Solicitation Amendment FA813727R00020002 SF 30.pdf
PDF 454 KB Posted
- Solicitation number
- FA813727R0002
About this file
This document is Amendment 0002 to Solicitation FA813727R0002, issued by the U.S. Air Force at Tinker Air Force Base on November 20, 2026, with an effective date of November 23, 2026. The amendment extends the proposal due date from November 23, 2026 to December 18, 2026 at 1400 hours (2:00 PM). The solicitation covers Project WWYK250063 for installation of a REACT VII Facility at Building B9001, Post V19, with an estimated project magnitude between $1,000,000 and $5,000,000. The solicitation is for design-build construction services requiring a fixed-price proposal with comprehensive scope coverage addressing technical, scheduling, and pricing components based on RS MEANS construction cost standards and local Oklahoma City cost indices.
The amendment adds multiple attachments to Section J, including a Submittal Register, two rounds of Pre-Bid RFI Responses, an RMDF (Rough Material Datasheet), ODS (Operational Data Sheet), OPSEC Review Memo, Liquidated Damages schedule, and 11 technical specification documents covering construction divisions. Award will be made on a Lowest Price Technically Acceptable (LPTA) basis to the lowest-priced proposal among at least two technically acceptable submissions. Technical evaluation focuses on two subfactors: Capability and Management (including on-site management team, subcontractor coordination, warranty/differing site conditions handling, and team contacts) and Schedule and Planning (requiring a construction schedule meeting the mandatory completion date with detailed consideration of submittals, milestones, permits, and Government approval timelines). Bidders must provide a 20% bid guarantee or $3,000,000, whichever is less, and submit pricing in unlocked Microsoft Excel format broken out by CSI division with supporting RS MEANS documentation and two vendor quotes for any non-RS MEANS items.
View the file
Other files
Show 40 more
Latest 50 of 152 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
J
2. AMENDMENT/MODIFICATION NUMBER
3. EFFECTIVE DATE
20 Nov 2026
4. REQUISITION/PURCHASE
REQUISITION NUMBER
5. PROJECT NUMBER (if applicable)
WWYK250063
6. ISSUED BY CODE FA8137
FA8137 AFSC PZIOC
CP 405 739 4040, 7858 5TH ST STE 1
TINKER AFB, OK 73145-9125
UNITED STATES
ISAAC DEMMERS, Email: darian.permetter@us.af.mil Telephone: 405-739-3250 Darian Permetter, Email: darian.permetter@us.af.mil Telephone: 405-739-8940
7. ADMINISTERED BY (if other than Item 6)
CODE
SCD: PAS:
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code)
CODE: FACILITY CODE:
9A. AMENDMENT OF SOLICITATION NUMBER
FA813727R0002
9B. DATED (SEE ITEM 11)
05 Oct 2026
10A. MODIFICATION OF CONTRACT/ORDER
NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; 1 or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (if required) See Section G - Contract Administration Data
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK
ONE
A.THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.)
SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
See Schedule
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
Darian Permetter
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
16C. DATE SIGNED
23 Nov 2026
Computer generated. Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA-FAR (48 CFR) 53.243
SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
The purpose of this amendment is to: Block 14 (Description of Amendment/Modification):
1. Include requirement applicable documents to Section J (Including RFI Responses).
2. Include Clause 52.228-1
3. Make revisions to section L and M
4. Extend proposal due date 23 November 2026 to 18 December 2026 @ 1400 (2:00 pm)
All other terms and conditions remain the same.
Section A - Solicitation/Contract Form
The following modifications were made:
Information From To Response Due Date 23 Nov 2026 18 Dec 2026 Solicitation Number FA813727R00020001 FA813727R00020002
Section J - List of Attachments
The following Header Attachment(s) were added:
Information Value Attachment Description Statement of Work Attachment Name 250063_ATT 10_Submittal Register Date 16 Nov 2026 Number 04
Information Value Attachment Description Statement of Work Attachment Name 250063_ATT 13_Prebid RFI Responses Round 1 Date 16 Nov 2026 Number 09
Information Value Attachment Description Statement of Work Attachment Name 250063_ATT 14_Prebid RFI Responses Round 2 Date 16 Nov 2026 Number 10
Information Value Attachment Description Statement of Work Attachment Name 250063_ATT 3_RMDF Date 16 Nov 2026 Number 05
Information Value Attachment Description Statement of Work Attachment Name 250063_ATT 4_ODS Date 16 Nov 2026 Number 06
Information Value Attachment Description Statement of Work Attachment Name 250063_ATT 6_OPSEC Review Memo Date 16 Nov 2026
FA813727R00020002
Number 07
Information Value Attachment Description Statement of Work Attachment Name 250063_ATT 8_Liquidated Damages Date 16 Nov 2026 Number 08
Information Value Attachment Description Statement of Work Attachment Name 250063_Pre-Bid RFI_Responses Signed Date 19 Nov 2026 Number 11
Information Value Attachment Description Statement of Work Attachment Name ATT 1_02 41 00 Date 19 Nov 2026 Number 12
Information Value Attachment Description Statement of Work Attachment Name ATT 2_09 22 00 Date 19 Nov 2026 Number 13
Information Value Attachment Description Statement of Work Attachment Name ATT 3_09 29 00 Date 19 Nov 2026 Number 14
Information Value Attachment Description Statement of Work Attachment Name ATT 4_09 68 00 Date 19 Nov 2026 Number 15
Information Value Attachment Description Statement of Work Attachment Name ATT 5_10 26 00 Date 19 Nov 2026 Number 16
Information Value Attachment Description Statement of Work Attachment Name ATT 6_22 05 48.00 20 Date 19 Nov 2026 Number 17
Information Value Attachment Description Statement of Work Attachment Name ATT 7_26 05 73 Date 19 Nov 2026 Number 18
Information Value Attachment Description Statement of Work Attachment Name ATT 8_26 51 00 Date 19 Nov 2026 Number 19
Section L - Instructions, Conditions, & Notices to Offerors or Quoters
Header Miscellaneous Text (Modified):
REVISION 1 - Section L - Instructions, Conditions, & Notices to Offerors or Quoters
1) TOTAL JOB: Offer Amount is for the total project completion. The contractor shall not make any changes to the design or specifications without prior approval of the Contracting Officer. Offers must be entered for all items. Failure to enter prices may render the offer/offeror nonresponsive. The Government reserves the right to make award without discussions.
2) SITE VISIT: A site visit will be scheduled to provide offerors with the opportunity to inspect the site where the work is to be performed and to satisfy themselves as to all general and local conditions that may affect cost of performance of the contract. The date, time, and location of this site visit will be announced via the solicitation and will be posted to the SAM.gov announcement.
3) TECHNICAL SPECIFICATIONS AND DRAWINGS: The technical specifications and drawings, referenced in Section J as attachments to this solicitation, have been prepared by the Civil Engineer. Any and all questions regarding these specifications and/or drawings must be submitted in writing to the Contract Specialist identified in Block 7 of the SF 1442. Any information obtained outside this procedure and acted upon may cause the resultant offeror to be non-responsive. Any and all questions received from industry will be responded to by amendment to the solicitation. Issuance of the amendment will incorporate all the terms and conditions into a resultant award.
4) AMENDMENT ACKNOWLEDGEMENT: It is the offeror's responsibility to be aware of amendments, as made available. Acknowledgement of amendments is required in accordance with the instructions provided in Block 11 of the SF30, Amendment of Solicitation. Offers that fail to acknowledge amendments may be considered as non responsive and rejected.
5) ACCEPTANCE PERIOD: Attention is called to Blocks 13D and 17 of the SF 1442. In accordance with (IAW) Block 17, the number inserted must be equal to or greater than the number of days listed in Block 13D.
6) PERFORMANCE PERIOD: Please reference Block 11 of the SF 1442.
7) MAGNITUDE OF CONSTRUCTION: Disclosure of the Magnitude of Construction, the estimated price range for each project is listed below: WWYK250063 - INSTALL REACT VII FACILITY, B9001, POST V19 THE ESTIMATED MAGNITUDE OF THIS PROJECT IS BETWEEN Magnitude of Construction: $1,000,000 - $5,000,000
8) WAGE DETERMINATION: The most current prevailing Davis Bacon Wage Determination shall be incorporated with the solicitation. It is anticipated that the most common Wage Determination for this project is construction type: Building. The Davis Bacon Wage Determinations in effect at the issuance of this solicitation is found in Section J for reference purposes only.
9) CONTRACTOR ID BADGE REQUIREMENTS: Contractors working on Tinker AFB shall comply with all procedures of Contractor Access to Air Force Installations, all contractor personnel will be assessed a charge of $50.00 for each badge lost, willfully damaged, or not surrendered to Pass and Registration. No charge will be made on a replacement required due to normal wear. Personnel will report to Accounting and Finance, Accounts Receivable Unit and a DD Form 1131, Cash Collection Voucher, will be prepared and presented to Pass and Registration prior to issuing a replacement identification. Identification will be surrendered to Security Forces personnel upon demand for the purpose of identification, investigation, abuse, misuse, or for any other reason necessary. Civilian and military retirees who conduct commercial business on base must obtain a badge through their place of employment. ALSO OF SPECIAL NOTE, all contractors/contractor personnel shall be subject to background checks as deemed necessary.
10) TRUCK ENTRY GATE NOTICE: Tinker Air Force Base has constructed a "Truck Entry Gate" (Gate 33), which is located at the corner of 59th Street and Air Depot Blvd (southwest corner of the base). Gate 33 shall be used for all deliveries by truck to this base. (Trucks will not be allowed to gain access through any other gate.)
11) CONTRACT GOVERNMENT HOLIDAYS: No contractor work will be conducted on these days; accordingly, the Government will not be billed for such holidays, except when services are required by the Government and are actually performed on a holiday. Holidays in addition to those reflected in this contract, which are designated by the Government, will be billable provided the assigned Contractor employee was available for performance and was precluded from such performance. The following days are contract holidays: New Year's Day, Martin Luther King, Jr. Day, President's Day, Memorial Day, Juneteenth, Independence Day, Labor Day, Columbus Day, Veterans Day, Thanksgiving Day, Christmas Day.
12) POINT OF CONTACT: All questions from prime contractors shall be submitted to the Contracting Specialist via email at isaac.demmers@us.af.mil on company letterhead paper. Please ensure that all questions reach the POC NLT 2:00p.m. (CT) on (TBD).
PROPOSAL REQUIREMENTS FOR TECHNICAL: In the Technical Proposal, address your proposed approach to meeting the minimum performance or capability requirements of the technical requirements identified in the RFP. The technical proposal should be specific and complete. Legibility, clarity, and coherence are very important. Your responses will be evaluated against the technical subfactors defined in Section M - Evaluation Factors for Award. Using the instructions provided below, provide as specifically as possible the actual methodology you would use for accomplishing/satisfying the technical subfactors. All the requirements specified in the RFP are mandatory. With your proposal submission, you are representing that your company will perform all the requirements specified in the RFP. Mere recitation of the RFP requirements, or phrases that refer to the government's SOW, without sufficient supporting information as to how work will be accomplished will not be accepted and could lead to proposal being found technically unacceptable. Narratives shall provide details of sufficient level to allow one skilled in engineering and the building trades to make a sound decision as to the technical viability of the proposal. The technical volume shall include:
a) Technical Proposal Cover Sheet. The technical proposal shall include a cover sheet containing date, RFP number, project number and title, bidder contact information, and assertion the proposal meets the mandatory completion date stated in the RFP or attachments.
b) Project Narrative. The project narrative shall clearly demonstrate the bidder's understanding of the project scope by including the following information:
1) Project synopsis (description)
2) Proposed method of accomplishing the work
3) Type of site field verification performed
4) Anticipated user impacts
5) Protection of government property during construction
6) Supplemental drawings/sketches
7) In-house design calculations
8) Estimating notes
9) Take-off calculations to justify quantities used in proposal (includes Subcontractor's calculations)
10) Manufacturer supplied drawings / calculations
11) Catalog/product technical information
12) Assumptions
13) Clarifications and exceptions
14) Supporting documentation
TECHNICAL SUBFACTOR 1: CAPABILITY AND MANAGEMENT
1) Describe capability and commitment to support an on-site management team, including a sole source of responsibility for both design and construction of this project IAW the SOW.
2) Describe how your organization will manage, supervise, and coordinate the subcontractor's work and who in the organization will be responsible for this management and coordination that is required IAW the SOW.
3) Describe how warranty support, unforeseen site conditions, design errors, etc. will be handled by your organization IAW the Warranty of Construction Clause RFO 52.246-21 and the Differing Site Condition Clause RFO 52.236-2.
4) Provide a Team List of the primary point of contacts IAW Contractor Specific Requirements within the SOW.
TECHNICAL SUBFACTOR 2: SCHEDULE AND PLANNING
The bidder shall include a proposed construction schedule that meets or improves the mandatory completion date stated in the RFP. The bidder's proposed schedule shall demonstrate a reasonable and realistic sequence of activities which represent all work to be performed throughout the entire order performance period, while considering the major work elements from the detailed price proposal, as well as submittal reviews, mobilization, material delivery times, anticipated weather delays, and final inspection/closeout IAW the SOW. In developing the schedule, note that there will be submittals; milestones (such as final inspections); and construction-related permits/ requests (such as Outage/Closure Requests or Excavation Permits) that will require longer lead times for Government coordination/approval listed in section 3.3 of the
SOW.
Specific timelines for staging area approvals, airfield waivers, outage requests and other Government approvals are provided in the SOW Section 3.3 in table listed as "Delivery Schedule & Submittals".
PROPOSAL REQUIREMENTS FOR PRICING: The Contractor shall provide an Electronic Cost Model Breakdown to support their proposed pricing in an unlocked Microsoft Excel Format. At a minimum, pricing shall be broken out by Construction Standards Institute (CSI) division or salient features of work. Proposals broken out by salient features of work and further subdivided by CSI division are preferred. The Contractor's proposed pricing shall be accomplished as described below and based on the most economical standard construction practices. Value engineering and design review shall be used in project design and scope development. Unreasonable methods and/or estimates of accomplishing the tasks required under this Statement of Work (SOW) shall not be accepted.
1) Line Item Costs: The cost of a line item shall be the item's total bare cost based on a national average as defined by the most current calendar years RS MEANS Price Book. The RS MEANS labor costs are included as line items of work. Line Item Pricing shall be based on the most current calendar year RS MEANS Facilities Construction Cost Book.
2) RS MEANS Facilities Construction Costs Book: Includes all items of work from the current year RS MEANS Facilities Construction Costs Book.
3) Non Pre-priced Items (NPI): Proposed pricing for Statement of Work Items that are not included in the RS MEANS Facilities Construction Costs Book shall be submitted, approved and/or negotiated as necessary to reach an overall agreed to price for the applicable SOW items.
4) Non-RS Means NPI item prices taken from local area sources shall be the lowest price offered from at least two (2) acceptable vendors. Equipment and material prices shall be based on the contractor's cost. The contractor is required to show proof of its cost by including the two (2) lowest offers. Labor costs shall be derived using the RS
MEANS productivity and crew cost rates. Any item departed from RS Means is classified as an NPI and must include the . A proposal priced from subcontractor quotations that supporting two (2) lowest written quotes and cost worksheets excludes the mandatory backing quotes or fails to use the RS Means baseline for standard items will be deemed non- .compliant with Section L and rated unacceptable
5) The Contractor shall submit a worksheet for each NPI item which shows all the costs and calculations used to develop the NPI item's price.
6) The Contractor shall retain all materials used in performing take-offs (calculations, sketches, field measurements, etc.) and obtaining cost information (catalog cut sheets, vendor quotes, etc.) for the NPIs and shall provide these materials in the proposal. Submission of these materials as part of the proposal shall satisfy the requirement for submittal of an item listed on the submittal register for a Task Order.
7) Local Area Adjustment Factor: The RS MEANS total weighted average city cost index (CCI) for the city of Oklahoma City, OK, or the nearest city.
(END)
Additional Regulation or Supplemental Clauses Incorporated by Full Text
The following Clause(s) were added:
FAR Clauses Incorporated by Full Text 52.228-1 Bid Guarantee. (Sep 1996)
Bid Guarantee (Sept 1996)
(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.
(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, bid bond supported by good and sufficient surety or sureties acceptable to the e.g., Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds-
(1) To unsuccessful bidders as soon as practicable after the opening of bids; and
(2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.
(c) The amount of the bid guarantee shall be percent of the bid price or $ , whichever is less.20% 3.000,000.00
(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.
(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.
(End of clause)
Section M - Evaluation Factors for Award
Header Miscellaneous Text (Modified):
REVISION 1 - Section M - Evaluation
Responsive proposals received at or before the deadline date and time will be evaluated as follows. This effort is Lowest Price Technically Acceptable (LPTA).
1. Contractor will be checked in SAM for contractor responsibility.
2. The Government's technical evaluation team shall evaluate the combined work plan and technical risk of each proposal to determine if the offeror provides a sound, compliant approach that meets the requirements and demonstrates a thorough knowledge and understanding of the specs and SOW and their associated risks.
3. The lowest priced proposal from at least two (2) technically acceptable proposals will become the awardee.
TECHNICAL RATING
The Technical evaluation will be based on each's offeror's approach for meeting the technical requirements listed below. The evaluation focuses on the technical approach as described in each offeror's technical volume. The technical evaluation does not consider price. Each subfactor within the technical factor will receive one of the ratings described below based on the criteria listed below. Individual subfactor ratings will be used to determine the overall technical acceptability of each offeror. To be determined technically acceptable at the factor level, the Offeror must be rated acceptable in each subfactor. A single deficiency within a subfactor will result in an unacceptable rating for that subfactor. A final unacceptable subfactor assessment will determine an overall technical unacceptable rating, and therefore, un-awardable. Only those proposals determined to be technically acceptable, either initially, or as a result of discussions, will be considered for award. The technical evaluation will also consider risk in determining overall acceptability. Risk pertains to the potential for unsuccessful contract performance. Risk will not receive a separate rating, rather, it will be inherent within the subfactor ratings, and the overall Technical rating. Only Low Risk approaches will be deemed acceptable.
TECHNICAL SUBFACTOR 1, CAPABILITY AND MANAGEMENT: This subfactor is met when the offeror sufficiently demonstrates and describes how the offeror will meet the capability and management requirements to complete the construction and administrative requirements with little potential for disruption of schedule, increased price, or degradation of performance. The evaluation will include the offeror's proposal to meet the following:
Sufficient description of commitment to support an on-site management team, including a sole source responsibility for both design and construction of this project. IAW Section 1.3 Contractor Personnel within the SOW.
Sufficient approach to manage, supervise, and coordinate all subcontractor's work and state who in the organization is responsible for this management and coordination.
Sufficient description of how warranty support, unforeseen site conditions, design errors, etc., will be handled by your organization. The responsible offeror shall meet warranty requirement specification listed in the Warranty of Construction Clause IAW RFO 52.246-21. The offeror will meet unforeseen site condition requirement specification listed in the Differing Site Condition Clause IAW RFO 52.236-2.
Sufficient description of your team list of the primary points of contact. The responsible offeror shall meet requirement specification IAW Contractor Specific Requirements within the SOW.
TECHNICAL SUBFACTOR 2, SCHEDULE AND PLANNING: This subfactor is met when the offeror sufficiently demonstrates and describes how the offeror can schedule and plan the construction project that will meet or improve the mandatory completion date with little potential for disruption of schedule, increased price, or degradation of performance. The evaluation will include the offeror's proposal to meet the following requirement specification IAW all of Section 3.3 of the SOW.
Sufficient construction schedule that meets the mandatory completion date stated in the OPR. The schedule shall demonstrate a reasonable and realistic sequence of activities which represent all work to be performed throughout the entire order performance period, while considering the major work elements from the detailed price proposal, as well as submittal reviews, mobilization, material delivery times, anticipated weather delays, and final inspection/closeout. The responsible offeror shall meet requirement specification IAW Section 3.3 of the SOW. Sufficient detail within the schedule that considers submittals, milestones (such as final inspections), and construction related permits/requests (such as Outage/Closure Requests or Excavation Permits) that will require longer lead times for Government coordination/approval.
The responsible offeror shall meet requirement specification listed in section (3.3.3) of the SOW.
Sufficient detail within the schedule that provides specific timelines for staging area approvals, airfield waivers, outage requests and other Government approvals as provided in the SOW Section 3.3.3 in table listed as "Delivery Schedule & Submittals"
The technical rating reflects the evaluation of the acceptability of the offeror's technical approach for meeting the government's requirement. The offeror's proposal shall be evaluated to determine whether the proposal is acceptable or unacceptable, using the ratings and descriptions outlined in the table below. One technical rating will be assigned to each technical subfactor. To be considered awardable, there must be an "acceptable" rating in every subfactor.
PRICE: The Contractor shall provide an Electronic Cost Model Breakdown to support their proposed pricing in an unlocked Microsoft Excel Format. At a minimum, pricing shall be broken out by Construction Standards Institute (CSI) division or salient features of work. Proposals broken out by salient features of work and further subdivided by CSI division are preferred. The Contractor's proposed pricing shall be accomplished as described below and based on the most economical standard construction practices. Value engineering and design review shall be used in project design and scope development. Unreasonable methods and/or estimates of accomplishing the tasks required under this Statement of Work (SOW) shall not be accepted.
This effort is Lowest Price Technically Acceptable (LPTA).
(END)
| SUMMARY OF CHANGES |
| Solicitation/Contract Form |
| List of Attachments |
| Instructions, Conditions, & Notices to Offerors or Quoters |
| Evaluation Factors for Award |
File details come from the government source that posted it. Updated .