Atch4_Construction Timeline.pdf
PDF 929 KB Posted
- Solicitation number
- FA520521R0003
About this file
This document includes an attachment to a Request for Proposal (RFP) for construction services. The RFP is for Project No. 1090686 to modernize the hospital at Misawa Air Base in Japan.
The attachment provides a construction timeline summary schedule spanning from October 2018 to February 2024. It outlines key milestones, design phases, procurement activities, and construction phases for the project. Construction is scheduled to last from October 2020 to December 2023 and will include site mobilization, ground level work renovating dental areas, lower level work including renovating nutrition and sterile processing departments, and facility-wide systems updates. The timeline provides duration details and dependencies for over 100 line items of work. The Department of the Air Force Pacific Air Forces is the agency issuing the RFP.
View the file
Other files
Show all 39
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment 4 to
Request for Proposal (RFP) No. FA520521R0003
Project No. 1090686, Hospital Modernization, Misawa Air Base, Japan
Construction Timeline
Summary Schedule – 2 sheets
Full Schedule – 8 sheets
Critical Path – 3 sheets
Note to Offeror: Period of performance is 1,200 calendar days to complete the entire construction, including 30 calendar days for mobilization.
Activity ID Activity Name Dur Start Finish Total Float
MISAWA Air Base Hospital 100% Designed, Ready to AdvertiseMISAWA Air Base Hospital 100% Designed, Ready to Advertise 1297 01-Oct-18 A 26-Feb-24 0
MILESTONESMILESTONES 1297 01-Oct-18 A 26-Feb-24 0
MS.900 MS: Notice to Proceed 0 01-Oct-18 A
MS.910 MS: Substantial Completion 0 30-Nov-23 60
MS.920 MS: Final Project Completion 0 26-Feb-24 0
PERMITSPERMITS 5 24-Dec-19 31-Dec-19 222
Perm.1000 Permits (TBD - None Identified at this Time as Required) 5 24-Dec-19 31-Dec-19 222
SITE INVESTIGATIONSSITE INVESTIGATIONS 5 05-Nov-18 A 09-Nov-18 A
Site.1100 Site Investigation 5 05-Nov-18 A 09-Nov-18 A
DESIGNDESIGN 254 12-Nov-18 A 23-Dec-19 0
DN.1200 Produce Charrette Report 5 12-Nov-18 A 14-Dec-18 A
35% Design35% Design 145 25-Dec-18 A 19-Apr-19 A
65% Design65% Design 81 18-Apr-19 A 02-Aug-19 0
95 - 100% Design95 - 100% Design 101 05-Aug-19 23-Dec-19 0
PROCUREMENTPROCUREMENT 392 24-Dec-19 15-Jul-21 472
Bid & Award Construction ContractBid & Award Construction Contract 234 24-Dec-19 25-Nov-20 87
Procure Vendors & EquipmentProcure Vendors & Equipment 196 01-Oct-20 15-Jul-21 472
Proc.1800 Prepare Key Purchase Orders, Negotiate and Sign P.O.'s 42 01-Oct-20 01-Dec-20 21
Proc.1810 Prepare P.O. to Relocate Mobile SPD Trailer (from US to Japan) 42 29-Oct-20 30-Dec-20 21
In-Country Key Equipment ProcurementsIn-Country Key Equipment Procurements 124 02-Dec-20 28-May-21 504
Out-of-Country Key Equipment ProcurmentsOut-of-Country Key Equipment Procurments 156 02-Dec-20 15-Jul-21 83
CONSTRUCTIONCONSTRUCTION 809 01-Oct-20 29-Dec-23 38
Site Mobilization & Pre-Construction SubmittalsSite Mobilization & Pre-Construction Submittals 77 01-Oct-20 26-Jan-21 108
CN.Mblz.3000 Site Mobilization & Acc ess & Pre-Construc tion Submittals 30 01-Oct-20 11-Nov-20 0
CN.Mblz.3030 AF Base Pre-Submittal Review&Comment / Contractor Incorporate Comments 30 15-Oct-20 30-Nov-20 9
CN.Mblz.3010 HW Removal (Lead Paint & Asbestos) 40 12-Nov-20 12-Jan-21 119
CN.Mblz.3020 IO&T Walkthrough Affected Departments / Develop Detailed Implementation Plans & Move Seqeuncing40 30-Nov-20 26-Jan-21 89
GROUND LEVELGROUND LEVEL 781 12-Nov-20 29-Dec-23 38
Phase C1 - Dental AdditionPhase C1 - Dental Addition 153 12-Nov-20 23-Jun-21 89
CN.C1.3100 C1 - Extend/Mod to Doghouse Ventilation Air Towers Mov e Lov ers from Eas t to West Side 10 12-Nov-20 25-Nov-20 10
CN.C1.3105 C1 - Temporary Redirection of Roof Top Water Collection System 5 12-Nov-20 18-Nov-20 0
Dental AdditionDental Addition 148 19-Nov-20 23-Jun-21 89
Dental Addition Fit-OutDental Addition Fit-Out 15 28-Apr-21 18-May-21 0
Phase C2 - West Dental AreaPhase C2 - West Dental Area 203 19-May-21 14-Mar-22 488
Move Out - West Dental Area C2Move Out - West Dental Area C2 20 19-May-21 16-Jun-21 9
Temporary Construction Barrier C2Temporary Construction Barrier C2 10 26-May-21 09-Jun-21 14
Renovations - West Dental Area C2Renovations - West Dental Area C2 172 19-May-21 27-Jan-22 519
Fit-Out - West Dental Area C2Fit-Out - West Dental Area C2 25 07-Jan-22 11-Feb-22 0
S/U & Commissioning - West Dental Area C2S/U & Commissioning - West Dental Area C2 20 14-Feb-22 14-Mar-22 488
Move In - West Dental Area C2Move In - West Dental Area C2 10 28-Feb-22 11-Mar-22 0
Phase C3 - Dental Are NE for Temporary Dental SpacesPhase C3 - Dental Are NE for Temporary Dental Spaces 100 28-Dec-21 20-May-22 401
SPD Staff moved into Permanent Space / Remove Temporary SPD TrailerSPD Staff moved into Permanent Space / Remove Temporary SPD Trailer 0 28-Dec-21 28-Dec-21 420
Remove SPD TrailerRemove SPD Trailer 81 29-Dec-21 25-Apr-22 420
Modify Existing Sprinklers as neededModify Existing Sprinklers as needed 15 14-Mar-22 01-Apr-22 0
ElectricalElectrical 20 14-Mar-22 08-Apr-22 0
Install Voice / Data, paging System Speakers, & Security System DevicesInstall Voice / Data, paging System Speakers, & Security System Devices 15 04-Apr-22 22-Apr-22 20
Install New Nurse Cal System Equipment & DevicesInstall New Nurse Cal System Equipment & Devices 15 11-Apr-22 29-Apr-22 0
UtilitiesUtilities 15 04-Apr-22 22-Apr-22 5
Provide Workstations with DataProvide Workstations with Data 20 04-Apr-22 29-Apr-22 15
Move In - SE Dental Area C3Move In - SE Dental Area C3 15 02-May-22 20-May-22 0
Phase C4 - Dental Area SEPhase C4 - Dental Area SE 238 23-May-22 04-May-23 163
Move Out - SE Dental Area C4Move Out - SE Dental Area C4 20 23-May-22 20-Jun-22 0
Temporary Construction Barrier C4Temporary Construction Barrier C4 10 31-May-22 13-Jun-22 5
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
2019 2020 2021 2022 2023 2024 2025 2026 2027
MISAWA Air Base Hospital 100% Designed, Ready to Ad
MILESTONES
MS: Notice to Proceed
MS.910 MS: Substantial Completion
MS.920 MS: Final Project Completion
PERMITS
Perm.1000 Permits (TBD - None Identified at this Time as Required)
SITE INVESTIGATIONS
DESIGN
35% Design
65% Design
95 - 100% Design
PROCUREMENT
Bid & Award Construction Contract
Procure Vendors & Equipment
Proc.1800 Prepare Key Purchase Orders, Negotiate and Sign P.O.'s
Proc.1810 Prepare P.O. to Relocate Mobile SPD Trailer (from US to Japan)
In-Country Key Equipment Procurements
Out-of-Country Key Equipment Procurments
CONSTRUCTION
Site Mobilization & Pre-Construction Submittals
CN.Mblz.3000 Site Mobilization & Acc ess & Pre-Construc tion Submittals
CN.Mblz.3030 AF Base Pre-Submittal Review&Comment / Contractor Incorporate Comments
CN.Mblz.3010 HW Removal (Lead Paint & Asbestos)
CN.Mblz.3020 IO&T Walkthrough Affected Departments / Develop Detailed Implementation Plans & Move Seqeuncing
GROUND LEVEL
Phase C1 - Dental Addition
CN.C1.3100 C1 - Extend/Mod to Doghouse Ventilation Air Towers Mov e Lov ers from Eas t to West Side
CN.C1.3105 C1 - Temporary Redirection of Roof Top Water Collection System
Dental Addition
Dental Addition Fit-Out
Phase C2 - West Dental Area
Move Out - West Dental Area C2
Temporary Construction Barrier C2
Renovations - West Dental Area C2
Fit-Out - West Dental Area C2
S/U & Commissioning - West Dental Area C2
Move In - West Dental Area C2
Phase C3 - Dental Are NE for Temporary Dental Spaces
SPD Staff moved into Permanent Space / Remove Temporary SPD Trailer
Remove SPD Trailer
Modify Existing Sprinklers as needed
Electrical
Install Voice / Data, paging System Speakers, & Security System Devices
Install New Nurse Cal System Equipment & Devices
Utilities
Provide Workstations with Data
Move In - SE Dental Area C3
Phase C4 - Dental Area SE
Move Out - SE Dental Area C4
Temporary Construction Barrier C4
US AIR FORCE Misawa, Japan
MISAWA Air Base Hospital Modernization Project Contract No. FA8903-15-D-0004 - Task Order FA8903-18-F-0072
DATE: 04-Feb-21 TIME: 09:07
Start Date: 01-Oct-18 Finish Date: 26-Feb-24
Data Date: 19-Jul-19 Run Date: 04-Feb-21
Time: 09:07
Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary 100% Design Ready to Advertise
Renovation - SE Dental Area C4Renovation - SE Dental Area C4 183 21-Jun-22 16-Mar-23 15
Fit-Out - SE Dental Area C4Fit-Out - SE Dental Area C4 15 03-Mar-23 23-Mar-23 0
S/U & Commissioning - SE Dental Area C4S/U & Commissioning - SE Dental Area C4 25 24-Mar-23 27-Apr-23 168
Move In - SE Dental Area C4Move In - SE Dental Area C4 20 07-Apr-23 04-May-23 0
Phase C5 - Dental Area NE Final RenovationsPhase C5 - Dental Area NE Final Renovations 163 05-May-23 29-Dec-23 0
Move Out - NE Dental Area C5Move Out - NE Dental Area C5 20 05-May-23 02-Jun-23 0
Temporary Construction Barrier C5Temporary Construction Barrier C5 5 12-May-23 18-May-23 10
Renovation - NE Dental Area C5Renovation - NE Dental Area C5 123 05-Jun-23 30-Nov-23 0
Fit-Out - NE Dental Area C5Fit-Out - NE Dental Area C5 0 30-Nov-23 30-Nov-23 0
S/U & Commissioning - NE Dental Area C5S/U & Commissioning - NE Dental Area C5 20 30-Nov-23 29-Dec-23 0
Move In - NE Dental Area C5Move In - NE Dental Area C5 10 15-Dec-23 29-Dec-23 0
Phase D1 Renovate from Temporary NFS (Gym) to Accomodate Records StoragePhase D1 Renovate from Temporary NFS (Gym) to Accomodate Records Storage 55 11-Feb-22 29-Apr-22 270
Renovate Gym after NFS relocated to Renovated NFS D1Renovate Gym after NFS relocated to Renovated NFS D1 50 11-Feb-22 22-Apr-22 270
Move In - Records Storae Area - D1Move In - Records Storae Area - D1 20 04-Apr-22 29-Apr-22 270
Phase D2 Pharmacy RenovationPhase D2 Pharmacy Renovation 125 02-May-22 27-Oct-22 329
Move Out - Pharmacy D2Move Out - Pharmacy D2 20 02-May-22 27-May-22 434
Renovation - Pharmacy D2Renovation - Pharmacy D2 105 02-May-22 28-Sep-22 349
Fit-Out - Pharmacy D2Fit-Out - Pharmacy D2 0 02-Aug-22 02-Aug-22 310
S/U & Commissioning - Pharmacy D2S/U & Commissioning - Pharmacy D2 20 29-Sep-22 27-Oct-22 270
Move In - Pharmacy D2Move In - Pharmacy D2 15 06-Oct-22 27-Oct-22 270
LOWER LEVELLOWER LEVEL 594 12-Nov-20 31-Mar-23 225
Phase A1 - Renovate Existing Gym (LG22) for Temporary NFSPhase A1 - Renovate Existing Gym (LG22) for Temporary NFS 120 12-Nov-20 07-May-21 270
Demolition of Gym/Temporary NFS for Nutritional Medicine (NFS) A1Demolition of Gym/Temporary NFS for Nutritional Medicine (NFS) A1 110 12-Nov-20 22-Apr-21 280
Move In - Temporary NFS for Nutritional Medicine (NFS) A1Move In - Temporary NFS for Nutritional Medicine (NFS) A1 10 23-Apr-21 07-May-21 270
Phase A2 Renovate NFSPhase A2 Renovate NFS 190 07-May-21 10-Feb-22 509
Move Out - NFS A2Move Out - NFS A2 20 07-May-21 04-Jun-21 270
Renovation - Nutritional Medicine (NFS)Renovation - Nutritional Medicine (NFS) 150 07-Jun-21 12-Jan-22 529
Fit Out NFS A2Fit Out NFS A2 10 20-Dec-21 04-Jan-22 276
S/U & Commissioning NFS A2S/U & Commissioning NFS A2 30 29-Dec-21 10-Feb-22 270
Phase B1 Mobile SPD & Whse/Mech RmPhase B1 Mobile SPD & Whse/Mech Rm 189 06-Jan-21 04-Oct-21 595
MOBILE SPD TRAILERMOBILE SPD TRAILER 51 19-Feb-21 30-Apr-21 703
Warehouse/Mechanical RoomWarehouse/Mechanical Room 189 06-Jan-21 04-Oct-21 595
Phase B2 SPD RenovationPhase B2 SPD Renovation 174 19-Apr-21 28-Dec-21 539
Move Out - SPD B2Move Out - SPD B2 25 19-Apr-21 21-May-21 688
Renovation - Sterile Processing Department (SPD)Renovation - Sterile Processing Department (SPD) 139 03-May-21 18-Nov-21 430
Fit Out SPD B2Fit Out SPD B2 0 18-Nov-21 18-Nov-21 420
S/U & Commissioning SPD B2S/U & Commissioning SPD B2 20 04-Nov-21 06-Dec-21 516
Move In - SPD B2Move In - SPD B2 15 07-Dec-21 28-Dec-21 420
Temporary Phasing Space (ALL PHASES) C3Temporary Phasing Space (ALL PHASES) C3 594 12-Nov-20 31-Mar-23 187
FACILITY WIDE SYSTEMS UPDATESFACILITY WIDE SYSTEMS UPDATES 633 17-Jun-21 29-Dec-23 38
FcltyWide.6801 NOTE: Items in Facility Wide Systems listed for Reference All Work TBD & Coordinated with Occupants in Sections0 17-Jun-21 631
ElectricalElectrical 40 17-Jun-21 12-Aug-21 631
Replacement of Catwalk SystemReplacement of Catwalk System 486 17-Jun-21 26-May-23 147
Facility Wide Upgrades Fire Alarm & Mass Notification SystemsFacility Wide Upgrades Fire Alarm & Mass Notification Systems 573 13-Sep-21 29-Dec-23 0
Communications/Low VoltageCommunications/Low Voltage 147 17-Jun-21 20-Jan-22 524
Mechanical & PlumbingMechanical & Plumbing 147 17-Jun-21 20-Jan-22 524
START UP & COMMISSIONINGSTART UP & COMMISSIONING 10 11-Oct-23 24-Oct-23 45
Mass Air BalancingMass Air Balancing 10 11-Oct-23 24-Oct-23 45
CLOSEOUTCLOSEOUT 40 02-Jan-24 26-Feb-24 0
CO..9000 Closeout Project 40 02-Jan-24 26-Feb-24 0
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
2019 2020 2021 2022 2023 2024 2025 2026 2027
Renovation - SE Dental Area C4
Fit-Out - SE Dental Area C4
S/U & Commissioning - SE Dental Area C4
Move In - SE Dental Area C4
Phase C5 - Dental Area NE Final Renovations
Move Out - NE Dental Area C5
Temporary Construction Barrier C5
Renovation - NE Dental Area C5
Fit-Out - NE Dental Area C5
S/U & Commissioning - NE Dental Area C5
Move In - NE Dental Area C5
Phase D1 Renovate from Temporary NFS (Gym) to Accomodate Records Storage
Renovate Gym after NFS relocated to Renovated NFS D1
Move In - Records Storae Area - D1
Phase D2 Pharmacy Renovation
Move Out - Pharmacy D2
Renovation - Pharmacy D2
Fit-Out - Pharmacy D2
S/U & Commissioning - Pharmacy D2
Move In - Pharmacy D2
LOWER LEVEL
Phase A1 - Renovate Existing Gym (LG22) for Temporary NFS
Demolition of Gym/Temporary NFS for Nutritional Medicine (NFS) A1
Move In - Temporary NFS for Nutritional Medicine (NFS) A1
Phase A2 Renovate NFS
Move Out - NFS A2
Renovation - Nutritional Medicine (NFS)
Fit Out NFS A2
S/U & Commissioning NFS A2
Phase B1 Mobile SPD & Whse/Mech Rm
MOBILE SPD TRAILER
Warehouse/Mechanical Room
Phase B2 SPD Renovation
Move Out - SPD B2
Renovation - Sterile Processing Department (SPD)
Fit Out SPD B2
S/U & Commissioning SPD B2
Move In - SPD B2
Temporary Phasing Space (ALL PHASES) C3
FACILITY WIDE SYSTEMS UPDATES
FcltyWide.6801 NOTE: Items in Facility Wide Systems listed for Reference All Work TBD & Coordinated with Occupants in S
Electrical
Replacement of Catwalk System
Facility Wide Upgrades Fire Alarm & Mass Notific ation Systems
Communications/Low Voltage
Mechanical & Plumbing
START UP & COMMISSIONING
Mass Air Balancing
CLOSEOUT
CO..9000 Closeout Project
US AIR FORCE Misawa, Japan
MISAWA Air Base Hospital Modernization Project Contract No. FA8903-15-D-0004 - Task Order FA8903-18-F-0072
DATE: 04-Feb-21 TIME: 09:07
Start Date: 01-Oct-18 Finish Date: 26-Feb-24
Data Date: 19-Jul-19 Run Date: 04-Feb-21
Time: 09:07
Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
MISAWA Air Base Hospital 100% Designed, Ready to AdvertiseMISAWA Air Base Hospital 100% Designed, Ready to Advertise 1297 01-Oct-18 A 26-Feb-24 0
MILESTONESMILESTONES 1297 01-Oct-18 A 26-Feb-24 0
MS.900 MS: Notice to Proceed 0 01-Oct-18 A
MS.910 MS: Substantial Completion 0 30-Nov-23 60
MS.920 MS: Final Project Completion 0 26-Feb-24 0
PERMITSPERMITS 5 24-Dec-19 31-Dec-19 222
Perm.1000 Permits (TBD - None Identified at this Time as Required) 5 24-Dec-19 31-Dec-19 222
SITE INVESTIGATIONSSITE INVESTIGATIONS 5 05-Nov-18 A 09-Nov-18 A
Site.1100 Site Investigation 5 05-Nov-18 A 09-Nov-18 A
DESIGNDESIGN 254 12-Nov-18 A 23-Dec-19 0
DN.1200 Produce Charrette Report 5 12-Nov-18 A 14-Dec-18 A
35% Design35% Design 145 25-Dec-18 A 19-Apr-19 A
DN.35..1300 Produce 35% Design 6 25-Dec-18 A 01-Mar-19 A
DN.35..1310 Prepare and Submit Cost Estimate & 30% Constructability Schedule 5 04-Feb-19 A 15-Mar-19 A
DN.35..1320 35% Review Period 30 04-Mar-19 A 12-Apr-19 A
DN.35..1330 35% Review Conference 3 15-Apr-19 A 19-Apr-19 A
65% Design65% Design 81 18-Apr-19 A 02-Aug-19 0
DN.65..1400 Produce 65% Design 52 18-Apr-19 A 01-Jul-19 A
DN.65..1410 65% Review Period 29 02-Jul-19 A 23-Jul-19 0
DN.65..1420 65% Review Conference 5 29-Jul-19 02-Aug-19 0
95 - 100% Design95 - 100% Design 101 05-Aug-19 23-Dec-19 0
DN.100..1500 Produce 95% Design 36 05-Aug-19 24-Sep-19 0
DN.100..1510 95% Review Period 11 25-Sep-19 09-Oct-19 0
DN.100..1520 95% Review Teleconference 1 11-Oct-19 11-Oct-19 0
DN.100..1530 Produce 100% Design 18 14-Oct-19 06-Nov-19 0
DN.100..1540 100% Review Period 11 07-Nov-19 21-Nov-19 0
DN.100..1570 100% Review Teleconference 1 26-Nov-19 26-Nov-19 0
DN.100..1550 Prepare Corrected 100% Design Submittal 13 27-Nov-19 17-Dec-19 0
DN.100..1560 Issue For Construction 4 18-Dec-19 23-Dec-19 0
PROCUREMENTPROCUREMENT 392 24-Dec-19 15-Jul-21 472
Bid & Award Construction ContractBid & Award Construction Contract 234 24-Dec-19 25-Nov-20 87
B&A.1700 Contracting Review and Funding Assignment 67 24-Dec-19 30-Mar-20 0
B&A.1710 Advertise & Pre-Proposal OpeningContract Terms&Conditions/ Construction Contrat Signed124 31-Mar-20 23-Sep-20 0
B&A.1730 Advertise & Pre-Proposal Opening Contract T&C's IO&T Contrat Signed 60 26-Aug-20 18-Nov-20 89
B&A.1720 Award Construction Contract 5 24-Sep-20 30-Sep-20 0
B&A.1740 Award IO&T Contract 5 19-Nov-20 25-Nov-20 89
Procure Vendors & EquipmentProcure Vendors & Equipment 196 01-Oct-20 15-Jul-21 472
Proc.1800 Prepare Key Purchase Orders, Negotiate and Sign P.O.'s 42 01-Oct-20 01-Dec-20 21
Proc.1810 Prepare P.O. to Relocate Mobile SPD Trailer (from US to Japan) 42 29-Oct-20 30-Dec-20 21
In-Country Key Equipment ProcurementsIn-Country Key Equipment Procurements 124 02-Dec-20 28-May-21 504
Proc.IC.1990 Fab & Deliver Water Treatment System (located in New Mech Rm (LD23A) 60 02-Dec-20 01-Mar-21 508
Proc.IC.1900 Receive & Review Shop Drawings, Review, Approve and Release to Fabricate: AHU's & Key Deliverables42 02-Dec-20 01-Feb-21 29
Proc.IC.1960 Relocate / Deliver: Mobile SPD Trailer (from USA to Japan & Project Site) 60 31-Dec-20 25-Mar-21 21
Proc.IC.1970 Fab & Deliver: AHU 10 (Dental Zone) 84 15-Jan-21 12-May-21 29
Proc.IC.1980 Fab & Deliver: AHU 6 (SPD Zone) 84 15-Jan-21 12-May-21 459
Proc.IC.1910 Fab & Deliver FIre Pump 42 02-Feb-21 01-Apr-21 535
Proc.IC.1920 Fab & Deliver Fire Preaction Valve Assemblies 42 02-Feb-21 01-Apr-21 123
Proc.IC.1930 Fab & Deliver FIre Alarm Control Panels 42 02-Feb-21 01-Apr-21 206
Proc.IC.1940 Deliver Fire Detection / Fire Protection System 60 02-Feb-21 26-Apr-21 536
Proc.IC.1950 Fab & Deliver: AHU 4 (Nutriet ional Med Zone) 84 02-Feb-21 28-May-21 338
Out-of-Country Key Equipment ProcurmentsOut-of-Country Key Equipment Procurments 156 02-Dec-20 15-Jul-21 83
Proc.OC.2000 Furnishing Fixtures & Equiment Dental Equipment (60) Competitive Bid Package 42 02-Dec-20 02-Feb-21 83
Proc.OC.2010 Government Approve CBP Furnishing Fixtures & Equiment Dental Equipment 30 03-Feb-21 17-Mar-21 83
Proc.OC.2020 Fab & Deliver Furnishing Fixtrues & Equiment Dental Equipment 84 18-Mar-21 15-Jul-21 83
CONSTRUCTIONCONSTRUCTION 809 01-Oct-20 29-Dec-23 38
Site Mobilization & Pre-Construction SubmittalsSite Mobilization & Pre-Construction Submittals 77 01-Oct-20 26-Jan-21 108
CN.Mblz.3000 Site Mobilization & Access & Pre-Construction Submittals 30 01-Oct-20 11-Nov-20 0
CN.Mblz.3030 AF Base Pre-Submittal Review&Comment / Contractor Incorporate Comments 30 15-Oct-20 30-Nov-20 9
CN.Mblz.3010 HW Removal (Lead Paint & Asbestos) 40 12-Nov-20 12-Jan-21 119
Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2019 2020 2021 2022 2023 2024 2025 2026
MISAWA Air Base Hospital 100% Designed, Ready to Adver ti se
MILESTONES
MS: Notice to Proceed
MS.910 MS: Substantial Completion
MS.920 MS: Final Project Completion
PERMITS
Perm.1000 Permits (TBD - None Identified at this Time as Required)
SITE INVESTIGATIONS
DESIGN
35% Design
65% Design
DN.65..1410 65% Review Period
DN.65..1420 65% Review Conference
95 - 100% Design
DN.100..1500 Produce 95% Design
DN.100..1510 95% Review Period
DN.100..1520 95% Review Teleconference
DN.100..1530 Produce 100% Design
DN.100..1540 100% Review Period
DN.100..1570 100% Review Teleconference
DN.100..1550 Prepare Corrected 100% Design Submittal
DN.100..1560 Issue For Construction
PROCUREMENT
Bid & Award Construction Contract
B&A.1700 Contracting Review and Funding Assignment
B&A.1710 Advertise & Pre-Proposal OpeningContract Terms&Conditions/ Construction Contrat Signed
B&A.1730 Advertise & Pre-Proposal Opening Contract T&C's IO&T Contrat Signed
B&A.1720 Award Construction Contract
B&A.1740 Award IO&T Contract
Procure Vendors & Equipment
Proc.1800 Prepare Key Purchase Orders, Negotiate and Sign P.O.'s
Proc.1810 Prepare P.O. to Relocate Mobile SPD Trailer (from US to Japan)
In-Country Key Equipment Procurements
Proc.IC.1990 Fab & Deliver Water Treatment System (located in New Mech Rm (LD23A)
Proc.IC.1900 Receive & Review Shop Drawings, Review, Approve and Release to Fabricate: AHU's & Key Deliverables
Proc.IC.1960 Relocate / Deliver: Mobile SPD Trailer (from USA to Japan & Project Site)
Proc.IC.1970 Fab & Deliver: AHU 10 (Dental Zone)
Proc.IC.1980 Fab & Deliver: AHU 6 (SPD Zone)
Proc.IC.1910 Fab & Deliver FIre Pump
Proc.IC.1920 Fab & Deliver Fire Preaction Valve Assemblies
Proc.IC.1930 Fab & Deliver FIre Alarm Control Panels
Proc.IC.1940 Deliver Fire Detection / Fire Protection System
Proc.IC.1950 Fab & Deliver: AHU 4 (Nutriet ional Med Zone)
Out-of-Country Key Equipment Procurments
Proc.OC.2000 Furnishing Fixtures & Equiment Dental Equipment (60) Competitive Bid Package
Proc.OC.2010 Government Approve CBP Furnishing Fixtures & Equiment Dental Equipment
Proc.OC.2020 Fab & Deliver Furnishing Fixtrues & Equiment Dental Equipment
CONSTRUCTION
Site Mobilization & Pre-Construction Submittals
CN.Mblz.3000 Site Mobilization & Access & Pre-Construction Submittals
CN.Mblz.3030 AF Base Pre-Submittal Review&Comment / Contractor Incorporate Comments
CN.Mblz.3010 HW Removal (Lead Paint & Asbestos)
US AIR FORCE Misawa, Japan
DATE: 04-Feb-21 TIME: 09:08
Start Date: 01-Oct-18 Finish Date: 26-Feb-24
Data Date: 19-Jul-19 Run Date: 04-Feb-21
Time: 09:08
Level of Effort
Actual Work
Remaining Work
Critical Remaining W...
CN.Mblz.3020 IO&T Walkthrough Affected Departments / Develop Detailed Implementation Plans & Move Seqeuncing40 30-Nov-20 26-Jan-21 89
GROUND LEVELGROUND LEVEL 781 12-Nov-20 29-Dec-23 38
Phase C1 - Dental AdditionPhase C1 - Dental Addition 153 12-Nov-20 23-Jun-21 89
CN.C1.3100 C1 - Extend/Mod to Doghouse Ventil ation Air Towers Move Lovers from East to West Side10 12-Nov-20 25-Nov-20 10
CN.C1.3105 C1 - Temporary Redirection of Roof Top Water Collection System 5 12-Nov-20 18-Nov-20 0
Dental AdditionDental Addition 148 19-Nov-20 23-Jun-21 89
CN.C1.3110 C1 - Demolish Existing West Dental Clinic Wall Metal-Clad Concrete Awning/Canopy10 19-Nov-20 04-Dec-20 0
CN.C1.3115 C1 - Excavate soil from Sub Basement for New Dental Additions 5 07-Dec-20 11-Dec-20 0
CN.C1.3120 C1 - Install 4 New Columns / Footers for New Slab of Dental addition (R - 6,7,8&9) 20 14-Dec-20 12-Jan-21 0
CN.C1.3125 C1 - Inspect/Perform any repair required to Sub basement Waterproofing / Moisture Membrane5 14-Dec-20 18-Dec-20 0
CN.C1.3130 C1 - Install any Underdrain Plumbing / utilities 10 13-Jan-21 26-Jan-21 10
CN.C1.3135 C1 - Fill with Expanded Polystyrene Foam (EPF) for slab subgrade 10 13-Jan-21 26-Jan-21 0
CN.C1.3140 C1 - Form, Rebar & Pour Floor Slab for Dental Addition 15 20-Jan-21 09-Feb-21 0
CN.C1.3145 C1 - Install Exterior Walls Cast-in-Place for Dental Addition 20 10-Feb-21 09-Mar-21 0
CN.C1.3150 C1 - Install Roof Deck System, New Flashing Roof Expansion Joint, Insulation & EPDM Membrane10 10-Mar-21 23-Mar-21 0
CN.C1.3155 C1 - Fill gaps between Dental Additi on & HVAC Towers with Expansion Joint & Covers15 24-Mar-21 13-Apr-21 30
CN.C1.3160 C1 - Install Water Collecting Roof 15 24-Mar-21 13-Apr-21 0
CN.C1.3165 C1 - Install Ribbon Windows 10 14-Apr-21 27-Apr-21 0
CN.C1.3170 C1 - Install New Dental Addition Entryway 15 28-Apr-21 18-May-21 89
CN.C1.3175 C1 - Extend Concrete Snow Melt System / Install New North Entry Sidewalk & Ramp20 19-May-21 16-Jun-21 89
CN.C1.3180 C1 - Replace/Restore Sod around Dental Addition 5 17-Jun-21 23-Jun-21* 89
Dental Addition Fit-OutDental Addition Fit-Out 15 28-Apr-21 18-May-21 0
CN.C1.3185 C1 - Initial Outfitting and Transition( IO&T)/DRMO - Ground Level C1 15 28-Apr-21 18-May-21 0
Phase C2 - West Dental AreaPhase C2 - West Dental Area 203 19-May-21 14-Mar-22 488
Move Out - West Dental Area C2Move Out - West Dental Area C2 20 19-May-21 16-Jun-21 9
CN.C2.3202 C2 - IO&T Coordinate Teardown/Reconfiguring Exisi tng Inventory/Reuse Items 5 19-May-21 25-May-21 9
CN.C2.3204 C2 - IO&T Relocate / Move Out Exiting Staff & Operations - Ground Level W C2 15 26-May-21 16-Jun-21 9
CN.C2.3206 C2 - IO&T Remove & Transport All Dissasembled Furniture / Eqpt to a Storage Warehouse for Reuse or Disposition10 03-Jun-21 16-Jun-21 9
Temporary Construction Barrier C2Temporary Construction Barrier C2 10 26-May-21 09-Jun-21 14
CN.C2-3208 C2 - Construct Temporary Construction Barriers (UF33 to UF18 & UF8 to UF15) 5 26-May-21 02-Jun-21 14
CN.C2-3210 C2 - Construct Temporary Construction Barriers (UE23 to UE03 & UE02 to UE03) 5 03-Jun-21 09-Jun-21 14
Renovations - West Dental Area C2Renovations - West Dental Area C2 172 19-May-21 27-Jan-22 519
Dental Department West Side (DIPC)Dental Department West Side (DIPC) 144 19-May-21 15-Dec-21 547
CN.C2.3225 C2 - Install Interior MEP for Dental Addition (Including AHU#10 in Mech Rm) 40 19-May-21 15-Jul-21 0
CN.C2.3235 C2 - Demolition/Modifications of Existing Dental West Wall 20 19-May-21 16-Jun-21 5
CN.C2.3222 C2 - Remove Existing AHU-10 in UF41 (Install Temp AHU if Reqd) 5 17-Jun-21 23-Jun-21 5
CN.C2.3220 C2 - Removal of Existing Interior Gypsum Wallboard & Thermal Insulation 40 17-Jun-21 12-Aug-21 9
CN.C2.3230 C2 - Install Interior Walls and Mechanical Room in New Dental Addition 40 17-Jun-21 12-Aug-21 10
CN.C2.3215 C2 - NOTE: Existing Waiting & Reception Remains Open 0 17-Jun-21 10
CN.C2.3213 C2 - Renovation West Half of Dental 126 17-Jun-21 15-Dec-21 9
CN.C2.3226 C2 - Set & Install AHU-10 (New and Exisitng AHU 10 shall not operate Simultaneously)10 24-Jun-21 08-Jul-21 656
CN.C2.3224 C2 - Install New AHU 10 (Services New Dental Area, W 1/2 of Dental & Temp Air to E Dental)10 24-Jun-21 08-Jul-21 5
CN.C2.3228 C2 - Install HVAC & Dutwork in New Dental Area 30 16-Jul-21 26-Aug-21 0
CN.C2.3241 C2 - Install Interior Doors Systems & Hardware 15 13-Aug-21 02-Sep-21 34
CN.C2.3237 C2 - Replace Exterior Walls w/Rigid Phenolic Foam Insulation, Air Barrier/ Vapor Retarder&New Gypsum Wallboard P2.40 13-Aug-21 08-Oct-21 9
CN.C2.3245 C2 - Add Temporary Drops for New Ceiling 10 27-Aug-21 10-Sep-21 10
CN.C2.3243 C2 - Install Interior Finishes / Ceiling / Wall Based Materials Flooring / Paint / Doors/ etc40 27-Aug-21 22-Oct-21 10
Fire Alarm / Fire Suppression New Dental AdditionFire Alarm / Fire Suppression New Dental Addition 55 13-Sep-21 02-Dec-21 48
CN.C2.3249 C2 - 1GLU-Fire Detection in New Dental Addition 10 13-Sep-21 24-Sep-21 53
CN.C2.3247 C2 - Fire Suppression System in New Dental Addi tion 20 13-Sep-21 08-Oct-21 10
CN.C2.3259 C2 - Demolition of Fire Protection Lower Level SPD 10 20-Sep-21 01-Oct-21 48
CN.C2.3251 C2 - Smoke Detection in New Dental Addit ion 10 04-Oct-21 18-Oct-21 48
CN.C2.3253 C2 - Fire/Smoke Indicating Lamps in New Dental Addition 10 19-Oct-21 01-Nov-21 48
CN.C2.3255 C2 - Strobes/Horns Speaker Systems * Connected to hospital PA system in New Dental Addition10 02-Nov-21 16-Nov-21 48
CN.C2.3257 C2 - Fire Alarm Control Panel i n New Dental Addition 10 17-Nov-21 02-Dec-21 48
Fire Alarm / Fire Suppression West Dental AreaFire Alarm / Fire Suppression West Dental Area 49 11-Oct-21 22-Dec-21 9
CN.C2.3263 C2 - Relocate Fire Suppression Pipe West Dental Area 20 11-Oct-21 05-Nov-21 10
CN.C2.3265 C2 - Smoke Detection West Dental Area 10 25-Oct-21 05-Nov-21 9
CN.C2.3274 C2 - Renovation of Fire Alarm System & Control Panel West Dental Area 10 08-Nov-21 22-Nov-21 19
CN.C2.3372 C2 - Install new Fire Alarm/Mass Notification Devised and Wir ing West Dental Area10 08-Nov-21 22-Nov-21 29
CN.C2.3270 C2 - Fire/Smoke Indicating Lamps West Dental Area 10 08-Nov-21 22-Nov-21 9
CN.C2.3276 C2 - Strobes/Horns Speaker Systems * Connected to hospital PA system West Dental Area10 23-Nov-21 08-Dec-21 9
Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2019 2020 2021 2022 2023 2024 2025 2026
CN.Mblz.3020 IO&T Walkthrough Affected Departments / Develop Detailed Implementation Plans & Move Seqeuncing
GROUND LEVEL
Phase C1 - Dental Addi ti on
CN.C1.3100 C1 - Extend/Mod to Doghouse Ventil ation Air Towers Move Lovers from East to West Side
CN.C1.3105 C1 - Temporary Redirection of Roof Top Water Collection System
Dental Addition
CN.C1.3110 C1 - Demolish Existing West Dental Clinic Wall Metal-Clad Concrete Awning/Canopy
CN.C1.3115 C1 - Excavate soil from Sub Basement for New Dental Additions
CN.C1.3120 C1 - Install 4 New Columns / Footers for New Slab of Dental addition (R - 6,7,8&9)
CN.C1.3125 C1 - Inspect/Perform any repair required to Sub basement Waterproofing / Moisture Membrane
CN.C1.3130 C1 - Install any Underdrain Plumbing / utilities
CN.C1.3135 C1 - Fill with Expanded Polystyrene Foam (EPF) for slab subgrade
CN.C1.3140 C1 - Form, Rebar & Pour Floor Slab for Dental Addition
CN.C1.3145 C1 - Install Exterior Walls Cast-in-Place for Dental Addition
CN.C1.3150 C1 - Install Roof Deck System, New Flashing Roof Expansion Joint, Insulation & EPDM Membrane
CN.C1.3155 C1 - Fill gaps between Dental Additi on & HVAC Towers with Expansion Joint & Covers
CN.C1.3160 C1 - Install Water Collecting Roof
CN.C1.3165 C1 - Install Ribbon Windows
CN.C1.3170 C1 - Install New Dental Addition Entryway
CN.C1.3175 C1 - Extend Concrete Snow Melt System / Install New North Entry Sidewalk & Ramp
CN.C1.3180 C1 - Replace/Restore Sod around Dental Addition
Dental Addition Fit-Out
CN.C1.3185 C1 - Initial Outfitting and Transition( IO&T)/DRMO - Ground Level C1
Phase C2 - West Dental Area
Move Out - West Dental Area C2
CN.C2.3202 C2 - IO&T Coordinate Teardown/Reconfiguring Exisi tng Inventory/Reuse Items
CN.C2.3204 C2 - IO&T Relocate / Move Out Exiting Staff & Operations - Ground Level W C2
CN.C2.3206 C2 - IO&T Remove & Transport All Dissasembled Furniture / Eqpt to a Storage Warehouse for Reuse or Disposition
Temporary Construction Barrier C2
CN.C2-3208 C2 - Construct Temporary Construction Barriers (UF33 to UF18 & UF8 to UF15)
CN.C2-3210 C2 - Construct Temporary Construction Barriers (UE23 to UE03 & UE02 to UE03)
Renovations - West Dental Area C2
Dental Department West Side (DIPC)
CN.C2.3225 C2 - Install Interior MEP for Dental Addition (Including AHU#10 in Mech Rm)
CN.C2.3235 C2 - Demolition/Modifications of Existing Dental West Wall
CN.C2.3222 C2 - Remove Existing AHU-10 in UF41 (Install Temp AHU if Reqd)
CN.C2.3220 C2 - Removal of Existing Interior Gypsum Wallboard & Thermal Insulation
CN.C2.3230 C2 - Install Interior Walls and Mechanical Room in New Dental Addition
CN.C2.3215 C2 - NOTE: Existing Waiting & Reception Remains Open
CN.C2.3213 C2 - Renovation West Half of Dental
CN.C2.3226 C2 - Set & Install AHU-10 (New and Exisitng AHU 10 shall not operate Simultaneously)
CN.C2.3224 C2 - Install New AHU 10 (Services New Dental Area, W 1/2 of Dental & Temp Air to E Dental)
CN.C2.3228 C2 - Install HVAC & Dutwork in New Dental Area
CN.C2.3241 C2 - Install Interior Doors Systems & Hardware
CN.C2.3237 C2 - Replace Exterior Walls w/Rigid Phenolic Foam Insulation, Air Barrier/ Vapor Retarder&New Gypsum Wallboard P2.
CN.C2.3245 C2 - Add Temporary Drops for New Ceiling
CN.C2.3243 C2 - Install Interior Finishes / Ceiling / Wall Based Materials Flooring / Paint / Doors/ etc
Fire Alarm / Fire Suppression New Dental Addition
CN.C2.3249 C2 - 1GLU-Fire Detection in New Dental Addition
CN.C2.3247 C2 - Fire Suppression System in New Dental Addi tion
CN.C2.3259 C2 - Demolition of Fire Protection Lower Level SPD
CN.C2.3251 C2 - Smoke Detection in New Dental Addit ion
CN.C2.3253 C2 - Fire/Smoke Indicating Lamps in New Dental Addition
CN.C2.3255 C2 - Strobes/Horns Speaker Systems * Connected to hospital PA system in New Dental Addition
CN.C2.3257 C2 - Fire Alarm Control Panel i n New Dental Addition
Fire Alarm / Fire Suppression West Dental Area
CN.C2.3263 C2 - Relocate Fire Suppression Pipe West Dental Area
CN.C2.3265 C2 - Smoke Detection West Dental Area
CN.C2.3274 C2 - Renovation of Fire Alarm System & Control Panel West Dental Area
CN.C2.3372 C2 - Install new Fire Alarm/Mass Notification Devised and Wir ing West Dental Area
CN.C2.3270 C2 - Fire/Smoke Indicating Lamps West Dental Area
CN.C2.3276 C2 - Strobes/Horns Speaker Systems * Connected to hospital PA system West Dental Area
Start Date: 01-Oct-18 Finish Date: 26-Feb-24
Data Date: 19-Jul-19 Run Date: 04-Feb-21
Time: 09:08
Level of Effort
Actual Work
Remaining Work
Critical Remaining W...
CN.C2.3277 C2 - Remove Existing Devices after entire New Al arm/Mass Notificat ion Zone can be active15 02-Dec-21 22-Dec-21 9
CN.C2.3278 C2 - Install Fire Al arm Control Panel West Dental Area 10 09-Dec-21 22-Dec-21 9
CeilingCeiling 20 12-Oct-21 08-Nov-21 571
CN.C2.3284 C2 - Add Temporary Drops for New Ceiling Phase 2 Lower Level SPD 20 12-Oct-21 08-Nov-21 571
Sprinker SystemSprinker System 30 27-Aug-21 08-Oct-21 0
CN.C2.3286 C2 - Modify Existing Sprinkler System (As needed) 15 27-Aug-21 17-Sep-21 0
CN.C2.3288 C2 - Install New Fire Sprinklers for West 1/2 of Dental Clinic 20 13-Sep-21 08-Oct-21 0
ElectricalElectrical 20 13-Sep-21 08-Oct-21 28
CN.C2. 3289 C2 - install Electrical Eqpt, Fixtures, Wire, Pull & Term 20 13-Sep-21 08-Oct-21 28
PlumbingPlumbing 40 11-Oct-21 07-Dec-21 563
Sanitary WasteSanitary Waste 20 11-Oct-21 05-Nov-21 563
CN.C2.3290 C2 - Install Plumbing in New Dental Addition - Sanitary Waste 20 11-Oct-21 05-Nov-21 563
Domestic Hot & Cold WaterDomestic Hot & Cold Water 20 08-Nov-21 07-Dec-21 563
CN.C2.3292 C2 - Install Plumbing in New Dental Addition - Hot & Cold Water (include new Heating Hot Water Ppg)20 08-Nov-21 07-Dec-21 563
Medical GasesMedical Gases 40 11-Oct-21 07-Dec-21 0
CN.C2.3293 C2 - Remove existing Dental Gas Eqpt in Mech Rm UF41(New and Existing Gas Eqpt shall not operate Simultaneously)20 11-Oct-21 05-Nov-21 0
CN.C2.3294 C2 - Install Medical Gases in New Dental Area 20 08-Nov-21 07-Dec-21 0
Communication / Mass Notification SystemsCommunication / Mass Notification Systems 34 08-Dec-21 27-Jan-22 11
TelecommunicationTelecommunication 20 08-Dec-21 06-Jan-22 0
CN.C2.3300 C2 - Install Telecommunications in New Dental Area 20 08-Dec-21 06-Jan-22 0
Nurse Call SystemNurse Call System 20 08-Dec-21 06-Jan-22 0
CN.C2.3305 C2 - Install Nurse Call system equipment & devices New Dental Area 20 08-Dec-21 06-Jan-22 0
Public Address SystemPublic Address System 20 08-Dec-21 06-Jan-22 0
CN.C2.3310 C2 - Install Voice / Data, Paging System Speakers in New Dental Area 20 08-Dec-21 06-Jan-22 0
Security SystemSecurity System 15 15-Dec-21 06-Jan-22 25
CN.C2.3350 C2 - Install Security System Devices 15 15-Dec-21 06-Jan-22 25
Cable TVCable TV 20 08-Dec-21 06-Jan-22 0
CN.C2.3315 C2 - Install Cable TV in New Dental Area 20 08-Dec-21 06-Jan-22 0
Refrigeration Monitoring SystemRefrigeration Monitoring System 15 07-Jan-22 27-Jan-22 0
CN.C2.3320 C2 - Install Refrigeration Monitoring System (If Reqd) 15 07-Jan-22 27-Jan-22 0
Fit-Out - West Dental Area C2Fit-Out - West Dental Area C2 25 07-Jan-22 11-Feb-22 0
CN.C2.3325 C2 - Initial Outfitting and Transition( IO&T)/DRMO 25 07-Jan-22 11-Feb-22 0
S/U & Commissioning - West Dental Area C2S/U & Commissioning - West Dental Area C2 20 14-Feb-22 14-Mar-22 488
CN.C2.3330 C2 - Complete Punchlist 20 14-Feb-22 14-Mar-22 450
SU.GL.7000 C2 - S/U & Commissioning 10 14-Feb-22 25-Feb-22 0
CN.C2.3335 C2 - Complete and Available 0 25-Feb-22 499
Move In - West Dental Area C2Move In - West Dental Area C2 10 28-Feb-22 11-Mar-22 0
CN.C2.3340 Move In Staff & Operations - Ground Level W C2 10 28-Feb-22 11-Mar-22 0
Phase C3 - Dental Are NE for Temporary Dental SpacesPhase C3 - Dental Are NE for Temporary Dental Spaces 100 28-Dec-21 20-May-22 401
SPD Staff moved into Permanent Space / Remove Temporary SPD TrailerSPD Staff moved into Permanent Space / Remove Temporary SPD Trailer 0 28-Dec-21 28-Dec-21 420
CN.C3.3400 SPD Staff Move in Permanent Space 0 28-Dec-21 420
Remove SPD TrailerRemove SPD Trailer 81 29-Dec-21 25-Apr-22 420
CN.C3.3405 C3 - Initial Outfitting and Transition( IO&T)/DRMO - Remove SPD Trailer Complex 15 29-Dec-21 20-Jan-22 486
CN.C3.3403 C3 - Remove Mobile SPD Trail er and Restore Area 21 29-Dec-21 28-Jan-22 420
CN.C3.3407 C3 - IO&T Remove & Transport C3l Dissasembled Furniture / Eqpt to a Storage Warehouse for Reuse or Disposition Rmv SPD10 06-Jan-22 20-Jan-22 486
CN.C3.3409 C3 - Ship SPD Trailer back (from Japan to USA) 60 31-Jan-22 25-Apr-22 420
Modify Existing Sprinklers as neededModify Existing Sprinklers as needed 15 14-Mar-22 01-Apr-22 0
CN.C3.3412 C3 - Modify Existing Sprinklers (as needed) Dental Area NE 15 14-Mar-22 01-Apr-22 0
ElectricalElectrical 20 14-Mar-22 08-Apr-22 0
CN.C3.3414 C3 - install Electrical Eqpt, Fixtures, Wire, Pull & Term 20 14-Mar-22 08-Apr-22 0
Install Voice / Data, paging System Speakers, & Security System DevicesInstall Voice / Data, paging System Speakers, & Security System Devices 15 04-Apr-22 22-Apr-22 20
CN.C3.3422 C3 - Install Voice / Data, Paging System Speakers & Security System Devices Dental Area NE15 04-Apr-22 22-Apr-22 20
Install New Nurse Cal System Equipment & DevicesInstall New Nurse Cal System Equipment & Devices 15 11-Apr-22 29-Apr-22 0
CN.C3.3432 C3 - Install New Nurse Call System Equipment and Devices Dental Area NE 15 11-Apr-22 29-Apr-22 0
UtilitiesUtilities 15 04-Apr-22 22-Apr-22 5
CN.C3.3434 C3 - Utilities are to remain in place & capped such as they do not impeded parking, driving lanes or sidewalks15 04-Apr-22 22-Apr-22 5
Provide Workstations with DataProvide Workstations with Data 20 04-Apr-22 29-Apr-22 15
CN.C3.3436 C3 - Provide Workstations with Data (2 in UE03, 8 Sm in UE02 & 2 in UE01) Dental Area NE20 04-Apr-22 29-Apr-22 15
Move In - SE Dental Area C3Move In - SE Dental Area C3 15 02-May-22 20-May-22 0
CN.C3.3440 Initial Outfitting and Transition(IO&T) /DRMO - Ground Level NE C3 15 02-May-22 20-May-22 0
Phase C4 - Dental Area SEPhase C4 - Dental Area SE 238 23-May-22 04-May-23 163
Move Out - SE Dental Area C4Move Out - SE Dental Area C4 20 23-May-22 20-Jun-22 0
Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2019 2020 2021 2022 2023 2024 2025 2026
CN.C2.3277 C2 - Remove Existing Devices after entire New Al arm/Mass Notificat ion Zone can be active
CN.C2.3278 C2 - Install Fire Al arm Control Panel West Dental Area
Ceiling
CN.C2.3284 C2 - Add Temporary Drops for New Ceiling Phase 2 Lower Level SPD
Sprinker System
CN.C2.3286 C2 - Modify Existing Sprinkler System (As needed)
CN.C2.3288 C2 - Install New Fire Sprinklers for West 1/2 of Dental Clinic
Electrical
CN.C2. 3289 C2 - install Electrical Eqpt, Fixtures, Wire, Pull & Term
Plumbing
Sanitary Waste
CN.C2.3290 C2 - Install Plumbing in New Dental Addition - Sanitary Waste
Domestic Hot & Cold Water
CN.C2.3292 C2 - Install Plumbing in New Dental Addition - Hot & Cold Water (include new Heating Hot Water Ppg)
Medical Gases
CN.C2.3293 C2 - Remove existing Dental Gas Eqpt in Mech Rm UF41(New and Existing Gas Eqpt shall not operate Simultaneously)
CN.C2.3294 C2 - Install Medical Gases in New Dental Area
Communication / Mass Notification Systems
Telecommunication
CN.C2.3300 C2 - Install Telecommunications in New Dental Area
Nurse Call System
CN.C2.3305 C2 - Install Nurse Call system equipment & devices New Dental Area
Public Address System
CN.C2.3310 C2 - Install Voice / Data, Paging System Speakers in New Dental Area
Security System
CN.C2.3350 C2 - Install Security System Devices
Cable TV
CN.C2.3315 C2 - Install Cable TV in New Dental Area
Refrigeration Monitoring System
CN.C2.3320 C2 - Install Refrigeration Monitoring System (If Reqd)
Fit-Out - West Dental Area C2
CN.C2.3325 C2 - Initial Outfitting and Transition( IO&T)/DRMO
S/U & Commissioning - West Dental Area C2
CN.C2.3330 C2 - Complete Punchlist
SU.GL.7000 C2 - S/U & Commissioning
CN.C2.3335 C2 - Complete and Available
Move In - West Dental Area C2
CN.C2.3340 Move In Staff & Operations - Ground Level W C2
Phase C3 - Dental Are NE for Temporary Dental Spaces
SPD Staff moved into Permanent Space / Remove Temporary SPD Trailer
CN.C3.3400 SPD Staff Move in Permanent Space
Remove SPD Trailer
CN.C3.3405 C3 - Initial Outfitting and Transition( IO&T)/DRMO - Remove SPD Trailer Complex
CN.C3.3403 C3 - Remove Mobile SPD Trail er and Restore Area
CN.C3.3407 C3 - IO&T Remove & Transport C3l Dissasembled Furniture / Eqpt to a Storage Warehouse for Reuse or Disposition Rmv SPD
CN.C3.3409 C3 - Ship SPD Trailer back (from Japan to USA)
Modify Existing Sprinklers as needed
CN.C3.3412 C3 - Modify Existing Sprinklers (as needed) Dental Area NE
Electrical
CN.C3.3414 C3 - install Electrical Eqpt, Fixtures, Wire, Pull & Term
Install Voice / Data, paging System Speakers, & Security System Devices
CN.C3.3422 C3 - Install Voice / Data, Paging System Speakers & Security System Devices Dental Area NE
Install New Nurse Cal System Equipment & Devices
CN.C3.3432 C3 - Install New Nurse Call System Equipment and Devices Dental Area NE
Utilities
CN.C3.3434 C3 - Utilities are to remain in place & capped such as they do not impeded parking, driving lanes or sidewalks
Provide Workstations with Data
CN.C3.3436 C3 - Provide Workstations with Data (2 in UE03, 8 Sm in UE02 & 2 in UE01) Dental Area NE
Move In - SE Dental Area C3
CN.C3.3440 Initial Outfitting and Transition(IO&T) /DRMO - Ground Level NE C3
Phase C4 - Dental Area SE
Move Out - SE Dental Area C4
Start Date: 01-Oct-18 Finish Date: 26-Feb-24
Data Date: 19-Jul-19 Run Date: 04-Feb-21
Time: 09:08
Level of Effort
Actual Work
Remaining Work
Critical Remaining W...
CN.C4.3505 C4 - IO&T Coordinate Teardown/Reconfiguring Exisi tng Inventory/Reuse Items 5 23-May-22 27-May-22 0
CN.C4.3500 C4 - IO&T Relocate / Move Out Exiting Staff & Operations 15 31-May-22 20-Jun-22 0
CN.C4.3510 C4 - IO&T Remove & Transport All Dissasembled Furniture / Equipment to a Storage Warehouse for Reuse or Disposition10 06-Jun-22 17-Jun-22 1
Temporary Construction Barrier C4Temporary Construction Barrier C4 10 31-May-22 13-Jun-22 5
CN.C4-3511 C4 - Construct Temporary Construction Barriers (UE21 & UE16 to UE13) 5 31-May-22 06-Jun-22 5
CN.C4-3512 C4 - Construct Temporary Construction Barriers (UE26 & UF07) 5 07-Jun-22 13-Jun-22 5
Renovation - SE Dental Area C4Renovation - SE Dental Area C4 183 21-Jun-22 16-Mar-23 15
CN.C4.3518 C4 - Renovation SE 1/4 Dental (Mainly Admin Functions) 90 21-Jun-22 26-Oct-22 0
CN.C4.3519 C2 -Extend AHU 10 & Dental G ases to SE 1/4 of Dental Dept 20 24-Aug-22 21-Sep-22 10
Fire Alarm / Fire SuppressionFire Alarm / Fire Suppression 89 06-Oct-22 16-Feb-23 24
CN.C4.3520 C4 - Install Fire Suppression Pipe 20 06-Oct-22 02-Nov-22 0
CN.C4.3530 C4 - Renovation of Fire Suppression 10 03-Nov-22 17-Nov-22 34
CN.C4.3535 C4 - Install New Fire Al arm System & Control Panel 10 18-Nov-22 05-Dec-22 34
CN.C4.3542 C4 - Install new Fire Alarm/Mass Notification Devised and Wir ing Phase 10 06-Dec-22 19-Dec-22 34
CN.C4.3540 C4 - Fire Detection Phase 10 06-Dec-22 19-Dec-22 24
CN.C4.3546 C4 - Relocate Fire Suppression Piping (as needed) 10 20-Dec-22 04-Jan-23 34
CN.C4.3544 C4 - Smoke Detection 10 20-Dec-22 04-Jan-23 24
CN.C4.3550 C4 - Fire/Smoke Indicating Lamps 10 05-Jan-23 19-Jan-23 24
CN.C4.3560 C4 - Strobes/Horns Speaker Systems * Connected to hospital PA System 10 20-Jan-23 02-Feb-23 24
CN.C4.3562 C4 - Install Fire Al arm Control Panel 10 03-Feb-23 16-Feb-23 24
Sprinker SystemSprinker System 25 03-Nov-22 12-Dec-22 0
CN.C4.3564 C4 - Modify Existing Sprinkler System (As needed) 20 03-Nov-22 05-Dec-22 0
CN.C4.3566 C4 - Install new Sprinklers for west half of dental clinic 5 06-Dec-22 12-Dec-22 0
Fire ProtectionFire Protection 25 13-Dec-22 19-Jan-23 0
CN.C4.3568 C4 - Fire Protection Demolition Plan 5 13-Dec-22 19-Dec-22 0
CN.C4.3570 C4 - Demolition of Fire Protection 20 20-Dec-22 19-Jan-23 0
ElectricalElectrical 20 03-Nov-22 05-Dec-22 50
CN.C4.3572 C4 - install Electrical Eqpt, Fixtures, Wire, Pull & Term 20 03-Nov-22 05-Dec-22 50
PlumbingPlumbing 20 20-Jan-23 16-Feb-23 0
Sanitary WasteSanitary Waste 10 20-Jan-23 02-Feb-23 0
CN.C4.3580 C4 - Renovate Sanitary Waste Plumbing (as Require) 10 20-Jan-23 02-Feb-23 0
Domestic Hot & Cold WaterDomestic Hot & Cold Water 10 03-Feb-23 16-Feb-23 0
CN.C4.3582 C4 - Renovate Domestic Hot & Cold Water Plumbing (as Required) 10 03-Feb-23 16-Feb-23 0
Communication / Mass Notification SystemsCommunication / Mass Notification Systems 19 17-Feb-23 16-Mar-23 15
TelecommunicationTelecommunication 10 17-Feb-23 02-Mar-23 0
CN.C4.3584 C4 - Install Telecommunications 10 17-Feb-23 02-Mar-23 0
Nurse Call SystemNurse Call System 19 17-Feb-23 16-Mar-23 15
CN.C4.3586 C4 - Install Nurse Call Devices & Wiring 10 17-Feb-23 02-Mar-23 15
CN.C4.3588 C4 - Remove Existing Devices (Old Devices Stay in Service until entire New Alarm/Mass Noti fication Zone can be Active10 03-Mar-23 16-Mar-23 15
Public Address SystemPublic Address System 10 17-Feb-23 02-Mar-23 15
CN.C4.3590 C4 - Install Voice / Data, Paging System Speakers 10 17-Feb-23 02-Mar-23 15
Security SystemSecurity System 15 17-Feb-23 10-Mar-23 19
CN.C4.3592 C4 - Install Security System Devices 15 17-Feb-23 10-Mar-23 19
Cable TVCable TV 10 17-Feb-23 02-Mar-23 25
CN.C4.3594 C4 - Install Cable TV 10 17-Feb-23 02-Mar-23 25
Fit-Out - SE Dental Area C4Fit-Out - SE Dental Area C4 15 03-Mar-23 23-Mar-23 0
CN.C4.3595 C4 - Initial Outfitting and Transition( IO&T)/DRMO 15 03-Mar-23 23-Mar-23 0
S/U & Commissioning - SE Dental Area C4S/U & Commissioning - SE Dental Area C4 25 24-Mar-23 27-Apr-23 168
SU.GL.3596 C4 - S/U & Commissioning 10 24-Mar-23 06-Apr-23 0
CN.C4.3597 C4 - Area Complete and Available 0 06-Apr-23 0
CN.C4.3598 C4 - Complete Punchlist 15 07-Apr-23 27-Apr-23 168
Move In - SE Dental Area C4Move In - SE Dental Area C4 20 07-Apr-23 04-May-23 0
CN.C4.3599 Initial Outfitting and Transition(IO&T) /DRMO - Ground Level SE C4 20 07-Apr-23 04-May-23 0
Phase C5 - Dental Area NE Final RenovationsPhase C5 - Dental Area NE Final Renovations 163 05-May-23 29-Dec-23 0
Move Out - NE Dental Area C5Move Out - NE Dental Area C5 20 05-May-23 02-Jun-23 0
CN.C5.3600 C5 - IO&T Coordinate Teardown/Reconfiguring Exisi tng Inventory/Reuse Items 5 05-May-23 11-May-23 0
CN.C5.3605 C5 - IO&T Relocate / Move Out Exiting Staff & Operations 15 12-May-23 02-Jun-23 0
CN.C5.3607 C5 - IO&T Remove & Transport All Dissasembled Furniture / Equipment to a Storage Warehouse for Reuse or Disposition10 18-May-23 01-Jun-23 1
Temporary Construction Barrier C5Temporary Construction Barrier C5 5 12-May-23 18-May-23 10
CN.C5.3610 C5 - Construct Temporary Construction Barriers (UE21 to UE22 & UE65) 5 12-May-23 18-May-23 10
Renovation - NE Dental Area C5Renovation - NE Dental Area C5 123 05-Jun-23 30-Nov-23 0
CN.C5.3620 C5 - Renovation NE 1/2 Dental (Mainly Admin Functions) 90 05-Jun-23 10-Oct-23 0
Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2019 2020 2021 2022 2023 2024 2025 2026
CN.C4.3505 C4 - IO&T Coordinate Teardown/Reconfiguring Exisi tng Inventory/Reuse Items
CN.C4.3500 C4 - IO&T Relocate / Move Out Exiting Staff & Operations
CN.C4.3510 C4 - IO&T Remove & Transport All Dissasembled Furniture / Equipment to a Storage Warehouse for Reuse or D
Temporary Construction Barrier C4
CN.C4-3511 C4 - Construct Temporary Construction Barriers (UE21 & UE16 to UE13)
CN.C4-3512 C4 - Construct Temporary Construction Barriers (UE26 & UF07)
Renovation - SE Dental Area C4
CN.C4.3518 C4 - Renovation SE 1/4 Dental (Mainly Admin Functions)
CN.C4.3519 C2 -Extend AHU 10 & Dental G ases to SE 1/4 of Dental Dept
Fire Alarm / Fire Suppression
CN.C4.3520 C4 - Install Fire Suppression Pipe
CN.C4.3530 C4 - Renovation of Fire Suppression
CN.C4.3535 C4 - Install New Fire Al arm System & Control Panel
CN.C4.3542 C4 - Install new Fire Alarm/Mass Notification Devised and Wir ing Phase
CN.C4.3540 C4 - Fire Detection Phase
CN.C4.3546 C4 - Relocate Fire Suppression Piping (as needed)
CN.C4.3544 C4 - Smoke Detection
CN.C4.3550 C4 - Fire/Smoke Indicating Lamps
CN.C4.3560 C4 - Strobes/Horns Speaker Systems * Connected to hospital PA System
CN.C4.3562 C4 - Install Fire Alarm Control Panel
Sprinker System
CN.C4.3564 C4 - Modify Existing Sprinkler System (As needed)
CN.C4.3566 C4 - Install new Sprinklers for west half of dental clinic
Fire Protection
CN.C4.3568 C4 - Fire Protection Demolition Plan
CN.C4.3570 C4 - Demolition of Fire Protection
Electrical
CN.C4.3572 C4 - install Electrical Eqpt, Fixtures, Wire, Pull & Term
Plumbing
Sanitary Waste
CN.C4.3580 C4 - Renovate Sanitary Waste Plumbing (as Require)
Domestic Hot & Cold Water
CN.C4.3582 C4 - Renovate Domestic Hot & Cold Water Plumbing (as Required)
Communication / Mass Notification Systems
Telecommunication
CN.C4.3584 C4 - Install Telecommunications
Nurse Call System
CN.C4.3586 C4 - Install Nurse Call Devices & Wiring
CN.C4.3588 C4 - Remove Existing Devices (Old Devices Stay in Service until entire New Alarm/Mass No
Public Address System
CN.C4.3590 C4 - Install Voice / Data, Paging System Speakers
Security System
CN.C4.3592 C4 - Install Security System Devices
Cable TV
CN.C4.3594 C4 - Install Cable TV
Fit-Out - SE Dental Area C4
CN.C4.3595 C4 - Initial Outfitting and Transition( IO&T)/DRMO
S/U & Commissioning - SE Dental Area C4
SU.GL.3596 C4 - S/U & Commissioning
CN.C4.3597 C4 - Area Complete and Available
CN.C4.3598 C4 - Complete Punchlist
Move In - SE Dental Area C4
CN.C4.3599 Initial Outfitting and Transition(IO&T) /DRMO - Ground Level SE C4
Phase C5 - Dental Area NE Final Renovations
Move Out - NE Dental Area C5
CN.C5.3600 C5 - IO&T Coordinate Teardown/Reconfiguring Exisi tng Inventory/Reuse Items
CN.C5.3605 C5 - IO&T Relocate / Move Out Exiting Staff & Operations
CN.C5.3607 C5 - IO&T Remove & Transport All Dissasembled Furniture / Equipment to a Storage Wa
Temporary Construction Barrier C5
CN.C5.3610 C5 - Construct Temporary Construction Barriers (UE21 to UE22 & UE65)
Renovation - NE Dental Area C5
CN.C5.3620 C5 - Renovation NE 1/2 Dental (Mainly Admin Functions)
Start Date: 01-Oct-18 Finish Date: 26-Feb-24
Data Date: 19-Jul-19 Run Date: 04-Feb-21
Time: 09:08
Level of Effort
Actual Work
Remaining Work
Critical Remaining W...
Sprinker SystemSprinker System 20 11-Oct-23 07-Nov-23 0
CN.C5.3625 C5 - Modify Existing Sprinkler System (As needed) 20 11-Oct-23 07-Nov-23 0
ElectricalElectrical 20 11-Oct-23 07-Nov-23 0
CN.C5.3630 A2 - install Electrical Eqpt, Fixtures, Wire, Pull & Term 20 11-Oct-23 07-Nov-23 0
Communication / Mass Notification SystemsCommunication / Mass Notification Systems 35 11-Oct-23 30-Nov-23 0
TelecommunicationTelecommunication 15 08-Nov-23 30-Nov-23 0
CN.C5.3635 C5 - Install Telecommunications 15 08-Nov-23 30-Nov-23 0
Nurse Call SystemNurse Call System 15 08-Nov-23 30-Nov-23 0
CN.C5.3637 C5 - install Nurse Call System 15 08-Nov-23 30-Nov-23 0
Public Address SystemPublic Address System 15 11-Oct-23 31-Oct-23 20
CN.C5.3639 C5 - Install Public Address System 15 11-Oct-23 31-Oct-23 20
Cable TVCable TV 15 11-Oct-23 31-Oct-23 20
CN.C5.3641 C5 - Install Cable TV 15 11-Oct-23 31-Oct-23 20
Fit-Out - NE Dental Area C5Fit-Out - NE Dental Area C5 0 30-Nov-23 30-Nov-23 0
CN.C5.3645 C5 - NOTE: No Construction Pause for IO&T 0 30-Nov-23 0
S/U & Commissioning - NE Dental Area C5S/U &…
This is the start of the file's text. The full file is on GovTribe.