About this file

This document contains a standardized technical proposal template and related federal contract opportunity notice. The technical proposal template provides a table of contents and sections for contractors to address preliminary notes, time schedules, statements of work, technical descriptions, quality control plans, regulatory compliance, attachments, and work elements for a potential project involving the conversion of a storage building at Ramstein Air Base in Germany.

The related federal contract opportunity is a solicitation notice for multiple award construction contracts worth an estimated total value of $425 million over five years. The Air Force plans to award up to five contracts to provide design-build, sustainment, maintenance, alteration, repair, renovation, and minor construction projects at military installations in the Kaiserslautern Military Community of Germany. Individual task orders will have values between $1,000 and $5 million. The solicitation is anticipated to be issued on November 1st with proposals due by December 1st, and will include a design-build seed project valued between $1 million to $5 million at Ramstein Air Base.

RFP Atch 5a - Standardized Technical Proposal (STP) for Seed Project

View the file

Other files for this federal contract opportunity

Other files attached to Multiple Award Construction Contract (MACC), newest first.
File Type Posted
FA5613-19-R-0003-0004.pdf PDF
(Amendment_0004)_Section_M.pdf PDF
(Amend_0004)_Section_L.pdf PDF
Consolidated_Q&A__6.pdf PDF
Atch_3k_-_Drinking_Water_Analysis.pdf PDF
RFP_Atch_3_-_(Rev_3_)_SOW_for_Seed_Proj_TYFR18-1047.pdf PDF
Consolidated_Q&A__5.pdf PDF
RFP_Atch_3i_-_Noise_Contour_Map_RAB.pdf PDF
RFP_Atch_3_-_(Rev_2)_SOW_for_Seed_Proj_TYFR18-1047.pdf PDF
RFP_Atch_3g_-_(Rev_1)_Shelf_Layouts_and_Dimensions.pdf PDF
FA5613-19-R-0003-0002.pdf PDF
Consolidated_Q&A__3.pdf PDF
FA5613-19-R-0003-0001.pdf PDF
RFP_Atch_5e_-_Premise_Wiring_Standard.pdf PDF
RFP_Atch_3g_-_Shelf_Layouts_&_Dimensions.pdf PDF
RFP_Atch_3_-_(Rev_1)_SOW_for_Seed_Proj_TYFR18-1047.pdf PDF
Atch_3_-_Pre-Prop_Conf_&_Site_Visit_Briefing.pdf PDF
Atch_1_-_Conf_&_Site_Visit_Attendance_Record.pdf PDF
Atch_2_-__Consolidated_Q&A_2_(Conf_&_Site_Visit).pdf PDF
Pre-Proposal_Conference_Minutes.pdf PDF
RFP_Atch_3f06_-_A01_-_New_planning,_floor_plan.pdf PDF
RFP_Atch_3a_-_Bldg_2167_Contaminant_Investigation_Report.docx DOCX document
RFP_FA5613-19-R-0003_(MACC).pdf PDF
RFP_Atch_2_-_Special_Contract_Requirements.pdf PDF
RFP_Atch_3f04_-_B03_-_Inventory_sectional_views.pdf PDF
RFP_Atch_5b_-_LD_Determination.pdf PDF
Cover_Ltr_-_RFP_Release.pdf PDF
RFP_Atch_3d_-_Bldg_2167_Sample_Taking_Plan.pdf PDF
RFP_Atch_3f04_-_B03_-_Inventory_sectional_views.dwg DWG drawing
RFP_Atch_4_-_Seed_Proj_Bid_Schedule_Worksheet.xlsx XLSX spreadsheet
RFP_Atch_3f01_-_Cover,_TOC,_location_plan.dwg DWG drawing
RFP_Atch_3f01_-_Cover,_TOC,_location_plan.pdf PDF
RFP_Atch_8_-_SubK_Consent_Ltr.doc DOC document
RFP_Atch_3_-_SOW_for_Seed_Proj_TYFR18-1047.pdf PDF
RFP_Atch_3f03_-_B02_-_Inventory_topview.dwg DWG drawing
RFP_Atch_3f05_-_B04_-_Inventory_elevations.pdf PDF
Invitation_for_Pre-Proposal_&_Conf_Site_Visit.pdf PDF
RFP_Atch_3e_-_Bldg_2167_Work_and_Safety_Plan.docx DOCX document
RFP_Atch_3f06_-_A01_-_New_planning_floor_plan.dwg DWG drawing
RFP_Atch_1_-_General_Requirements_&_Provisions.pdf PDF
RFP_Atch_9_-_Client_Authorization_Ltr.docx DOCX document
RFP_Atch_7_-_PPQ.doc DOC document
RFP_Atch_3f03_-_B02_-_Inventory_topview.pdf PDF
RFP_Atch_6_-_PPI.doc DOC document
RFP_Atch_3c_-_Bldg_2167_Room_Book.xls XLS spreadsheet
RFP_Atch_3f02_-_B01_-_Inventory_floor_plan.pdf PDF
RFP_Atch_5c_-_Material_Submittal_Form_66_TYFR_18-1047.pdf PDF
RFP_Atch_3f02_-_B01_-_Inventory_floor_plan.dwg DWG drawing
Invitation_Atch_1_-_PreRegistration_Form.docx DOCX document
RFP_Atch_3b_-_Bldg_2167_Disposal_Concept.xlsx XLSX spreadsheet
Show all 50

Multiple Award Construction Contract (MACC) has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Standardized Technical Proposal (STP) Table of Contents

A: PRELIMINARY

NOTES

PROJECT #:

TITLE:

BUILDING #:

LOCATION:

INSPECTOR:

PROPOSED CONTRACT PROCEDURE:

B: TIME

SCHEDULE

PERFORMANCE PERIOD

Calendar Days:

LATEST END DATE:

EXCLUSION PERIOD:

PHASES:

C: STATEMENT

OF WORK (SOW)

Contractor shall provide SOW based on the

Government provided Statement of Work(SOW) Yes No

D: TECHNICAL

DESCRIPTION

1. Contract Requirements

a. NEW WORK

b. REPAIR/OTHER

Yes No

Yes No

E: QUALITY

CONTROL

1. SPECIFIC TASK ORDER QUALITY CONTROL, ISO

9001-2000 (in the original contract)

2. ABATEMENT PLAN FOR CONTAMINATED

MATERIAL

3. OTHER SPECIAL CONSTRAINTS

Yes No

Yes No

Yes No

F: CURRENT

REGULATIONS

1. DIN STANDARD FOR THIS SPECIFIC TASK

ORDER

2. OTHER REGULATIONS VDE,VDS

Yes No

G: ATTACHMENT

ONE

1. MAGNITUDE (SELECT ONE VALUE ONLY)

2. STATUTORY COST LIMITATION: THE NEW

WORK PORTION OF THIS PROJECT IS

ESTIMATED TO BE BELOW THE CURRENT

VALID STATUTORY COST LIMITATION OF

3. LIQUIDATED DAMAGES ARE REQUESTED. THE

VALUE IS ATTACHED. MANDATORY OVER

$700,000.00.

4. WORK HOURS

Days

Weekend

US / German Holidays

5. RESTRICTED AREAS

6. GOVERNMENT FURNISHED PROPERTY

7. Work Clearance Report: AF IMT 103 is required. The contractor shall obtain the required form from the Ramstein Air Base.

Less than $25,000

Between $25,000 and $100,000

Between $100,000 and $250,000

Between $250,000 and $500,000

Between $500,000 and $1,000,000

Between $1,000,000 and $5,000,000

Yes No

There is only repair work involved

N/A

Yes No

Yes No

Yes No

$1,000,000.00

8. WELDING PERMIT: A welding permit is required. The contractor will obtain the form at the Ramstein Office .

9. UTILITY SHUT-DOWN: Utility interruption is required. Request must be submitted in writing to the C. O. at least 10 working days prior to proposed interruption.

10. TRAFFIC RESTRICTION

11. CRANE ERECTION / AIR TRAFFIC

INTERFERENCE

12. AIRFIELD CONSTRUCTION WAIVER

13. CONSTRUCTION / MATERIAL LAYDOWN AREA

14. AS-BUILT DRAWINGS

15. MAINTENANCE MANUALS (Due not later than final inspection)

Yes No

Yes No

Yes No

Yes No

Yes No

Yes No

Yes No

Yes No

H. OTHER

ATTACHMENTS

AS NEEDED

1. 700 CONS MATERIAL SUBMITTAL FORM 66

2. ELECTRONIC & PAPER DRAWINGS IAW THE

GENERAL REQUIREMENTS & PROVISIONS

Yes No

Ye No

I: Work Elements

1. Construction Effort Without Design Needed

2. Construction Effort With Design Package Provided

3. Partial Design-Build Effort

Yes

Yes

Yes

No

No

No

1285969251 Rectangle

1285969251 Rectangle

1285969251 Rectangle

1285969251 Line

1290858689U Typewritten Text s

1290858689U Typewritten Text

Titel: EIC-Convert to KC-135 Part Storage
Building: 2167
Lacation: Ramstein AB
Inspector: Mr. Thomas Wazulin
Proposed contract procedure: MACC
Calender days: 360
Latest end date: N/A
Exclusion period: N/A
Phases: 2
Check Box8:
0:
0: Yes
1:
1:
0:
3: No
1:
1: Yes
2:
0: Yes
3:
2: Yes
1: No
0: Yes

0: No

Check Box10:
1:
2:
1:
2: Yes
0: No
2:
2: No

3: Yes

2:
2: No
3:
3: Off
0:
1:
0:
0: 3
Work hours: From 0600 to 1800
Check Box13:
0:
1:
0:
1:
0:
0: Yes
1:
0: Yes
10: No
11: No
12: Yes

0: No

1:
0: Yes
1: Yes
2:
0: Yes

0: Yes

1:
2: No
0: Yes
2:
1: No

Project: TYFR18-1047