This document is an Information for Bidders form from the State of Colorado's Office of the State Architect for the Colorado Department of Transportation, pertaining to Project No. 23704/Fort Garland 7+1 Bay VSF. The document outlines the bidding process, requirements, and key instructions for potential contractors. Bidders are required to use the provided Bid form, submit bids on all alternates, and indicate completion timelines in calendar days from the Notice to Proceed to Substantial Completion and from Substantial Completion to Final Acceptance.

The document specifies that a bid security of at least 5% is required for projects estimated at $50,000 or more, and bids must exclude federal excise, manufacturers', state sales, and use taxes. The method of award will be based on the lowest responsible bidder, considering Colorado resident bidder preference and using either deductible or additive alternates (but not both) to determine the final bid. The bidding process includes provisions for requesting "or equal" materials, submitting addenda, and adhering to state laws regarding apprenticeship, prevailing wages, and environmental product declarations with specific Global Warming Potential (GWP) limits.

View the file

Other files

File Type Posted
Fort Garland - Advertisement - Appendix B - Bid Form.pdf PDF
Fort Garland - Advertisement - Appendix E - Contract Wage Compliance Form.pdf PDF
Fort Garland - Advertisement - Appendix J - Scope of Work.pdf PDF
Fort Garland - Advertisement - Appendix K - Construction Drawings.pdf PDF
Fort Garland - Advertisement - Appendix N - Buy Clean Colorado Form.xlsx XLSX spreadsheet
Fort Garland - Advertisement - Appendix O - Code Compliance Notice.pdf PDF
Fort Garland - Advertisement - Appendix D - Applicable Prevailing Wage Rates (Building).pdf PDF
Fort Garland - Advertisement - Appendix D - Applicable Prevailing Wage Rates (Heavy).pdf PDF
Fort Garland - Advertisement - Appendix G - Labor and Material Bond.docx DOCX document
Fort Garland - Advertisement - Appendix L - Construction Specifications.pdf PDF
Fort Garland - Advertisement - Appendix M - Stormwater Management Plan.docx DOCX document
SBP-6.15 Award DBB_2025 (1).docx DOCX document
SBP-6.26 Notice Procd Const DBB_2025 (1).docx DOCX document
Fort Garland - Advertisement - Appendix H - Sample Contract.pdf PDF
SBP-070 SubCompletion-2025.docx DOCX document
SBP-7.3 Settlement_2025_0.docx DOCX document
SBP01 Notice Approval Occupncy Use R7-2022 (11).docx DOCX document
Fort Garland - Advertisement - Appendix B1 - Bid Bond.docx DOCX document
Fort Garland - Advertisement - Appendix C - Direct Labor Burden Calculation.docx DOCX document
Fort Garland - Advertisement - Appendix F - Performance Bond.docx DOCX document
Fort Garland - Advertisement.pdf PDF
SBP-6.27 Acceptance_2025.docx DOCX document
Show all 22

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SBP-6.12

Rev 7/2025

STATE OF COLORADO

OFFICE OF THE STATE ARCHITECT

STATE BUILDINGS PROGRAM

INFORMATION FOR BIDDERS

Institution or Agency:

Project No./Project Name:

1. BID FORM: Bidders are required to use the Bid form attached to the solicitation.

Each bidder is required to bid on all alternates and indicate the time from the date of the Notice to Proceed to Substantial Completion in calendar days. In addition, the bidder is required to indicate the period of time to finally complete the project from Substantial Completion to Final Acceptance, in calendar days.

Bids indicating times for Substantial Completion and Final Acceptance in excess of the number of days indicated in the Advertisement for Bids for completion of the entire Project may be found non-responsive and may be rejected. The bid shall not be modified or conditioned in any manner. Bids and applicable bid security shall be submitted according to the following instructions:

2. INCONSISTENCIES AND OMISSIONS: Bidders may request clarification of any seeming inconsistencies, or matters seeming to require explanation, in the bidding documents at least three (3) business days prior to the time set for the opening of Bids. Decisions of major importance on such matters will be issued in the form of addendum.

3. APPLICABLE LAWS AND REGULATIONS: All work under this Contract shall comply with the provisions of all state and local laws, approved state building codes, ordinances and regulations which might in any manner affect the work to be done or those to be employed in or about the work. Labor for work shall be governed by the provisions of Colorado law which are hereinafter set forth in Articles 27 and 52 of the General Conditions. This includes the requirements for apprenticeship and prevailing wage on Public Projects. The bidder should be aware that reporting of embodied carbon emissions of eligible materials shall be governed by the provisions of Colorado State Law. This includes the requirements for Environmental Product Declarations (EPDs) that meet the maximum acceptable Global Warming Potential (GWP) limits as established by the Office of the State Architect.

4. BID SECURITY: A bid security of not less than 5% of the bid price is required when the price is estimated to be $50,000 or more. The security shall be a bond by a surety company, the equivalent in cash, or otherwise supplied in a form

SBP-6.12

Rev 7/2025 satisfactory for the State. Noncompliance requires the bid to be rejected as nonresponsive.

5. TAXES: The Bid submitted shall exclude all applicable federal excise or manufacturers’ taxes and all state sales and use taxes as hereinafter set forth in Article 9.3 of the GENERAL CONDITIONS.

6. OR EQUAL: The words “OR EQUAL” are applicable to all specifications and drawings relating to materials or equipment specified. Any material or equipment that will fully perform the duties specified, will be considered “equal”, provided the bid submits proof that such material or equipment is of equivalent substance and function and is approved, in writing. Requests for the approval of “or equal” shall be made in writing at least five (5) business days prior to bid opening. During the bidding period, all approvals shall be issued by the Architect/Engineer in the form of addenda at least two (2) business days prior to the bid opening date.

7. ADDENDA: Owner/architect initiated addenda shall not be issued later than two

(2) business days prior to bid opening date. All addenda shall become part of the Contract Documents and receipt must be acknowledged on the Bid form.

8. METHOD OF AWARD - LOWEST RESPONSIBLE BIDDER: If the bidding documents for this project require alternate prices, additive and/or deductible alternates shall be listed on the alternates bid form provided by the Principal Representative.

Bidders should note the Method of Award is applicable to this Bid as stated below.

A. DEDUCTIBLE ALTERNATES: The lowest responsible Bid, taking into account the Colorado resident bidder preference provision of Colorado law, will be determined by, and the contract will be awarded on the base bid combined with deductible alternates, accepted in numerical order as listed in the Bid Alternates Form provided by the Principal Representative. The subtraction of alternates shall result in a sum total within available funds. If this bid exceeds such amount, the right is reserved to reject all bids. An equal number of alternates shall be subtracted from the base bid of each bidder within funds available for purposes of determining the lowest responsible bidder.

B. ADDITIVE ALTERNATES: The lowest responsible Bid, taking into account the Colorado resident bidder preference provision of Colorado law, will be determined by and the contract will be awarded on the base bid combined with additive alternates in numerical order in as listed in the Bid Alternates Form provided by the Principal Representative. The addition of alternates shall result in a sum total within available funds. If this bid exceeds such amount, the right is reserved to reject all bids. An equal number of alternates shall be added to the base bid of each bidder within funds available for purposes of determining the lowest responsible bidder.

C. DEDUCTIBLE AND ADDITIVE ALTERNATES: Additive alternates will not be used if deductible alternates are used and deductible alternates will not be used if additive alternates are used.

9. NOTICE OF CONTRACTOR’S SETTLEMENT – Agencies/institutions must indicate in the initial Solicitation where settlement will be advertised in electronic media.

INFORMATION FOR BIDDERS
DEDUCTIBLE ALTERNATES: The lowest responsible Bid, taking into account the Colorado resident bidder preference provision of Colorado law, will be determined by, and the contract will be awarded on the base bid combined with deductible alternates, accepted in numerical order as listed in the Bid Alternates Form provided by the Principal Representative. The subtraction of alternates shall result in a sum total within available funds. If this bid exceeds such amount, the right is reserved to reject all bids. An equal number of alternates shall be subtracted from the base bid of each bidder within funds available for purposes of determining the lowest responsible bidder.
ADDITIVE ALTERNATES: The lowest responsible Bid, taking into account the Colorado resident bidder preference provision of Colorado law, will be determined by and the contract will be awarded on the base bid combined with additive alternates in numerical order in as listed in the Bid Alternates Form provided by the Principal Representative. The addition of alternates shall result in a sum total within available funds. If this bid exceeds such amount, the right is reserved to reject all bids. An equal number of alternates shall be added to the base bid of each bidder within funds available for purposes of determining the lowest responsible bidder.
DEDUCTIBLE AND ADDITIVE ALTERNATES: Additive alternates will not be used if deductible alternates are used and deductible alternates will not be used if additive alternates are used.
TextInput.136: Colorado Department of Transportation
TextInput.182: 23704/Fort Garland 7+1 Bay VSF
Submission Instructions: www.bidnet.com