Sequencing Plan KRSM062067 Bldg 2013.pdf
PDF 223 KB Posted
- Attached to
- Repair Interior/Exterior B-2013, Repair Interior B-2005, Repair Steam Heat System B-2024
- Solicitation number
- FA8201-11-B-0006
About this file
Sequencing Plan
View the file
Other files
Show all 47
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
COLOR / PATTERN ZONE
PREFERRED
SEQUENCING
ORDER
MAX.
DOWN
TIME
VALVE ROOM/
CLEAN ROOM
CLEANING LINE/
NEW RESTROOM
CE EQUIPMENT ROOMS/
MENS RESTROOM/
WOMENS RESTROOM
TURBINE BALANCER
ROOM
F
FUEL TANK SERVICE /
STORAGE
GEAR BOX REPAIR /
OFFICE
2 2
F
35a
5a
F
FEXIBLE
SCHEDULE
4 4
5a
6 61 / 7
1 / 7
1 / 7
INITIALIZATION /
FINALIZATION OF
NW. OFFICE / MIC
5b
1 / 7
2 WEEKS
4 WEEKS
OPEN
NOTE #3
OPEN
2 WEEKS
4 WEEKS
3 DAYS
5b
BREAK / LOCKER
ROOM6
F
6 OPEN
COLOR / PATTERN ZONE
PREFERRED
SEQUENCING
ORDER
MAX.
DOWN
TIME
F F
BLDG. 2005, INTERIOR AND EXTERIOR. THIS
BLDG. IS LOCATED WEST OF BLDG. 2013
SOUTH AWNING OF BLDG. 2013
EXTERIOR OF BLDG. 2013
BLDG. 2024, INTERIOR AND EXTERIOR. THIS
BLDG. IS LOCATED SOUTHEAST OF BLDG.
10 4 WEEKS
9 OPEN
8 3 WEEKS
NOTE #4
S E
Q U
E N
C I N
G
P
L A
N
B U
I L
D I N
G S
NOTES:
1. ACCESS SHALL BE PROVIDED 1 DAY PER WEEK TO
TEST STANDS IN NORTHEAST CORNER OF VALVE
ROOM.
2. ROOM 5B DOES NOT HAVE TO BE COMPLETED IN 3
DAYS BUT THE TURBINE BALANCER ITSELF CAN ONLY
BE INACCESSIBLE FOR A MAXIMUM OF 3 DAYS. ACCESS
TO USE THIS MACHINE NEEDS TO BE FROM 0500-0630
HOURS DAILY.