This document contains a schedule of material submittals form and details for a federal contract opportunity to repair runway edges and shoulders at Moron Air Base in Spain. The form lists over a dozen required submittals grouped under general conditions and small project design-build categories, including a warranty letter, construction schedule, progress schedule, work plan, mobility plan, project sign, quality control plan, environmental protection plan, waste management plan, as-built drawings, key staff, and health and safety plan. The opportunity notice seeks proposals for the $5-10 million runway repair project to be received by 1300 hours local time on April 30, 2021. The work will be governed by specifications and drawings from a pre-proposal site visit on April 15, 2021, and Spanish materials, labor, and equipment must be used where feasible and consistent with requirements. No award will be made until funds are available, and the government reserves the right to cancel the solicitation.

View the file

Other files for this federal contract opportunity

Other files attached to Repair Runway Edges & Shoulders, newest first.
File Type Posted
FA5575-21-R-0001 Questions and Answers - 2.pdf PDF
Solicitation Amendment FA557521R00010003.pdf PDF
Solicitation Amendment FA557521R00010003 SF30.pdf PDF
FA5575-21-R-0001 Questions and Answers.pdf PDF
Solicitation Amendment FA557521R00010002 SF30.pdf PDF
Solicitation Amendment FA557521R00010002.pdf PDF
Solicitation Amendment FA557521R00010001.pdf PDF
Attachment D Concept Drawings Dated 15 Dec 20.pdf PDF
Solicitation Amendment FA557521R00010001 SF30.pdf PDF
Attachment F Construction Cost Estimate Breakdown Form Dated 10 Feb 21.xlsx XLSX spreadsheet
Attachment E Record Drawings.pdf PDF
Attachment D Concept Drawings.pdf PDF
Attachment B Integrated Natural Resources Management Plan for Moron Air Base Jun 2015.pdf PDF
Attachment A Asphalt Coring Report of Runway Edges and Shoulders.pdf PDF
Statement of Work English.pdf PDF
Attachment F Construction Cost Estimate Breakdown Form.xlsx XLSX spreadsheet
Solicitation FA557521R0001.pdf PDF
Attachment I Airfield Construction Requirements Checklist Form.pdf PDF
Attachment G Request for Waiver to Airfield and Airspace Criteria Form.pdf PDF
Attachment C Environmental Final Governing Standards for Spain May 2014.pdf PDF
Attachment H Deliberate Risk Assessment Worksheet.pdf PDF
Show all 21

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Material Submittals Schedule

SCHEDULE OF MATERIAL SUBMITTALSPROJECT NUMBER
QUUG 19-1006PROJECT TITLE

RPR RUNWAY EDGES & SHOULDERS, MULTI

SOLICITATION / CONTRACT NO.

(To be completed by Project Engineer)(To be completed by Contract Administrator)
NUMBER OF COPIES REQUIRED
LINE NUMBERITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTALCERTIFICATION OF COMPLIANCESHOP DRAWINGSSAMPLESCOLOR SELECTIONMANUFACTURER'S RECOMMENDATIONMANUFACTURER'S WARRANTYCATALOG DATAOPERATING INSTRUCTIONSSCHEDULES, LISTINGS, REPORTS, PLANSTECHNICAL DATATEST REPORTSFIELD REPORTSREQUIRED SUBMISSION DATE

fergusog: Enter the due date from the Contractor (MM/DD/YY)

DATE RECEIVED IN CONTRACTING

fergusog: Enter the date received from the Contractor. (MM/DD/YY)

DATE TO CIVIL ENGINEERING

fergusog: Enter the date submittal was given to CE for review. (MM/DD/YY)

RETURN SUSPENSE DATE

fergusog: Enter the date the submittal is due back from CE

(MM/DD/YY)

SUBMITTAL NUMBERS

fergusog: Enter the Submittal Number

DATE CONTRACTOR NOTIFIED CONTRACTOR RESUBMITTAL

fergusog: Enter Resubmittal Number

FINAL APPROVAL

fergusog: Enter the submittal final approval date

(MM/DD/YY)

REMARKS

fergusog: Enter any comments pertaining to the submittal

APPROVED

fergusog: Enter date the Contractor was notified of submittal approval

(MM/DD/YY)

fergusog: Enter Resubmittal Number

DISAPPROVED

fergusog: Enter date the Contractor was notified of submittal disapproval

(MM/DD/YY)

fergusog: Enter the submittal final approval date

(MM/DD/YY)

fergusog: Enter any comments pertaining to the submittal

PART 12 - GENERAL CONDITIONS
01Warranty Letter1Acceptance+15
02Construction ScheduleCNTP+7
03Progress Schedule1CNTP+10
04Work PlanCNTP+7
05Mobility Plan1CNTP+15
06Project SignCNTP+15
07Quality Control Plan1CNTP+15
08Environmental Protection Plan1CNTP+15
09Waste & Debris Certificate1CNTP+15
10As-Built Drawings1Acceptance+15
11DD Form 13541Acceptance+15
12As-Built Spatial Data1As Built Drawings+10
13Key Staff1DNTP+15
14Health and Safety Plan1CNTP +15
PART 13 - SMALL PROJECT DESIGN-BUILD PROGRESS SCHEDULES
15Design-Build Schedule1DNTP+10
16Monthly Updates1Every 1st of month
A-E firm shall complete list of submittals when developing final construction specifications, including those outlined in the Performance Technical Specifications provided with the SOW

&"Arial,Bold"&8Schedule of Material Submittals, Feb 05 (SAF/AQCP) Page &P of &N