This document is a Direct Labor Burden Calculation form issued by the Colorado State Office of the State Architect State Buildings Program for the Colorado Department of Transportation's Fort Garland 7+1 Bay Vehicle Storage Facility (VSF) project. The form is required to be submitted prior to executing a construction agreement and is designed to document the labor overhead percentages that contractors pay to employees, including taxes, pension costs, health and dental insurance, and other benefits.

The form requires contractors and subcontractors to detail their labor burden percentage, which will be used in calculating future Change Order Proposals. Major subcontractors such as electricians, plumbers, mechanical contractors, excavators, millwork, concrete, and block layers must each provide a separate Labor Burden Calculation Sheet. The state reserves the right to request additional confirmation of the information provided. The related contract opportunity involves constructing a new 7+1-bay Vehicle Storage Facility on undeveloped land adjacent to an existing CDOT maintenance yard in Costilla County, Colorado.

View the file

Other files

File Type Posted
Fort Garland - Advertisement - Appendix B - Bid Form.pdf PDF
Fort Garland - Advertisement - Appendix E - Contract Wage Compliance Form.pdf PDF
Fort Garland - Advertisement - Appendix J - Scope of Work.pdf PDF
Fort Garland - Advertisement - Appendix K - Construction Drawings.pdf PDF
Fort Garland - Advertisement - Appendix N - Buy Clean Colorado Form.xlsx XLSX spreadsheet
Fort Garland - Advertisement - Appendix O - Code Compliance Notice.pdf PDF
Fort Garland - Advertisement - Appendix D - Applicable Prevailing Wage Rates (Building).pdf PDF
Fort Garland - Advertisement - Appendix D - Applicable Prevailing Wage Rates (Heavy).pdf PDF
Fort Garland - Advertisement - Appendix G - Labor and Material Bond.docx DOCX document
Fort Garland - Advertisement - Appendix L - Construction Specifications.pdf PDF
Fort Garland - Advertisement - Appendix M - Stormwater Management Plan.docx DOCX document
SBP-6.15 Award DBB_2025 (1).docx DOCX document
SBP-6.26 Notice Procd Const DBB_2025 (1).docx DOCX document
Fort Garland - Advertisement - Appendix A - Information for Bidders.pdf PDF
Fort Garland - Advertisement - Appendix H - Sample Contract.pdf PDF
SBP-070 SubCompletion-2025.docx DOCX document
SBP-7.3 Settlement_2025_0.docx DOCX document
SBP01 Notice Approval Occupncy Use R7-2022 (11).docx DOCX document
Fort Garland - Advertisement - Appendix B1 - Bid Bond.docx DOCX document
Fort Garland - Advertisement - Appendix F - Performance Bond.docx DOCX document
Fort Garland - Advertisement.pdf PDF
SBP-6.27 Acceptance_2025.docx DOCX document
Show all 22

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATE OF COLORADO

OFFICE OF THE STATE ARCHITECT

STATE BUILDINGS PROGRAM

DIRECT LABOR BURDEN CALCULATION

Institution/Agency:
Colorado Department of Transportation
Project No./Name:
23704/Fort Garland 7+1 Bay VSF

This form is required to be submitted for review prior to execution of a construction agreement.

List items below by the percentage of what makes up the total labor overhead; Items include benefits that a contractor pays to employees on their payroll. Examples include taxes, pension cost, health and dental insurance etc. The Labor Burden percentage must be agreed to by both the contractor and Principal Representative and will be included in the contract as part of Exhibit A and will be used in the calculation of any future Change Order Proposals (SC-6.312) Line 2.

Major sub-contractors defined as electricians, plumbers, mechanical contractors, excavators, millwork, concrete, block layers etc. Please provide one (1) Labor Burden Calculation Sheet per contractor and for each sub-contractor. These labor burdens shall be used in the calculation of any future Change Order Proposals (SC-6.312) Line 10.

State reserves the right to require back-up confirmation of all information included in this calculation.

State Form SBP–6.18 Issued 8/2023 image1.jpg image2.emf

Microsoft_Excel_Worksheet.xlsx Sheet1

Contractor/Subcontractor Name:

Percent of Salary Paid

Payroll Taxes

Pension Costs

Health Insurance

Dental Insurance

Life Insurance

Other (Specify) Description: _________________________

Other (Specify) Description: _________________________

Total Labor Burden Percentage: 0%