SEED_SOW_App_D_16-0123_FGUA_Fee_Inspection_Memo.pdf
PDF 61 KB Posted
- Attached to
- Multiple Award Construction Contract
- Solicitation number
- FA481419RA001
About this file
This memo from the Florida Governmental Utility Authority provides estimated construction inspection fees for water and sewer utility modifications related to the repair and renovation of HVAC and a communications facility at MacDill Air Force Base. The fees are based on a review of 95% design plans and total $1,890 for service outages, terminations if needed, and all FGUA inspections for water and wastewater utility work impacting FGUA facilities. An additional $1,495 fee is listed for a temporary construction water meter, which includes a $500 refundable deposit. The memo outlines required FGUA coordination including a pre-construction meeting and final inspection to determine if work meets standards, as well as contact information for scheduling inspections during construction.
Solicitation Package
View the file
Other files
Show 40 more
Latest 50 of 57 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FGUA Board of Directors LEA ANN THOMAS, Chair, Polk County / DOUG MEURER, P.E., Lee County / KEN CHEEK, P.E., Citrus County
SHANE PARKER, P.E., Hendry County / MICHAEL CARBALLA, Pasco County / ANGEL ROUSSEL, P.E., Marion County
FGUA Operations Office
Government Services Group, Inc.
280 Wekiva Springs Rd., Suite 2070
Longwood, FL 32779-6026
(877) 552-3482 Toll Free
(407) 629-6900 Tel
(407) 629-6963 Fax
WATER & SEWER UTILITY CONSTRUCTION FEES
TO: Brian Boyle, Utilities Privatization, GS-11 USAF AMC 6 CES/CEP
FROM: Michael Wilson, FGUA Utility Manager
DATE: September 28, 2018
SUBJECT: NVZR 16-0123 - Repair HVAC & Renovate Comm Facility B262
The FGUA has reviewed the 95% Design Plans print dated September 26, 2018 for the above-referenced project and provides this memo regarding estimated utility outage and construction inspection fees for modifications to the FGUA utility system related to this project.
FGUA Inspection Requirements - All FGUA Inspections require72 Hour Notification
Three stages of coordination between the construction contractor (Contractor) and FGUA are required: Pre-construction Meeting, Construction Inspections, and Final Inspection. The purpose of the FGUA inspections is to determine if the WORK meets
Hillsborough County Technical Specifications and provide notification to the Government if deviations are observed that will affect FGUA ownership of the completed WORK. Final acceptance of the WORK remains the responsibility of your (Contractor’s) work to meet standards. It is the Contractor’s responsibility to notify the FGUA if water or sewer connection/construction activity is anticipated and to schedule these meetings. Please provide at least one-week notice of any scheduled meeting. During the
Pre-Construction meeting, the FGUA will provide specific project inspection requirements, and procedures for contacting and scheduling inspections with the FGUA. FGUA point of contact is Jim Gorry 727-809-0914.
Prior to commencing any site work, the Contractor shall complete and submit AF Form 103 and FGUA Form 427 with appropriate fees to the FGUA Utility Operations Center located at 9109 Bayshore Boulevard, Bldg. 84 (on-base WWTP). All plan and shop drawing submittal review will remain the responsibility of the Government Agency contracting the WORK. Please refer also to the MacDill Design Guide for information regarding service termination, service outage, service connection, temporary construction water meter, etc. All fees are paid in advance to the FGUA prior to any Utility Work commencement.
Construction & Inspection Fees
Fees are based upon review of the 95% Design Plans print dated September 26, 2018. Fees are subject to modification upon receipt of additional documentation. As a courtesy to the Government, the FGUA reviews early versions of the WORK and provides estimated fees, however we cannot guarantee that the Inspection Fees quoted will be complete without the benefit of final documents or 100% plans.
The following items are covered under the cost shown below:
Water and/or sewer service outages and termination(s) by the FGUA – water outage
All FGUA inspections (water & wastewater utilities only) – included for construction work impacting FGUA facilities
*One Temporary Construction Water Meter with BFPD - installed and removed by FGUA
We appreciate the opportunity to be of service to MacDill AFB, and its construction contractors and look forward to assisting in your successful completion of your project.
Service Outages & Inspection Fees, Project NVZR 16-0123 (Repair HVAC & Renovate Comm Facility B262): $1,890.00
*Temporary Construction Water Meter: $1,495.00 (includes $500 refundable deposit)