00 80 05.pdf

PDF 10 KB Posted

Attached to
TINKER AFB MAC BOA WWYK190023 Renovate Restrooms B117
Solicitation number
FA813726R0030
Issued by

About this file

This document is a Special Provisions section (00 80 05) of the Tinker Air Force Base General Requirements specification that establishes mandatory procedures and safety protocols for contractors performing work on or near the active airfield, including runways, taxiways, and clear zones as defined by Unified Facilities Criteria 3-260-1.

Contractors must submit written closure requests to the Contracting Officer at least 45 calendar days prior to needed runway or taxiway closures, specifying the nomenclature, work area, requested date, estimated duration, detailed work description, required equipment list, and estimated personnel needs. The Contracting Officer coordinates with Base Operations to approve closures and notifies contractors in writing of approved dates and durations; contractors bear responsibility for having all personnel, materials, and equipment ready on the approved date and must complete work within the approved timeframe, as Base Operations cannot accommodate closure extensions under most circumstances. Contractors must provide personnel with ear plugs and/or ear muffs in addition to all OSHA-required safety equipment, maintain clean work sites with no Foreign Object Debris (FOD) to prevent aircraft damage, obtain control tower clearance before crossing active runways or taxiways, use approved low-intensity amber flashing lights on landing areas, and maintain two-way radio contact with the control tower when required. Contractors must request written approval from the Contracting Officer at least 21 calendar days in advance for any temporary structures or equipment exceeding 12 feet within 1,000 feet of runways or 50 feet elsewhere on the base. Additionally, contractors must maintain on-site cleaning equipment capable of removing loose materials, remove all materials and equipment to staging areas daily, stockpile nothing within 1,000 feet of runway centerlines, identify evacuation areas on the first day of work, and may be required to conduct full runway and taxiway inspections accompanied by government representatives upon completion of work.

View the file

Other files

File Type Posted
03 11 13.00 10.pdf PDF
03 20 00.00 10.pdf PDF
03 30 00.pdf PDF
07 14 00.pdf PDF
07 19 00.pdf PDF
07 21 16.pdf PDF
07 22 00.pdf PDF
07 31 13.pdf PDF
07 52 00.pdf PDF
07 72 20.pdf PDF
08 34 01.pdf PDF
08 34 19.10 20.pdf PDF
08 52 00.pdf PDF
09 29 00.pdf PDF
10 21 13.pdf PDF
10 22 13.pdf PDF
13 34 19.pdf PDF
21 13 13.pdf PDF
23 03 00.pdf PDF
23 05 48.00 40.pdf PDF
23 07 00.pdf PDF
23 09 23.01.pdf PDF
23 34 23.00 40.pdf PDF
23 52 00.pdf PDF
23 65 00.pdf PDF
23 70 03.pdf PDF
26 00 00.00 20.pdf PDF
26 05 48.00 10.pdf PDF
26 29 23.pdf PDF
26 32 14.00 10.pdf PDF
31 23 15.pdf PDF
31 23 16.pdf PDF
32 01 13.pdf PDF
32 11 11.pdf PDF
32 11 29.pdf PDF
32 12 10.1.pdf PDF
32 12 10.2.pdf PDF
32 13 14.pdf PDF
190023 Renovate Restrooms B117 RFIs_FINAL_COR_Signed.pdf PDF
TAFB_Tech_Reqs (Div 02-48).zip ZIP file
Model.zip ZIP file
000_TABLE OF CONTENTS.pdf PDF
01 32 16.00 20.pdf PDF
01 33 16.00 10.pdf PDF
01 42 00.pdf PDF
01 78 00.pdf PDF
Tinker General Requirements Specifications_Nov 2022_Change Log.pdf PDF
Initial Site Visit WWYK190023.pdf PDF
Att12_190023_Drawings_Final.pdf PDF
Section L - Instructions to Offerors.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Tinker AFB Tinker General Requirements

SECTION 00 80 05

SPECIAL PROVISIONS FOR WORKING ON OR NEAR THE AIRFIELD ON TINKER AFB

PART 1 GENERAL

The following provisions shall apply when work is required to take place on the active airfield, within the clear zones, or in the primary surfaces as defined by Unified Facilities Criteria 3- 260-1, Airfield and Heliport Planning and Design.

1.1 CLOSURES

a. All runway and taxiway closures require coordination and scheduling with Base Operations. Written requests for closures shall be submitted to the Contracting Officer no less than 45 calendar days prior to the requested date of closure. The request shall include:

1. The nomenclature of the runway/taxiway to be closed

2. The area of the runway/taxiway where the work is to take place

3. The requested date of closure

4. The estimated duration of closure

5. A detailed description of the work to be performed

6. A list of the equipment required to perform the work

7. An estimate of the personnel required to perform the work

b. The Contracting Officer shall coordinate with Base Ops to close the requested runway/taxiway on or as close as possible to the date requested and for the length of time requested. The Contracting Officer shall notify the contractor, in writing, of the date and length of time approved for closure.

c. It is the responsibility of the contractor to have the necessary personnel, materials, and equipment ready to start work on the approved date of closure and to complete the work in the time requested. Under most circumstances, Base Operations will be unable to adjust flight and runway/taxiway utilization schedules to accommodate extensions to closures.

d. The contractor shall notify the Contracting Officer, in writing, when the work on the closed runway/taxiway is complete.

1.2 SAFETY

1.2.1 Personnel

The contractor shall provide all of his personnel ear plugs and/or ear muffs to prevent injury to their auditory systems while working on the Airfield. Jet aircraft operating on the runways, taxiways, and aprons make these areas zones of high-level noise. The government will not be held liable for auditory system damage due to non or improper use of noise protection equipment.

This requirement is in addition to the contractor providing his personnel with safety equipment required by OSHA for the work to be performed.

January 2022 Page 1 Section 00 80 05

1.2.2 Aircraft

The contractor shall maintain a clean work site and shall implement all measures necessary to insure that material and equipment do not interfere with or damage aircraft operating or parked in areas of the airfield that are not closed. NO FOD.

1.3 ACCESS RESTRICTIONS

No unescorted contractor vehicles, equipment, or personnel shall be on or cross any active runway or taxiway unless clearance is requested from, and granted by, the control tower. All contractor vehicles and mechanized equipment operating on the landing areas (the first 1,000 feet from either end of the runway) will be identified by approved, mounted, low intensity, amber flashing lights. When contractor operations require repeated vehicle or personnel crossing of an active runway, taxiway, or other controlled area, a two-way radio, furnished by the Government, will be used to maintain contact with the control tower. Use of the radio for other purposes will be strictly prohibited. The radio will be returned to the Government at the end of each workday, and will be reacquired as necessary.

1.4 HEIGHT RESTRICTIONS

The construction of any temporary structure or the use of any equipment that extends more than 12 feet above the ground within 1000 feet of a runway or that extends 50 feet above the ground elsewhere on Tinker AFB shall be approved by the Government prior to installation or use. Written request for approval shall be submitted to the Contracting Officer no later than 21 calendar days prior to the date needed.

1.5 CLEANLINESS

The contractor shall maintain the cleanliness of his work site and all traversed runways, taxiways, aprons, and ramps at all times. He shall utilize methods and equipment to prevent spilling or dropping materials in these areas and shall utilize whatever method or equipment necessary to insure the removal of loose materials from these areas. The contractor shall remove all material and equipment to his staging area at the end of each work day. No material is to be stockpiled nor equipment stored within 1000 feet of the centerline of a runway.

1.6 EMERGENCIES

1.6.1 Evacuation Area

On the first day of work on the airfield, the contractor, a representative of the Contracting Officer, and a representative of Base Ops shall identify an area a safe distance from the runway where the contractor is to move his personnel and equipment during an aircraft emergency.

1.6.2 Evacuation

During an aircraft emergency, the contractor shall vacate the work site.

He shall move all personnel and equipment to the designated evacuation area. Evacuation orders will be given on short notice and will require expeditious action by the contractor.

January 2022 Page 2 Section 00 80 05

1.7 INSPECTION AND CLEANING

The contractor shall maintain, on site and in good working order, equipment capable of cleaning loose materials from the runway, taxiway, ramp, or apron. The contractor, accompanied by a Government representative, may be required to inspect the entire length of the runway and taxiway to insure that all personnel, debris, material, equipment, and tools have been removed from these areas.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

-- End of Section --