This document provides details for a Multiple Award Construction Contract solicitation. The 700th Contracting Squadron, Kapaun Air Station, Germany is soliciting proposals for up to five indefinite-delivery, indefinite-quantity construction contracts for the Kaiserslautern Military Community and Ramstein and Spangdahlem Air Bases in Germany. The estimated total value of task orders awarded under the contracts is $425 million over five years. Task orders will range from $1,000 to $5 million for design-build, sustainment, maintenance, alteration, repair, renovation, and minor construction projects. A seed project between $1 million and $5 million is included at Ramstein Air Base. The solicitation is expected to be released on November 1, 2018 with proposals due by December 1, 2018. The period of performance for the contracts is one five-year ordering period beginning October 1, 2019 through September 30, 2024.
RFP Atch 5b - Liquidated Damages (LD) Determination for Seed Project
View the file
Other files for this federal contract opportunity
Show all 50
Multiple Award Construction Contract (MACC) has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
LIQUIDATED DAMAGES DETERMINATION
SUBJECT: Project No: TYFR 18-1047
Title: EIC-Convert to KC-135 Parts Storage
1. In accordance with FAR 36.206 and DOD FAR Sup 236.206, liquidated damages (LDs) will be assessed for each calendar day of delay required to complete work on subject contract.
As a minimum, LDs in the amount of EURO 323.48 for the first day and EURO 250.92 for each day thereafter will be charged, based upon the following:
a. The contractor has complete control of the pace of work.he place of work
b. The contract provides for liquidated damages for delay of work for each calendar day of the contract.
c. Considering the requirement, the rate of assessment is reasonable.
Elizabeth Preston
Contracting Officer
Date:
LEGAL
Staff Judge Advocate 1.0 hours @ 72.57 = 72.57 EURO
(first day only)
CIVIL ENGINEERING
Inspection 2.0 hours @ 27.76 = 55.52 EURO
Supervision/Admin 1.0 hours @ 34.63 = 34.63 EURO
Total Engineering Cost/Day 90.15 EURO
CONTRACTING
Contracting Officer 1.0 hours @ 56.82 = 56.82 EURO
Administrator 2.0 hours @ 43.20 = 86.39 EURO
Vehicle Costs 17.56 EURO
(See attached chart)
Total Contracting Cost/Day 160.77 EURO
ADDITIONAL DAMAGES
Loss of Quarters EURO per day
Loss of Use of Runways/Taxiways EURO per day
Loss of Use of Building EURO per day
Other EURO per day
Total Other Costs/Day 0.00 EURO