ADDITIONAL PROJECT INFORMATION
Repair Interior - Bldg 2005
Repair Interior/Exterior - Bldg 2013
Repair Steam Heat System - Building 2024
MAMS II Area
Solicitation No: FA8201-11-B-0006
Amendment 04
5 July 2011
The purpose of Amendment 04 is to amend the Solicitation to extend the bid due date from 28 July
2011 to 4 August 2011 and to include the following project documents which have been added to the section of the Solicitation entitled “Section J – List of Documents, Exhibits, and Other Attachments.”
(Please note changes to the attached specifications are highlighted in yellow.)
TITLE DATE # OF PAGES
Additional Project Information 5 July 2011 2
Repair Interior - Bldg 2005, Repair
Interior/Exterior - Bldg 2013, Repair Steam
Heat System - Building 2024 – Project Overview 5 July 2011 6
General Wage Decision, UT100037 17 June 2011 6
LIST OF SPECIFICATIONS
SECTION DESCRIPTION # OF PAGES
01 32 01 Project Schedule (Revised 29 June 2011) 6
DIVISION 01 GENERAL REQUIREMENTS
01 11 01 Summary of Work (Revised 29 June 2011) 21
01 35 26 Governmental Safety Requirements (Revised 29 June 2011) 21
DIVISION 15 MECHANICAL
158230 Electrical Evaporative Steam Humidification System 4
SCHEDULE OF DRAWINGS
DRAWING # DESCRIPTION
BLDG 2013 SEQUENCING PLAN
BLDG 2005 EQUIPMENT PLAN
BLDG 2013 EQUIPMENT PLAN
BLDG 2024 EQUIPMENT PLAN
BLDG 2013 - SK-M-001-1 PACKAGED HUMIDIFIER
BLDG 2013 - SK-MH-101-1 HVAC REMODEL PLAN
BLDG 2013 – SK-MH-101-2 HVAC REMODEL PLAN
BLDG 2013 – SK-PL-101-1 PLUMBING REMODEL PLAN
BLDG 2013 – SK-PL-101-2 PLUMBING REMODEL PLAN
BLDG 2013 – SK-E-002-1 PANEL 8E – FEED FROM UTILITY TRANSFORMER
BLDG 2013 – SK-E-002-2 PANEL NH
BLDG 2013 – SK-EP-101-1 DRAWING NOTES – ELECTRICAL POWER PLAN
BLDG 2013 – SK-EP-603-1 BLDG 2013 ONE-LINE DIAGRAM REMODEL
QUESTIONS:
Any additional questions regarding this solicitation must be submitted by email not later than Thursday, 14 July 2011, at 2:00pm (MST) to shelly.karcheski@hill.af.mil and don.mattonen@hill.af.mil.
SUMMARY OF CHANGES:
Submittal Specification was added to the General Requirements Specification.
Submittal requirements (i.e. size, numbers, etc.) for As-Built Drawings changed from original submission.
Updated submittal requirements included in General Requirements Specification.
Additional clarification for the clean room provided.
Scheduling Provisions – 1) Contractor to hold weekly meetings, 2) submit schedule in WBS format, and
3) ensure old equipment is not shut down before the new equipment is ready.
Removal of tree near the northeast corner of Building 2013 due to the hazard it poses to the nitrogen system.
Equipment and furniture movement in accordance with sequencing plan.
Instructions pertaining to the alcohol tank and exhaust hood.
Addition of the following:
Oxygen Sensors
Nitrogen and air drops
Humidification System mailto:shelly.karcheski@hill.af.mil mailto:don.mattonen@hill.af.mil