Consolidated_Q&A__6.pdf
PDF 43 KB Posted
- Attached to
- Multiple Award Construction Contract (MACC) Federal contract opportunity
- Solicitation number
- FA5613-19-R-0003
About this file
This document contains a consolidated question and answer file and a description of a federal contract opportunity for a Multiple Award Construction Contract on various military installations in Germany. The consolidated Q&A file addresses technical, cost, and past performance questions from offerors regarding requirements for the MACC solicitation such as construction phasing and quality control plans. The federal contract opportunity notice provides details about solicitation number FA5613-19-R-0003, including that the Air Force intends to award up to five IDIQ contracts plus two additional on-ramp contracts for design-build, sustainment, maintenance, alteration, repair, renovation, and minor construction projects across Ramstein and Spangdahlem Air Bases. The estimated total value of task orders over the five-year ordering period is $425 million, with individual task orders ranging from $1,000 to $5 million. The anticipated solicitation release date is November 1, 2018 and the proposal receipt date is December 1, 2018.
View the file
Other files for this federal contract opportunity
Show all 50
Multiple Award Construction Contract (MACC) has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Consolidated Q&A #6 Multiple Award Construction Contract (MACC)
FA5613-19-R-0003
K – Contracting C – Cost/Pricing T- Technical P – Past Perf.
Solicitation/A ttachment Reference
Cross Reference Discussion/Comment/Question Government Response
T-01 SOW 1.5.2.8 Construction Phasing
The SOW mentions “individual phase durations should be considered only in developing the Government’s proposed overall contract duration.” Please confirm that the Government is looking for a time durations for phases or major elements of work (i.e. 3 months) as part of the Construction Phase-In Plan for the proposal deliverable.
The construction phasing diagram shall not indicate durations. Durations shall only be considered for the overall contract duration. See
SOW 1.3.
T-02 SOW 1.5.2.8 Construction Phasing
Can the Government please clarify their definition of a Swing Space Duration?
Swing Space Duration describes for how long the occupants of the bldg. have to be relocated to another bldg., if necessary.
T-03
L.4.3.2 Subfactor 2- Quality Management Plan
Quality Control Plan
Please provide Offerors with the specification/standard that governs design quality control measures being sought for this effort
The quality control plan is not based on a specification or standard. It is an 86 CES/CEN internal requirement.
Correction on Q&A #5, T-07
Amendment 1 Attachment 3g Shelf Layouts & Dimensions
Offerors request the Government provide additional information about the depth of the shelves.
On Q&A #5, T-07, the Government provided the answer to this question with:
Type A: 60cm Type B: 50cm Type C: 75cm
However, the information for the Type B and C were erroneously switched. The correct shelf depth measurements are as follows:
Type A: 60cm Type B: 75cm Type C: 50cm
We apologize for the errors.
Consolidated Q&A #6 Multiple Award Construction Contract (MACC)