Additonal Project Information.pdf

PDF 103 KB Posted

Attached to
Repair Interior/Exterior B-2013, Repair Interior B-2005, Repair Steam Heat System B-2024
Solicitation number
FA8201-11-B-0006
Issued by

About this file

Additional Project Information (Amendment 04)

View the file

Other files

File Type Posted
15410 - Water Distribution Piping and Equiment-26July2011.pdf PDF
15420 - Drainage and Vent Systems and Equipment-26July2011.pdf PDF
15515 - HVAC-26July2011.pdf PDF
Contractor Questions Answers - 14 July 2011 -FA8201-11-B-0006 - MAMS II Area - Bldgs 2005 20132024.pdf PDF
16010 - General Requirements-26July2011.pdf PDF
Amendment 05 - FA8201-11-B-0006 - Bldgs 2005 2013 2024.pdf PDF
Humidifier Drawings Spec.pdf PDF
B2005-Equipment_Layout.pdf PDF
B2024-Equipment_Layout.pdf PDF
B2013-Equipment_Layout.pdf PDF
Wage Determination-UT100037- 17 June 2011-UT37.mht MHT file
Amendment of Solicitation - 04.pdf PDF
SECTION 01 11 01 - Revised 29 June 2011.pdf PDF
B2013-Sequencing Plan.pdf PDF
Project Overview 5 July 2011.pdf PDF
SAFETY 01 35 26.pdf PDF
SECTION 01 32 01-Project Schedule.pdf PDF
Amendment 03.pdf PDF
Amendment 02 - SF 30.doc DOC document
Site Visit Attendance Record.pdf PDF
06 61 16 Countertops.pdf PDF
Asbestos Survey.pdf PDF
Bldgs 2024 Pics.zip ZIP file
Building 2013 Pics - Set 5.zip ZIP file
LBP Letter.pdf PDF
Amendment to Solicitation.pdf PDF
Building 2013 Pics - Set 4.zip ZIP file
Additional Specs.pdf PDF
Building 2013 Pics - Set 1.zip ZIP file
Contractor Questions FA8201-11-B-0006 - MAMS II Area - Bldgs 2005 20132024.pdf PDF
Building 2013 Pics - Set 3.zip ZIP file
LBP Evaluation.pdf PDF
Fire Alarm-Performance Based Spec.pdf PDF
Wage Determination - UT100037 - 13 May 2011.pdf PDF
Bldg 2005 Pics.zip ZIP file
Building 2013 Pics - Set 2.zip ZIP file
100 Fire Mech Specs Div. 13 15 PDF.zip ZIP file
SECTION 01 11 00.pdf PDF
Visitor Authorization List.pdf PDF
100 Arch Specs PDF.zip ZIP file
Sequencing Plan KRSM062067 Bldg 2013.pdf PDF
SECTION 01 57 20 ENVIRONMENTAL.pdf PDF
100 Electrical Specs Div 16 PDF.zip ZIP file
Drawings KRSM 062067 062069 072070-Complete Set-Locked.pdf PDF
SAFETY 01 35 26.pdf PDF
Solicitation FA8201-11-B-0006.pdf PDF
Wage Determination UT 100037 4 Feb 2011 UT37.pdf PDF
Show all 47

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ADDITIONAL PROJECT INFORMATION

Repair Interior - Bldg 2005

Repair Interior/Exterior - Bldg 2013

Repair Steam Heat System - Building 2024

MAMS II Area

Solicitation No: FA8201-11-B-0006

Amendment 04

5 July 2011

The purpose of Amendment 04 is to amend the Solicitation to extend the bid due date from 28 July

2011 to 4 August 2011 and to include the following project documents which have been added to the section of the Solicitation entitled “Section J – List of Documents, Exhibits, and Other Attachments.”

(Please note changes to the attached specifications are highlighted in yellow.)

TITLE DATE # OF PAGES

Additional Project Information 5 July 2011 2

Repair Interior - Bldg 2005, Repair

Interior/Exterior - Bldg 2013, Repair Steam

Heat System - Building 2024 – Project Overview 5 July 2011 6

General Wage Decision, UT100037 17 June 2011 6

LIST OF SPECIFICATIONS

SECTION DESCRIPTION # OF PAGES

01 32 01 Project Schedule (Revised 29 June 2011) 6

DIVISION 01 GENERAL REQUIREMENTS

01 11 01 Summary of Work (Revised 29 June 2011) 21

01 35 26 Governmental Safety Requirements (Revised 29 June 2011) 21

DIVISION 15 MECHANICAL

158230 Electrical Evaporative Steam Humidification System 4

SCHEDULE OF DRAWINGS

DRAWING # DESCRIPTION

BLDG 2013 SEQUENCING PLAN

BLDG 2005 EQUIPMENT PLAN

BLDG 2013 EQUIPMENT PLAN

BLDG 2024 EQUIPMENT PLAN

BLDG 2013 - SK-M-001-1 PACKAGED HUMIDIFIER

BLDG 2013 - SK-MH-101-1 HVAC REMODEL PLAN

BLDG 2013 – SK-MH-101-2 HVAC REMODEL PLAN

BLDG 2013 – SK-PL-101-1 PLUMBING REMODEL PLAN

BLDG 2013 – SK-PL-101-2 PLUMBING REMODEL PLAN

BLDG 2013 – SK-E-002-1 PANEL 8E – FEED FROM UTILITY TRANSFORMER

BLDG 2013 – SK-E-002-2 PANEL NH

BLDG 2013 – SK-EP-101-1 DRAWING NOTES – ELECTRICAL POWER PLAN

BLDG 2013 – SK-EP-603-1 BLDG 2013 ONE-LINE DIAGRAM REMODEL

QUESTIONS:

Any additional questions regarding this solicitation must be submitted by email not later than Thursday, 14 July 2011, at 2:00pm (MST) to shelly.karcheski@hill.af.mil and don.mattonen@hill.af.mil.

SUMMARY OF CHANGES:

Submittal Specification was added to the General Requirements Specification.

Submittal requirements (i.e. size, numbers, etc.) for As-Built Drawings changed from original submission.

Updated submittal requirements included in General Requirements Specification.

Additional clarification for the clean room provided.

Scheduling Provisions – 1) Contractor to hold weekly meetings, 2) submit schedule in WBS format, and

3) ensure old equipment is not shut down before the new equipment is ready.

Removal of tree near the northeast corner of Building 2013 due to the hazard it poses to the nitrogen system.

Equipment and furniture movement in accordance with sequencing plan.

Instructions pertaining to the alcohol tank and exhaust hood.

Addition of the following:

Oxygen Sensors

Nitrogen and air drops

Humidification System mailto:shelly.karcheski@hill.af.mil mailto:don.mattonen@hill.af.mil