FA520521R00030004_Atch2_Addendum No 2.pdf

PDF 229 KB Posted

Attached to
Project No. 1090686, Hospital Modernization Misawa Air Base, Japan
Solicitation number
FA520521R0003
Issued by

About this file

This addendum modifies the solicitation for Project No. 1090686, Hospital Modernization at Misawa Air Base in Japan. The addendum revises specifications and drawings to update hazardous materials handling procedures and fire resistance requirements. It removes one specification on asbestos and adds or revises notes on several drawings. The work includes renovating and upgrading the hospital building for the Department of the Air Force's Pacific Air Forces. The prime contractor must incorporate the changes to the specifications and drawings into their proposal.

View the file

Other files

File Type Posted
FA520521R00030004.pdf PDF
FA520521R00030004_Atch3_Revised Specifications.pdf PDF
FA520521R00030004_Atch1_Consolidated List of Govt Response.pdf PDF
FA520521R00030004_Atch5_Revised Soliciation Page 1 and 21.pdf PDF
FA520521R00030004_Atch4_Revised Drawing Sheets.pdf PDF
FA520521R00030003_Atch2_Revised Soliciation Page 1 and 21.pdf PDF
FA520521R00030003.pdf PDF
FA520521R00030002_Atch2_Revised Specifications.pdf PDF
FA520521R00030002_Atch7_Revised Soliciation Page 1 and 21.pdf PDF
FA520521R00030002_Atch5_Revised Cut Sheets for JSN S0442 and S0960.pdf PDF
FA520521R00030002_Atch6_Consolidated List of Govt Response.pdf PDF
FA520521R00030002_Atch3_Revised Drawing Sheets.pdf PDF
FA520521R00030002.pdf PDF
FA520521R00030002_Atch1_Addendum No 1.pdf PDF
FA520521R00030002_Atch4_Revised Submittal Register.pdf PDF
FA520521R00030001.pdf PDF
Atch2_Drawings_PDF3of10_Structural.pdf PDF
Atch2_Drawings_PDF8of10_Plumbing.pdf PDF
Atch7-2_Structural Interior Design Volume 1 thru 3.pdf PDF
Atch2_Drawings_PDF6of10_Equipment.pdf PDF
RFP FA520521R0003_Hospital Modernization.pdf PDF
Atch2_Drawings_PDF4of10_Architectural.pdf PDF
Atch6_List of Contractor Furnished US Material.pdf PDF
Atch7-3_Mobile Sterile Processing Department Trailer Information.pdf PDF
Atch9_Past Performance Questionnaire Cover Letter.pdf PDF
Atch1_Specifications_Volume 2 of 2.pdf PDF
Atch2_Drawings_PDF10of10_Electrical.pdf PDF
Atch2_Drawings_PDF7of10_FireProtection.pdf PDF
Atch4_Construction Timeline.pdf PDF
Atch1_Specifications_Volume 1 of 2.pdf PDF
Atch2_Drawings_PDF2of10_Civil.pdf PDF
Atch2_Drawings_PDF1of10_General.pdf PDF
Atch8_Hazardous Material Survey Report.pdf PDF
Atch2_Drawings_PDF9of10_Mechanical.pdf PDF
Atch7-1_Equipment Data and Cut Sheets Logistics Category A.pdf PDF
Atch3_Other Contract Requirements.pdf PDF
Atch2_Drawings_PDF5of10_Interiors.pdf PDF
Atch5_Submittal Register.pdf PDF
Atch10_Past Performance Questionnaire.docx DOCX document
Show all 39

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ADDENDUM NO. 2

FOR

PROJECT NO. 1090686

HOSPITAL MODERNIZATION, MISAWA AIR BASE, JAPAN

Date: 21 May 21

Perform the work required by the Contract Documents in accordance with the following revisions made as noted below.

1. Changes in Specifications:

Section Number Paragraph Description 01 57 20.00 10 1.1 Revised Reference Publications list 01 57 20.00 10 1.2.11.4 Revised Hazardous Materials paragraph 01 57 20.00 10 1.2.11.6 Revised Hazardous Materials paragraph 01 57 20.00 10 1.7.3.c Revised Hazardous Materials paragraph 01 57 20.00 10 1.7.3.d(3) Revised Hazardous Materials paragraph 01 57 20.00 10 2.1.a, b, c Revised Hazardous Materials paragraph 01 57 20.00 10 2.1.f Revised Hazardous Materials paragraph 01 57 20.00 10 3.6 Revised Hazardous Materials paragraph 01 57 20.00 10 3.17.2a, b Revised Hazardous Materials paragraph 01 57 20.00 10 3.17.3.b(2) Revised Hazardous Materials paragraph 01 57 20.00 10 3.17.3.c Revised Hazardous Materials paragraph 01 57 20.00 10 3.17.3.d(2) Revised Hazardous Materials paragraph 02 82 00 1.3.3.1 Revised section 02 82 00 1.3.9 Revised section 02 82 00 1.5.1 Revised section 02 82 00 3.1.6 Removed containers 02 82 00 3.1.6.2 Revised warning labels 02 84 33 Removed entire section

2. Changes in Drawings:

Sheet Identification Number

Description

AD100A Revised note 11, added note 20 AE101 Revised General Notes 4 & 5 AE100A Revised General Notes 4 & 5 AE101C-B1 Added ramp at SPD.

AD101A-C1 Revised note 11, added note 20 AE101A-C1 Revised General Notes 4 & 5 AE101A-C1.5 Revised General Notes 4 & 5 AD101A-C2 Revised note 11, added note 20 AE101A-C2 Revised General Notes 4 & 5 AE101A-C3 Revised General Notes 4 & 5 AD101A-C4 Revised note 11, added note 20 AE101A-C4 Revised General Notes 4 & 5 AD101A-C5 Revised note 11, added note 20 AE101A-C5 Revised General Notes 4 & 5 AD101C-D2 Revised note 11

Attachment 2 to

FA520521R00030004

AE101C-D2 Revised General Notes 4 & 5 AE121A Room Numbers Revised AE504 Added General Note: 15mm GWB, added note to detail A2 AE510 Added General Note: 15mm GWB AE601 Added General Note: 15mm GWB, revised solid fill notes AE602 Added General Note: 15mm GWB AE610 Revised door schedule IN101A Added recessed floor note SB102 Revised plan note to reference interior sheet.

GI005 Drawing A1/GI005: added rated walls to storage and mechanical rooms.

GI006 Drawing A2/GI006: revised rated wall.

GI007-C1 Drawing A1/GI007-C1: updated room tags to include room numbers.

GI008-C2 Drawing A1/GI008-C2: updated room tags to include room numbers.

GI009-C3 Drawing A1/GI009-C3: updated room tags to include room numbers.

GI010-C4 Drawing A1/GI010-C4: updated room tags to include room numbers.

GI011-C5 Drawing A1/GI011-C5: updated room tags to include room numbers.

GI110 Updated General Notes - Initial Outfitting and Transition, adding note 3. Corrected typos for DRMO notes. Removed column in IO+T Sequence and Construction Pauses for clarity.

GI110-A1 Updated General Notes - Initial Outfitting and Transition, adding note 3. Corrected typos for DRMO notes.

GI110-A2 Updated General Notes - Initial Outfitting and Transition, adding note 3. Corrected typos for DRMO notes. Revised sheet reference for Phase A2.

GI110-B1 Updated General Notes - Initial Outfitting and Transition, adding note 3. Corrected typos for DRMO notes and clarified other IO+T notes. Added IO+T Notes for SPD temp moves.

GI110-B2 Updated General Notes - Initial Outfitting and Transition, adding note 3.

GI110-C2 Updated General Notes - Initial Outfitting and Transition, adding note 3. Corrected typos for DRMO notes and clarified other IO+T notes. Update workstation power and data connection note at workstations.

GI110-C3 Updated General Notes - Initial Outfitting and Transition, adding note 3. Update workstation power and data connection note at workstations. Added note for lockers. Corrected typos for DRMO notes.

GI110-C4 Updated General Notes - Initial Outfitting and Transition, adding note 3. Corrected typos for DRMO note.

GI110-C5 Updated General Notes - Initial Outfitting and Transition, adding note 3.

GI110-D1 Updated General Notes - Initial Outfitting and Transition, adding note 3. Corrected typos for DRMO notes and clarified other IO+T notes.

GI110-D2 Updated General Notes - Initial Outfitting and Transition, adding note 3.

E002 Updated Responsibility Matrix ET602 Revised detail B1