Attachment F Construction Cost Estimate Breakdown Form Dated 10 Feb 21.xlsx

XLSX spreadsheet 52 KB Posted

Attached to
Repair Runway Edges & Shoulders Federal contract opportunity
Solicitation number
FA557521R0001
Issued by
Department of the Air Force United States Air Forces in Europe - Air Forces Africa

About this file

This document provides a construction cost estimate breakdown template for the repair of runway edges and shoulders at Moron Air Base in Spain. The project value is estimated between $5 million and $10 million. A pre-proposal conference will be held on April 15, 2021, with questions due by April 20, 2021 and proposals due by April 30, 2021. The work requirements will be defined in the specifications and drawings. According to the Agreement of Defense Cooperation between the US and Spain, Spanish materials, labor and equipment must be utilized where feasible and consistent with requirements. No award will be made until funds are available, and the US Government reserves the right to cancel the solicitation.

View the file

Other files for this federal contract opportunity

Other files attached to Repair Runway Edges & Shoulders, newest first.
File Type Posted
FA5575-21-R-0001 Questions and Answers - 2.pdf PDF
Solicitation Amendment FA557521R00010003.pdf PDF
Solicitation Amendment FA557521R00010003 SF30.pdf PDF
FA5575-21-R-0001 Questions and Answers.pdf PDF
Solicitation Amendment FA557521R00010002 SF30.pdf PDF
Solicitation Amendment FA557521R00010002.pdf PDF
Solicitation Amendment FA557521R00010001.pdf PDF
Attachment D Concept Drawings Dated 15 Dec 20.pdf PDF
Solicitation Amendment FA557521R00010001 SF30.pdf PDF
Attachment J Schedule of Material Submittals Form.xlsx XLSX spreadsheet
Attachment B Integrated Natural Resources Management Plan for Moron Air Base Jun 2015.pdf PDF
Attachment A Asphalt Coring Report of Runway Edges and Shoulders.pdf PDF
Statement of Work English.pdf PDF
Attachment F Construction Cost Estimate Breakdown Form.xlsx XLSX spreadsheet
Attachment E Record Drawings.pdf PDF
Attachment D Concept Drawings.pdf PDF
Attachment I Airfield Construction Requirements Checklist Form.pdf PDF
Attachment G Request for Waiver to Airfield and Airspace Criteria Form.pdf PDF
Attachment C Environmental Final Governing Standards for Spain May 2014.pdf PDF
Attachment H Deliberate Risk Assessment Worksheet.pdf PDF
Solicitation FA557521R0001.pdf PDF
Show all 21

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Summary

CONSTRUCTION COST ESTIMATE BREAKDOWN
CONTRACTORADDRESS
CONTRACT FOR (Work to be performed)PROPOSED CONTRACT PRICE
RPR RUNWAY EDGES & SHOULDERS, MULTI / REPARAR FRANJAS EXTERIORES Y MÁRGENES DE PISTA, MULTI
PURCHASE REQUEST NUMBERPROJECT NUMBERWORK LOCATION
QUUG 19-1006MORÓN AIR BASE, SPAIN
LINE
NO.ITEMTOTAL COST ESTIMATE
(1)(€)
SUMMARY

RESUMEN

BASE BID

OFERTA BASE

TOTAL DESIGN INCLUDING OVERHEAD AND PROFIT

TOTAL DISEÑO INCLUYENDO GASTOS GENERALES Y BENEFICIO

TOTAL CONSTRUCTION INCLUDING OVERHEAD AND PROFIT

TOTAL CONSTRUCCIÓN INCLUYENDO GASTOS GENERALES Y BENEFICIO

TOTAL BASE BID

TOTAL OFERTA BASE

OPTION BID 1

OFERTA OPCIÓN 1

TOTAL DESIGN INCLUDING OVERHEAD AND PROFIT

TOTAL DISEÑO INCLUYENDO GASTOS GENERALES Y BENEFICIO

TOTAL CONSTRUCTION INCLUDING OVERHEAD AND PROFIT

TOTAL CONSTRUCCIÓN INCLUYENDO GASTOS GENERALES Y BENEFICIO

TOTAL OPTION BID 1

TOTAL OFERTA OPCION 1

OPTION BID 2

OFERTA OPCIÓN 2

TOTAL DESIGN INCLUDING OVERHEAD AND PROFIT

TOTAL DISEÑO INCLUYENDO GASTOS GENERALES Y BENEFICIO

TOTAL CONSTRUCTION INCLUDING OVERHEAD AND PROFIT

TOTAL CONSTRUCCIÓN INCLUYENDO GASTOS GENERALES Y BENEFICIO

TOTAL OPTION BID 2

TOTAL OFERTA OPCION 2

TOTAL GENERAL

GRAND TOTAL

TOTAL GENERAL

GRAND TOTAL

&"Times New Roman,Regular"&P of &N

Base Bid Design

CONSTRUCTION COST ESTIMATE BREAKDOWN
CONTRACTORADDRESS
CONTRACT FOR (Work to be performed)PROPOSED CONTRACT PRICE
RPR RUNWAY EDGES & SHOULDERS, MULTI / REPARAR FRANJAS EXTERIORES Y MÁRGENES DE PISTA, MULTI
PURCHASE REQUEST NUMBERPROJECT NUMBERWORK LOCATION
QUUG 19-1006MORÓN AIR BASE, SPAIN
LINE
NO.ITEMQUANTITYMATERIAL COSTLABOR COSTTOTAL LINE COST
UNIT OF
MEASUREUNIT
NUMBERUNIT COSTTOTAL
COSTUNIT COSTTOTAL

COST

(1)(2)(3)(4)(5)(6)(7)(8)
BASIC BID DESIGN

DISEÑO DE OFERTA BASE

PROJECT DESIGN SERVICES

SERVICIOS DE REDACCIÓN DE PROYECTO

135% Design submission
Presentación del 35% del diseñoJob
265% Design submission
Presentación del 65% del diseñoJob
395% Design submission
Presentación del 95% del diseñoJob
4100% Design submission
Presentación del 100% del diseñoJob
TOTAL BASE BID DESIGN

TOTAL DISEÑO DE OFERTA BASE

TOTAL MATERIAL COST
TOTAL LABOR COST
TOTAL MATERIAL EXECUTION COST
OVERHEAD%
PROFIT%
TOTAL COST ESTIMATE

DATE: FIRM NAME:

TITLE: BY:

These costs and overhead and profit percentages will be applied in any possible future modifications

Base Bid Construction

CONSTRUCTION COST ESTIMATE BREAKDOWN
CONTRACTORADDRESS
CONTRACT FOR (Work to be performed)PROPOSED CONTRACT PRICE
RPR RUNWAY EDGES & SHOULDERS, MULTI / REPARAR FRANJAS EXTERIORES Y MÁRGENES DE PISTA, MULTI
PURCHASE REQUEST NUMBERPROJECT NUMBERWORK LOCATION
QUUG 19-1006MORÓN AIR BASE, SPAIN
LINE
NO.ITEMQUANTITYMATERIAL COSTLABOR COSTTOTAL LINE COST
UNIT OF
MEASUREUNIT
NUMBERUNIT COSTTOTAL
COSTUNIT COSTTOTAL

COST

(1)(2)(3)(4)(5)(6)(7)(8)
BASE BID CONSTRUCTION

CONSTRUCCIÓN DE OFERTA BASE

CIVIL WORK

OBRA CIVIL

1Installation of temporary barriers
Instalación de barreras temporalesm
2Obscuring of the permanent airfield markings
Oscurecimiento de las marcas permanentes del aeródromom2
3Painting of the temporary airfield markings
Pintado de las marcas temporales del aeródromom2
4Double saw cut of the joints
Corte doble de juntasm
5Milling of the entire thickness of the asphalt courses
Fresado de todo el espesor de las capas de asfaltom2 x cm
6Scarification, addition, removal, grading and compaction of the base course material
Escarificación, adición, retirada, nivelación y compactación de material de la capa basem3
7Application of curing coat
Aplicación de riego de curadot
8Application of prime coat
Aplicación de riego de imprimaciónt
9Placing and compaction of the intermediate asphalt course
Extendido y compactación de capa de asfalto intermediat
10Application of tack coat
Aplicación de riego de adherenciat
11Placing and compaction of the surface asphalt course
Extendido y compactación de capa de asfalto de rodadurat
12Sealing of the construction joints
Sellado de juntas de construcciónm
13Removal of the temporary painted airfield markings with high pressure water
Retirada de las temporales marcas pintadas del aeródromo con agua a alta presiónm2
14Painting of the permanent markings
Pintado de marcas permanentesm2
15Removal of the temporary barriers
Retirada de barreras temporalesm
TOTAL CIVIL WORK

TOTAL OBRA CIVIL

ELECTRIC WORK

TRABAJOS ELÉCTRICOS

16Installation of temporary unserviceability lights
Instalación de luces fuera de servicio temporalesLS
17Disconnection, modification, disassembly, hiding, removal and/or turning off of the permanent airfield lights
Desconexión, modificación, desensamblaje, ocultación, retirada y/o apagado de las luces permanentes del aeródromou
18Connection, installation and/or turning on of the temporary airfield lights
Conexión, instalación y/o encendido de luces temporales del aeródromoLS
19Disconnection, modification, disassembly, hiding, removal and/or turning off of the permanent airfield signs
Desconexión, modificación, desensamblaje, ocultación, retirada y/o apagado de los letreros permanentes del aeródromoLS
20Connection, installation and/or turning on of the temporary airfield signs
Conexión, instalación y/o encendido de los letreros temporales del aeródromoLS
21Disconnection, disassembly, removal and/or turning off of the temporary airfield signs
Desconexión, desensamblaje, retirada y/o apagado de los letreros temporales del aeródromoLS
22Connection, modification, assembly, installation and/or turning on of the permanent airfield signs
Conexión, modificación, ensamblaje, instalación y/o encendido de los letreros permanentes del aeródromoLS
23Disconnection, disassembly, removal and/or turning off of the temporary airfield lights
Desconexión, desensamblaje, retirada y/o apagado de las luces temporales del aeródromoLS
24Connection, modification, assembly, installation and/or turning on of the permanent airfield lights
Conexión, modificación, ensamblaje, instalación, y/o encendido de las luces permanentes del aeródromou
25Removal of the temporary unserviceability lights
Retirada de temporales luces de fuera de servicioLS
TOTAL ELECTRIC WORK

TOTAL TRABAJOS ELÉCTRICOS

SUMMARY

RESUMEN

TOTAL CIVIL WORK

TOTAL OBRA CIVIL

TOTAL ELECTRIC WORK

TOTAL TRABAJOS ELÉCTRICOS

TOTAL BASE BID CONSTRUCTION

TOTAL CONSTRUCCIÓN DE OFERTA BASE

TOTAL MATERIAL COST
TOTAL LABOR COST
TOTAL MATERIAL EXECUTION COST
OVERHEAD%
PROFIT%
TOTAL COST ESTIMATE

DATE: FIRM NAME:

TITLE: BY:

These costs and overhead and profit percentages will be applied in any possible future modifications

Option Bid 1 Design

CONSTRUCTION COST ESTIMATE BREAKDOWN
CONTRACTORADDRESS
CONTRACT FOR (Work to be performed)PROPOSED CONTRACT PRICE
RPR RUNWAY EDGES & SHOULDERS, MULTI / REPARAR FRANJAS EXTERIORES Y MÁRGENES DE PISTA, MULTI
PURCHASE REQUEST NUMBERPROJECT NUMBERWORK LOCATION
QUUG 19-1006MORÓN AIR BASE, SPAIN
LINE
NO.ITEMQUANTITYMATERIAL COSTLABOR COSTTOTAL LINE COST
UNIT OF
MEASUREUNIT
NUMBERUNIT COSTTOTAL
COSTUNIT COSTTOTAL

COST

(1)(2)(3)(4)(5)(6)(7)(8)
OPTION BID 1 DESIGN

DISEÑO DE OFERTA OPCIÓN 1

PROJECT DESIGN SERVICES

SERVICIOS DE REDACCIÓN DE PROYECTO

135% Design submission
Presentación del 35% del diseñoJob
265% Design submission
Presentación del 65% del diseñoJob
395% Design submission
Presentación del 95% del diseñoJob
4100% Design submission
Presentación del 100% del diseñoJob
TOTAL OPTION BID 1 DESIGN

TOTAL DISEÑO DE OFERTA OPCIÓN 1

TOTAL MATERIAL COST
TOTAL LABOR COST
TOTAL MATERIAL EXECUTION COST
OVERHEAD%
PROFIT%
TOTAL COST ESTIMATE

DATE: FIRM NAME:

TITLE: BY:

These costs and overhead and profit percentages will be applied in any possible future modifications

Option Bid 1 Construction

CONSTRUCTION COST ESTIMATE BREAKDOWN
CONTRACTORADDRESS
CONTRACT FOR (Work to be performed)PROPOSED CONTRACT PRICE
RPR RUNWAY EDGES & SHOULDERS, MULTI / REPARAR FRANJAS EXTERIORES Y MÁRGENES DE PISTA, MULTI
PURCHASE REQUEST NUMBERPROJECT NUMBERWORK LOCATION
QUUG 19-1006MORÓN AIR BASE, SPAIN
LINE
NO.ITEMQUANTITYMATERIAL COSTLABOR COSTTOTAL LINE COST
UNIT OF
MEASUREUNIT
NUMBERUNIT COSTTOTAL
COSTUNIT COSTTOTAL

COST

(1)(2)(3)(4)(5)(6)(7)(8)
OPTION BID 1 CONSTRUCTION

CONSTRUCCIÓN DE OFERTA OPCIÓN 1

CIVIL WORK

OBRA CIVIL

1Double saw cut of the joints
Corte doble de juntasm
2Milling of the entire thickness of the asphalt courses
Fresado de todo el espesor de las capas de asfaltom2 x cm
3Replacement of the rigid pavements with flexible pavements
Sustitución de firmes rígidos por firmes flexiblesm3
4Scarification, addition, removal, grading and compaction of the base course material
Escarificación, adición, retirada, nivelación y compactación de material de la capa basem3
5Application of curing coat
Aplicación de riego de curadot
6Application of prime coat
Aplicación de riego de imprimaciónt
7Placing and compaction of the intermediate asphalt course
Extendido y compactación de capa de asfalto intermediat
8Application of tack coat
Aplicación de riego de adherenciat
9Placing and compaction of the surface asphalt course
Extendido y compactación de capa de asfalto de rodadurat
10Sealing of the construction joints
Sellado de juntas de construcciónm
TOTAL CIVIL WORK

TOTAL OBRA CIVIL

ELECTRIC WORK

TRABAJOS ELÉCTRICOS

11Disconnection, modification, disassembly, hiding, removal and/or turning off of the permanent airfield lights and their frangible couplings located within both 304.8-meter ends of RWY 02/20
Desconexión, modificación, desensamblaje, ocultación, retirada y/o apagado de las luces permanentes del aeródromo y sus acoplamientos frangibles situadas en los primeros 304.8 m de RWY 02/20u
12Connection, modification, assembly, installation and/or turning on of the permanent airfield lights located within both 304.8-m ends of RWY 02/20
Conexión, modificación, ensamblaje, instalación y/o encendido de luces permanentes situadas en los primeros 304.8 m de RWY 02/20u
TOTAL ELECTRIC WORK

TOTAL TRABAJOS ELÉCTRICOS

SUMMARY

RESUMEN

TOTAL CIVIL WORK

TOTAL OBRA CIVIL

TOTAL ELECTRIC WORK

TOTAL TRABAJOS ELÉCTRICOS

TOTAL OPTION BID 1 CONSTRUCTION

TOTAL CONSTRUCCIÓN DE OFERTA OPCIÓN 1

TOTAL MATERIAL COST
TOTAL LABOR COST
TOTAL MATERIAL EXECUTION COST
OVERHEAD%
PROFIT%
TOTAL COST ESTIMATE

DATE: FIRM NAME:

TITLE: BY:

These costs and overhead and profit percentages will be applied in any possible future modifications

Option Bid 2 Design

CONSTRUCTION COST ESTIMATE BREAKDOWN
CONTRACTORADDRESS
CONTRACT FOR (Work to be performed)PROPOSED CONTRACT PRICE
RPR RUNWAY EDGES & SHOULDERS, MULTI / REPARAR FRANJAS EXTERIORES Y MÁRGENES DE PISTA, MULTI
PURCHASE REQUEST NUMBERPROJECT NUMBERWORK LOCATION
QUUG 19-1006MORÓN AIR BASE, SPAIN
LINE
NO.ITEMQUANTITYMATERIAL COSTLABOR COSTTOTAL LINE COST
UNIT OF
MEASUREUNIT
NUMBERUNIT COSTTOTAL
COSTUNIT COSTTOTAL

COST

(1)(2)(3)(4)(5)(6)(7)(8)
OPTION BID 2 DESIGN

DISEÑO DE OFERTA OPCIÓN 2

PROJECT DESIGN SERVICES

SERVICIOS DE REDACCIÓN DE PROYECTO

135% Design submission
Presentación del 35% del diseñoJob
265% Design submission
Presentación del 65% del diseñoJob
395% Design submission
Presentación del 95% del diseñoJob
4100% Design submission
Presentación del 100% del diseñoJob
TOTAL OPTION BID 2 DESIGN

TOTAL DISEÑO DE OFERTA OPCIÓN 2

TOTAL MATERIAL COST
TOTAL LABOR COST
TOTAL MATERIAL EXECUTION COST
OVERHEAD%
PROFIT%
TOTAL COST ESTIMATE

DATE: FIRM NAME:

TITLE: BY:

These costs and overhead and profit percentages will be applied in any possible future modifications

Option Bid 2 Construction

CONSTRUCTION COST ESTIMATE BREAKDOWN
CONTRACTORADDRESS
CONTRACT FOR (Work to be performed)PROPOSED CONTRACT PRICE
RPR RUNWAY EDGES & SHOULDERS, MULTI / REPARAR FRANJAS EXTERIORES Y MÁRGENES DE PISTA, MULTI
PURCHASE REQUEST NUMBERPROJECT NUMBERWORK LOCATION
QUUG 19-1006MORÓN AIR BASE, SPAIN
LINE
NO.ITEMQUANTITYMATERIAL COSTLABOR COSTTOTAL LINE COST
UNIT OF
MEASUREUNIT
NUMBERUNIT COSTTOTAL
COSTUNIT COSTTOTAL

COST

(1)(2)(3)(4)(5)(6)(7)(8)
OPTION BID 2 CONSTRUCTION

CONSTRUCCIÓN DE OFERTA OPCIÓN 2

CIVIL WORK

OBRA CIVIL

1Compaction of the soil used for the filling in of the trenches exposed after the removal of the electric conduits of the runway edge lights located outside the shoulders within both 304.8-meter ends of RWY 02/20
Compactación de terreno utilizado para el relleno de las zanjas abiertas tras la retirada de las conducciones eléctricas de las luces de borde de pista situadas fuera de los márgenes en ambos primeros 304.8 m de RWY 02/20m3
TOTAL CIVIL WORK

TOTAL OBRA CIVIL

ELECTRIC WORK

TRABAJOS ELÉCTRICOS

2Deduction for the disconnection, modification, disassembly, hiding, removal and/or turning off of the permanent airfield lights and their frangible couplings located within both 304.8-meter ends of RWY 02/20 (included in Option Bid 1)
Deducción por la desconexión, modificación, desensamblaje, ocultación, retirada y/o apagado de las luces permanentes del aeródromo y sus acoplamientos frangibles situadas en los primeros 304.8 m de RWY 02/20 (incluido en la Oferta Opción 1)u
3Deduction for the connection, modification, assembly, installation and/or turning on of the permanent airfield lights located within both 304.8-m ends of RWY 02/20 (included in Option bid 1)
Deducción por conexión, modificación, ensamblaje, instalación y/o encendido de luces permanentes situadas en los primeros 304.8 m de RWY 02/20 (incluido en la Oferta Opción 1)u
4Disconnection, disassembly and removal of the elevated runway edge lights and their frangible couplings located within both 304.8-m ends of RWY 02/20
Desconexión, desensamblaje y retirada de luces de borde de pista y acoplamientos frangibles situados en ambos primeros 304.8 m de RWY 02/20u
5Disconnection, modification, disassembly, hiding, removal and/or turning off of the other permanent airfield lights located within both 304.8-meter ends of RWY 02/20
Desconexión, modificación, desensamblaje, ocultación, retirada y/o apagado de las otras luces permanentes del aeródromo situadas en ambos primeros 304.8 m de RWY 02/20u
6Removal of secondary leads of runway edge light transformers in manholes located outside the shoulders within both 304.8-meter ends of RWY 02/20
Retirada de cables secundarios de los transformadores de luces de borde pista situados fuera de los márgenes en ambos primeros 304.8 m de RWY 02/20u
7Removal of runway edge lights isolating transformers in manholes located outside the shoulders within both 304.8-meter ends of RWY 02/20
Retirada de los transformadores de aislamiento de las luces de borde pista en arquetas situadas fuera de los márgenes en ambos primeros 304.8 m de RWY 02/20u
8Installation of the new concrete embedded electrical conduits of the semi-flush runway edge lights located within both 304.8-meter ends of RWY 02/20 including demolition of existing installation
Instalación de conducciones eléctricas reforzadas con hormigón de las luces de superficie de borde de pista situadas en ambos primeros 304.8 m de RWY 02/20 incluyendo demolición de instalación existenteu
9Installation of the FAA type L-868 standard deep bases of the semi-flush runway edge lights located within both 304.8-meter ends of RWY 02/20
Instalación de bases de profundidad estándar tipo L-868 FAA de las luces de superfricie de borde de pista situadas en ambos primeros 304.8 m de RWY 02/20u
10Installation of new secondary lead cables for new semi-flush runway lights, from existing manholes located outside the shoulders, including appropriate FAA type L-823 connectors
Instalación de nuevos cables de conductores secundarios para las nuevas luces de superficie, desde las arquetas existentes situadas fuera de los márgenes, incluyendo los conectores apropiados tipo L-823 FAAu
11Installation of new FAA type L-830 transformers for new semi-flush runway edge lights
Instalación de nuevos transformadores tipo L-830 FAA para las nuevas luces de superficie de borde de pistau
12Installation of the new FAA type L-850C semi-flush runway edge lights located within both 304.8-meter ends of RWY 02/20
Instalación de nuevas luces de superficie de borde de pista tipo L-850C FAA situadas en ambos primeros 304.8 m de RWY 02/20u
13Connection, modification, assembly, installation and/or turning on of the other permanent airfield lights located within both 304.8-m ends of RWY 02/20
Conexión, modificación, ensamblaje, instalación y/o encendido de las otras luces permanentes del aeródromo situadas en ambos primeros 304.8 m de RWY 02/20u
TOTAL ELECTRIC WORK

TOTAL TRABAJOS ELÉCTRICOS

SUMMARY

RESUMEN

TOTAL CIVIL WORK

TOTAL OBRA CIVIL

TOTAL ELECTRIC WORK

TOTAL TRABAJOS ELÉCTRICOS

TOTAL OPTION BID 2 CONSTRUCTION

TOTAL CONSTRUCCIÓN DE OFERTA OPCIÓN 2

TOTAL MATERIAL COST
TOTAL LABOR COST
TOTAL MATERIAL EXECUTION COST
OVERHEAD%
PROFIT%
TOTAL COST ESTIMATE

DATE: FIRM NAME:

TITLE: BY:

These costs and overhead and profit percentages will be applied in any possible future modifications

Instructions

INSTRUCTIONS FOR COMPLETING CONSTRUCTION COST ESTIMATE BREAKDOWN

Column 1 - Item. Description of materials required, work to be done, special equipment needed, etc. Breakdown should be in sufficient detail to permit itemizing of all direct costs. Items will be furnished by the Government.

Column 2 - Units of Measure. Description of the unit in which each item is to be estimated (examples: square meters - m2, cubic meters - m3, linear meters - m, unit - u, kilograms - kg, ton - t). Units of measure will be furnished by the Government.

Column 3 - Quantity. Quantity required for the item in terms of unit of measure shown on Column 2. Quantity will be furnished by the Government only for unit price contract. Otherwise, the contractor is responsible for determining the quantity.

Column 4 and 5 - Material Costs. Enter the unit cost of the material corresponding to the item to be supplied in Column 4 and the total material cost for that item in Column 5. Cost must be in euros.

Column 6 and 7 - Labor Costs. Enter the unit cost of the labor corresponding to the item to be performed in Column 6 and the total labor cost for that item in Column 7. Costs must be in euros.

Column 8 - Total Line Cost. Enter the sum of the total material cost and the total labor cost of the item to be performed. Cost must be in euros.

NOTE: In addition to other totals derived on various pages, the grand total of Column 5, 7 and 8, plus overhead and profit will be shown on the last page. Overhead and profit must be applied over the total material execution.

INSTRUCTIONS TO OFFERORS

1. The purpose of this form is to provide a standard format by which the offeror submits to the Government a summary of incurred and estimated costs (and attached supporting information) suitable for detailed review and analysis. Prior to the award of a contract resulting from this proposal, the offeror may be required to submit a certificate of current cost or pricing data.

2. In addition to the specific information required by this form, the offeror is expected, in good faith, to incorporate in and submit with this form any additional data, supporting schedules, or substantiation which are reasonable, required for the conduct of an appropriate review and analysis in the light of the specific facets of this procurement. For effective negotiations, it is essential that there be a clear understanding of:

a. The existing and verifiable data.

b. The judgmental factors applied in projecting from known data to the estimate, and

c. The contingencies used by the offeror in his proposed price.

In short, the offeror's estimating process itself needs to be disclosed.

3. When attachment of supporting cost or pricing data to this form is impracticable, the data will be described (with schedules as appropriate), and made available to the contracting officer or his authorized representative, upon request.

4. By submission of this proposal the offeror grants to the contracting officer or his authorized representative the right to examine, for the purpose of verifying the cost or pricing data submitted, those books, records, documents and other supporting data which will permit adequate evaluation of such cost or pricing data, along with the computations and projections used therein. This right may be exercised in connection with any negotiations prior to contract award.

File details come from the government source that posted it. Updated .