This is an AF Form 3064 (Contract Progress Schedule), a Department of Defense template used to track and report progress on federal contracts. The form is approved under OMB No. 0704-0188 and carries an estimated public reporting burden of 15 minutes per response.

The form provides fields for essential contract identification and tracking information, including contract number (FA480324C0036), project title, award date, completion date, purchase requisition number, project number, and Notice to Proceed (NTP) date. It includes sections for the contractor's name, address, and signature, as well as approval signatures from the installation engineer and contracting officer. The primary function of this form is to display work elements broken down by line item and track scheduled versus actual completion percentages across multiple reporting periods spanning from June through January, with each month divided into two 15-day periods. The form contains 30 numbered rows for work elements and includes summary rows for calculating scheduled completion, actual completion, and total percentages. This is a template document without specific contract details populated, serving as a blank form for contractors to report their progress on Air Force contracts.

View the file

Other files

File Type Posted
Attachment 15-REAL ID Act -Shaw AFB Access Handout.pdf PDF
Attachment 16-CONTRACTOR MEMO (optional_informational).pdf PDF
Attachment 17-B611 HVAC Repair Sign In Sheet-3 Feb 26.pdf PDF
Attachment 03-2022_Appendices_Shaw AFB HM_SW_HW_Refrigerant Requirements-6 Jan 26.pdf PDF
Attachment 09-AF form 66 03.27.2025.pdf PDF
Attachment 18-B611 HVAC Repair-Contractor Questions-Answers-4 Mar 26.pdf PDF
Attachment 01-SOW Revised VLSB 24-0032 Repair HVAC B611 03.03.2026.pdf PDF
Attachment 02-Blank Pricing Sheet VLSB 24-0032 B611 HVAC Repair-6 Jan 26.pdf PDF
Attachment 04-2023_SOW Template_Contract Environmental Provisions_FINAL-7 Feb 23.pdf PDF
Solicitation Amendment FA480326B00010001.pdf PDF
Attachment 14-Base Access Template (CAO Jul 24).pdf PDF
Attachment 03-2022_Appendices_Shaw AFB HM_SW_HW_Refrigerant Requirements-6 Jan 26.docx DOCX document
Attachment 05-Mechanical Layout-Sep 07.pdf PDF
Attachment 08-Shaw AFB Design Standards 21 Aug 18.pdf PDF
Attachment 15-REAL ID Act -Shaw AFB Access Handout.docx DOCX document
Attachment 06-Ltd Asb Survey Report 3-18-25.pdf PDF
Attachment 09-AF form 66 03.27.2025.xlsx XLSX spreadsheet
Solicitation - FA480326B0001.pdf PDF
Attachment 01-SOW VLSB-24-0032 B611 HVAC Repair- 11 Sep 25.pdf PDF
Attachment 02-Blank Pricing Sheet VLSB 24-0032 B611 HVAC Repair-6 Jan 26.xlsx XLSX spreadsheet
Attachment 04-2023_SOW Template_Contract Environmental Provisions_FINAL-7 Feb 23.docx DOCX document
Attachment 07-DD Form 1354 - AUG 2022.pdf PDF
Attachment 11-Progress Schedule Blank-1 Jun 90.xlsx XLSX spreadsheet
Attachment 12-SF 1413 Statement of Acknowledgment-01 Oct 23.pdf PDF
Attachment 14-Base Access Template (CAO Jul 24).docx DOCX document
Attachment 16-CONTRACTOR MEMO (optional_informational).docx DOCX document
Attachment 10-Progress Report Blank-1 Apr 96.pdf PDF
Attachment 13-Wage Determination-SC20260030-2 Jan 26.pdf PDF
Show all 28

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

8. PROJECT TITLE:

2. AWARD DATE

3. COMPLETION DATE 9. SUBMITTED BY:

4. PURCHASE REQ. NO.

5. PROJECT NO.

6. NTP DATE

LINE NO. % 1-15 16-30 1-15 16-31 1-15 16-30 1-15 16-31 1-15 16-31 1-15 16-28 1-15 16-31 1-15 16-30 1-15 16-31 1-15 16-30 15-Jan 16-31

A B C

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%

AF Form 3064, JUN 90 PREVIOUS EDITION IS OBSOLETE

Total

Scheduled Complete This Period

Actual Complete This Period

Scheduled Completed Total

Actual Completed Total

Jun M

Sept D

Oct E

Nov Dec G

Jan H

Feb I

Mar J

Apr K

May L

7. ACTUAL COMPLETION

DATE

WORK ELEMENTS

CONTRACT PROGRESS SCHEDULE Form Approved (See Contractor's Instructions on Reverse) OMB NO. 0704-0188

Public reporting burden for this collection of information is estimated to average 15 minutes per response. Including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden to Department of Defense, Washington Headquarters Services, Directorate for Information, Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington VA 22202- 4302, and to the Office of Management and Budget Paperwork Reduction Project 0704-0188, Washington DC 20503. Please DO NOT RETURN your form/questionnaire to either of these addresses. Send your completed form/questionnaire to: SAF/AQCP, 1060 Air Force Pentagon, Washington DC 20330- 1060.

Jul M

1. CONTRACT NUMBER

FA480324C0036

10. APPROVAL RECOMMENDED BY INSTALLATION ENGINEER:

DATE SIGNED

CONTRACTOR'S NAME, ADDRESS (Street, City, State, Zip) CONTRACTOR'S SIGNATURE: 11. APPROVED BY CONTRACTING OFFICER:

Schedule (2)

File details come from the government source that posted it. Updated .