250063_Pre-Bid RFI_Responses Signed.pdf

PDF 372 KB Posted

Attached to
WWYK250063 - INSTALL REACT VII FACILITY, B9001, POST V19
Solicitation number
FA813727R0002
Issued by

About this file

This document is a memorandum containing Pre-Bid Request for Information (RFI) responses for a federal construction contract. The project, WWYK250063 Install React VII Facility, Building 9001 at Tinker Air Force Base, Oklahoma, involves the design and construction of an interior industrial facility with fire-rated walls, mechanical and electrical systems, and specialized finishes. The contract is FA813727R0002, issued by the Department of the Air Force, 72d Air Base Wing (AFMC), and is designated as a 100% Women-Owned Small Business (WOSB) set-aside.

The memorandum addresses 113 RFI responses covering critical project specifications including: contract document hierarchy (SOW dated September 21, 2026 governs); Davis-Bacon wage determination posting requirements; dual Contract Line Item Numbers (CLINs 0001 and 0002) evaluated on combined total price; mandatory bid guarantee at 100% of bid price with FAR 52.228-1; revised proposal due date of November 23, 2026; RS Means-based pricing requirements with two vendor quotes for non-priced items; 240-calendar-day performance period with $227.75 per calendar day liquidated damages; special inspection requirements per IBC 2024 Chapter 17; and design-build responsibilities limited to structural engineering and fire protection systems. Key technical clarifications address fire-rated assemblies (2-hour exterior walls and roof; 1-hour Aisle 19 barrier wall), intumescent coating applications, penetration firestopping, roof/ceiling assembly details, electrical equipment specifications, mechanical systems coordination, and foundation design using presumptive soil values with field verification. The Government emphasized that cancellation of previous solicitation FA813726R0026 requires complete new proposals under the current solicitation, with amendments forthcoming to address multiple specification and drawing conflicts and clarifications.

View the file

Other files

File Type Posted
ATT 8_26 51 00.pdf PDF
ATT 7_26 05 73.pdf PDF
Solicitation Amendment - FA813727R00020002.pdf PDF
26 05 73 POWER STUDIES.pdf PDF
ATT 1_02 41 00.pdf PDF
Solicitation Amendment FA813727R00020002 SF 30.pdf PDF
ATT 5_10 26 00.pdf PDF
ATT 6_22 05 48.00 20.pdf PDF
ATT 3_09 29 00.pdf PDF
ATT 4_09 68 00.pdf PDF
26 51 00 INTERIOR LIGHTING.pdf PDF
Revised L and M - WWYK250063.pdf PDF
ATT 2_09 22 00.pdf PDF
Solicitation Amendment - FA813726R00260001.pdf PDF
Wage Determination - OK20260049 05-18-2026.pdf PDF
Solicitation Amendment FA813727R00020001 SF 30.pdf PDF
WWYK250063 - Site Visit Sign In Sheet.jpg JPG image
00 70 00.pdf PDF
07 14 00.pdf PDF
23 05 15.pdf PDF
09 90 00.pdf PDF
SOW Att 02c_Controlled Area Training - Certificate.pdf PDF
z400i.pdf_safe.pdf PDF
250063_ATT 10_Submittal Register.xlsx XLSX spreadsheet
220042 As Built Drawings.pdf PDF
017800_Attch2_DD1354 Checklist.docx DOCX document
dafi91-202.pdf PDF
dodio-2000.16v1_afi10-245-o.pdf PDF
250063_ATT 3_RMDF.pdf PDF
08 71 00.pdf PDF
afman91-203_oc-alcsup.pdf PDF
SOW Att 04_Automated Casting Cell.pdf PDF
01 50 00.pdf PDF
250063_ATT 4_ODS.pdf PDF
250063_ATT 13_Prebid RFI Responses Round 1.pdf PDF
Room finish schedule.xlsx XLSX spreadsheet
ARCH-COMBINED.pdf PDF
dafi21-101.pdf PDF
23 05 93.pdf PDF
4500-S.pdf PDF
07 84 00.pdf PDF
tinkerafb_INRMP_App G.pdf PDF
05 05 23.16.pdf PDF
007200_Attch13_AF487.pdf PDF
250063_SOW.pdf PDF
23 09 23.02.pdf PDF
05 40 00.pdf PDF
REACT VII SA-01.pdf PDF
JOIST SPECIAL INSPECTIONS.xlsx XLSX spreadsheet
SOW Att 02a_Controlled Area Training.pptx PPTX presentation
Show 40 more

Latest 50 of 152 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEPARTMENT OF THE AIR FORCE

HEADQUARTERS 72D AIR BASE WING (AFMC)

TINKER AIR FORCE BASE OKLAHOMA

6 November 2026

MEMORANDUM FOR AFSC/PZIOC (ATTN: Tamra Torres)

THROUGH: 72 ABW/CENM

FROM: 72 ABW/CEED

Tepa Companies

SUBJECT: Pre-Bid RFI Responses Project: WWYK250063 Install React VII Facility, B9001, Post V19

Reference: Memo, 23 October 2026, Pre-Bid RFIs, WWYK250063 Install React VII Facility, B9001, Post V19

1. This office reviewed the referenced RFIs for the subject project and provided answers below. Please forward to the contractor(s) for their use in preparing proposals

(1) Per Section J (List of Attachments); Section L, paragraph 8, Section J lists only Attachment 01 (250063_ATT 9_SOW) and Attachment 02 (250063_ATT 11_Drawings), both dated 21 Sep 2026, while the specifications, Submittal Register (ATT 10), RMDF (ATT 3), ODS (ATT 4), OPSEC memo (ATT 6), Liquidated Damages (ATT 8), SOW Att 04, prior RFI responses (ATT 13/14), and Tinker AFB standards are posted but not listed. Please confirm:

a. The complete and exhaustive list of documents that will constitute the contract, including each specification section by number.

b. Whether the Government responses in 250063_ATT 13 and 250063_ATT 14, issued under FA813726R0026, are incorporated into and binding under

FA813727R0002.

c. Which SOW governs, since 250063_ATT 9_SOW is marked Revision 0 (21 Sep

26) while the superseded SOW under FA813726R0026 was Revision 1 (04 Aug 2026), and the page footers of both still read 02 Oct 2025.

d. Whether Specification Sections 26 05 73 (Power Studies) and 26 51 00 (Interior Lighting), which were included in the FA813726R0026 specification set, remain part of this solicitation.

Government Response:

a. The specifications and submittal register are both part of the contract. The list of specifications is included in the SOW. The drawings, TAFB Facility Standards, TAFB Fire Protection Standard, TAFB Electrical Standards, and TAFB Mechanical Standard are also contract documents.

b. ATT 13 and ATT 14 are both binding.

c. SOW dated 21 Sep 26 governs.

d. Yes, they have been included as attachments to these RFIs.

(2) Per Section J; Section L, paragraph 8, Section L states the Davis-Bacon Wage

Determination "is found in Section J," but Section J of FA813727R0002 does not list a wage determination (FA813726R0026 listed WD OK20250049, Mod 2). Please confirm:

a. The wage determination number and modification that applies to this solicitation.

Government Response: Wage Determination will be/has been placed into the SAM.gov solicitation post.

(3) Per Section B (CLINs 0001 and 0002); Section A ("Additional Funding"), CLIN 0001

(EEIC 52200) and CLIN 0002 (EEIC 53200) carry identical descriptions, and the Section A title now reads "Post V19 Additional Funding." Please confirm:

a. The specific scope of work to be priced under CLIN 0001 versus CLIN 0002.

b. Whether award will be evaluated on the sum of CLINs 0001 and 0002.

c. Whether "Additional Funding" indicates any change in scope from

FA813726R0026 beyond those identified in the posted documents.

Government Response: CLINs 0001 and 0002 have been edited to reflect both project and design. The award will be evaluated on the sum of both CLINs (total evaluated price). “Additional Funding” does not indicate any change in scope beyond what has been identified in the posted documents.

(4) Per Section L, paragraph 12, Special Note, the solicitation states the Government contemplates award of "both projects on one (1) contract" and directs an independent offer "for each project," but only Project WWYK250063 is identified. Please confirm whether this Special Note applies to FA813727R0002, and if so, identify the second project.

Government Response: The note does not apply to this project; it has been struck out of the SF1442 (Solicitation). This will be included in the amended solicitation.

(5) Per Section L, paragraph 12; SF 1442 Block 13a, the question deadline is listed as

"NLT 2:00 p.m. (CT) on (TBD)" and offers are due 02 Nov 2026. Please confirm:

a. The date by which the Government will issue its RFI responses by amendment.

b. Whether the offer due date will be extended if RFI responses are issued fewer than ten (10) calendar days before 02 Nov 2026.

Government Response: The date that RFI responses will be posted will be the day of posting for this document. The RFP due date has been extended to 23 November 2026.

(6) Per SF 1442 Block 13b, the block reads "An offer guarantee is, is not required" with neither option selected, and FAR 52.228-1 does not appear in Section I. Please confirm whether a bid guarantee is required for FA813727R0002, and if so, the required amount and form.

Government Response: An offer guarantee IS required and was annotated in Block 13b. The amount of the bid guarantee is set to 100% of the bid price. 52.228-1 has been included via amendment.

(7) Per Section L (Proposal Requirements for Technical); Section M (Technical Subfactors 1 and 2), Section M references SOW Sections 3.12, 3.12.5.1 to 3.12.3.2 (Design Program Manager), 3.12.6, 3.6, 3.6.1, and 3.6.2, and Section L references SOW Sections 1.3 and 3.3; 250063_ATT 9_SOW contains no Section 3.12, and SOW Section 3.6 is "Minimum Guidance Documents." Please confirm

a. The SOW paragraphs against which Technical Subfactors 1 and 2 will be evaluated.

b. Whether a Design Program Manager is a required key position, and if so, the minimum qualifications.

c. The meaning of "mandatory completion date stated in the OPR" in Section M, and confirm the mandatory completion date is 240 calendar days after NTP per SF 1442 Block 11.

Government Response:

a. The correct paragraphs have been sited in the revised L&M.

b. Design Program Manager IS NOT a required key position.

c. OPR stands for “Owner Project Requirements”. The Mandatory completion date is “240 calendar days after NTP”.

(8) Per Section L (Proposal Requirements for Pricing), Section L requires line-item pricing based on RS Means national average bare costs, NPI worksheets, and "the two (2) lowest offers" from vendors, language that references a "Task Order," while Section I (52.216-1) contemplates a single Firm-Fixed-Price contract evaluated LPTA. Please confirm:

a. Whether the Electronic Cost Model Breakdown may be based on the offeror's actual subcontractor and vendor pricing rather than RS Means line items.

b. Whether the two-vendor quotation requirement applies only to NPI items.

c. That a proposal priced from actual subcontractor quotations will not be rated unacceptable or unreasonable solely for departing from RS Means unit costs.

Government Response:

a. No. To ensure a fair, consistent, and mathematically comparable evaluation of all proposals, the Electronic Cost Model Breakdown must utilize the line items and structure of the current calendar year RS Means Facilities Construction Cost Book.

Offerors are not permitted to bypass the RS Means pricing structure for standard, cataloged construction tasks. Actual subcontractor pricing may be used to inform the offeror's internal pricing, but it must be mapped to and fit within the requested RS Means CSI divisions and unit bare-cost format. For any specialized scope of work where a comparable RS Means line item does not physically exist, offerors shall utilize the Non Pre-priced Items (NPI) process.

b. Yes, confirmed. The requirement to provide the two (2) lowest vendor/subcontractor offers and the associated cost development worksheets applies strictly to Non Pre-priced Items (NPI) that cannot be found in the current calendar year RS Means Facilities Construction Cost Book. Standard RS Means line items do not require the submission of backing vendor or subcontractor quotes.

c. No, not confirmed. A proposal built upon actual subcontractor rates that departs from RS Means unit costs will be rated unacceptable if the offeror fails to input those standard items into the required RS Means format or fails to provide the mandatory backing quotes for NPIs.

While the Government recognizes that local market conditions may cause minor variances in unit costs, the final proposal must still be built using the standard RS Means baseline. Any item departed from RS Means is classified as an NPI and must include the supporting two (2) lowest written quotes and cost worksheets. A proposal priced from subcontractor quotations that excludes the mandatory backing quotes or fails to use the RS Means baseline for standard items will be deemed non-compliant with Section L and rated unacceptable.

The L&M has been revised to reflect this requirement.

(9) Per Section I (52.232-5 and 52.232-16), Section I now incorporates both FAR 52.232-

5, Payments under Fixed-Price Construction Contracts, and FAR 52.232-16, Progress Payments (Deviation 2026-O0038), which was not in FA813726R0026. Please confirm which payment clause governs, and whether FAR 52.232-16 was included in error.

Government Response: FAR52.232-5 will govern this requirement. FAR 52.232-16 was included via CLS error and will be removed in the amended solicitation.

(10) Per Section I (DFARS 252.237-7023 and 252.237-7024), the solicitation now incorporates Continuation of Essential Contractor Services, which requires a written plan with the offer for services listed in an attachment that is left blank. Please confirm that no mission-essential contractor services are designated under this contract and that no continuity plan is required with the offer.

Government Response: DFARS 252.237-7023 and 252.237-7024 were both included via CLS error and will be removed in the amended solicitation.

(11) Per 250063_ATT 8 (Liquidated Damages); Section I (52.211-12), the liquidated damages rate is $227.75 per calendar day and ATT 8 labels the total "Phase 1," while SOW Section 2.3 states there is no Government-required phasing. Please confirm that $227.75 per calendar day is the single liquidated damages rate for the entire contract and that no additional phase rates apply.

Government Response: PZ Response: PZIOC confirms that $227.75 per calendar day is the single liquidated damages rate for the entire contract and that no additional phase rates apply.

(12) Per Section L, paragraph 4; FA813726R0026, please confirm that Solicitation

FA813726R0026 has been cancelled, that offers and bid bonds submitted under it will not be considered, and that a complete new offer is required under FA813727R0002.

Government Response: Solicitation FA813726R0026 has been cancelled, offers and bid bonds submitted under it will not be considered, and a complete new offer is required under FA813727R0002.

(13) Per Section M (LPTA; Technical Subfactors 1 and 2); SOW Sections 2.1, 2.6, and

4.2.7.3, the work requires 1-hour and 2-hour fire-resistance-rated assemblies, delegated structural design, and construction inside the occupied B9001 controlled industrial floor adjacent to an occupied casting operation, yet Section M does not evaluate past performance or relevant experience. Please confirm:

a. Whether the Government will add a Past Performance or Relevant Experience subfactor (for example, a minimum of two projects completed within the last five years, each valued at $4,000,000 or more.

b. If no such subfactor is added, whether the Contracting Officer will establish special standards of responsibility under FAR 9.104-2 addressing experience.

Government Response:

a. The proposal will be evaluated for technical acceptability per Section M.

(14) Per 2026 TAFB Fire Protection Standard, paragraph 1.7.2.1.1; Spec Section 07 84 00, paragraph 1.5.1; Submittal Register (ATT 10) Item 160, installers of firestopping must be FM 4991 approved or UL Certified Firestop Contractors, and intumescent coating installer qualifications are a Government-approved submittal. Please confirm whether offerors must identify the qualified firestop installer and the manufacturer-approved intumescent coating applicator in the technical proposal, and whether omission will be treated as a deficiency.

Government Response: The 2026 TAFB Fire Protection Standard states the installer shall obtain from the manufacturer, and submit to the government, written certification of training and retain proof of certification for duration of firestop installation meeting the requirements of section 1.7.2.2.1 and section 1.7.2.3.3. Additionally, section

1.7.2.3.4 requires submittals for government approval of the firestopping material to be provided for each type of application.

(15) Per Section L, Technical Subfactor 1(1); SOW Section 3.5(1) through (3), the offeror must accept sole responsibility for both design and construction, and signed and sealed structural, fire alarm, and sprinkler working documents are required. Please confirm whether offerors must identify, in the technical proposal, the licensed structural engineer and fire protection engineer of record and their experience on comparable DoD projects.

Government Response: Yes, a designer should be considered including a fee proposal.

(16) Per DFARS 252.204-7024 (Notice on the Use of the Supplier Performance Risk

System), please confirm that the Contracting Officer will consider SPRS and CPARS records, including prior terminations for default, cure notices, and liquidated damages assessed on Tinker AFB contracts, in the responsibility determination for this award.

Government Response: The contracting officer will consider SPRS and CPARS records, including prior terminations for default, cure notices, and liquidated damages assessed on Tinker AFB contracts, in the responsibility determination for this award.

(17) Per Section L, Technical Subfactor 1(1); Section M, Technical Subfactor 1; SOW

Section 3.5; Drawings (all sheets marked "35% DESIGN"), the solicitation requires "sole source responsibility for both design and construction," while SOW 3.5 limits

Contractor working documents to structural, fire alarm, sprinkler, and sheet metal.

Please confirm:

a. The exhaustive list of design deliverables for which the Contractor is responsible.

b. That the Government retains design responsibility for the fire-resistance rating scheme, the selection of rated assemblies, and all other design elements shown on the Government drawings and not listed in SOW 3.5.

c. The Government review period for each Contractor design deliverable, and whether that review time is excluded from the 240-calendar-day performance period.

Government Response:

a. The list of deliverables is reflected in the referenced working documents section of submittal register.

b. Confirmed.

c. The Government review period for submittals is 14 calendar days unless otherwise defined in SOW 3.3.3. These review times are included in the 240-day period of performance.

(18) Per SOW Section 1.1, SOW Section 1.1 states Government-furnished dimensions, structural, mechanical, and electrical data, and utility locations are "approximate and shall be field verified," while the Contractor must provide a "complete, fully operating" system. Please confirm that a material discrepancy between the Government-furnished data and actual field conditions discovered after award constitutes a Differing Site Condition under FAR 52.236-2.

Government Response: Contractors were given the opportunity to visit the site and field verify actual conditions. Conditions that could be field verified during a pre-bid site visit would not fall under this clause. Conditions such as subsurface conditions that could not be verified during the pre-bid site visit would fall under this clause.

(19) Per SOW Section 2.1 (new paragraph); SOW Att 04, SOW 2.1 requires a "fire-retardant dust barrier that spans from floor to roof deck" and states "a drawing showing the work has been included in attachment 4"; SOW Att 04 (REACT 7 Layout Plan, 8/13/2026) shows an equipment layout and does not show a dust barrier. Please provide:

a. The location, length, and height of the required dust barrier, including the roof deck elevation at the barrier location.

b. The performance standard for "fire-retardant" (for example, NFPA 701 or ASTM E84 Class A) and whether the barrier must comply with NFPA 241.

c. The required duration of the barrier and confirmation that its removal at completion is the Contractor's responsibility.

d. Whether negative air pressure, HEPA filtration, or air monitoring is required on the occupied side.

Government Response:

a. The purpose of the barrier is to protect government personnel and equipment.

The barrier should separate the construction work from the occupied space. The Contractor should select the location in coordination with the Government that achieves this intent without impeding the work in the adjacent space. Roof deck elevation is 29’0”.

b. The fire-retardant standard is NFPA 701 and the barrier must comply with NFPA 241.

c. The barrier will be required during dust-generating construction activities and can be removed once those activities are completed. Yes, the removal is the responsibility of the contractor.

d. SOW 2.1 does not require negative air pressure, HEPA filtration, or air monitoring.

(20) Per SOW Section 2.1; SOW Att 04, the adjacent space is "currently under construction but will be occupied during construction," and SOW Att 04 shows a "Future Automated Casting Cell" in the Investment Mold Casting High-Bay along the Aisle 19 wall. Please confirm:

a. The entity performing the construction in the adjacent space and the date it will be occupied.

b. Whether casting cell equipment will be installed against or within ten (10) feet of the west face of the Aisle 19 barrier wall before or during the Contractor's coating, penetration, and steel panel work.

c. Whether operation of the casting cell (furnaces, molten metal, or other ignition sources) will be suspended by the Government during spray application of intumescent coating and solvent-borne materials.

d. That Government-directed restrictions on access through the adjacent space, or work stoppages to accommodate the casting operation, will be treated as compensable delays.

Government Response:

a. Construction should be completed by early December. The space will be in use but not “occupied” during your construction. People will be in and out as needed to run the robot. Contractor shall accommodate personnel entering and leaving the casting cell space when performing work in the space.

b. Casting cell equipment will be more than 10 feet from the west face of the wall.

c. The casting cell doesn’t contain ignition sources.

d. Delays will be reviewed on a case-by-case basis.

(21) Per SOW Section 4.2.7.3(1)(c); Drawing A-102, Keyed Note 17 and General Notes

1.C, 1.D, and 4, the west face of the Aisle 19 wall consists of existing steel wall panels that "shall receive a 1-Hour rated intumescent coating." Intumescent coatings are tested and listed (UL 263 / ASTM E119) to protect structural steel members; the Contractor has not identified any listed design in which an intumescent coating applied to a single-skin steel wall panel produces a 1-hour fire resistance- rated wall. Please confirm:

a. The UL (or other nationally recognized testing laboratory) design number for the 1-hour west-face assembly consisting of intumescent coating applied to the existing steel wall panels.

b. If no listed design exists, whether the 1-hour rating of the Aisle 19 barrier is provided solely by the UL U415 System A / U469 shaft wall on the east face, and whether the west-face intumescent coating is deleted.

c. That the Government, as designer of record for this assembly, retains responsibility for its fire-resistance performance, and that the Contractor is not required to obtain, or pay for, a manufacturer's engineering judgment to validate the specified assembly.

Government Response: An amendment addressing RFI 21 will be issued.

(22) Per SOW Section 4.2.7.3(1); Drawing A-102, General Notes 1.C, 1.D, and 4, field observation during the site visit indicates the existing steel wall panels on the west face of the Aisle 19 wall are perforated; perforation is not shown or described on any Government drawing. An intumescent coating cannot form a continuous, measurable film across perforations. Please confirm:

a. Whether the perforations are "openings" under General Note 4 that must be infilled and sealed with steel of equal or greater gauge than the existing panels over the entire west face from 20 feet south of column line U to 20 feet north of column line X.

b. If so, the square footage of steel overlay, the attachment method, and whether the overlay steel itself must receive the intumescent coating.

c. The manufacturer, profile, gauge, perforation pattern and open area of the existing panels, and whether acoustic insulation is present behind them and must be removed or replaced.

d. That the perforated condition of the existing panels constitutes a Differing Site Condition under FAR 52.236-2 if additional infill, overlay, or alternate construction is required to achieve the specified rating.

Government Response: The west surface of the wall, facing the REACT area, along Aisle 19 has corrugated metal panels facing the west. These are not perforated metal panels. There are perforated panels behind the corrugated panels. The perforated face of these panels are facing east and are visible from Aisle 19. An amendment addressing RFI 22 will be issued.

(23) Per Submittal Register (ATT 10) Items 160 through 165 and 521 through 524, the register cites Specification Section 07 81 00 (intumescent installer qualifications, adhesion testing, thickness testing, manufacturer inspection, and preconstruction meeting) and SOW Sections 4.2.4(4) and 4.2.5 for 2-hour and 1-hour intumescent coating, but Section 07 81 00 is not included in the specifications and SOW 4.2.4 and

4.2.5 do not address intumescent coatings. Please provide Specification Section 07 81 00, or confirm the governing requirements for:

a. The test standard and listing basis for each intumescent application (west-face wall panels, purlins, Z-clips, columns, coping angle, base plates, and C-channels).

b. Required dry film thickness, primer and topcoat compatibility, surface preparation standard (SSPC), and environmental exposure category.

c. Special inspection of intumescent coatings under IBC Section 1705.15, and whether that inspection is a Contractor cost or required.

Government Response: Specification Section 07 81 00 Spray applied Fireproofing is Listed in the SOW Appendix B. The USGS for 07 81 00 will be included in the forthcoming amendment.

(24) Per SOW Section 2.8 (EM Survey); SOW Section 4.2.7.3(1)(a), surface preparation of the existing west-face panels will require abrading the existing factory or field-applied coatings in an occupied industrial space. Please confirm:

a. Whether the EM survey referenced in SOW 2.8 sampled the existing coatings, sealants, and caulks on both faces of the Aisle 19 wall, and provide a copy of the survey report.

b. Whether abrasive blasting, power-tool cleaning, and airless spray application are permitted in B9001, and any restrictions on hours, ventilation, or VOC content.

c. Whether spray application must be performed outside normal duty hours, and if Government-directed, whether that work is compensable notwithstanding SOW Section 2.2.

Government Response:

a. There were no samples taken in the survey.

b. An amendment addressing RFI 24 shall be forthcoming. Intumescent paint shall be a water abased formulation with no listed LFL/LEL. For water based Intumescent coating applications, ventilation must be provided for safety and compliance with OSHA standards and applicable health regulations. The area of work for application of the intumescent coating shall be partitioned off from the work areas of Building 9001 to prevent over spray of the material and to contain vapors that shall be exhausted to the exterior of the Loading dock space.

Compliance with the following shall be required: OSHA 29 CFR 1910.94, OSHA 29 CFR 1910.134, Air Force Instruction (AFI) 48-137 implemented as DAFI 48- 137 / DAFGM2025_01 & Tinker AFB Instruction (TINKERAFBI) 48-103, 72d Operational Medical Readiness Squadron / Bioenvironmental Engineering (72

OMRS/SGPB).

c. Yes, the application must be performed outside of normal duty hours. Any additional cost for non-standard hour work should be included in the Contractor’s proposal.

(25) Per Drawing A-102, Keyed Notes 4, 5, 16, and 17, intumescent coating is required on

"all wall structural members (columns, purlins, etc.)" and on Z-clips to "achieve a minimum of a 1-hour fire rating," and the members are identified only as "existing channel framing." Please provide:

a. The size, shape, and weight per foot of each existing column, purlin, and channel member to be coated, so the required coating thickness can be determined.

b. The UL design number(s) applicable to intumescent coating on existing cold-formed purlins and on Z-clips, or confirm that the Government will accept a manufacturer's engineering judgment and that its cost is not part of the base price.

c. Whether the coating rating is to be restrained or unrestrained.

Government Response:

a. All structural steel and connections in the 1-Hour wall along the west side of Aisle 19 within the project area scope of work shall be field verified by the contractor. Refer also to SOW.

b. There is no requirement for application of intumescent coating on existing cold-formed purlins.

c. The structural steel framing system is to be considered unrestrained. The Intumescent coating rating shall be considered unrestrained.

(26) Per Drawing A-102, General Notes 1, 1.A, 1.B, and 3, the Government's penetration counts (minimum 15 east side, minimum 19 west side) are "more or less (MOL) than what is actually in place." Please confirm:

a. Whether firestop systems listed under UL 1479 are required for penetrations through the west-face steel wall panels, and identify any listed system the Government has confirmed exists for that substrate.

b. The F- and T-ratings required at the east-face shaft wall and the west-face panel penetrations.

c. That penetrations in excess of the Government counts will be compensated by contract modification, or provide a unit-price basis for the overrun.

Government Response: An amendment addressing RFI 26 shall be forthcoming. KTR is responsible for verifying Existing conditions refer to SOW 1.1.

(27) Per SOW Section 4.2.7.3(2)(d) and (e); Drawing A-102, Keyed Note 16 and plan callout, the shaft wall is to be installed from slab to the first purlin, between purlins, and from the top purlin to the deck, with purlins passing through the plane of the rated assembly. Please confirm:

a. The listed design or detail that maintains the 1-hour rating where the shaft wall is interrupted by existing purlins and attached with Z-clips.

b. The governing stud designation, since Keyed Note 16 calls for 2-1/2" C-H 24 GA studs and the plan callout calls for 212CH-34 studs.

c. That the SOW reference to "UL 469" is intended to read UL Design U469, as "UL

469" does not identify a fire resistance design.

Government Response: An amendment addressing RFI 27 shall be forthcoming.

(28) Per Drawing A-102 ("1-HR Fire Rated Barrier Wall ... extend North/South a min. of

20'"); SOW Section 4.2.7.3, the barrier wall terminates in open floor area 20 feet beyond column lines U and X. Please confirm:

a. The code basis for the 20-foot extensions, and that a barrier which does not extend wall-to-wall satisfies the continuity requirements applicable to fire barriers under the IBC as adopted by UFC 1-200-01.

b. The total length of the barrier and the height from slab to underside of roof deck at Aisle 19.

c. Whether the fire-rated wall identification labeling required by the 2026 TAFB Fire Protection Standard, paragraph 1.7.1, is required on both faces of the barrier.

Government Response:

a. The 20-foot extensions of the I-Hour rated wall along the west side of Aisle 19 is to protect the egress routes of occupants. There are exit doors at the north and the south end of the space. Both exterior egress routes run parallel to the exterior wall.

b. Contractor to field verify actual length and height to meet the requirements of the drawings and SOW.

c. Yes. Fire-rated wall identification labeling in accordance with the 2026 TAFB Fire Protection Standard, Paragraph 1.7.1, will be provided on both faces of the fire barrier.

Labels will be installed at the required spacing and in a manner that allows personnel approaching the wall from either side to readily identify the fire-resistance rating of the assembly. This approach is consistent with the intent of the standard and facilitates inspection, maintenance, and emergency response activities.

(29) Per 250063_ATT 11_Drawings, Sheet A-102, the re-issued Sheet A-102 contains

General Notes 1 through 4 (penetration inventory, steel panel infill and enclosures, NFPA 70E lock-out/tag-out, and firestopping) that were not on Sheet A-102 in 250063_ATT02_Drawings_Amend_01 as issued 05 Aug 2026; the revision block still shows only Amendment 1 (03 AUG 26) and the new notes are not clouded. Please confirm:

a. The complete list of changes between 250063_ATT02_Drawings_Amend_01 and

250063_ATT 11_Drawings.

b. That 250063_ATT 11_Drawings governs in its entirety.

Government Response:

a. General notes on A-102 were added and opening 105A was removed.

b. 250063_ATT 11_Drawings governs currently. An additional amendment will be issued that will govern.

(30) Per 250063_ Redline A-502; Drawing A-502, Detail 2 and Keyed Note 1, the posted hand-marked redline deletes the Fry Reglet aluminum wall end cap and dimension notes at Detail 2, adds "light gauge metal framing," and directs "stretch wall to 5/8" gyp board"; the redline is not listed in Section J and is not sealed, dated, or numbered.

Please confirm:

a. Whether 250063_ Redline A-502 is a contract document that supersedes Detail 2 on Sheet A-502.

b. The framing size and gauge, and the listed head-of-wall and expansion-joint system that maintains the rating at the revised Detail 2 condition.

c. The required rating of the south door expansion joint, since SOW Section

4.2.7.2(9) requires a 2-hour joint and Sheet A-502 Keyed Note 1 describes a 1-hour rated expansion joint.

Government Response:

a. The posted hand-marked redline drawings shall not be considered as part of the project documents and shall not be relied upon for information in respect to this project.

b. The 1-Hour rated wall shall meet the W469 wall assembly requirements or shall be an Equal tested & passed wall assembly. Detail 2/502 applies to the jamb assemblies.

The head assembly is to be similar. Shop drawings are required to be submitted for all the junctures, corners, head and sill variations for all fire rated assemblies in this project. Detail 3/A-52.

c. These details are located at different location s. Detail 2/A-502 is the typical jamb/head detail at the opening in the 1-Hour wall along aisle 19 located door 103B.

The required fire resistance rating of the REACT VII perimeter walls and the roof/ceiling assembly is 2Hours. The Aisle 19 barrier wall assembly system is a 1-hour element. SOW 4.2.7.2 (9) is applicable to the location of the south door, Door 104. The details for Door 104 are depicted in 3/A-502. Refer also to FLOOR PLAN 1/A-102 & enlarged Plan 2/A-105.

(31) Per Drawings G-003 and G-005; Drawings A-105, A-501, and A-502; SOW Sections

4.2.6(3) and 4.2.7.2(9); 250063_ATT 13, Response 6, Sheets G-003 and G-005 identify a 1-hour fire barrier, while the wall types, roof/ceiling, coping, expansion joint, 90-minute doors, and Response 6 indicate 2-hour construction. Please confirm the required fireresistance rating of the REACT VII perimeter walls and the roof/ceiling assembly, and confirm that the Aisle 19 barrier is the only 1-hour element.

Government Response: Confirmed, note where the walls and ceiling here at the opening where door number 103B is located, the walls and ceiling that extend to the east are a portion of the barrier wall system. Due to the differing structural systems, a I” fire rated expansion joint is required. Refer to detail 2 and Keynote 1 on drawing /A- 502.

An amendment addressing RFI 31 regarding the 1-Hour Barrier Wall systems shall forthcoming. The exterior wall and roof assembly systems of the React VII facility shall be 2-hour rated. The structural tube steel columns, beams and roof perimeter angle shall also to be 2-hour rated. The Aisle 19 barrier wall shall be 1-Hour rated

(32) Per Drawings A-105 and A-501; SOW Section 4.2.2(1), Wall Types 1 through 4A reference UL Design U415 System C, but the details show a 6" C-H stud with (2) 2- 1/2" slotted tracks at the head, an HSS column within the cavity, and the wall terminating at the underside of the wide flange beam with no listed head-of-wall joint.

Please confirm the intended listed assembly and provide the head-of-wall detail and listed joint system.

Government Response: The 2 ½ inch slotted head track is allowed as U415 is based upon the 2 ½ “ USG C-H studs 25 ga system. UL allows for a system that is wider. In this instance two 2 ½” 25 gauge tracks were used as 5” slotted tracks are not available. Slotted tracks must be UL listed.

System No. HW-D-0551 includes an option to use slotted track. Other alternatives are also allowed in addition to the slotted track (e.g.: CEMCO Fire Gasket 1 fire stopping for building joints, Cemco FAS Track 1000 DL, & CEMCO FAS J- Track which is specifically designed for use in shaft wall assemblies.) Shop drawings are required to be submitted for all the junctures, corners, head and sill variations for all fire rated assemblies in this project.

(33) Per Drawings A-105 and A-501; SOW Section 4.2.6(3), "2-hour intumescent coating" is required on HSS columns, base plates, perimeter angles, and the 1/4" steel coping angle, with no UL design numbers provided. Please provide the UL design number for each member, and confirm whether members enclosed within a rated wall cavity also require coating.

Government Response: Intumescent coatings are tested for each manufacturer.

Required coating thicknesses for intumescent coatings vary based upon the steel thickness and steel member configuration characteristics.

Base plates and Grouting must fit between the the wall sill tracks. Anchors are limited to epoxy capsule anchors.

Steel members enclosed within a wall cavities and within the ceiling cavity shall be coated with a 2-Hour intumescent coating.

(34) Per Drawing A-501, Detail 6; SOW Section 4.4.3(1)(e), the roof/ceiling assembly references UL Design H505 with openweb steel joists, metal deck, and concrete structural panels. Please confirm that UL H505 is the required listed design, the required gypsum board product and thickness (SOW 5/8" Type X versus A-501 3/4" Ultracode Core), and the governing joist designation.

Government Response: An amendment addressing RFI 34 regarding the roof/ceiling assembly shall forthcoming.

Drawing detail 6/A-501, as shown, requires 5/8” Gypsum Board Fire Code X attached to the bottom chord of the joists via hat channel furring.

At the 10’-0” Acoustical Grid Ceiling below the gypsum board ceiling located under the trusses, this shall be an acoustical grid ceiling.

Refer also to SOW 4.2.2 (10) which stipulates the suspended acoustical 2x2grid system.

(35) Per SOW Section 4.5.1(3); Drawings M-102 and E-103, ducts, sprinkler piping, conduit, cord-reel supports, and equipment supports penetrate the rated roof/ceiling membrane. Please confirm whether fire dampers or ceiling radiation dampers are required at each duct penetration of the lid, and provide the listed systems the Government intends for membrane penetrations.

Government Response: The lid is a fire rated assembly and penetrations shall be constructed to maintain the fire rating.

(36) Per Drawing A-105, Wall Types 5 and 6 have no stated fire-resistance rating, and Wall

Type 6 shows gypsum board applied to a 4" HSS column with no framing. Please confirm the required rating and framing for Wall Types 5 and 6.

Government Response: Wall types 5 & 6 are not rated wall assemblies and are not attached to the 4" HSS column. The 4" HSS columns located inside interior walls are structural members supporting the W10X19, W10X22, and W12X22 beams. Refer drawings S-102 & S-502.

(37) Per Drawings A-301 and S-101 ("4" min. clear to interior face of columns"); SOW

Sections 4.2.2(3) and 4.2.6(1)-(2); 250063_ATT 13, Response 27, a 4-inch clearance between the REACT VII wall and the existing building is shown, while the SOW requires 6x6 supply ducts, containment netting, and a Level 4 painted gypsum finish in that space. Please confirm the minimum clear dimension that the Contractor shall use for the structural design and wall layout.

Government Response: Provide clearance for ductwork.

(38) Per Drawing A-601 (Doors 103A and 105, fire-rated coiling doors); Drawing FA-101;

SOW Section 4.2.3.2(1), no automatic-closing release device, detectors, or fire alarm interface is shown for the fire-rated coiling doors. Please confirm the required closing method, release devices, and fire alarm connections for Doors 103A and 105.

Government Response: The new roll up doors will be required to have automatic closure on fire alarm activation as well as detection on both sides of the door.

(39) Per Drawing E-103, the VAV-104 circuit is labeled "U1H-14,16,18." Please confirm the correct designation is Panel U18H, circuits 14, 16, and 18.

Government Response: The designation should be Panel U18H, circuits 14, 16, and 18.

(40) Per Drawing E-104; 250063_ATT 14, Response 10, Drawing E-104 lists Door "105A" while the Government response identifies Door 105A as a Type 7 door and Door 105 as a Type 6 coiling door. Please confirm the door designations and the power requirements for each operator.

Government Response: There is a naming mismatch between the electrical plan and the architectural door schedule. The exact designation (105 vs 105A) per Sheet A-601 provides explicit electrical specs (voltage, phase, HP) so the contractor can size branch circuits and overcurrent protection correctly. Sheet A-601 governs and clarifies the branch circuits size to match the manufacturer's submittal of the approved operator; coordinate with the other trades.

(41) Per Drawing S-503; Drawings M-102 and E-103, the AHU, ERV, Panels U18H and

U18L, and the 75 kVA transformer are located on the REACT VII roof accessed only by ladder. Please confirm that ladder-only access is acceptable to the Government for maintenance, and that NEC 110.26 working clearances may be provided within the guardrail and netting enclosure.

Government Response: While ladder access is acceptable for maintenance, NEC

110.26 requires dedicated, clear working space (minimum 30" width, 36" depth for 120/208V, and 78" height) in front of panels and transformers. During design these clearances were checked and can be achieved. Contractor shall coordinate with the other trades to ensure the guardrails/netting is designed with removable or swing-out sections to guarantee safe working clearances and equipment maintenance/replacement accessibility.

(42) Per SOW Sections 1.8 and 2.2, outages "may be required to be performed outside of normal duty hours," and "work outside normal duty hours to meet schedule will be performed at no additional cost." Please confirm that the noadditional- cost provision applies only to after-hours work the Contractor elects for its own schedule, and that Government-directed after-hours outage windows, including NFPA 70E de-energization required by Drawing A-102 General Note 2, are compensable.

Government Response: Confirmed, cost should be included in Contractor’s proposals.

(43) Per SOW Section 2.5; SOW Section 3.3.3 (FAA Form 7460-1, 60 days);

007100_Attch1 (Airfield Construction Waiver), SOW 2.5 states the work is not located in an airfield operations area. Please confirm that neither FAA Form 7460-1 nor an Airfield Construction Waiver is required for this interior project, including for lifts and hoisting equipment used inside B9001.

Government Response: Confirmed.

(44) Per 007200_Attch14 (Information Required for New Boiler), please confirm that no boiler or fuel-fired equipment is included in this scope and that this form is not a required submittal.

Government Response: No boiler or fuel fired equipment is specified for this project.

(45) Per SOW Section 3.3.1; Section I (FAR 52.232-5(e)), SOW 3.3.1 requires the schedule to reserve "the final 10% of the contract cost for final acceptance," with no payment until all closeout items are submitted and approved, while FAR 52.232-5(e) permits retainage only when progress is unsatisfactory. Please confirm:

a. Which provision governs retainage on this contract.

b. The exhaustive list of closeout submittals and actions that must be completed before the final 10% is released.

c. The Government's maximum review time for each closeout item, and that

Government review time after the Contractor's final submittal does not count against the 240-calendar-day performance period or accrue liquidated damages.

Government Response:

a. Both FAR 52.232-5(e) and the verbiage in SOW 3.3.1 Govern. Failure to provide closeout submittals allows the Government to refrain from approving the final invoice for the final 10%. FAR 52.232-5(e) allows the Government to withhold 10% of the amount invoiced for work that is unsatisfactory until satisfactory progress is achieved.

b. The exhaustive list of closeout submittals can be found in the document labeled “250063_ATT 10_Submittal Register.

c. The PoP is running until we approve the final submittal and start processing the final

PR.

(46) ATT 13 and ATT 14 (Pre-Bid RFI Responses dated 30 Jul 2026 and 21 Aug 2026) were issued under the earlier solicitation for this project. Please confirm these pre-bid RFI responses apply to this solicitation. Where a pre-bid RFI response conflicts with the current bid documents or with the answers to these RFIs, please confirm which takes precedence.

Government Response: The previous RFI responses were provided in an attempt to clarify any current RFIs that might have been submitted. Where a conflict exists the most recent response will take precedence.

(47) RFI R1-7 states revised door, frame and hardware schedules will be provided, and RFI R1-13 references a revised Sheet E-601. Please confirm whether these revisions are the Amendment 1 sheets included in ATT 11, or will be issued by amendment.

Government Response: Revised Door schedule, revised Frame schedule, and revised Hardware schedule on sheets A-601, and & A-602 were included in Amendment 1.

The revision area in each title block is dated: 03 AUG 26. Refer to the revision block of each drawing sheet to verify that the correct drawing sheets are being used.

(48) SF 1442 Block 13a calls for sealed offers at the Block 8 address, but Block 8 is blank, and DFARS 252.215-7012 calls for the cost portion by email. Please confirm proposal submission is via email, and provide the email addresses required.

Government Response: Send complete proposal including cost portion via email to the POC listed in SAM.gov posting. (isaac.demmers@us.af.mil)

(49) Section L, para 8 states the Davis-Bacon wage determination is found in Section J.

Contractor cannot locate it among the 138 files posted on SAM.gov. Please provide the applicable wage rates (wage determination number and modification).

Government Response: Wage determination has been posted in the attachments section of the SAM.gov post and included in section J via amendment.

(50) FAR 52.222-34 and the 52.222-33 notice are included (pp. 15, 42). However, due to the project size, please confirm a Project Labor Agreement is not required.

Government Response: FAR 52.222-34 and 52.222-33 were added via CLS error. A Project Labor Agreement is not required.

(51) SF 1442 Block 13b is checked, but FAR 52.228-1 is not in the clause list, no amount is stated, and neither Section L nor Section M lists a bid bond as a submission requirement. Please confirm a bid guarantee is not required.

Government Response: FAR 52.228-1 has been added to the clause list via amendment. A bid bond IS required.

(52) CLIN 0001 (EEIC 52200) and CLIN 0002 (EEIC 53200) have the same description, and the Special Note (p. 40) refers to "each project." Please describe the work to be priced under each CLIN, and confirm this solicitation covers one project.

Government Response: CLINs 0001 and 0002 have been edited to reflect both project and design. The award will be evaluated on the sum of both CLINs (total evaluated price). “Additional Funding” does not indicate any change in scope beyond what has been identified in the posted documents. The solicitation covers one project

(53) Please confirm this is a 100% WOSB set-aside and only SBA-certified WOSBs can pursue this project.

Government Response: This is a 100% WOSB set-aside and only SBA-certified WOSBs can propose for this project.

(54) Pages 11, 13 and 39 reference FA813725F0046 and FA813726R0026, and Sections L and M cite different SOW paragraphs (1.3/3.3 vs. 3.12/3.6). Please confirm these references do not apply, and identify the correct SOW paragraphs for the technical evaluation.

Government Response: These references do not apply and the correct SOW paragraphs have been identified in Sections L and M.

(55) DFARS 252.237-7024 (p. 44) calls for a written plan with the offer, but the referenced attachment is blank. Please confirm a Mission-Essential Contractor Services plan is not required.

Government Response: DFARS 252.237-7023 and 252.237-7024 were both included via CLS error and will be removed in the amended solicitation. Mission-Essential Contractor Services plan is not required.

(56) Section L requires RS Means line items and two vendor quotes for items not in RS Means. Please confirm that subcontractor lump-sum quotes with takeoffs are acceptable.

Government Response: Confirmed.

(57) SOW 4.2.7.2(7) specifies a SLABLOC 50/100 moisture mitigation, SLABFLEX 300 joint filler, SLABHARD GPE build coats and SLABSEAL 300 topcoat system. The spec book contains 09 67 23.15 (Fuel Resistive Resinous Flooring, thin-film epoxy/urethane), which requires an SSPC QP 8 contractor, an independent Protective Coatings Specialist, a Certified Industrial Hygienist and a QP 5 coating inspection firm.

SOW Appendix B and ATT 10 list "09 67 23.13." Please confirm: (a) the SOW 4.2.7.2 system governs, and (b) the 09 67 23.15 qualification, third-party inspection and patch-test requirements do not apply.

Government Response: The project shall include the requirement for the SSPC QP 5 Level II independent Protective Coatings Specialists and shall be the QC Specialist, who works for the QC manager and qualified in accordance with Section 01 45 00 Quality Control. The Coating Inspector must be present during all field tests, surface preparation, flooring application, initial cure of the flooring system, and during all flooring repair work. The Coating Inspector shall provide all tools/equipment necessary to perform field tests and inspection. The Coating Inspector is responsible for field tests and specified level of inspection. This includes the requirements listed in 3.11.2 through 3.11.3 of Specification Section 09 67 23.15.

(58) Spec 07 14 00 requires a 20-year no-dollar-limit warranty and a 48-hour flood test, written for a plaza deck. For the interior fluid-applied membrane under the epoxy floor (SOW 4.2.7.2(8)), please confirm the manufacturer's standard warranty is acceptable and the flood test is not required.

Government Response: The warranty shall be in accordance with Specification Section 09 67 23.15, paragraph1.8.

(59) SOW Appendix B and the ATT 10 submittal register list sections not included in the spec book: 02 41 00, 03 15 13, 03 30 00, 05 12 00, 05 21 00, 05 30 00, 05 50 13, 05 51 33, 07 60 00, 07 81 00, 09 22 00, 09 29 00, 09 68 00, 10 26 00, 22 05 48.00 20, 23 34 23.00 40, 26 05 73, 26 51 00, 31 00 00 and 31 23 16. The SOW requires Contractor-prepared specifications only for the structural systems (SOW 3.5(1), 4.4.1).

Please confirm that the Contractor is not required to prepare the non-structural sections, and that this work and its submittals follow the drawings, the SOW, the TAFB standards and the manufacturers' requirements.

Government Response:

02 41 00, 09 22 00, 09 29 00, 09 68 00, 10 26 00, 22 05 48.00 20, 26 05 73, & 26 51 00 are included as an attachment to these RFI responses.

03 15 13, 03 30 00, 05 12 00, 05 30 00, 05 50 13, 05 51 33, 07 81 00, 31 00 00, & 31 23 16 are to be produced by the Contractor.

03 01 00, 05 05 23.16, & 05 40 00 were mistakenly provided as part of the solicitation and are to be produced by the Contractor.

(60) Spec 10 22 13 is included in the spec book but is not listed in SOW Appendix B or shown on the drawings. Please confirm wire mesh partitions are not in scope.

Government Response: Wire mesh partitions are not included in the scope of this project.

(61) G-005 Keyed Note 1 states the exterior wall and ceiling are 1-hour. A-105 and A-501 show UL U415 System C and UL H505 2-hour assemblies, and A-601 shows 90-minute doors. Please confirm the required rating of the React VII perimeter walls and ceiling.

Government Response: An amendment addressing RFI 61 will be forthcoming. The requirement is that the wall and roof shall be 2-Hour assemblies. Also refer to RFI 31.

(62) A-501 Detail 7 shows a 2x2 acoustical ceiling at 10'-0" below the UL H505 2-hour gypsum ceiling. Please confirm the acceptable support method for the acoustical grid.

(63) RFI R2-10 describes Door 105A as an LHR 3070 Type 7 door with a 45-minute rating.

E-104 identifies 105A as an overhead door at 230 VAC, and the A-601 door schedule has no Door 105A. Please identify the location, type and size of Door 105A.

Government Response: Door number 105A has been deleted from this project. Refer to A-102 (Revision 03 AUG 26, Amendment 1) , A-601 ((Revision 03 AUG 26, Amendment 1), and A-602 A-601 (Revision 03 AUG 26, Amendment 1).

(64) RFI R1-7 states revised door, frame and hardware schedules will be provided. A-602 Amendment 1 Hardware Group 6 (Door 104) still shows a Simplex 8010 lock and Von Duprin XP98/99 device.