General Requirements Specification 01 11 01 (Amendment 04)
View the file
Other files
Show all 47
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
KRSM 062027, 062069, 062070 RPR INTERIOR/EXTERIOR B-2013, RPR INTERIOR B-2005, RPR STEAM
HEAT SYSTEM B2024 June 6, 2011
SECTION 01 11 01
SECTION TABLE OF CONTENTS
DIVISION 01 – HILL AFB GENERAL REQUIREMENTS
SECTION 01 11 01
SUMMARY OF WORK
11/10
Revised 29 June 2011
PART 1 GENERAL
1.1 REFERENCES
1.2 DEFINITIONS
1.3 SUBMITTALS
1.4 WORK COVERED BY CONTRACT DOCUMENTS
1.4.1 Materials and Workmanship
1.4.2 Weather Precautions
1.4.3 Project Description
1.4.4 Project Location
1.5 SITE VISITS
1.6 CONTRACT DRAWINGS
1.6.1 Project Drawings
1.6.2 Working Drawings
1.6.3 Shop Drawings
1.6.4 As-Built Drawings
1.7 WORK RESCHEDULING
1.8 OCCUPANCY OF PREMISES
1.9 PROTECTION OF GOVERNMENT PROPERTY AND EXISTING WORK
1.10 ON-SITE PERMITS
1.10.1 Digging Permits
1.10.2 Utility Outage Requests.
1.10.3 Utility Connection Requests
1.10.4 Burn Permits
1.10.5 Welding Cutting and Brazing Permits
1.11 SAFETY
1.12 ENVIRONMENTAL PROTECTION
1.13 SALVAGE MATERIAL AND WORKSITE CLEANUP
1.14 USE OF UTILITIES
1.15 CONTRACTOR BASE CREDENTIALS
1.16 STORAGE
1.17 WARRANTIES
1.18 TESTING
1.19 TRANSFER AND ACCEPTANCE OF MILITARY REAL PROPERTY
1.20 CONTRACT CLOSE OUT
PART 2 PRODUCTS
NOT USED
PART 3 EXECUTION
NOT USED
SECTION 01 11 01
SECTION 01 11 01
SUMMARY OF WORK
10/10
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
ASTM INTERNATIONAL
ASTM E 2114 Standard Terminology for Sustainability
Relative to the Performance of Buildings.
Energy Star Energy Star Energy Efficiency Labeling
System
U.S. ENVIRONMENTAL PROTECTION AGENCY (EPA)
Energy Star Energy Star Energy Efficiency Labeling
System
SECTION 01 11 01
1.2 DEFINITIONS
Definitions pertaining to sustainable development are as defined in ASTM E
2114, and as specified below.
a. "Environmentally preferable products" have a lesser or reduced effect on the environment in comparison to conventional products and services. This comparison may consider raw materials acquisition, production, manufacturing, packaging, distribution, reuse, operation, maintenance, or disposal of the product.
b. "Indoor environmental quality" is the physical characteristics of the building interior that impact occupants, including air quality, illumination, acoustics, occupant control, thermal comfort, daylighting, and views.
c. "Operational performance" is the functional behavior of the building as a whole or of the building components.
d. "Sustainability" is the balance of environmental, economic, and societal considerations.
1.3 SUBMITTALS
1.3.1 Government approval is required for submittals with a "G" designation and for submittals shown on submittal schedule section 01000-General
Requirements-Elec and 01000-General Requirements; submittals not having a
"G" designation are for Contractor Quality Control approval. The Contracting
Officer may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective sections. Submittals shall use Air Force Form 3000 and shall be provided as soon as possible, but in no case shall material and progress schedule submittals exceed fourteen (14) days following notice to proceed.
1.3.2 Units of weights and measures used on all submittals are to be the same as those used in the contract drawings. Each submittal is to be complete and in sufficient detail to allow ready determination of compliance with contract requirements.
1.3.3 Contractor's Quality Control (CQC) System Manager and the Designer of
Record, if applicable, shall check and approve all items prior to submittal and stamp, sign, and date.
1.3.4 Proposed deviations from the contract requirements must be submitted in writing in the form of a request for change. Government approval of submittals that deviate from contract requirements that were not marked as such and clearly identified in writing, shall not be construed to change or modify any contract requirements.
1.3.5 Design Reviews: The Government will review design submittals for conformance with the technical requirements of the solicitation. Government review is only for conformance with the contract requirements. Acceptance of design submittals is not be construed as a complete check, and indicates only that the general method appears to meet the requirements of the
Solicitation. The Designer of Record is responsible for the technical adequacy and functionality of the design.
SECTION 01 11 01
1.3.6 Sample Reviews: Approval of a sample is only for the characteristics or use named in such approval and shall not be construed to change or modify any contract requirements. Before submitting samples, the Contractor to assure that the materials or equipment will be available in quantities required in the project. No change or substitution will be permitted after a sample has been approved.
1.3.7 Submittals requiring Government approval are to be scheduled and made prior to the acquisition of the material or equipment covered thereby.
Include catalog cuts, diagrams, operating charts or curves and all other required documents necessary for determination of compliance with contract.
The Government will:
a. Note date on which submittal was received.
b. Review submittals for approval within scheduling period specified and only for conformance with project design concepts and compliance with contract documents.
c. Identify returned submittals with one of the actions defined in paragraph 1.3.8 below of this section and with markings appropriate for action indicated.
d. Upon completion of review of submittals requiring Government approval, copies of the approved submittal will be retained by the Contracting
Officer and one copy of the submittal will be returned to the Contractor.
1.3.8 Review Notations. Government review will be completed within 14 calendar days after date of submission. Submittals will be returned to the
Contractor with the following notations:
a. Submittals marked "approved" or "accepted" authorize the Contractor to proceed with the work covered.
b. Submittals marked "approved as noted" "or approved except as noted, re-submittal not required," authorize the Contractor to proceed with the work covered provided he takes no exception to the corrections.
c. Submittals marked "not approved" or "disapproved," or "revise and resubmit," indicate noncompliance with the contract requirements or design concept, or that submittal is incomplete. Resubmit with appropriate changes. No work shall proceed for this item until re-submittal is approved.
1.3.9 Contractor shall make corrections required by the Contracting Officer.
If the Contractor considers any correction or notation on the returned submittals to constitute a change to the contract drawings or specifications; notice as required under the clause entitled, "Changes," is to be given to the Contracting Officer. Contractor is responsible for the dimensions and design of connection details and construction of work.
Failure to point out deviations may result in the Government requiring rejection and removal of such work at the Contractor's expense.
1.3.10 WITHHOLDING OF PAYMENT
SECTION 01 11 01
Payment for materials incorporated in the work will not be made if required approvals have not been obtained. No payment for materials incorporated in the work will be made if all required Designer of Record or required
Government approvals have not been obtained. No payment will be made for any materials incorporated into the work for any conformance review submittals or information only submittals found to contain errors or deviations from the Solicitation or Accepted Proposal.
1.4 WORK COVERED BY CONTRACT DOCUMENTS
1.4.1 Material and Workmanship:
All equipment, material, and articles incorporated into the work covered by this contract shall be new and of the most suitable grade for the purpose intended, unless otherwise specifically provided in this contract.
References in the specifications to equipment, material, articles, or patented processes by trade name, make, or catalog number, shall be regarded as establishing a standard of quality and shall not be construed as limiting competition. The Contractor may, at its option, use any equipment, material, article, or process that, in the judgment of the Contracting Officer, is equal to that named in the specifications, unless otherwise specifically provided in this contract.
All work under this contract shall be performed in a skillful and workmanlike manner. The Contracting Officer may require, in writing, that the Contractor remove from the work any employee the Contracting Officer deems incompetent, careless, or otherwise objectionable.
In accordance with FAR 52.236-6 At all times during performance of this contract and until the work is completed and accepted, the Contractor shall directly superintend the work or assign and have on the worksite a competent superintendent who is satisfactory to the Contracting Officer and has authority to act for the Contractor.
1.4.2 Weather Precautions:
Contractor shall ensure that weather sensitive materials are placed within the conditions recommended by the material supplier. No pavements shall be placed on frozen ground. Concrete placed when weather temperatures can be expected to fall below 32 degrees F shall be covered with approved blankets.
1.4.3 Project Description:
Building 2013 is the only facility of its type in the U.S. Air Force. It is a mission critical asset situated in the MAMS II area. The continued throughput of the F-16 EPU is critical. All reasonable precautions necessary to ensure continued production shall be taken.
Briefly and without force or effect upon the contract documents, the work of this contract can be summarized as follows:
Replace flooring and ceilings, repaint and repair restroom, repair HVAC system, relocate porch canopy to front of door, install interior wall between work process areas, repaint window frames, and misc repairs.
SECTION 01 11 01
The existing fire alarm system in building 2013 shall be replaced. Sheet EX101 of the project drawings shows existing conditions only. Reference EX101 and specification section 28 31 64 when completing the work described below. The contractor shall: Install a new addressable intelligent fire alarm system throughout the facility. New system is to include a new remote enunciator panel. Ensure that explosion proof devices are placed in compliance with current code. The existing system must remain operational until the new system is approved and accepted in writing by the Contracting Officer.
a. Remove existing Smoke detection devices throughout facility. Install new as required under NFPA 72 and NFPA 90A.
b. Provide and install Horn/Strobes on ceilings throughout the facility as required by NFPA
72. Install strobes only in restrooms.
c. Remove existing Pyrotronics panel. Install new panel in compliance with UFC 3-600-01 and NFPA 72 and in the ‘Base Facility Design Standard, Hill Air Force Base’ dated 15
Apr 2010.
d. Provide and install all new fire alarm wiring, devices, conduits, smoke detectors and connectors. Remove the existing alarm system in its entirety once the new system is complete and accepted. (This does not include any fully functional heat detectors installed in the EPU tank repair area). NOTE: Mounting boxes in false ceilings and hard pan ceilings not being reused for new alarms shall be removed, as well as connecting conduits back to alarm loop conduit boxes, and the ceiling patched or false ceiling panel replaced. Alarm wiring is NOT permitted to be abandoned. Abandoned empty conduits and boxes in false ceiling spaces shall be marked ‘For Future Use’ and all others removed.
e. Pull stations shall be installed per code requirements (NFPA 72) adjacent to facility exits.
f. Provide shop drawings of alarm system for Government approval prior to installation.
g. Certifications and requirements for installers and other work related to the fire alarm system shall be according to specification section 28 31 64.
All work and materials required to repair interior of B-2005. Work to include painting, door repair, ceiling repair, and floor repair.
All work and materials required to repair B-2024. Work to include inspection, replacement and repair of electrical panel and starters.
1.4.4 Project Location:
The work shall be located at Hill Air Force Base, Buildings 2013, 2005 and
2024, as indicated.
SECTION 01 11 01
1.5 SITE VISITS:
1.5.1 The Contractor shall attend scheduled site visits and take steps reasonably necessary to ascertain the nature and location of the work, and investigate the general and local conditions which can affect the work or its cost. Such investigation shall include but is not limited to:
a. The conditions bearing upon transportation, disposal, handling, and storage of materials.
b. The availability of labor, and necessary utilities including water, gas, and electric power.
c. The availability and suitability of pavements and roadways.
d. Prevalent weather conditions or similar physical conditions at the site.
e. The conformation and existing conditions of the ground, pavements and soils.
f. The character and condition of equipment and facilities needed preliminary to and during work performance.
1.5.2 The Contractor shall examine and note the character, quality, and quantity of surface and subsurface materials or obstacles to be encountered insofar as that information is reasonably ascertainable from an inspection of the site. The contractor shall note any exploratory work performed by the
Government and provided in the drawings and specifications or made a part of this contract as attachments. Any failure of the Contractor to take the actions described and acknowledged in this paragraph will not relieve the
Contractor from responsibility for estimating properly the difficulty and cost of successfully performing the work, or for proceeding to successfully perform the work without additional expense to the Government.
1.5.2.1 The Government assumes no responsibility for any conclusions or interpretations made by the Contractor based on the information made available by the Government. Nor does the Government assume responsibility for any understanding reached or representation made concerning conditions which can affect the work by any of its officers or agents before the execution of this contract, unless that understanding or representation is expressly stated in this contract.
1.6 CONTRACT DRAWINGS:
1.6.1 Project Drawings:
The following drawings accompany this specification and are a part thereof.
Drawings: KRSM 062067 RPR INTERIOR/EXTERIOR B 2013, KRMS 062069 RPR
INTERIOR B 2005, KRSM 072020 RPR STEAM HEAT SYSTEM B 2024.
Sheets 1 through 50
B2005 Equipment Layout
B2013 Equipment Layout
B2013 Equipment Layout Sequencing Plan
B2024 Equipment Layout
SECTION 01 11 01
1.6.2 Working Drawings
The Contractor shall keep on the work site a copy of the Project drawings and specifications and shall at all times give the Air Force Project manager access thereto. Anything mentioned in the specifications and not shown on the drawings, or shown on the drawings and not mentioned in the specifications, shall be of like effect as if shown or mentioned in both. In case of difference between drawings and specifications, the specifications shall govern. In case of discrepancy in the figures, in the drawings, or in the specifications, the matter shall be promptly submitted to the
Contracting Officer, who shall promptly make a determination in writing. Any adjustment by the Contractor without such a determination shall be at its own risk and expense. The Contracting Officer shall furnish AutoCAD sets of contract drawings, maps, and MS Word Versions of the specifications for use in creating As-Built Record Drawings. Contactor shall immediately check the furnished drawings and notify the Government of any discrepancies.
a. Wherever in the specifications or upon the drawings the words
“directed”, “required”, “ordered”, “designated”, “prescribed”, or words of like import are used, it shall be understood that the “direction”, “requirement”, “order”, “designation”, or “prescription”, of the
Contracting Officer is intended and similarly the words “approved”, “acceptable”, “satisfactory”, or words of like import shall mean
“approved by,” or “acceptable to”, or “satisfactory to” the Contracting
Officer, unless otherwise expressly stated.
b. Where “as shown,” as indicated”, “as detailed”, or words of similar import are used, it shall be understood that the reference is made to the drawings accompanying this contract unless stated otherwise. The word “provided” as used herein shall be understood to mean “provide complete in place,” that is “furnished and installed”.
1.6.3 Shop Drawings:
1.6.3.1 The term Shop Drawings means drawings, submitted to the Government by the Contractor, subcontractor, or any lower tier subcontractor pursuant to a construction contract, showing in detail the following items.
a. The proposed fabrication and assembly of structural elements and the installation (i.e., fit, and attachment details) of materials or equipment.
b. Drawings, diagrams, layouts, schematics, descriptive literature, illustrations, schedules, performance and test data, and similar materials furnished by the contractor to explain in detail specific portions of the work required by the contract. The Government may duplicate, use, and disclose in any manner and for any purpose shop drawings delivered under this contract.
1.6.3.2 If this contract requires shop drawings, the Contractor shall coordinate all such drawings, and review them for accuracy, completeness, and compliance with contract requirements and shall indicate its approval thereon as evidence of such coordination and review. Shop drawings submitted to the Contracting Officer without evidence of the Contractor’s approval may be returned for resubmission. The Contracting Officer will indicate an approval or disapproval of the shop drawings and if not approved as submitted shall indicate the Government’s reasons therefore.
Any work done before such approval shall be at the Contractor’s risk.
Approval by the Contracting Officer shall not relieve the Contractor from responsibility for any errors or omissions in such drawings, nor from responsibility for complying with the requirements of this contract, except
SECTION 01 11 01
with respect to variations described and approved in accordance with paragraph below.
a. If shop drawings show variations from the contract requirements, the
Contractor shall describe such variations in writing, separate from the drawings, at the time of submission. If the Contracting Officer approves any such variation, the Contracting Officer shall issue an appropriate contract modification, except that, if the variation is minor or does not involve a change in price or in time of performance, a modification need not be issued.
b. The Contractor shall submit to the Contracting Officer for approval three copies (unless otherwise indicated) of all shop drawings as called for under the various headings of these specifications. Two sets
(unless otherwise indicated) of all shop drawings, will be retained by the Contracting Officer and one set will be returned to the Contractor.
Upon completing the work under this contract, the Contractor shall furnish a complete set of all shop drawings as finally approved. These drawings shall show all changes and revisions made up to the time the equipment is completed and accepted.
1.6.4 As-Built Record Drawings:
1.6.4.1 Upon completing the work under this contract, the Contractor shall furnish 2 complete electronic sets in AutoCAD of the As-Built record drawings including all shop drawings as finally approved, 1 AutoCAD file on
CD of updated bldg 2013 equipment plan, and the following hard copies: 1 full size set on Mylar, 2 sets ANSI D size, 2 sets half size (15” x 22”) with full width metal clamp with Mylar top and bottom cover sheet, 3 seperately bound O&M manuals marked to show specific product choice and applicable options. AutoCAD files shall be fully editable. Partial files, files with missing attachments or layers, or files formatted as read only or protected will not be accepted. These drawings shall show changes and revisions made up to the time the contract is completed and accepted.
Include all unusual or uncharted obstructions that were encountered in the contract area during construction.
a. Revisions made shall ensure related section and elevation views, details, legend, plans, profiles, schedules and notes are marked as needed to prevent conflicting data on differing sheets. Comments shall be complete without reference to change orders, letters, memos, etc.
The marked-up drawings shall be labeled to show project title and number.
b. Surveying data will be in Universal Transverse Mercator 1983 (UTM83) coordinate system, Transverse Mercator projection, Geodetic Reference
System 1980 (GRS80) spheroid, or World Geodetic System 1984 (WGS84) datum, and use metric coordinate units.
c. Particular attention should be given to work, which will be concealed and difficult to measure and record after construction, and work which may require servicing or replacement during the life of the facility.
The following are areas of concern that need special checking to ensure that the marked-up prints are complete and accurate:
1. Location, size and type of existing and new utility lines.
Measurements will be shown for all change of direction points and all surface or underground components such as valves, manholes, drain inlets, clean outs, meters, etc. The
SECTION 01 11 01
description of exterior utilities shall include the actual quantity, size, and material of the utility lines.
2. Changes to location, size and type of interior plumbing and electrical lines below the floor slab.
3. Changes to layout and schematic drawings of electrical circuits and piping.
4. Correct dimensions and details transferred from shop drawings.
5. Actual location of anchors, construction and control joints, etc., in concrete.
6. Change in location of equipment and architectural features.
7. Cross out words such as “or equal” and list specifically the items of material provided.
1.6.4.2 The Air Force project managers will review the contractor’s marked-up drawings when verifying the performance shown by progress reports. If the drawings are not current, the progress report will be adjusted downward by the Civil Engineering project manager to reflect the contractor’s non-compliance. Marked-up drawings will be submitted within five working days after substantial completion. Final payment will not be authorized until complete and accurate red-lined drawings are accepted by the Contracting
Officer.
1.7 WORK SCHEDULING
1.7.1 Contractor shall allow for a maximum of [ 5 ] calendar days where construction activity is prohibited by Air Force Exercises or similar military events. Further allowance for [ 14 ] calendar days where excavation, utility outages, road closures, or other subsurface activity may be halted while other construction activities are permitted to continue.
Government will provide 24 hour notification each time the restrictions are invoked.
Normal duty hours for work shall be:
A. 0500 to 1550 Hours exclusive of Fridays, Saturdays, Sundays, and holidays unless other times are approved by the Contracting Officer, or otherwise stated in the contract. Coordinate the work schedule with the CE project manager, building foreman, and facility engineer.
1.7.2 Contract Progress Schedules AF Form 3064 and 3065. See Section 01 32 01
Project Schedule for information on this requirement.
1.8 OCCUPANCY OF PREMISES
1.8.1 Building Occupancy.
Building(s) will be occupied during performance of work under this Contract unless expressly stated otherwise -in writing- from the Contracting
Officer.
1.8.1.1 Before work is started, the Contractor shall arrange with the
SECTION 01 11 01
Contracting Officer a sequence of procedure, means of access, space for storage of materials and equipment, and the use of approaches, corridors, stairways, roads and truck gates.
1.8.1.2 Contractor shall make provisions to maintain occupied areas of any building under repair at no less than 65 degrees F and no warmer than 85 degrees F. Unoccupied areas shall be maintained above 40 degrees F to prevent freezing of water lines and fire protection systems.
1.8.1.3 Temporary heating, if required, shall be UL approved electric heaters and shall be physically monitored at least every 4 hours.
1.9 PROTECTION OF EXISTING GOVERNMENT PROPERTY WORK
1.9.1 Contractor shall conduct all operations in such a manner as to prevent injury or damage to government property and any portions of the existing work which are to remain. This requirement is not limited to just the project site but includes landscaping, curbs, pavements, and utilities adjacent to the site as well as along routes to and from the site. Where any ambiguity exists the contractor shall request clarification from the
Contracting Officer before beginning work.
1.9.2 Contractor shall make repairs to or replace portions of existing work that is damaged or altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work shall be in a condition equal to or better than that which existed before new work started.
1.9.3 In the event the contractor fails or refuses to make satisfactory repairs or replacements to property damaged by the contractor under this contract the government will have the repairs made and charge the cost to the contractor.
1.10 ON-SITE PERMITS
1.10.1 Digging Permits
1.10.1.1 Notify the Contracting Officer prior to notice to proceed of anticipated excavation and intended routes and methods. At least 15 days prior to starting excavation work the Contractor shall request a Base Civil
Engineering Excavation Permit. Permits are available from the Red Stake
Office in Building 593 South.
1.10.1.2 The Contractor shall protect from damage all existing improvements and utilities at or near the work site, and on adjacent property of a third party, the locations of which are made known to or should be known by the
Contractor.
1.10.1.3 The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to obtain necessary permits and utility marking or failure to exercise reasonable care in performing the work. This includes irrigation lines and sprinkler components. If the Contractor fails or refuses to repair the damage promptly, the Contracting Officer may have the necessary work performed and charge the cost to the Contractor.
SECTION 01 11 01
1.10.1.4 The Contractor shall verify the elevations of existing piping, utilities, and any type of underground obstruction not indicated or specified to be removed. Verify elevations before installing new work closer than nearest manhole or other structure at which an adjustment in grade can be made.
a. Hand digging shall be required to locate utilities shown on the contract drawings, Excavation Permit, or 3 feet on either side of locations identified by Base Maintenance Shops. For facilities that store munitions hand digging is required within 10 feet of the bldg to locate the existing grounding cable.
b. All excavation work within 15ft of a Questar high pressure natural gas distribution line will require Questar Gas technicians to be on-site during the excavation. Contractor shall coordinate this through Blue
Stakes.
1.10.2 Utility Outage Requests.
1.10.2.1 Notify the Contracting Officer prior to notice to proceed of anticipated utility outages and closures of streets, parking lots, and pedestrian walkways. Work shall be scheduled to hold outages to a minimum.
Utility outages and connections required during the prosecution of work that affect existing systems shall be arranged for at the convenience of the Government and shall be scheduled on weekends unless otherwise approved by the Contracting Officer. Contractor shall not be entitled to additional payment for utility outages and connections required to be performed outside the regular work hours. Outages and closures shall be scheduled with the Air Force Project Manager no less than 21 calendar days prior to the outage or closure. The Contractor shall obtain in writing from the
Project Manager a statement or schedule giving the permissible times for the outage or closure for particular installations and the maximum time allowed for such outage or closure. Permits shall be posted at a conspicuous location in the construction area.
1.10.3 Utility Connection Requests.
1.10.3.1 Utility connections required during the prosecution of work that affect existing systems regardless of necessity for a utility outage shall be arranged for at the convenience of the Government and shall be scheduled on weekends unless otherwise approved by the Contracting Officer. All newly installed underground utilities shall include tracer wire and marking strip and be surveyed by HAFB before the utilities are buried. Provide at least
7 day advance notice of utility connections when an outage is not required.
Comply with paragraph governing utility outages otherwise.
1.10.3.2 Provide 48 hours of advance notice to the Project Manager when new utility lines will be ready for inspection and surveying. The Contractor shall uncover any utility lines buried prior to notification. Contractor shall not be entitled to additional payment for uncovering and reburying any utility lines that were covered prior to providing this 48 hour notice.
1.10.4 Burning Permits.
SECTION 01 11 01
Open burning of any sort is strictly prohibited.
1.10.5 Welding, Cutting and Brazing Permits.
1.10.5.1 Air Force (AF) Form 592 is required daily for all welding, cutting, brazing, soldering and similar hot work. The form shall be properly filled out and displayed while all hot work is underway. The
Contractor will be required to attend the Welding, Cutting, Brazing certification class prior to construction startup. This class is conducted on the first Thursday of every month and the Base Fire Station Bldg 9.
1.11 SAFETY.
1.11.1 Governmental Requirements for Construction Safety are given in section 01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS. In addition to the requirements listed in that section the contractor shall provide and maintain work environments and procedures which will --
a. Safeguard the public and Government personnel, property, materials, supplies, and equipment exposed to Contractor operations and activities.
b. Avoid interruptions of Government operations and delays in project completion dates.
c. Comply with all pertinent provisions of the latest version of U.S. Army
Corps of Engineers Safety and Health Requirements Manual, EM 385-1-1, in effect on the date of the solicitation.
d. Comply with the standards issued by the Secretary of Labor at 29 CFR
Part 1926 and 29 CFR Part 1910.
1.11.2 Whenever the Contracting Officer becomes aware of any noncompliance with these requirements or any condition which poses a serious or imminent danger to the health or safety of the public or Government personnel, the
Contracting Officer shall notify the Contractor orally, with written confirmation, and request immediate initiation of corrective action. This notice, when delivered to the Contractor or the Contractor’s representative at the work site, shall be deemed sufficient notice of the noncompliance and that corrective action is required. After receiving the notice, the
Contractor shall immediately take corrective action. If the Contractor fails or refuses to promptly take corrective action, the Contracting
Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. The Contractor shall not be entitled to any equitable adjustment of the contract price or extension of the performance schedule on any stop work order issued under this clause.
1.11.3 If this contract involves of a hazardous nature, or performance on a
Government facility that on the advice of technical representatives involves hazardous materials or operations that might endanger the safety of the public and/or Government personnel or property, Then Before commencing the work, the Contractor shall --
a. Submit a written proposed plan for implementing this clause. The plan shall include an analysis of the significant hazards to life, limb, and property inherent in contract work performance and a plan for controlling these hazards; and
b. Meet with representatives of the Contracting Officer to discuss and develop a mutual understanding relative to administration of the overall safety program.
1.12. ENVIRONMENTAL PROTECTION
Requirements for environmental protection and hazardous materials are given in detail in section 01 57 19 ENVIRONMENTAL PROTECTION. In addition to the requirements listed in that section The Contractor shall, without additional expense to the Government, be responsible for obtaining any necessary licenses and permits, and for complying with any Federal, State, and municipal laws, codes, and regulations applicable to the performance of the work. The Contractor shall also be responsible for all damages to persons or property that occur as well as any fines levied as a result of the
Contractor’s fault or negligence. The Contractor shall be responsible for all materials delivered and work performed until completion and acceptance of the entire work, except for any completed unit of work which may have been accepted under the contract.
1.13. SALVAGE MATERIAL AND WORKSITE CLEANUP
The Contractor shall at all times keep the work area, including storage areas, free from accumulations of waste materials and obstructions. At the end of each work day and at project final completion, the Contractor shall leave the work area in a clean, neat, and orderly condition satisfactory to the Contracting Officer. Before completing the work, the Contractor shall remove from the work site any rubbish, tools, scaffolding, equipment, and materials that are not the property of the Government.
1.13.1 It is ESSENTIAL that dust, dirt and any other debris be kept at an absolute minimum during the construction period. The concern is cross contamination into production areas by fugitive material. Effective mitigation strategies e.g. use of dual visqueen layers, appropriate surface prep, taping, formatted removal, negative pressure etc. and daily clean up need to be vigorously employed.
Building 2013 clean room will receive an additional inspection conducted by the Base Clean Room Officer; Mr. Brent Hale 586-4476. He shall perform an additional finger wipe down test, a particle monitoring test, differential pressure test, temperature test and humidity test. These tests shall conducted per TO 00-25-203 (available upon request) are required so that class 10,000 clean room requirements are met and that certification will be achieved.
The Contractor shall provide final clean-up in the clean room (room 129) according to the following procedure:
Wipe downs shall be with a damp cloth or mop.
Cleaning shall be performed with a lint free cloth, fold the dirty side to the inside for repeated wiping.
Vacuuming shall be performed with a HEPA vacuum
Final inspection shall be conducted by the Hill AFB clean room officer. He shall perform a finger wipe-down test.
The finger wipe-down test consists of wiping a surface and if any visible particulates are present the test fails. Magnification will not be used and the test is irrespective of skin color.
SECTION 01 11 01
Inspection in other production areas of building 2013 shall also utilize a finger wipe-down test.
Buildings 2024 and 2025 and CE equipment rooms will not require the degree of cleaning required above. These areas shall be mop cleaned and have no visible particulates.
Restrooms and offices shall be in the state of cleanliness as in their pre-construction state.
a. All excavated material (dirt, asphalt, concrete, etc.) and construction/demolition debris shall be managed in accordance with
Section 01 57 19 ENVIRONMENTAL CONTROLS.
b. All fire alarm control panels (FACP), Monaco Radio Fire Alarm
Transceivers (BT), Vindicator Intrusion Detection Panels (IDS) and
Vindicator Card Access Systems (ACSYS) to be removed under this contract shall remain property of the government and shall be delivered to the Civil Engineering Electronics Shop (Bldg. 20, east end).
Cabinets will be delivered with all electronics and internal wiring intact. However, the batteries in the cabinets will be removed by the contractor and disposed of as hazardous waste as required under Section
01 57 19 ENVIRONMENTAL PROTECTION.
1.14. USE OF UTILITIES.
In general, the contractor will be allowed the use of electrical, and natural gas utilities without reimbursement while performing work under this contract, if available. In some cases reimbursement will be required as when extensive temporary heating may be required. In such cases, rates for utility costs will be established at the time of award. Toilet facilities on the site may be used by the workmen subject to the regulation of the
Government, if they are available.
1.15. CONTRACTOR BASE CREDENTIALS.
The procedure for obtaining base identification passes for contractor personnel to work on any Air Force Material Command (AFMC) base shall be as follows:
The Contractor shall submit a written request on company letterhead stationery, if available, to the Contracting Officer specifying:
a. Contract number.
b. Location of work site:
c. Date entry to the base must begin and contemplated termination date of entry.
d. Names of contractor and subcontractor employee requiring access to the base.
e. The name of the individual who will submit the Request of
Identification Credentials for each employee for whom identification credentials are needed.
The Contracting Officer will:
f. Endorse the request.
g. Attach a copy of the contract cover page and any other pages that provide performance information, such as the need for and duration of access to the work site.
h. Forward this request to the Security Forces, Pass and
Registration Office of the installation where the work is to be performed.
i. Provide blank Application For AFMC Identification Card, AFMC
Form 496 and Unescorted Entry Authorization Certificate, AF
Form 2586 to the Prime Contractor.
Any non-US citizen not in possession of a “Green Card” will not be allowed access on base without the Contracting Officer first clearing the employee through the Foreign Disclosure Office OO-
ALC/LGMS, Bldg 1209, 777-6857 or 777-6858.
The Prime Contractor shall be required to complete and submit AFMC Form 496, for each of the firm's employees and for each subcontractor employee who must have access to the installation. For contracts, 90 days or less contractor employees will be issued an AF Form 75 unless the work is in a controlled or restricted area. For contracts in a controlled or restricted area or greater than 90 days an AFMC Form 387 will be issued.
The Prime Contractor shall also be required to complete and submit AF Form
2586 for each of the firm’s employees and for each subcontractor employee who must have access to a controlled or restricted area at the installation. The
Prime Contractor shall ensure that all contractor personnel including subcontractors attend the Explosive Safety Briefing if applicable. See paragraph 1.14G. An Explosive Safety Awareness Statement signed by those requesting badges is required prior to processing AF Form 2586. The Weapon
Safety Monitor will provide the Contracting Officer copies of the awareness statements. The Security Forces, Pass and Registration Office, upon issuance of the appropriate badge for AF Form 2586, will provide the original completed AF Form 2586 to the individual receiving the badge. The original form shall be given to the Contracting Officer for accountability.
The Prime Contractor shall also request AF Form 75, Visitor/Vehicle Pass or
DD Form 2220, DoD Registered Vehicle, for vehicle decals when the AFMC Form
496 is submitted. To obtain the vehicle decal from the Security Forces, Pass and Registration Office, the Contractor shall produce:
1. A valid driver’s license.
2. Proof of financial responsibility or insurance, which meets the minimum requirements of the contract clause, entitled "Required Insurance."
3. Current vehicle registration.
4. Proof of Davis County emissions certification if the vehicle is not registered in a county within the State of
Utah, which requires emissions testing.
Follow the guidance in AFI 31-101, The Installation Security Program, when work under this contract requires unescorted entry to controlled areas. The
Contractor will request completion of an AF Form 2586, Unescorted Entry
Authorization Certificate for each prime contractor employee and subcontractor employee for which a controlled area badge is required.
Contractor employees with controlled area badges are required to escort contractor employees without badges, at all times, in and out of controlled areas. Establishment of a free zone will be necessary. The free zone must have clearly defined boundaries. The contractor shall erect temporary snow fencing around construction site. For bid purposes assume fence perimeter to be 3500 linear feet. Using organization shall provide escorts for contract personnel where necessary. It is recommended the free zone begin at some point in the boundary of the controlled area, which enables entry by the
Contractor and other authorized personnel. The free zone must be closed during non-duty hours. The boundaries of the free zone must be under surveillance by the OPR for the area or designated responsible activity.
Contractor employees, at all times while on a military installation, shall wear visible contractor-provided identification either as a part of, or attached to, their outer clothing. The identification shall clearly identify the individual as being a contractor employee.
During performance of the contract, the Contractor shall be responsible for obtaining required identification for newly assigned personnel, and for prompt return of credentials and vehicle registration decals to the
Security Forces, Pass and Registration Office, for any employee who no longer requires access to the work site.
At the termination or completion of the contract, or upon the expiration of credentials (if any such expirations are specified), the Contractor must be sure that all base identification credentials and vehicle registration decals for all contractor and subcontractor employees are returned to the Security Forces, Pass and Registration Office.
Prior to submitting an invoice for final payment, the Prime Contractor shall obtain a clearance certification from the issuing Pass and
Registration Office which states that all base identification credentials and vehicle decals have been returned or "accounted for."
This certification shall be attached to the final invoice at the time of submittal for payment. Failure to comply with these requirements will result in withholding final payment until compliance is effected.
If it becomes necessary for the Contractor to enter any unmanned base entry gate, they must first contact 75 SFS/SFO at 777-5531. If the
Contractor assumes custody or control of a particular gate they will insure:
1. Only cleared contractor personnel for that respective project gain access to the base through that gate.
SECTION 01 11 01
2. Lock and Key Control will be established in such a manner as to clearly define an audit trail of who have keys to the gates and the times the gates are opened and closed, 24 hours a day.
1.16 STORAGE
The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting
Officer. The Contractor shall hold and save the Government, its officers and agents, free and harmless from liability of any nature occasioned by the
Contractor’s performance.
Temporary buildings (construction trailers, storage sheds, shops, offices) are not permitted unless approved in advance by Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the Contractor and shall be removed by the Contractor at its expense upon completion of the work.
The Contractor shall, under regulations prescribed by the Contracting
Officer, use only established roadways. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any
Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The
Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
Store materials so as to avoid hindering the work of other Contractors and to avoid damage or soiling of materials. All materials and equipment shall be stored and handled to preclude the inclusion of foreign matter and damage by water or breakage. Store packaged materials in original containers until ready for use. Materials showing evidence of water or other damage shall be rejected and removed from the base. All materials shall be stored as recommended by the manufacturer, unless specifically noted otherwise in the contract documents. Store in accordance with general provisions entitled
Operations and Storage Areas (FAR 52.236-10).
When pipe and conduit are stored on the site, they shall be stored in racks or blocked to prevent rolling.
When combustible materials are stored on the site they shall be stored in an
OSHA approved combustible materials locker at least 50 feet (15 meters) from all buildings unless otherwise specifically indicated by the Contracting
Officer.
It is the responsibility of the Contractor to secure all property within the construction site. If government property is included, the Contractor must secure it also, and notify the Contracting Officer and the Civil Engineering
Project Manager.
The Contractor in the event of storing 1000 rounds or more of fastener gun charges shall obtain an explosive license from the Civil Engineering Weapons
Safety Manager in order to comply with regulations.
1.17 WARRANTIES FAR 52.246-21
SECTION 01 11 01
In addition to any other warranties in this contract, the Contractor warrants that work performed under this contract conforms to the contract requirements and is free of any defect in equipment, material, or workmanship performed by the Contractor or any subcontractor or supplier at any tier.
This warranty shall continue for a period of 1 year from the date of final acceptance of the work. If the Government takes possession of any part of the work before final acceptance, this warranty shall continue for a period of 1 year from the date the Government takes possession.
The Contractor shall remedy at the Contractor’s expense any failure to conform, or any defect. In addition, the Contractor shall remedy at the
Contractor’s expense any damage to Government-owned or controlled real or personal property, when that damage is the result of --
The Contractor’s failure to conform to contract requirements; or
Any defect of equipment, material, workmanship, or design furnished.
The Contractor shall restore any work damaged in fulfilling the terms and conditions of this clause. The Contractor’s warranty with respect to work repaired or replaced will run for 1 year from the date of repair or replacement.
The Contracting Officer shall notify the Contractor, in writing, within a reasonable time after the discovery of any failure, defect, or damage.
If the Contractor fails to remedy any failure, defect, or damage within a reasonable time after receipt of notice, the Government shall have the right to replace, repair, or otherwise remedy the failure, defect, or damage at the Contractor’s expense.
With respect to all warranties, express or implied, from subcontractors, manufacturers, or suppliers for work performed and materials furnished under this contract, the Contractor shall –
Obtain all warranties that would be given in normal commercial practice;
Require all warranties to be executed, in writing, for the benefit of the
Government, if directed by the Contracting Officer; and
Enforce all warranties for the benefit of the Government, if directed by the Contracting Officer.
In the event the Contractor’s warranty under paragraph (b) of this clause has expired, the Government may bring suit at its expense to enforce a subcontractor’s, manufacturer’s, or supplier’s warranty.
Unless a defect is caused by the negligence of the Contractor or subcontractor or supplier at any tier, the Contractor shall not be liable for the repair of any defects of material or design furnished by the
Government nor for the repair of any damage that results from any defect in
Government-furnished material or design.
This warranty shall not limit the Government’s rights under the Inspection and Acceptance clause of this contract with respect to latent defects, gross mistakes, or fraud.
1.18 TESTING
All testing required by this contract are the responsibility of the contractor unless expressly stated otherwise. The Contractor shall notify
SECTION 01 11 01
the Civil Engineering Project Manager at least 24 hours in advance of any testing.
The Contractor shall submit test reports to the Civil Engineering Project
Manager in not more than 7 days following test completion.
The Contractor shall not proceed with any work, which would cover up the work being tested until the work being tested has been approved by the Civil
Engineering Project Manager.
1.19 TRANSFER AND ACCEPTANCE OF MILITARY REAL PROPERTY
At the completion of the project the contractor shall finalize the DD Form
1354 including UFC 1-300-08 Appendix D which were provided by the government.
Instructions to complete the DD Form 1354 are contained in Unified Facilities
Criteria (UFC) 1-300-08.
1.20 CONTRACT CLOSEOUT.
1.20.1 Closeout procedure.
a. Pre-final Inspections.