This modification amends a solicitation for hospital modernization services at Misawa Air Base in Japan. The scope of work includes construction and renovation of various areas of the hospital facility. The modification provides 911 pages of as-built drawings to supplement previous responses. It also extends the proposal due date from June 1 to June 11 to allow consideration of additional questions received. Offerors must request access to the large as-built drawings file. The revised solicitation pages supersede prior versions. The opportunity remains unchanged otherwise.

View the file

Other files

File Type Posted
FA520521R00030004.pdf PDF
FA520521R00030004_Atch3_Revised Specifications.pdf PDF
FA520521R00030004_Atch1_Consolidated List of Govt Response.pdf PDF
FA520521R00030004_Atch2_Addendum No 2.pdf PDF
FA520521R00030004_Atch5_Revised Soliciation Page 1 and 21.pdf PDF
FA520521R00030004_Atch4_Revised Drawing Sheets.pdf PDF
FA520521R00030003_Atch2_Revised Soliciation Page 1 and 21.pdf PDF
FA520521R00030002_Atch2_Revised Specifications.pdf PDF
FA520521R00030002_Atch7_Revised Soliciation Page 1 and 21.pdf PDF
FA520521R00030002_Atch5_Revised Cut Sheets for JSN S0442 and S0960.pdf PDF
FA520521R00030002_Atch6_Consolidated List of Govt Response.pdf PDF
FA520521R00030002_Atch3_Revised Drawing Sheets.pdf PDF
FA520521R00030002.pdf PDF
FA520521R00030002_Atch1_Addendum No 1.pdf PDF
FA520521R00030002_Atch4_Revised Submittal Register.pdf PDF
FA520521R00030001.pdf PDF
Atch2_Drawings_PDF3of10_Structural.pdf PDF
Atch2_Drawings_PDF8of10_Plumbing.pdf PDF
Atch7-2_Structural Interior Design Volume 1 thru 3.pdf PDF
Atch2_Drawings_PDF6of10_Equipment.pdf PDF
RFP FA520521R0003_Hospital Modernization.pdf PDF
Atch2_Drawings_PDF4of10_Architectural.pdf PDF
Atch6_List of Contractor Furnished US Material.pdf PDF
Atch7-3_Mobile Sterile Processing Department Trailer Information.pdf PDF
Atch9_Past Performance Questionnaire Cover Letter.pdf PDF
Atch1_Specifications_Volume 2 of 2.pdf PDF
Atch2_Drawings_PDF10of10_Electrical.pdf PDF
Atch2_Drawings_PDF7of10_FireProtection.pdf PDF
Atch4_Construction Timeline.pdf PDF
Atch1_Specifications_Volume 1 of 2.pdf PDF
Atch2_Drawings_PDF2of10_Civil.pdf PDF
Atch2_Drawings_PDF1of10_General.pdf PDF
Atch8_Hazardous Material Survey Report.pdf PDF
Atch2_Drawings_PDF9of10_Mechanical.pdf PDF
Atch7-1_Equipment Data and Cut Sheets Logistics Category A.pdf PDF
Atch3_Other Contract Requirements.pdf PDF
Atch2_Drawings_PDF5of10_Interiors.pdf PDF
Atch5_Submittal Register.pdf PDF
Atch10_Past Performance Questionnaire.docx DOCX document
Show all 39

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE

J

PAGE OF PAGES

1 2

2. AMENDMENT/MODIFICATION NO.

3. EFFECTIVE DATE

18-May-2021

4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO.(If applicable)

1090686

6. ISSUED BY CODE FA5205 7. ADMINISTERED BY (If other than item 6) CODE

FA5205 35 CONS/LGC

UNIT 5201

APO AP 96319-5201

United States Capt Byron Muhlenberg, Contracting Officer, Telephone:315-226-2502 Email:

byron.muhlenberg.2@us.af.mil Mr. Takafumi Nosaki, Contract Specialist, Telephone: 315-226-2059 Email:

takafumi.nosaki.jp@us.af.mil

See Item 6

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X 9A. AMENDMENT OF SOLICITATION NO.

FA520521R0003

X 9B. DATED (SEE ITEM 11)

18-Mar-2021

10A. MOD. OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO

BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

See Schedule.

POC: Takafumi Nosaki, Contract Administrator/Comm Ph: 0176-77-2059

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

TEL: EMAIL:

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA

BY

(Signature of Contracting Officer)

16C. DATE SIGNED

18-May-2021

EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

30-105-04 STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

FA520521R0003

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

The following items are applicable to this modification:

This amendment provides as-built drawings to supplement the Government responses in Attachment 11 of the solicitation, “Consolidated List of the Government Response/Clarification” dated 29 Apr 21 provided under Amendment No. 0002 issued on 30 Apr 21; and extends the solicitation closing date specified for receipt of proposals for the subject solicitation in consideration of the 2nd questionnaires received from the prospective offerors.

(a) A total of nine hundred and eleven (911) as-built drawings (Attachment 1 to this amendment; see the paragraph (c) below for receiving instruction) are hereby provided to supplement the “Consolidated List of the Government Response/Clarification” dated 29 Apr 21. Accordingly, Section J, “List of Documents, Exhibits and Other Attachments”, page 21 of the solicitation is revised as follows and is replaced with the attached revised page 21 of the solicitation (Attachment 2 to this amendment).

DOCUMENT TYPE DESCRIPTION PAGE DATE

Attachment 1 Specifications Volume 1 of 2 1001 Rev. 15 Apr 2021 Specifications Volume 2 of 2 922 Rev. 15 Apr 2021 Attachment 2 Drawings – General 32 Rev. 15 Apr 2021 Drawings – Civil 7 23 Dec 2019 Drawings – Structural 7 23 Dec 2019 Drawings – Architectural 54 Rev. 15 Apr 2021 Drawings – Interiors 14 Rev. 15 Apr 2021 Drawings – Equipment 10 Rev. 15 Apr 2021 Drawings – Fire Protection 29 23 Dec 2019 Drawings – Plumbing 51 Rev. 15 Apr 2021 Drawings – Mechanical 84 Rev. 15 Apr 2021 Drawings – Electrical 98 Rev. 15 Apr 2021 Attachment 3 Other Contract Requirements 6 Rev. 15 Apr 2021 Attachment 4 Construction Timeline 14 4 Feb 2021 Attachment 5 Submittal Register 13 Rev. 15 Apr 2021 Attachment 6 List of Contractor Furnished U.S. Material (CFUSM) 2 1 Feb 2021 Attachment 7-1 Equipment Data and Cut Sheets – Logistics Category A 526 Rev. 15 Apr 2021 Attachment 7-2 Structural Interior Design (SID) Package Volume 1 thru 3 102 23 Dec 2019 Attachment 7-3 Mobile Sterile Processing Department (SPD) Trailer

Information 70 16 Jan 2020

Attachment 8 Hazardous Material Survey Report 47 Nov 2018 Attachment 9 Past Performance Questionnaire (PPQ) Cover Letter 1 3 Mar 2021 Attachment 10 Past/Present Performance Questionnaire (PPQ) 5 3 Mar 2021 Attachment 11 Consolidated List of the Government

Response/Clarification with As-built Drawings 922 Rev. 17 May 2021

(b) The proposal closing date specified in block 13.A. of Standard Form (SF) 1442 is hereby extended for additional ten (10) calendar days from “1 Jun 21” to “11 Jun 21”; therefore, page 1 of SF1442 is revised and replaced with the attached revised page 1 of the SF1442 numbered with FA520521R00030003 (Attachment 2 to this amendment).

(c) Due to the large file size of the as-build drawings, the as-built drawings will be provided through the DoD SAFE upon a request. Offerors who wish to receive the as-built drawings should send a request via email to thao.truong.2@us.af.mil and takafumi.nosaki.jp@us.af.mil.

(d) The offerors are required to replace with the revised solicitation pages provided under this amendment.

(e) Except as provided herein, all terms and conditions remain unchanged.

Attachments:

1. As-built drawing sheets (58 individual PDF, 911 sheets total)

2. Revised solicitation page 1 and 21, numbered with FA520521R00030003