26 05 73 POWER STUDIES.pdf
PDF 5 MB Posted
- Solicitation number
- FA813727R0002
About this file
This is a technical specification document (Section 26 05 73) for Power System Studies required for Tinker Air Force Base electrical systems.
The contractor must furnish short-circuit, protective device coordination, and arc flash hazard analysis studies reflecting the as-built conditions of the installation. All studies must be performed in EasyPower® and comply with Tinker Air Force Base Electrical Standards (January 2024). The System Analyzer performing the studies must be a registered professional electrical engineer with a minimum of three years of experience with power system studies and must provide license number and state registration. The System Verifier may inspect and record settings and markings on existing equipment and place hazard labels; when working with energized equipment, the System Verifier must be a Qualified Person per NFPA 70E or work under direct supervision of a Qualified Person.
Required studies include: load flow analysis per IEEE 3002.2 to identify initial steady-state conditions and fault current availability; fault current study per IEEE 3002.3 providing three-phase and single-phase fault values at each voltage transformation point and distribution bus; system coordination study demonstrating selective operation of devices and including composite time-current characteristic curves; and arc flash hazard study per IEEE 1584.1 to determine worst-case incident energy with recommendations to reduce energies exceeding 8 cal/cm². Arc flash warning labels (3.5" × 5" to 4" × 6" thermal transfer type) must be provided for equipment likely to require examination or servicing while energized, including panelboards, switchgear, and motor control centers. The contractor must submit arc flash label formats for approval before printing and comply with label requirements in UFC 3-560-01 and NFPA 70E. All deliverables including field examination plans, test reports, model files in native editable formats, and study reports require government approval where marked with "G" classification per Section 01 33 00 submittal procedures.
View the file
Other files
Show 40 more
Latest 50 of 152 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .