This document is a Questions and Answers file for the Dyess AFB B6119 Demolition project. The document provides critical details for potential contractors, including site-specific requirements for a demolition project at Dyess Air Force Base. Key project details include: everything on site must be removed except for a single transformer, with no landfill available on base for debris or hazardous materials disposal; contractors are responsible for obtaining their own fill material, handling asbestos removal, and following federal/state regulations for concrete recycling. Additional notable requirements include: onsite personnel need a State ID, power is not available on site, no additional drawings beyond project demolition and as-builts exist, and the contractor must coordinate utility disconnections and potential permits. The document directs contractors to reference the Statement of Work (SoW) and contact the Contracting Office for specific details on bonds, contract award timeline, and other technical specifications.

View the file

Other files for this federal contract opportunity

Other files attached to Demo B6119, newest first.
File Type Posted
B6119 Demo RFQ COMBO Amendment 0003.pdf PDF
B6119 Demo RFQ COMBO Amendment 0002.pdf PDF
FNWZ 21-0071 Demo B6119 QA Sheet - Final (12-11-2025).pdf PDF
B6119 Demo RFQ COMBO Amendment 0001.pdf PDF
FNWZ 21-0071 Demo 6119 DWGs.pdf PDF
FNWZ21-0071 Demolish Thrift Shop_B6119_SOW.pdf PDF
FNWZ 21-0071 - Attachment E - Pricing Worksheet - Contractor.xlsx XLSX spreadsheet
FNWZ 21-0071 - Att E - AF Form 3064.xlsx XLSX spreadsheet
FNWZ 21-0071 - Att E - AF Form 3065.xlsx XLSX spreadsheet
Wage Determination.pdf PDF
B6119 Demo RFQ COMBO.pdf PDF
Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Dyess AFB

B6119 Demolition

Questions and Answers

1. Can I get the foundation Blueprints

a. Foundation Blueprints were provided in the SoW

2. Will the gentleman that did the asbestos test have an Asbestos removal plan that he would like for us to abide by or do you want us to have another person come out and advise us.

a. Contractor will have to find another person to come out and advise them for a removal plan

3. Can we get original blueprints

a. Original blueprints are provided in the SoW

4. What are the hours of operations allowed on base?

a. Please refer to the specifications in the SoW regarding the hours of operations.

5. Will the driveway by the building need to be removed. As well as the apron and will that need to be filled back with a concrete slab?

a. Yes, driveway and aprons need to be removed, please refer to the DWGs

6. Does this solicitation require any bonds? Thank you!

a. Please refer to the Contracting Office

7. What wages for Asbestos Handlers are we to assume for the project?

a. As wage rates can vary based on location, project type, and current market conditions, it is the contractor’s responsibility to research and determine the appropriate prevailing wages for your workforce.

8. Is the building on lands that have ever been a range, or is there any history of MEC/UXO found on site?

a. None to our knowledge.

9. Are there ancillary items to remain on the facility site?

a. There are no ancillary items to remain on site.

10. Are there any restrictions to recycling concrete?

a. No restrictions, contractors must follow federal/state regulations in removing concrete.

11. Can we assume there will be water available within 50 feet at no cost to the contractor?

a. Yes, the contractor is responsible for filling out a Fire Hydrant Request Form from the SoW, to use the water.

12. If required, is there fill material available on site? If available, is there a charge for it?

a. There is no filling material available on site, the contractor is responsible to gather material.

13. Are there any disconnect fees for the utilities?

a. There are NO fees to disconnect any utilities.

14. If a permit is required, what is the permit process?

a. Please refer to the specifications for the types of permits that are required.

15. Please confirm whether metal and machinery can be salvaged or if the installation is retaining any items.

a. Everything is to be removed, the only item that the government wants is the transformer. Please refer to the DWGs for further details.

16. Are there any specific guidelines that include the handling of C&D and ACM waste?

a. Please refer to the specifications for further guidelines.

17. Do all onsite personnel need to be U.S. citizens?

a. Onsite personnel need a State I.D

18. Is the contractor responsible for FOD control?

a. No, the contractor is not responsible for FOD control since the work does not take place near the airfield.

19. Is SHPO a concern?

a. Not a concern.

20. Is power available at the site? Is it free of charge?

a. Power is NOT available on site.

21. Are there any additional drawings other than the project demolition and the as-builts?

a. There are no additional drawings for this building.

22. What is the SWPP/E&SC process, and is a permit required?

a. Please refer to the specifications in the SoW, no permit is required

23. Can the QC Manager, SSHO, and Superintendent be one person?

a. CE sees no concerns; contractor must refer to CONS if acceptable.

24. Will the contract be awarded 30 days after proposals are submitted?

a. Please refer to the Contracting Office

25. Is there a landfill onsite where construction debris can be disposed of? Is there a fee?

a. There’s no landfill on base to dispose of construction debris, the contractor is responsible for removing them off base.

26. Is there a landfill on base to dispose of hazardous materials? If yes, is there a charge?

a. There’s no landfill on base to dispose of hazardous materials, the contractor is responsible for removing them off base.