Statute, local building permits are not required. Code reviews (including framing and insulation) and one final code review inspection for each building shall be paid for by CDOT. Any additional code review inspections due to the original inspection not passing will be paid for by the Contractor.

The Contractor is responsible for responding to and satisfying code comments related to the metal building’s deferred submittal. The metal building may not be ordered by the Contractor until a Notice of Compliance is received for the metal building submittal from the State’s code consultant, Code Consultants International (CCI).

CDOT requires that the geotechnical engineer of record who provided the Geotechnical Report, Terracon, or any mutually agreeable certified geotechnical engineer, perform the independent excavation and compaction observation and all testing required, as specified. The Contractor is to contract, at its cost, with the geotechnical engineer of record for all testing, including sub-grade testing, concrete testing, and observation costs.

Terracon Contact Information: Nicholas M Novotny (720) 531-0761 / nick.novotny@terracon.com

This site falls under the jurisdiction of the Costilla County Fire Department, 301 Beaubien Avenue, Fort Garland, 81133. Inspections by CCFD for fire-related items are required and shall be coordinated and paid for by the Contractor.

Refer to Project drawings and Specification for additional details and requirements.

Site Work:

Prior to any site-disturbing activities, the Contractor will be responsible for locating all utilities. The Contractor shall notify the Utility Notification Center of Colorado (UNCC) to conduct locates for buried utilities.

1. Construct and maintain reinforced silt fencing and other erosion control measures around the Limits of Disturbance area shown on the Civil and SWMP drawings.

2. Conduct site excavation and grading per the Civil Drawings. Install new asphalt paving, curb, gutter, water quality basins, water quality outlet control structures, riprap, temporary and permanent SWMP measures, and seeding per Civil and SWMP plans and notebook.

Provide striping, painting at parking spaces as detailed.

mailto:nick.novotny@terracon.com

3. Install new concrete aprons, sidewalks, curbs, equipment pads, curb stops, bollards, fuel island and propane tanks pad as shown in the Civil, Structural, and Architectural drawings.

4. Install electric vehicle charging station(s) underground rough-ins for power and data, parking signage and striping, and exterior waste oil tank per plans and specification.

5. Provide and install chain link fencing and gates per plans and specification, including new 30’ powered slide gate with integral man gate and loop detectors for exit. Tie new fence into existing where required

6. All earthwork, backfill, and compaction shall be placed and performed in strict accordance with the Specification and Division 200, including but not limited to section 206, and Division 700 of the current edition of the CDOT Standard Specifications for Road and Bridge Construction and the geotechnical engineer recommendations.

7. Contractor shall coordinate with water utility to install a new water line from the main in Highway 159 to the VSF building water service entry shown on the Civil and Plumbing drawings, including all required permits and inspections. CDOT will pay any required tap fees directly to utility.

8. Contractor shall connect the VSF sanitary sewer piping to a new Septic System per Plumbing, Civil and Onsite Wastewater Treatment System drawings and specification.

9. Contractor shall connect the VSF vehicle bay floor drains to a sand & oil interceptor, then to the Water Treatment System per plans and specification.

10. Contractor to work with XCEL Energy to install new electrical service per plans and specification. Provide new underground / overhead electric conduits and conductors from transformer to meter location as shown on plans. Coordinate meter installation with XCEL Energy. Connect new power lines to the new VSF. Provide new underground electric conduits and conductors (where indicated) from the VSF to the powered gates, pole lights, fuel island, generator, water treatment equipment, and to vehicle-charging stations, as shown in the drawings.

11. Provide power and data via underground conduits and conductors (where indicated) to the VSF entry doors, fuel island, vehicle entry gate and pedestal, water treatment equipment and EV charging stations. Provide card readers and cabling as specified in the door hardware schedule and connect to the card reader network system.

Storm Water Quality Permit:

12. Because the area of disturbance is greater than an acre (2.5 acres), the Contractor shall be responsible for obtaining and paying for a construction Storm Water Quality Permit with Colorado Department of Public Health and Environment (CDPHE). The Storm Water Management Plan (SWMP) drawings are provided in the civil drawings as required for permit; a SWMP Narrative is included in the Bid Documents. Contractor shall obtain a SWMP Application. Both CDOT and the contractor will be permit holders. Details of the permit can be found here: https://www.colorado.gov/pacific/cdphe/cor400000-stormwater-discharge https://www.colorado.gov/pacific/cdphe/cor400000-stormwater-discharge https://www.colorado.gov/pacific/cdphe/cor400000-stormwater-discharge

13. All required 14 day inspections (and within 24 hours of a water event) during the course of the project, per the SWMP Permit, must be conducted by a Certified Transportation Erosion Control Supervisor. The certified Supervisor cannot be the Project Superintendent.

Contractor to provide this inspector on-site as needed.

Pre-Engineered Metal Buildings:

14. (VSF Building) Provide an approximately 8,000 gross square foot pre-engineered metal building (PEMB) with seven vehicle storage bays, two of which are wash bays. Provide two demising walls, one separating the vehicle bays from the wash bays, and one separating the administrative area, restrooms, storage and offices from the vehicle bays, per plans. Provide a mezzanine in the administrative area with steel floor framing and decking, concrete topping slabs, and pre-engineered stairs and landing.

15. It is required that the contractor and PEMB manufacturer follow the building layouts and details shown on the drawings, including all engineering disciplines. Modification of the design drawing information without prior authorization by CDOT and the engineering team will result in the contractor being responsible for any A/E or PEMB re-design work or drawing modification. All X-bracing should be as located in the drawings.

16. All PEMBs are required to be designed as “Partially Enclosed” for wind load determination and lateral design. All lateral load and other parameters for building design are shown on the Structural Drawings.

17. The structure shall be a pre-engineered metal building, from a vendor on CDOT’s approved vendor list as specified in Specification Section 13 34 19 and on the Drawings.

Any requested substitution to this list must be submitted during the bidding question period, highlighted how the requested substitution meets the specification

18. The roof structure of the VSF is shed style standing seam metal roof. Refer to the drawings for roof slopes and heights.

19. The wall panels for the building shall be comprised of minimum 26 gauge prefinished steel siding. The roof panels shall be comprised of minimum 24 gauge prefinished metal roofing.

Trim, flashing and expansion joint covers to match adjacent metal panel. Only the specified Hylar/Kynar finishes are acceptable for exterior metal panels. Silicon resin exterior finishes are not acceptable and will not be approved.

20. All exposed structural steel in the VSF, not covered with metal liner panel, shall be painted per the Specification. Exposed metal in the VSF wash bay shall be painted with epoxy paint.

21. Provide snow guards at all PEMB roofs. Design of snow guards shall be included in the shop drawings submitted for approval prior to ordering.

22. There shall be a shed-style standing seam metal roof canopy over some of the exterior man doors. Refer to plans for specific locations.

Concrete:

23. The VSF floor is slab-on-grade with spread footings. There are 8-inch curbs around the building perimeter and at the wash bay and administrative bay demising walls.

24. The VSF shall have a concrete approach apron that extends from the overhead door 20 feet out from the building. Thickness and reinforcing of slabs shall be as scheduled on the drawings and slope away from the building to drain. The exterior concrete apron shall be broom finished and treated with penetrating sealant per the specification.

25. All interior slabs and approach aprons shall be capable of supporting the wheel load from an HS20-44 truck, except the mezzanine and stair landing topping slabs.

26. All rooms with floor drains shall slope to drain. Cross section slope shall not exceed ANSI cross slope. Refer to Structural and Architectural drawings for floor slope plans. Coordinate wall framing with floor elevations for each room.

27. All new interior concrete floors shall have sawn shrinkage control joints that will be filled with expansion joint filler strips and polyurethane sealant. All concrete floors shall be cured and/or sealed with concrete sealer and finished as called out in the Specification.

28. Provide concrete pads for equipment, both interior and exterior. Provide a concrete pad for the air compressor, generator, pressure washer, water heater, heat pumps, waste oil collection tank, fuel island, water treatment system equipment, and propane tanks.

Thickness of the pads and reinforcement shall be as scheduled on the civil and structural drawings.

29. All interior and exterior vertical joints in foundation walls are to be sealed with a non-sag urethane sealant.

Bollards:

30. Install 6-inch diameter steel pipe post bollards in and around the buildings, at corners and at the overhead doors for protection of the structures. Provide exterior bollards to protect tanks, gas meters or other equipment as shown on the drawings. Cast bollards into an isolated foundation and extend 42 inches above the top of the adjacent slab or finished surface. The pipe bollards shall be filled with concrete and painted with the yellow paint system as specified. Fabricate and install 6” bolt-down steel bollards with caps where indicated and per drawings and specification.

31. Interior plumbing, fixtures, and equipment in the vehicle storage areas shall be protected by 4 inch, bolt-down steel bollards with caps, painted safety yellow; see drawings and specification for more details.

Flooring:

32. The concrete floor and curbs throughout the buildings shall be sealed with concrete sealer per the Specification. Finishes for each room are called out in the Finish Schedule.

Walls:

33. The VSF walls shall be insulated per the wall section details. The VSF roof shall have thermal blocks at purlins and multiple layers of insulation as required to meet the Specifications, Drawings and IECC. VSF exterior walls shall have batt and liner system insulation in walls to meet requirement in the Specification, Drawings and IECC. All VSF exterior walls and roofs shall have a vapor barrier complying with IECC requirements for thermal envelope.

34. VSF Offices: The interior walls of the offices and restrooms shall have sound insulation.

Extend walls to structure above per plans and details. Note: All gypsum board walls shall have a rubber base except restrooms.

35. All restroom walls shall have floor-to-ceiling fiber glass reinforced panels (FRP). At all restroom walls and ceilings provide moisture- and mold-resistant gypsum board.

36. VSF vehicle bays: Install pre-finished metal panels (MP) on interior walled surfaces, as shown on drawings. Install per manufacturer’s recommendation, up to 8’-6”. Balance of wall shall be finished with Skyliner or other approved vapor barrier system.

37. VSF wash bay: provide pre-finished metal panels (MP) at walls and ceiling of wash bay.

Provide flashing and corner trim pieces at all edges, corners and joints. Exposed metal in the VSF wash bay shall be painted with epoxy paint.

Ceilings:

38. Offices: The ceiling in the administrative area shall be lay-in acoustical tiles in a suspended grid ceiling and gypsum board at the restrooms.

39. VSF vehicle storage bays: Furnish and install Skyliner or other approved vapor barrier system per manufacturer’s instructions.

40. VSF wash bay: Furnish and install metal panels (MP) per manufacturer’s instructions.

Doors / Windows:

41. Provide 3-foot by 7-foot insulated metal exterior doors set in hollow metal frames with specified hardware as noted in the drawings and specs. Note: Exterior doors have card access readers with lever handles. Card readers, electric strikes, conduit, back boxes and network cabling for the card readers are all to be installed by the contractor. The contractor shall employ one of the certified installers for the card reader system.

42. The exterior man doors shall have a half-panel tempered, insulated glass vision panel in each door.

43. Interior doors shall be a 3-foot by 7-foot sound-insulated, hollow metal door set in a hollow metal frame with specified hardware.

44. The VSF building shall have 16-foot by 16-foot insulated sectional overhead doors in each bay. The sectional overhead doors at the VSF shall have one row of tempered glazing and one row of insulated polycarbonate glazing at the wash bay. The overhead doors shall be operated via a hand-held remote device as well as a waterproof interior operator panel with typical 3-button station.

45. Doors into/out of VSF wash bay are to have stainless steel hardware as specified.

46. The exterior of the VSF building shall be fitted with operable aluminum windows for office areas and fixed clerestory windows in vehicle bays, located per drawings. Windows to be insulated with low-e glazing in compliance with the IECC and Specification.

47. Office interiors shall have fixed hollow metal frames with windows facing into the vehicle areas as shown and scheduled.

Casework and shelving:

48. Provide built-in casework with countertop, backsplash and cabinets at the kitchenette area in the VSF. Total depth of casework and countertop is not to exceed 24 inches to comply with ADA reach requirements for outlets, see drawings.

49. Provide 30-inch-deep countertops with grommets and plastic laminate supports at the crew areas in the VSF. Provide 12-inch-deep adjustable melamine shelving above the countertops as located on the plans.

50. Provide 20-inch-deep adjustable melamine shelving in the VSF Storage Room.

Heating, Cooling and Ventilation:

51. VSF vehicle bays: provide exhaust ventilation with wall-mounted exhaust fans and louvers.

The wash bay shall have NEMA4X rated exhaust fans and a supply louver. Exhaust fans in the vehicle areas shall be tied to carbon monoxide / nitrogen dioxide (CO/NO2) detectors and shall have an override for users to turn the fans on as needed. Override system shall not disable the detection system, and in the event of above-acceptable levels of fumes, the detection system shall operate independent of any user override. Provide a waterproof enclosure for CO/NO2 detector in wash bay.

52. Provide destratification ceiling fans in each VSF bay per plans. There are no ceiling fans in the wash bays.

53. VSF vehicle bays: provide infrared, low-intensity, gas-fired tube heaters, suspended from the roof with runs coordinated with-in areas shown on drawings. Radiant tube heaters in wash bay shall be rated for wet environments.

54. The VSF administrative areas shall have unit heaters / split system heat pump with auxiliary electric duct mounted heating coils and air condensing units, as shown on the mechanical drawings. All exterior piping to have hard cover UV protection over the insulation, as specified.

Plumbing:

55. Provide a trench drain in the VSF vehicle bay area and the wash bay per the drawings.

The trench drain is a pre-fabricated trench set into the floor slab. It is 12 inches wide and slopes to a center catch basin(s). The grates for the trench drain shall be HS20-44 rated.

Provide catch basins with lift-out sediment tray filters where indicated and per Specification and Drawings. Provide a sand and oil interceptor per drawings and Specification.

56. Provide floor drains in the restrooms, near the air compressor and water heater, and in the vehicle storage bay below the emergency shower.

57. Provide freeze-proof exterior hose bibs and interior hose bibs located as shown on the drawings.

58. Sanitary Sewer Wastewater from the VSF will be conveyed via 4” waste line to a septic tank / leach field system complying with Costilla County requirements and the WW drawings. Wastewater from the VSF vehicle bay floor drains will be conveyed via 4” waste line to an Wastewater Treatment System (WTS) designed by others. Underground tanks, piping, conduits, disconnects, sub-panels, concrete equipment curbs, etc. for the WTS are included in this contract and are to be provided and installed by the GC per plans and specification. Provide plumbing yard clean-outs where indicated, and per plans and Specification.

59. Domestic water shall be supplied by a new 1.5” tap at the main, then via a 1.5” inch water line to the building service entry as located on the civil and plumbing drawings.

60. Provide and install one propane gas tank-type water heater to supply all fixtures requiring hot water in the VSF.

61. The restrooms shall include plumbing fixtures and accessories as shown on the drawings.

The restrooms and all devices / accessories shall meet all the provisions of ICC/ANSI A117.1.

62. Provide a utility hand sink and mop sink with a mop holder in the VSF, where shown on the plans. Provide a kitchen sink in the admin area of the VSF. Provide water stub out at location shown for an owner-provided refrigerator in the VSF. Provide and install one high-low accessible drinking fountain/bottle filler where shown. Provide and install an emergency shower/eyewash station where shown.

Specialty Equipment:

63. Provide and install a waste oil collection system for the VSF. New components to be provided include the following:

a. A low-profile collection basin with handle that can be quick-coupled to a compressed air, waste pipe system.

b. Exterior Waste Oil Tank, per Specification.

c. Air-operated diaphragm waste oil evacuation pump per Specification.

d. Automatic air shut-off system per Specification.

64. Provide and install one (1) stationary, propane gas-fired pressure washer, properly vented with flue damper and braced back to wall at VSF adjacent to the wash bay, with all accessories per Specification. Rough in gas, water and power for future second pressure washer. Provide concrete curb for future second pressure washer.

65. Provide one (1) vertical-mount tank air compressor mounted on a concrete pad, as specified for the VSF. Provide compressed air distribution system, as specified; refer to drawings for air outlet locations.

66. Provide flammable storage cabinet in vehicle bay of the VSF building.

Electrical:

67. Power distribution as follows: install new 120/208v, 3-phase electrical service with new conduits, conductors, transformer, meter, and panels as shown in the electrical one line diagram. Ensure that all new equipment is selected for correct phase power. Coordinate transformer and meter installation with Highline Electric Association.

All grounding and bonding shall comply with NEC Article 250 and Specification Section 260526, including bonding to building steel, water piping, and communication systems.

68. At the VSF provide and install Panel P-1, P-2, P-3 and P-5. At the fuel island, provide and install Panel P-4.

69. Install convenience receptacles as shown on the plans. Mount at 44 inches above the floor in Vehicle Bays. Mount above counter height at kitchenette. Provide GFCI at wet areas as shown in the plans. Provide one 20-amp GFCI receptacle in each restroom.

70. Along the exterior of the buildings provide NEMA rated 20-amp duplexes (GFI and weatherproof) receptacles as shown on the drawings.

71. VSF Vehicle storage area to have one 50 amp disconnect wired for 208 volts; locate as shown on drawings.

72. All components and electrical devices within the wash bay to be NEMA 4 rated and waterproof, including all wiring and accessories.

73. Provide and install alternate power transfer switch for generator (by Owner) per one-line diagram and drawings and specfication. Rough in conduit and conductors to generator pad for final connection by Owner.

74. Provide underground power/conduit to fuel island for fuel pump and master switch. Install emergency shutoff switch per plans. Provide underground conduits / pull strings to junction boxes for data to fuel pump.

75. Provide underground conduits / pull strings to in-grade junction boxes for power and data at EV-Ready spaces per drawings.

76. Provide underground power/conduit to new gate motor location, operator, and entry kiosk as required.

Lighting:

77. Restrooms: provide and install one (1) LED vanity fixture centered over mirror and recessed LED can light in each.

78. Each restroom shall have an occupancy sensor to operate the lights and fan with 10-minute delay. Each office will have an occupancy sensor to operate lighting.

79. VSF Building to have:

a. LED high bay luminaires, suspended from ceiling as scheduled at VSF.

b. Wall-mounted LED strips with acrylic lens, located on back wall.

c. Daylight harvesting / occupancy sensors to control high bay lighting with overrides.

d. Overhead lighting, task lighting as scheduled at VSF Admin Bay.

80. Exterior lighting: Photocell-controlled, night-sky compliant LED fixtures located on the building, and light poles, as shown on drawings.

81. Provide illuminated exit signs over egress doors and other emergency lighting as required by the IBC and the IFC.

82. Provide and install pole lighting at the fuel island per plans and Specification.

Phones / Data:

83. The contractor shall install all conduits with pull strings, both underground and inside the building, boxes, covers, the demark panel and the IT cabinet. CDOT will have a separate contractor install cabling at its cost.

84. Communication Conduit: The contractor shall trench and install (2) 2” telecommunication conduits from the location shown on the “CDOT ITS Fiber As-Built Exhibit” to the demark panel in the VSF, and then to office rooms to locations shown on drawings. Exterior Conduit is to be minimum two inches in diameter, with pull string. The installation of the conduit must follow the industry standard of using "Sweeps" and NOT elbows. The total amount of bends must not exceed 270 degrees. Should more bends be required, a pull box needs to be installed. Conduit shall have length identifying pull tape.

85. Demark: Contractor will provide and install:

a. Telephone backboards (extended demark) to be of industry standard specification, painted plywood and shall be located per plans.

b. Card Reader Network Equipment.

c. CDOT’s Contractor will install the network gear and make all cabling runs and terminations

86. Provide recessed boxes, covers and conduit at locations noted on the drawings for telephone/data drops. Where there is a drop ceiling, extend conduit back to the demark. All low voltage cabling shall be inside conduit.

87. Provide J-Boxes with recessed conduit in Vehicle bays for owner provided Wireless Access Point. J-Box to be at 10 feet above finish floor; coordinate height with metal girts.

88. Provide conduit and wiring for the networked card reader at the fuel island and at the electric gate entry kiosk. Provide conduit and power and data to the future EV charging stations per plans.

Life Safety:

89. The entire facility shall have the specified smoke and/or heat and carbon monoxide detection. Smoke and/or heat detection shall be provided, designed and installed to meet all NFPA requirements, including type, location, spacing and sound pressure requirements for detectors and annunciation devices such as horns and strobes. Combined carbon monoxide/nitrogen dioxide detector shall automatically engage the ventilation system to exhaust the harmful gas. An override switch shall be provided to allow the ventilation system to be turned on/off manually.

90. Provide hand-held fire extinguishers, one for every 1,500 square feet and located as determined by the local Fire AHJ. Extinguishers to be mounted to wall and labeled.

Onsite Water Treatment System (OWTS)

91. Refer to schematic drawing WTS-1 by Weaver Consultants Group. Contractor to provide and install Oil/Water Separator, Process Tanks, Reclaim Water Storage Tank, and all water conveyance piping and electrical conduits and power between tanks and Pre-Filtration Skid.

Pre-Filtration Skid provided by others (Weaver).

Buy Clean Colorado Act Requirements

92. All CDOT projects solicited for design after 1/1/2024, are required to comply with the Buy Clean Colorado Act (BCCA). This law establishes a maximum acceptable global warming potential (GWP) limit for categories of eligible materials. Complying with BCCA requires documentation and sign off from the project design consultants, contractors, and state buildings delegate. In order to better understand the requirements, contractors are encouraged to read the educational materials and do the training on the Buy Clean Colorado Act OSA Website: https://osa.colorado.gov/energy-environment/buy-clean-colorado-act.

93. The design team has determined that the following materials must comply with GWP limits under BCCA: Asphalt and Asphalt Mixtures, Cement and Concrete Mixtures, Glass, Reinforced Steel, Structural Steel. The GWP limits for these materials are shown on the Environmental Product Declaration form EE5.2, included with the Bid Documents. The Design Team shall be responsible for completing tabs “Instructions” and “EPD Design Submittal” on form EE5.2.

94. The Contractor shall be responsible for reviewing information provided on the Design Submittal and supplying the Environmental Product Declaration (EPD) submittal prior to ordering materials. Once approved the contractor will complete tabs “EPD Construction https://urldefense.proofpoint.com/v2/url?u=https-3A__osa.colorado.gov_energy-2Denvironment_buy-2Dclean-2Dcolorado-2Dact&d=DwMFaQ&c=sdnEM9SRGFuMt5z5w3AhsPNahmNicq64TgF1JwNR0cs&r=CD0yTlFI6uTmBFhR-okqd-NjVpT6guXbEd8SMKfIKgE&m=T1YK6qXzgeR9gosKrj7KbY0yfMYP1qppp00gZp1Lk_l31HMaY2oPmCHBLznhnH-l&s=1oSlcbHErH3xai8_R3RAs82CoBsZm7sGYLIkTK_ceYw&e=

Submittal” and “Transportation” on form EE5.2 confirming that the material submittal is less than or equal to the acceptable threshold.

95. The Office of the State Architect permits waivers to the Buy Clean Colorado Act reporting if the specified eligible material is technically infeasible, non-compliant with code, significantly (5%) more expensive over the material’s lifecycle, would cause a time delay verses non-compliant material or if there is only a single supplier of the material. In this situation the contractor must submit the alternative EPD and provide justification for the waiver. Once accepted by the architect, State Buildings Delegate and Office of the State Architect the non-compliant submittal may be approved.

96. The General Contractor, Architect/Engineer and The CDOT State Buildings Delegate will be responsible for completing tab “Final Sign-Off” on form EE-5.2.

Environmental Requirements

97. It is possible that petroleum contaminated soil and/or other contaminated solid waste debris may be encountered during ground disturbing activities, soil should be monitored for visual and/or olfactory indications of contamination or debris . If potentially contaminated materials are encountered, Section 250 of CDOT standard specifications shall be followed.

98. To the extent practical, all vegetation removal and work on structures necessary to complete the project shall be conducted outside of the nesting season for migratory birds (April 1 to August 31).

99. Migratory bird nest surveys and protection shall occur as outlined in the Project Special

Provision (PSP) 240 if construction will occur between April 1 and August 31.

100. Raptor nest surveys and protection shall occur as outlined in the PSP 240 if construction will occur between February15 and July 15.

101. A dusk and dawn survey for bald eagle roosts shall occur within seven days prior to any construction during the winter season, from November 15 to March 15. Protection of any identified bald eagle roosts should occur as outlined in the PSP 240, and in accordance with Colorado Parks and Wildlife.

102. A pre-construction survey will be completed to confirm the extent of active prairie dog burrows within the project area. CDOT’s Prairie Dog Policy will be followed, and avoidance/relocation techniques will be employed, as needed, to ensure that direct impacts to prairie dog colonies within the project footprint do not occur.

103. The project area shall be evaluated for burrowing owl nesting habitat. If suitable nesting habitat occurs, burrowing owl nest surveys shall occur as outlined in the PSP 240 if construction will occur between March 15 and October 31 and within 660 feet of prairie dog burrows.

104. If night work will occur, the minimum amount of lighting will be used and lights will be directed at the ground to reduce light shine.

105. Comply with Section 240 requirements per below:

Section 240 Protection of Migratory Birds Biological Work Performed by a CDOT Biologist

Add Section 240 to the Standard Specifications for this project as follows:

Description

240.01 This work consists of protecting migratory birds during construction.

Materials and Construction Requirements

240.02 The Contractor shall schedule clearing and grubbing operations and work on structures to avoid taking (pursue, hunt, take, capture, or kill; attempt to take, capture, kill or possess) migratory birds protected by the Migratory Bird Treaty Act (MBTA).

(a) Vegetation Removal. When possible, vegetation shall be cleared before the time active nests are present. Vegetation removal activities shall be timed to avoid the migratory bird breeding season which begins on April 1 and runs to August 31. All areas scheduled for clearing and grubbing between April 1 and August 31 shall first be surveyed within the work limits by a CDOT biologist for active migratory bird nests. The CDOT biologist will also survey for active migratory bird nests within 50 feet outside of the work limits. Project personnel shall enter areas outside CDOT right of way only if a Form 730, Permission to Enter Property, has been signed by the property owner. The Contractor shall avoid all active migratory bird nests. The Contractor shall avoid the area within 50 feet of the active nests or the area within the distance recommended by the biologist until all nests within that area have become inactive. Inactive nest removal and other necessary measures shall be incorporated into the work as follows:

1. Tree and Shrub Removal or Trimming. Tree and shrub removal or trimming shall occur before April 1 or after August 31 if possible. If tree and shrub removal or trimming will occur between April 1 and August 31, a survey for active nests will be conducted by the CDOT biologist within the seven days immediately before the beginning of work in each area or phase of tree and shrub removal or trimming. The Contractor shall notify the Engineer at least ten working days in advance of the need for the CDOT biologist to perform the survey.

If an active nest containing eggs or young birds is found, the tree or shrub containing the active nest shall remain undisturbed and protected until the nest becomes inactive. The nest shall be protected by placing fence (plastic) a minimum distance of 50 feet from each nest to be undisturbed. This buffer dimension may be changed if determined appropriate by the CDOT biologist and approved by the Engineer. Work shall not proceed within the fenced buffer area until the young have fledged or the nests have become inactive.

If the fence is knocked down or destroyed by the Contractor, the Engineer will suspend the work, wholly or in part, until the fence is satisfactorily repaired at the Contractor’s expense. Time lost due to such suspension will not be considered a basis for adjustment of time charges but will be charged as contract time.

The CDOT Biologist will record location of each protected nest, bird species, protection method used, and date installed. A copy of these records will be provided to the Engineer.

2. Grasses and Other Vegetation Management. Due to the potential for encountering ground nesting birds’ habitat, if work occurs between April 1 and August 31, the area shall be surveyed by the CDOT biologist within the seven days immediately before ground disturbing activities. The Contractor shall notify the Engineer at least ten working days in advance of the need for the CDOT biologist to perform the survey.

The undisturbed ground cover to 50 feet beyond the planned disturbance, or to the right of way line, whichever is less, shall be maintained at a height of 6 inches or less beginning April 1 and continuing until August 31 or until the end of ground disturbance work, whichever comes first.

If birds establish a nest within the survey area, an appropriate buffer of 50 feet will be established around the nest by the CDOT biologist. This buffer dimension may be changed if determined appropriate by the CDOT biologist and approved by the Engineer. The Contractor shall install fence (plastic) at the perimeter of the buffer. Work shall not proceed within the buffer until the young have fledged or the nests have become inactive.

If the fence is knocked down or destroyed by the Contractor, the Engineer will suspend the work, wholly or in part, until the fence is satisfactorily repaired at the Contractor’s expense. Time lost due to such suspension will not be considered a basis for adjustment of time charges but will be charged as contract time.

(b) Work on structures. The Contractor shall prosecute work on structures in a manner that does not result in a taking of migratory birds protected by the Migratory Bird Treaty Act (MBTA). The Contractor shall not prosecute the work on structures during the primary breeding season, April 1 through August 31, unless he takes the following actions:

(1) The Contractor shall remove existing nests before April 1. If the Contract is not awarded before April 1 and CDOT has removed existing nests, then the monitoring of nest building shall become the Contractor’s responsibility upon the Notice to Proceed.

(2) During the time that the birds are trying to build or occupy their nests, between April 1 and August 31, the Contractor shall monitor the structures at least once every three days for any nesting activity.

(3) If birds have started to build any nests, the nests shall be removed before they are completed. Water shall not be used to remove the nests if nests are located within 50 feet of any surface waters.

(4) Installation of netting may be used to prevent nest building. The netting shall be monitored and repaired or replaced as needed. Netting shall consist of a mesh with openings that are ¾ inch by ¾ inch or less.

If an active nest becomes established, i.e., there are eggs or young in the nest, all work that could result in abandonment or destruction of the nest shall be avoided until the young have fledged or the nest is unoccupied as determined by the CDOT Biologist and approved by the Engineer. The Contractor shall prevent construction activity from displacing birds after they have laid their eggs and before the young have fledged.

If the project continues into the following spring, this cycle shall be repeated. When work on the structure is complete, the Contractor shall remove and properly dispose of netting used on the structure.

Use of CDOT Maintenance personnel or others to remove nests without fledglings before construction must be coordinated with Region Environmental personnel.

(c) Taking of a Migratory Bird. The taking of a migratory bird shall be reported to the Engineer.

The Contractor shall be responsible for all penalties levied by the U. S. Fish and Wildlife Service (USFWS) for the taking of a migratory bird.

(d) Raptor Nest Surveys. The CDOT Biologist will conduct raptor nest surveys within 0.5 mile of the construction site before the start of construction and before each construction phase.

This survey can be done with binoculars. If construction activities are located within the Colorado Parks and Wildlife (CPW) recommended buffer zone for specific raptors, "NO WORK" zones shall be established according to the CPW standards or by the CDOT Wildlife Biologist in consultation with the CPW around active sites during construction. The

"NO WORK" zone shall be marked with either fencing or signing. Work shall not proceed within a “NO WORK” zone until the CDOT Biologist has determined that the young have fledged, or the nest is unoccupied.

(e) Burrowing Owl Activity. The presence and proximity of active prairie dog burrows may necessitate pre-construction surveys for Burrowing Owl following guidelines developed by the CPW. Surveys will be performed of active prairie dog burrows within 150 ft. of the project area from March 15-October 31. CPW guidelines recommend a minimum of three surveys each separated by approximately one week. If Burrowing Owls are detected during survey efforts the CDOT Regional Biologist, in coordination with the CPW, will determine if construction activities need to be modified or limited in certain areas of the project to comply with the CPW Recommended Buffer Zones and Seasonal Restrictions for Colorado Raptors. The CPW recommends a 150 ft. buffer to protect nesting Burrowing Owls.

(f) Bald Eagle Winter Roost Surveys. The CDOT Biologist will conduct dusk and dawn surveys of Bald Eagle roosts within seven days before the start of any construction during the winter season, November 15 to March 15. If a Bald Eagle roost is identified, construction activity shall not proceed within 0.25 mile of active nocturnal roost sites between November 15 and March 15.

End of Scope of Work