Questions from the Pre Proposal Conference 19 Nov 21 Final.docx

DOCX document 308 KB Posted

Attached to
FY22 McConnell AFB - Multiple Award Construction Contract (MACC) Federal contract opportunity
Solicitation number
FA4621-22-R-0002
Issued by
Department of the Air Force Air Mobility Command

About this file

This document provides details for a Multiple Award Construction Contract solicitation issued by the 22nd Contracting Squadron of McConnell Air Force Base. The solicitation will result in the award of up to six firm-fixed price ID/IQ contracts for construction services with a total value not to exceed $75 million over six years. A variety of construction tasks are required including design-build, renovation, additions, upgrades, and repair of facilities, roadways, taxiways and runways. Offerors must be registered in SAM and have a current ORCA. Proposals will be evaluated using best value tradeoff with past performance significantly more important than price. A pre-proposal conference and site visit will take place on November 17th. Questions are due by November 11th and proposals are due by December 7th. The North American Industry Classification size standard for this total small business set-aside is $39.5 million.

View the file

Other files for this federal contract opportunity

Other files attached to FY22 McConnell AFB - Multiple Award Construction Contract (MACC), newest first.
File Type Posted
FA462122R0002 - Amendment 2.pdf PDF
Final Questions for MACC 2022.docx DOCX document
Warranty Barcode Spreadsheet.xlsx XLSX spreadsheet
Attach 18 - Updated TOC and Spec 26 51 00.pdf PDF
Attach 19 - Drawing changes 30 Nov 21.pdf PDF
conform-faqs.doc DOC document
B852 Site Visit Photos.pdf PDF
Attach 16 - Spec 28 31 76.pdf PDF
Attach 17 - Rev Drawings 11-22-2021.pdf PDF
FA462122R0002 - Amendment 1.pdf PDF
1029383 Asbestos Survey - Final.pdf PDF
Boeing Trainer PDF.pdf PDF
Pre-Proposal Conference Meeting Minutes w Attachments - FA4621-22-R-0002 - 23 Nov 21.pdf PDF
Pre Site Visit Q and As Final responses.docx DOCX document
Existing Mechanical Schedules.pdf PDF
Attach 1 - General Statement of Work (SOW).pdf PDF
Attach 13 - PRQE 063118 Phasing Plan.pdf PDF
Solicitation - FA462122R0002 11-5 Final.pdf PDF
Attach 2 - MACC Combined Spec Sections.pdf PDF
Attach 7 - Wage Det Residential KS02 - 1 Jan 21.pdf PDF
Attach 10 - PRQE 063118 Statement of Work (SOW).pdf PDF
Attach 11 - PRQE 063118 Specifications.pdf PDF
Attach 12 - PRQE 063118 Drawings.pdf PDF
Attach 14 - PRQE 063118 Submittal Register.xls XLS spreadsheet
Attach 3 - MACC General Conditions.pdf PDF
Attach 6 - Wage Det Highway KS47 - 25 Jun 21.pdf PDF
Attach 9 - PRQE 063118 Price Schedule.xlsx XLSX spreadsheet
Attach 15 - NAF General Provisions 2021.pdf PDF
Attach 4 - Wage Det Building KS57 - 30 Jul 21.pdf PDF
Attach 5 - Wage Det Heavy KS30 - 6 Aug 21.pdf PDF
Attach 8 - Past Present Performance Questionnaire (PPPQ).pdf PDF
Show all 31

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions contractors submitted from the Pre Proposal Conference & Site Visit

1. [Reference Seed Project Requirements] The demolition and new construction requirements for the fire alarm / mass notification system are described in the Construction Drawing set, Sheet FA101. The technical specifications do not provide a specification section for CSI Division 28 – Electronic Safety and Security. Please advise as follows:

0. [FA/MNS] Will a technical specification section applicable to this work be provided? If not, should the offeror assume that the installation of the same type of FA/MNS devices (brand and model) as is currently used on site will be acceptable?

0. [FA/MNS] The RFP-furnished submittal register does not include submittals for Division 28 – Electronic Safety and Security. Will the Contractor be required to provide submittals related to the FA/MNS-related work (e.g., product data, shop drawings, system pre-test and acceptance test reports, etc.)?

0. [FA/MNS] If the Contractor is to provide FA/MNS shop drawings, will these need to be signed and sealed by an FPE?

0. [FA/MNS] The project is a design-bid-build project. Will the Contractor need to validate the audibility requirements of the MNS devices (by providing calculations), or has this already been addressed by the DOR in its design?

Please refer to the added Spec. 28 31 76 enclosed herein to provide the required information for the Fire Alarm System. To be incorporated via amendment.

1. [Reference Seed Project Requirements] Will the Contractor be required to provide a new Estop (emergency shut-down) control for the new mechanical system, including DDC management and interface with the FA/MNS system?

Answer: Yes, the contractor will be required to provide new Shelter-in-Place Emergency Shutdown buttons in the hallway locations indicated by Keyed Note 16 on sheet MH101 of Attachment 12 and Keyed Note 14 on sheet MH103 of Attachment 12. The controls sequence of operations for the buttons can be found on sheet M-701 of Attachment 12. Note that the emergency shutdown buttons are not tied into the FA/MNS system.

1. [Reference Seed Project Requirements] The RFP requires that the Contractor furnish new DDC controls for the new mechanical system. Please confirm that this requirement includes associated programming of the existing remote EMCS to accommodate the new system.

Answer: Yes, the new DDC controls will be tied into the remote EMCS system at Bldg. 691 (HVAC shop building) such that the HVAC shop technicians will be able to view the data points and alarms provided by the Bldg. 852 DDC System remotely at Bldg. 691.

1. [Reference Seed Project Requirements] The RFP does not include requirements for electronic access control or intrusion detection systems. Please confirm that no electronic access control (e.g., card readers) or intrusion detection system (e.g., door contacts) is required for the proposed project.

Answer: No electronic access control or intrusion detection system is needed. Please see Attachment 11, Specification section 08 71 00 paragraph 2.3.5, which specifies the required lock manufacturer and series, and paragraph 2.3.8 which details the keying requirements. Please disregard specification section 08 71 00 paragraph 2.3.6.16 which describes programmable card requirements. This section is not applicable.

1. [Reference Seed Project Requirements] Please confirm that the keying for new door locks will be by the CE Lock Shop. If so, will the Contractor be required to furnish the permanent cores for the new locksets?

Answer: The Contractor will be required to coordinate with the CE Lock Shop to have the CE Lock shop key the new door locks for the building. The Contractor will be required to furnish the permanent cores for the new locksets to the CE Lock Shop in accordance with the requirements of Attachment 11, Specification Section 08 71 00 paragraph 2.3.5 and 2.3.7.

1. [Reference Seed Project Requirements] Please confirm that the Superintendent can also serve as the SSHO for the proposed Seed project.

Answer: The Project superintendent can also serve as the Site Safety and Occupational Health Officer (SSHO) for the seed project.

1. [Reference Seed Project Requirements] Will the new roof-level mechanical equipment (such as exhaust fans) need to be integrated into (connected to) the existing lightning protection system? If so, will the Contractor need to retest and recertify the entire lightning protection system?

Answer: The new roof-level mechanical equipment will need to be integrated into the existing lightning protection system in accordance with Attachment 11 Specification Section 26 05 26.00 40 paragraph 3.1 and Specification Section 26 20 00, paragraph 3.1.10. In the event a new lightning protection system is installed under a separate contract after installation of the roof-level mechanical system equipment under this contract, the LP system will be provided by the contractor on the separate contract.

1. [Reference Seed Project Requirements] Will the Contractor be required to provide any attic stock for finishes (including acoustical ceiling tile, VCT, and carpet tile)? If so, please identify quantities required.

Answer: In accordance with Attachment 12, sheet IN601, GENERAL FINISH NOTE 8, “Contractor is to provide extra materials of ceiling tiles, carpet, floor tile, etc. in the amount of 5%.”Also, please refer to the specifications for each finish to determine attic stock requirements.

1. [Master Contract] Reference RFP page 97 of 103, M.2. Basis for Contract Award which states, “This acquisition will utilize the Tradeoff source selection procedures … for a best value award decision. … This is a competitive, best value, subjective trade-off source selection in which competing offerors' past performance history will be evaluated on a basis significantly more important than cost or price considerations. The Government intends to award six (6) contracts as a result of this solicitation. Tradeoffs may be made between past performance and cost/price, with past performance considered significantly more important than cost/price.” Question: During the pre-proposal conference it was stated that the proposals would first be ranked by price and then the past performance evaluated, which is the method used for LPTA (low price, technically acceptable) acquisitions. Please clarify whether is opportunity will be a best value or an LPTA acquisition.

Answer: This is a best value acquisition not an LPTA. As indicated in Section M.2. “This is a competitive, best value, subjective trade-off source selection in which competing offerors' past performance history will be evaluated on a basis significantly more important than cost or price considerations. The Government intends to award up to six (6) contracts as a result of this solicitation. Tradeoffs may be made between past performance and cost/price, with past performance considered significantly more important than cost/price. “ Additionally, per M.3.3 “If the six (6) lowest priced evaluated offerors are judged to have an overall "Substantial Confidence" performance rating, those offers represent the best value for the Government and up to six (6) awards from that group may be made, in order of price. If the six (6) lowest priced evaluated offerors are not judged to have an overall "Substantial Confidence" performance rating, evaluations will continue (in ascending order by price) until up to six (6) offerors are rated with "Substantial Confidence" or, until all offerors are evaluated if less than six (6) are rated "Substantial Confidence". The Source Selection Authority shall then make an integrated assessment best value award decision on up to six (6) awards.”

1. [Master Contract] Reference Section L - Instructions, Conditions, and Notices to Offerors, pages 84 through 90 of 103. The RFP lists no requirements for submissions of personnel resumes as part of the Offeror’s proposal response. Please verify that no personnel resumes are required as part of the proposal response.

Answer: The RFP does not list any requirements for submissions of personnel resumes as part of the Offeror’s proposal response because no personnel resumes are required.

1. [Master Contract] Reference General Statement of Work (SOW) for Multiple Award Construction Contract (MACC) dated 09 SEP 2021, pages 7 and 8 of 8, paragraph 3.17 Subsequent Task Order Evaluation Criteria which provides a comprehensive list of required information for individual task order proposal submissions. Question: Is the Seed Project proposal exempt from these requirements? If not, please advise where these are to be included in the proposal and if there are any page limitations to this portion of the proposal response.

Answer: Paragraph 3.17, Subsequent Task Orders Evaluation Criteria is specifically indicated for task orders that will be awarded after the initial award. The Seed project is the initial Task Order that will be awarded to the offeror that provides the overall best value based on the seed project proposals. As indicated in the solicitation, Section 10 e. on page 1 of the solicitation, “The Seed Project shall be awarded to the Best Value offeror. Subsequent task orders may be awarded based on Best Value or low bid price.” Additionally, per L.1.1.1., “Award will be made using subjective, best value trade-off source selection procedures. Subject to availability of funds, the Government plans to award up to six (6) contracts to the offerors representing the best value. The offer representing the overall best value to the Government shall be awarded a Task Order for the seed project.”

12. Can I get your holder of the roof warranty so I can contact them for pricing?

Answer: The roof replacement project is still in the design phase so the roofing contractor has not been selected at this time. Please see Attachment 10, Statement of Work, paragraph 3 for more information regarding the coordination required between the roofing construction project and the seed project.

13. Can we use a current project (that doesn’t have CPARS yet) as a PPQ? If so, whom shall we send the PPQ to?

Answer: Yes, you may have PPPQs completed for projects that have not yet had a CPARS report. Per L.2.5.3.3 “Limit contract references to work performed in the last three (3) years…”. PPPQs should be sent to individuals involved in the project on the Project Owners side, i.e. Engineers, CORs, Contracting personnel. Per L.2.5.3.3 “PPPQs will only be accepted from Project Owners or their authorized representatives.”

14. Please confirm that proposals are required to be submitted in both hard copy and electronic copy on CD. If so, please clarify the quantities of copies required. Block 13.a of the SF 1442 states “sealed offers in original and 1 copy”. Section L.2.1, Organization, indicates one original plus 3 copies of both volumes and the cover page, plus 1 CD containing all required submittals.

Answer: Proposals are required to be submitted in both hard copy and CD, instructions per Section L.2.1. shall be utilized. Specifically, “Proposals shall consist of an original plus three (3) hard copies, and one (1) electronic CD containing the three (3) sections /parts as defined in the table below, all of which shall be within the required page limits specified.”

15. We would like to request once again that the deadline for proposals be extended no less then 10 business days. With the Holidays it is going to be extremely difficult not only for subs contractors to be able to properly obtain pricing and put together proposals, but also for the potential GC’s to submit and have returned the appropriate PPQs for submission.

Answer: The proposal due date will be extended by one day to 7 Dec 2021. Due to risks associated with the award process, we do not intend to adjust the proposal due date any further or allow for electronic submission.

16. Has the building been tested for hazardous materials and deemed “none found”? There were no documents provided so the assumption is that tests were performed and nothing found OR that no tests were performed. There is nothing is the SOW or Specs that we found that puts the burden of testing on the Contractor. If testing is expected will it therefore be assumed that if Asbestos/Heavy metals or Lead are found that a change order would be issued immediately for abatement prior to the start of Phase one and the schedule adjusted accordingly?

Answer: The design team had different areas of the building tested and no asbestos was detected. Please see attached Asbestos survey. It was not deemed necessary to test for heavy metals or lead. The contractors are to assume no heavy metals or lead are present to be abated.

17. The drawings call for the replacement of damaged sheet rock and a level 5 finish. It also calls for patching some areas to match existing walls. Are patches expected to have a level 5 finish? A “patch” is nearly always going to be visible, as seen in other areas of the hallways throughout the building.

Answer: Patches are expected to have a level 5 finish.

18. In rooms that have wood or carpet wainscotting it is certain the removal of said coating WILL damage all wallboards and adhesive will not be removable . Is it expected in these rooms that ALL wallboards be replaced and provided a level five finish or can the bottom half of the wallboard that contains the wainscotting be removed and replaced to match the remaining upper boards?

Answer: As long as the end result is a level 5 finish, 22d CES will not dictate means and methods of achieving this finish level.

19. Is brick veneer to be sealed after cleaning?

Answer: No, the brick veneer is not to be sealed after cleaning.

20. Is exterior brick veneer to replaced where previously damaged?

Answer: Yes, brick veneer is to be replaced in areas where exterior penetrations are changing and efflorescence remediation on the north exterior wall only, to include damaged brick veneer on the north wall. Please refer to Attachment 12, Sheet AE201.

21. Please confirm that all existing fire suppression, plumbing and electrical conduit not being reused is to be capped and abandoned in place.

Answer: No, any existing fire suppression, plumbing, and electrical conduit not being reused is to be removed unless otherwise noted. See Attachment 12, sheet P-401, DEMOLITION NOTES, all plumbing piping that is not being reused is to be demo’d to the main or to the mechanical equipment unless otherwise noted. See Attachment 12, sheet FX101, PLAN NOTE 4: Location of existing fire hose valve – demo all those locations, including hose valves, cabinets, and any related piping all the way back to connection to main piping. Plug or cap any opening that is not being used. See Attachment 12, sheets ED101, ED102, ED103, ED111, ED112, and ED113, GENERAL NOTE 3: Demolish all unused conduit, wire, switch boxes, junction boxes, lighting controls and supports. Do not abandon unused items or components in place unless noted otherwise.

22. The building is going to be occupied and in use during construction. In the event the end user is unable or unwilling to accommodate any given phase of the contract, will mods to the contract for time only extensions be done automatically by contracting or will they need to be requested by the contractor?

Answer: Any modifications for time extensions will require the involvement of all parties, and can be requested by the contractor or initiated by either the Contracting office or Civil Engineering. In a situation like this, typically the contractor requests the time extension based on the effects as they determine they are/will be, as there may be multiple issues that play into the duration of the time extension other than just the number of days access was delayed (i.e. cold start up delays, etc.).

23. Regarding Attachment 10 Statement of Work, referencing section 2.1 Bldg 852 HVAC System Repairs, in paragraph two the document states “the fire sprinkler system shall be replaced with a new designed and constructed system.” However, the project drawings do not depict an entire replacement, only moving of heads/head replacement and rework of the riser. Please clarify on this discrepancy.

Answer: This is not a discrepancy. Specification Section 21 13 13 is a performance specification, which requires the re-design of the fire sprinkler system of the building to incorporate the changes as shown on Sheets FX001 and FX101 of the plans.

24. Regarding the two project options, will there be an extension in period of performance granted to complete these options? Or are they to be completed during their area’s respective phases?

Answer: The options will be completed concurrently with the base bid work; there will not be an extension in period of performance.

25. Please confirm it is the responsibility of the government, not the contractor, to remove and place into storage any item not to be thrown away ( i.e.: equipment, materials, furniture, electronics, etc.). Per statements in the phasing plan, anything left behind during demolition is to be thrown out by the contractor.

Answer: It is the responsibility of the government to remove and place into storage any item to be retained, in accordance with Attachment 12, Sheet AD101, DEMOLITION GENERAL NOTE 13. The only exceptions are the following: 1. APU training equipment in old room number 108 as shown in sheet AD101 and Attachment 13 under Phases 0 and 2; 2. The Boeing equipment in new room number 99 as shown on sheets AE101, AE104, and AE301 and described in Attachment 13 under Phase 1; 3. The two generators which will remain in old room number 114 as shown on sheet ED102. See Attach 17 – Revised Drawings Anything else remaining will be thrown out by the contractor.

26. Regarding the contractor provided Conex’s for storage, are these to be temperature controlled to keep contents within a specific temperature range?

Answer: No temperature controls are needed for the Conex boxes.

27. Please confirm contractor is not responsible for providing or installing furniture.

Answer: Contractor is not responsible for providing or installing furniture. However, the electrical subcontractor shall reinstall projection equipment at locations indicated on plans and as directed by end user in accordance with Attachment 12, sheet AE101, CONSTRUCTION GENERAL NOTE 7, and sheet AV101, GENERAL NOTE 5.

28. Regarding Sheet AE201, referencing the requirement for re-tuck pointing joints as needed. We interpret this requirement to apply only to the north elevation of the building (per Key Note #12). However, General Note #1 makes it sound as if the contractor is responsible for tuck-pointing all failing joints on ALL building elevations. Please clarify if the contractor is to re-point only failing joints on the north elevation of the building or for all elevations.

Answer: In accordance with Attachment 12, Sheet AE201, GENERAL NOTE 1 and KEY NOTE 3, all brick control joint sealants only are to be inspected, removed and resealed. The sealant color is to be consistent and submitted for approval. KEY NOTE 3 is referenced at every control joint on all four sides of the building. Re-tuck pointing only applies to the north elevation of the building only per Key Note #12 on Sheet AE201.

29. Section L states to provide a letter of bondability for 10 Million single and $25 Million aggregate. The 1442 states to submit a bid bond. Please advise if the government needs both for this submission.

Answer: Both a bid bond for the Seed project and a letter of bond ability for the base contract are required.

30. Does the government want to include copies of the Attachment 8 PPQs in the proposal that we send out to the client contacts?

Answer: No, copies of the PPPQs should be received from the individuals completing them. Please provide a list of the individuals that PPPQs have been sent to NLT 30 Nov 2021 (7 days prior to the proposal due date).

31. What fire alarm panel is existing in that building? If you have a picture or name and model number would be helpful.

Answer: See attached pictures in B852 Site Visit Photos.

32. Is the A/V equipment being provided already programmed so that no programming is required.

Answer: Yes, the A/V equipment is already programmed and not the responsibility of the contractor.

33. What brand is the AV equipment being reinstalled.

Answer: See attached pictures in B852 Site Visit Photos.

34. The Plans say DDC to make compatible with one of the two existing systems. What are the existing systems?

Answer: The two approved existing systems are either Schneider or Automated Logic.

35. Per L.2.5.3.4. If the offeror intends to fulfill the requirements of this RFP in a teaming arrangement or joint venture, the offeror must provide complete information as to the arrangement, including identifying the responsibilities of each entity, and the contractual relationships and authorities of the firms involved. Per M.3.2.(2)(ii) The evaluation will take into account performance of predecessor companies, major subcontractors, consultant, or teaming contractor or partner whose effort, as demonstrated in the proposal, will significantly influence performance of the proposed construction and/or design-build effort and the ratings of these entities will contribute to the overall rating of the principal offeror. Per GOA rulings, please confirm that the Government will permit the use of sister company experience and past performance via a commitment letter providing it describes the arrangement, including identifying the responsibilities of each entity, and the contractual relationship and authorities of the firms involved.

Answer: Sister company information may be utilized for past performance. Information indicating the relationship shall be provided separately from the Past Performance documentation, and shall not count as part of the Past Performance volume page count. A commitment letter, describing the arrangement, including identifying the responsibilities of each entity, the commitment of resources, and the contractual relationship and authorities of the firms involved shall be provided.

36. Will all of the equipment shown by the shaded lines in Room 99 on Sheet AE101 be installed prior to Phase 1 construction commencing? The section view of this room on Sheet AE301 only shows some of the equipment.

Answer: Yes, although we do not have firm dates we have been told that all equipment shown by shaded/dashed lines in new room number 99 on sheet AE101 will be installed prior to the start of Phase 1.

37. What are the approximate dimensions of the equipment shown by the shaded lines in Room 99 on Sheet AE101? Are there any pictures of the proposed equipment available?

Answer: Please see attached document to find the known dimensions of the Boeing training equipment. This document is titled “Boeing Trainer PDF”. Also, please refer to Attachment 12, Sheet AE301, Detail C, which shows the height of the ART trainer equipment.

38. Per the Phasing Plan, Phase 1: A temporary door and partition will need to be installed in Hallway B as shown on sheet AD101. This is a required secondary emergency egress for the occupants of rooms 104 and 105/106. Are there any specific requirements of how the temporary doors and partitions are to be constructed (i.e wall construction, door material, door frame material, panic bar) ?

Answer: No, there are no specific requirements of how the temporary doors and partitions are to be constructed other than that they must be present and properly labeled as an emergency exit. There must be a clear path and temporary emergency lighting must be maintained at all times to either the west or south entrance. The accessible emergency exit (through either the west or south entrance) must be clearly visible at all times. The timing of replacing the south and west entrances must be planned and is recommended to be accomplished during Phase 1 in order to ensure that the users have an exit path at all times. Ultimately, before the contract can progress to Phase 2 and users can occupy the old room numbers 104 and 105/106, the McConnell AFB fire department will need to approve of the secondary emergency egress and any required changes must be performed by the contractor. This must happen within the first 4 months of construction (Phase 1).

39. Are existing mechanical schedules available? If so, will the Government please provide them?

Answer: Yes, please see attachment labeled “Existing Mechanical Schedules”.

40. Per the Phasing Plan, Phase 0: The contractor will be required to provide temporary generator power to maintain essential building operations (listed below) and the phased construction areas occupied by the end user if normal power to the facility cannot be maintained. Are there any specifications regarding the temporary generator used to provide temporary power (i.e. sound attenuation)?

Answer: No, there are no specific requirements for the temporary generator except that they shall be sized to accommodate the loads required to be maintained within the facility.

41. Phasing Plan: The Phasing Plan shows each of the three phases are to have a four-month duration. However, the Phasing Plan also states that phases can start prior to completion of previous phases. Does starting a phase early result in a decreased period of performance for the full project?

Answer: No. The contract project duration will remain the same. However, the contractor will be permitted to complete phases as listed in the Phasing Plan early, if possible.

42. Spec Section 01 11 00, 1.2.1.1 states Building 852 Project's demolition and construction will be done WITHOUT phasing to simplify the complexity of issues. This conflicts with the Phasing Plan and Drawings. Which is correct?

Answer: The phasing plan is correct. Please disregard spec section 01 11 00, 1.2.1.1.

43. Spec Section 01 11 00, 1.4 states Building will be unoccupied during performance of work under this Contract. This conflicts with the Phasing Plan and Drawings. Which is correct?

Answer: The phasing plan and drawings are correct. Please disregard spec section 01 11 00, 1.4.

44. Spec Section 02 41 00, 3.1.14 states Salvage each item of equipment and fixtures as a whole unit; listed, indexed, tagged, and stored. Salvage each unit with its normal operating auxiliary equipment. Transport salvaged equipment and fixtures, including motors and machines, to a designated storage area as directed by the Contracting Officer. This equipment is not listed in section 01 11 00 Summary of Work. Please confirm this is correct and what equipment needs to be included.

Answer: Spec section 02 41 00, 3.1.14 is correct. The items to be salvaged are referenced on sheet MD102, KEYED NOTES 10, 14, 23, 27. This list may not be all inclusive.

45. Spec Section 02 41 00 3.1.14 and 01 11 00 Summary of Work state Salvage each item of equipment and fixtures as a whole unit; listed, indexed, tagged, and stored. Salvage each unit with its normal operating auxiliary equipment. Transport salvaged equipment and fixtures, including motors and machines, to a designated storage area as directed by the Contracting Officer. Who will be responsible for offloading and placing salvaged equipment?

Answer: The contractor shall be responsible for moving, offloading, and placing salvaged equipment per Spec. 01 11 00, para. 1.8.

46. Considering that Thanksgiving falls within this RFP’s 30-day response window and that so many federal agencies and federal contractors take at least half of Thanksgiving week off, would 22 CONS please consider extending the proposal due date by one week?

Answer: The proposal due date will be extended by one day to 7 Dec 2021. Due to risks associated with the award process, we do not intend to adjust the proposal due date any further or allow for electronic submission.

47. Regarding the date/time that offerors finalize their bids and proposal delivery logistics, would 22 CONS please consider allowing all offerors to submit their proposals electronically before the proposal deadline with the paper original and paper copies due within 2-3 business days after the electronic proposal deadline? Because prime offerors receive subcontractor quotes very close to the proposal deadline, electronic deadlines are more equitable than hard copy deadlines, which provide an advantage to companies who can hand-deliver their proposals.

Answer: The method of submission was selected based on risks with the award process. We do not intend to adjust the submission method.

48. Who will be responsible for relocating the furniture and equipment?

Answer: This is the responsibility of the users. See Attachment 12, sheet AD101, DEMOLITION GENERAL NOTE 13.

49. Can we have the name of the roofer awarded the contract for the reroofing project so that we can enlist them for pricing for our roof penetrations?

Answer: The roofer hasn’t been selected. The roof design project is still in the design phase (90% design currently).

50. Knowing that the moisture shown on the interior of the block walls in rooms 105 and 106 is coming from the outside, what measure should be taken to prevent a recurrence?

Answer: The measures that should be taken to prevent the moisture coming in from the exterior of the block walls in old room number 105/106 are listed on sheet AE201 of Attachment 12 as GENERAL NOTES 1 and 5, as well as KEY NOTES 3, 9, 12, 14. The brick veneer and mortar joints are to be inspected and joints are to be re-pointed to a depth equal to twice its width. Any cracked veneer is to be replaced, the brick veneer on the north exterior wall is to be cleaned with a non-acidic solution and tuck-pointed, the flashing is to be inspected and lap joints are to be resealed. Weep holes are to be cleaned out and open. And there is also a separate roof replacement project that will address any issues with the roof itself.

51. Please confirm that FF&E (desks, chairs, tv’s, etc.) are not part of this contract.

Answer: FF&E are not part of this contract.

52. Please provide blocking detail for areas behind TVs.

Answer: This is considered means and methods for the contractor based on the sizes of the TV’s. See attached pictures in B852 Site Visit Photos.

53. Please confirm VCT in main corridors are to be protected and are not part of this scope.

Answer: The VCT in the main hallways is to be protected and is not part of this scope. The only sections of VCT in the main hallways that are to be replaced are indicated on Attachment 12, sheet AE102, CONSTRUCTION PLAN NOTE 5 and sheet AE103, CONSTRUCTION PLAN NOTE 5.

54. Please provide name of warranty holder on new roof.

Answer: The roof project is still in the design phase (90%) and so a roofing contractor has not been selected at this time.

55. Please provide power requirements for temporary power in all phases.

Answer: The contractor is to determine the power requirements for temporary power in all phases such that power needs of all essential building operations, and any occupied spaces in the construction area (once phase 1 and/or 2 is completed) are satisfied.

56. Please provide HVAC requirements for temporary cooling and heating in all phases.

Answer: Contractor to make determination for bidding purposes based on all heat loads considered from equipment remaining and contractor/Government personnel present on site.

57. Please reference the MACC Combined Specs, 01 45 00.00 10, Section 3.3 Quality Control Organization and 3.3.1 Personnel Requirements. Also reference 01 35 26 Safety Requirements, Paragraph 1.6.1.1 - Site Safety and Health Officer (SSHO).

1. Please clarify: Are the terms “Site Safety and Health Officer (SSHO)” and “Safety and Health Manager” being used interchangeably?

Answer: Yes

1. For the Seed Project Task Order specifically: Please confirm that the Superintendent can serve as the SSHO, and that a CQC System Manager is required to be on site at all times during construction and must have no other duties.

Answer: The Superintendent can serve as the SSHO. Furthermore, FAR 52.236-6 requires a Superintendent on site at all times during construction. The CQC System Manager is required to be on site at all times during construction to ensure adequate QC during all construction activities. The CQC System Manager can have no other duties. Thus, the PM cannot be the CQC Manager.

58. Please reference page 100, Section M.3.2 (ii): “Some important factors which will be considered during past performance evaluations include: 1. Projects with a similar contract type and magnitude (such as MACC/MATOC, SABER, JOC Firm Fixed Price ID/IQ contracts) using terms and conditions similar to those set forth in this solicitation…”. Section L.2.5.3.2 also indicates that work involving JOC, MATOC, and SABER construction contracts will be considered “More Relevant”. Please clarify: Will the government accept overall IDIQ contracts (such as MACCs, SABERs, and JOCs) as one or more of the seven (7) relevant contracts, or must each of the relevant contracts be an individual contract (e.g.., a stand-alone project or a task order awarded under an IDIQ contract)?

Answer: Offerors may cite IDIQ contracts as past performance citations and may provide PPPQs (or CPARS) for either IDIQ contracts or project contracts.

59. Please reference page 100, Section M.3.2.(ii): #7. “Projects on which offeror and proposed design firm(s) have previously worked together.”Please clarify: Is the Offeror required to submit relevant projects and PPPQs from their proposed design firm as part of the seven (7) contracts submitted in Volume II? Or is information regarding the proposed design firm limited to an explanation of the teaming arrangement in accordance with solicitation Section L.2.5.3.4? If past performance is required, please provide design firm PPPQ forms.

Answer: If the contractor is planning to team with a design firm, then the teaming information should be contained in the Teaming/Joint Venture section. If the contractor is not planning to team with a design firm, they should ensure that their past performance demonstrates their ability to properly select and manage design firms for different projects/contracts.

60. Please reference page 86, section L.2.1 Organization. Please clarify: Is the requirement to include the Cover Page, Volume I, and Volume II in the same binder with each part separated by tabs/identifier pages, or are Volume I and Volume II required to be submitted in separate binders? If Volume I and Volume II must be bound separately, is the 1-page Cover Page required in each volume?

Answer: No, each volume is not required to be submitted in separate binders, each proposal copy should be separately bound. Per Section L.2.3 “Each proposal copy should be separately bound permitting the volume to lie flat when open. Staples shall not be used. A cover sheet should be included for each proposal copy, clearly marked with the original/copy number, solicitation identification (number and name), and the offeror's name. Each section shall have a section identifier page that indicates the factor title of the material in the section. The section identifier page will not be considered towards total page count, but should not contain any information other than the factor title of the material.”

61. Spec 23 09 23.02 - Does prime contractor need to hire 23 09 23 controls directly? Does prime contractor have to hire third-party DIV 25 integration contractors?

Answer: The Government does not have a preference on how the contractor hires a controls contractor per Spec. 23 09 23. The contractor shall hire a DIV 25 integration contractor per the requirements of Spec Section 25 05 11.

62. Please confirm who has roofing warranty and provide point of contact for the facility.

Answer: The new roof project is still in the design phase (90%) and so a roofing contractor has not been selected at this time.

63. Spec 23 09 23.02 - Is there a proprietary DIV23 controls contractor at the facility? If so, please provide company and point of contact.

Answer: No.

64. Is there a proprietary DIV28 Fire Alarm contractor at the facility? If so, please provide company and point of contact.

Answer: No.

65. Please confirm phasing may run concurrently.

Answer: Yes, phasing may run concurrently. However the contractor must turn over the Phase 1 (see Attachment 13) spaces no later than four months after start of construction and have a secondary emergency egress through the construction space, and the contractor must turn over the Phase 2 spaces no later than eight months after start of construction and maintain a secondary emergency egress through the construction space. IF the contractor opts to begin Phase 2 concurrently with Phase 1, the requirements stated above will be enforced.

66. Spec 09 68 00 Par 3 - Is the concrete substrate expected to require substantial corrections? i.e. should Ctr expect to test moisture, alkalinity, and repair substrate then wait for 90 days, or would a shorter timeline be expected if in accordance with the Manufacturer’s instructions? Intent is to gauge the prep required and the timeline associated with flooring scope.

Answer: Please review specifications on floor preparation requirements.

67. Door 99.2 Hinge Type - Please provide hinge type / location for new door 99.2 on etr frame. If frame is not to remain, please provide Head/Jamb/Sill details.

Answer: Door 99.2 should be removed from sheet AE611. This was the double personnel doors in new room 99 as seen on sheet AE101. The decision late in the design process was to demo this door and replace with glass and aluminum storefront windows. See sheet AE104, CONSTRUCTION PLAN NOTE 8. See Detail 5/AE303 and window W4 on sheet AE611.

68. Phasing Plan - For the (2) User CONEX Boxes to be supplied by G.C. – are any utility connections required. If so, please confirm utilities and respective connection points relative to the CONEX locations.

Answer: No utility connections are required for the two CONEX Boxes.

69. What are the requirements for protection of the Boeing equipment? For example, does the equipment need to be operable? Does it need to be secured from dust? Will the equipment need to be recalibrated to ensure that it has been properly protected? etc.

Answer: During Phase 1 construction (see Attachment 13), the Boeing equipment does need to be operable, but it must be protected from damage due to accidental contact, drops, spills, dust, etc. The equipment will not be mobile, and the contractors will be forced to work around the equipment. After the completion of Phase 1, the equipment will be tested by Boeing and the contractor will be responsible for any construction induced damages. 22d CES will not dictate means and methods of protecting the Boeing equipment, but recommends that the equipment be properly covered and that scaffolding be used as necessary.

70. Solicitation H6.0 and note (4) on Chiller Schedule note that Chiller must be Daikin / other vendors not considered. Does this Sole-sourced requirement extend to the DOAS and AHU, which also have Daikin listed as B.O.D.?

Answer: No, McConnell AFB has a sole source agreement for Daikin chillers only.

71. MEP01 suggests a temporary generator will be required to facilitate continued operations, Spec Section 01 00 00 1.27 suggests government will be providing these utilities.

Answer: MEP01, Note 2 requires that the contractor provide a temporary generator to maintain essential building operations. MEP01, Note 3 requires temporary utility power for all other construction activities. Spec Section 01 00 00 paragraph 1.27.F.4 states that base electric power can be utilized if it is conveniently available. However, all temporary facilities needed to effectuate the temporary use of Base power shall be at the Contractor’s expense, including the cost of removal at the end of the project.

72. Per Demo Sheets, “Repair wall surface to level 5 finish” Is contractor to resurface walls seam-to-seam? Or only patch back affected areas?

Answer: The contractor shall perform work in accordance with plans and specifications. If not defined by plans and specifications, contractor shall utilize their own means and methods to prepare walls accordingly to Level 5 finish.

Questions Recorded from Site Visit by government representatives

Q: Will customer empty the rooms out of all items?

A: Yes, please see Attachment 12, sheet AD101, DEMOLITION GENERAL NOTE, which states the following “Users will remove all pieces of equipment for teaching (white boards, TVs, furniture, artwork, signs, etc.) prior to construction that is intended to be kept. Any other equipment is to be demolished.” This include any furniture remaining by the users not including equipment in the occupied/utilized rooms (i.e. old Room 108, old Room 114, etc) designated in the design plans and Phasing Plan. However, in new room number 99 (old Room 105/106) there will be some significantly large pieces of equipment remaining that must be worked around. This equipment is shown on Attachment 12, Sheet AE104 in new room number 99 and is drawn using dashed lines. The note in the room states “new Boeing equipment to be installed prior to construction shown dashed. Not part of this project. Equipment will be fixed in place.” CONSTRUCTION PLAN NOTE 10 also states that the contractor is responsible for protecting existing equipment including damage occurring during construction. This equipment is further discussed in Attachment 13, Phasing Plan, under the first paragraph of Phase 1, which states “it will be the responsibility of the contractor to protect this equipment from dust, debris, etc. during the construction effort in this room. This may include wrapping the equipment in plastic or similar and building scaffolding as needed. Also, refer to Attachment 13 Phasing Plan, Phase 0 that discusses old room numbers 108 and 114, which will have some large pieces of equipment remaining. The equipment includes a large Auxiliary Power Unit trainer (three large components on wheels), and the associated generator. The users will secure the items as much as possible so the contractor can temporarily move the equipment to prep/install the flooring in these areas.

Q: How will the temporary HVAC and electrical work? Will there be occupants in building at that time?

A: Please reference Attachment 13, Phasing Plan as well as Attachment 12, Sheets AD101 and MEP01. At the start of Phase 1 the entire construction project area as shown on sheet AD101 and in the diagram below will be vacated. It will be the responsibility of the contractor to provide temporary generator power, temporary distribution panels, and cabling as required to maintain essential building operations. The contractor will provide temporary utility power to the project site as required for all construction related activities only. The contractor will also provide temporary heating and cooling as required to maintain essential building operations as well as provide freeze protection in all unoccupied areas as necessary.

The existing building addition (shown in the diagram below) will be fully occupied and operational for the duration of this project.

The essential building operations will be maintained by contractors from all trades to ensure there are no interruptions to service. Any required shutdowns to the essential building operations shall be coordinated and scheduled with the contracting officer in accordance with Attachment 11, Specification Section 01 00 00 paragraph 1.18.

The essential building operations are the following:

· The existing COMM room network equipment, power, lighting, HVAC equipment and controls, which is within the construction zone and is listed as old room number 122A and new room number 85.

· The existing exterior lighting system and controls that surrounds the entire construction zone.

· The existing fire alarm and mass notification system.

· The existing building addition (shown in the diagram below) and all interconnections.

At the completion of Phase 1 the construction area delineated as Phase 1 on sheet AD101 will be fully occupied, and it will be the responsibility of the contractor to provide temporary services until such a point that the base building services are able to provide all required services, to include (power, COMM, and HVAC).

At the completion of Phase 2 the construction area delineated as Phase 2 on sheet AD101 will be fully occupied, and it will be the responsibility of the contractor to provide temporary services until such a point that the base building services are able to provide all required services, to include (power, COMM, and HVAC).

Q: What are the dimensions of the Boeing equipment?

A: Please see attached document to find the known dimensions of the Boeing training equipment. This document is titled “Boeing Trainer PDF”. Also, please refer to Attachment 12, Sheet AE301, Detail C, which shows the height of the ART trainer equipment.

Q: When will the Boeing equipment be put into the building?

A: The exact dates of the Boeing equipment install are unknown at this point, but the contractor needs to assume that all pieces of equipment will be installed prior to start of construction.

Q: When will the roof be put on? What kind of coordination will be needed for this?

A: Although the dates of the roof construction project are not currently known, it is expected that the roof replacement project will take place prior to the seed construction project. The required coordination between the seed construction project and the roof replacement project can be found in Attachment 10, Statement of Work, under Paragraph 3.

Q: Ms. Mundy mentioned something about Schneider & Automated Logic during the breifing – please recap what she said?

A: The new control system must be completely compatible with one of the two approved control systems used on base: Schneider and Automated Logic.

Q: Does the scope of work address the fire alarm requirements for the seed project?

A: The fire alarm requirements are delineated in Attachment 12, sheet FA101. It was brought up that the specification section concerning fire alarm requirements is missing from the specification project. Please utilize the attached fire alarm specification section for requirements and bidding purposes.

Q: Does the seed project require the contractor to install access controls to the facility? (i.e. card scanner, keypad, etc.).

A: The Contractor will be required to coordinate with the CE Lock Shop to have the CE Lock shop key the new door locks for the building. The Contractor will be required to furnish the permanent cores for the new locksets to the CE Lock Shop in accordance with the requirements of Attachment 11, Specification Section 08 71 00 paragraph 2.3.5 and 2.3.7.

Q: Will the Boeing training equipment be installed in the “ART Room” at the north of the facility prior to construction?

A: Yes, the equipment is currently scheduled to be installed prior to construction.

Q: Is Boeing responsible for the electrical in the “ART Room”?

A: Boeing is only responsible for the electrical to the equipment they are installing from the devices/outlets on the wall to their equipment.

Q: Is the electrical in the “ART Room” currently sufficient to power the trainer equipment that will be installed?

A: Yes, however Boeing has asked for a few changes to the drawings based on updates to their project. This will require Electrical Panels UP and EP as shown on Sheet E-103 be moved 15 feet to the west along the north wall in Room 99. Also, the disconnect switches on the west wall (as depicted on Sheet ED103 and annotated by Note 13) shall NOT be demolished but rather moved to the north wall to the west of the relocated Electrical Panels UP and EP discussed above. The wiring to these disconnect switches back to the panelboard in old Room 114 shall be upsized to accommodate the 115VAC, 400 HZ, 3Phase, 40 AMP requirements of the WARP trainer. Also, Boeing has requested that the generator and associated panels in old room 114 be maintained (not demolished). These devices are indicated on sheet ED102 as KEYED NOTES 6 and 21.

Q: Can the Government provide additional details about how the seed project contractor will need to coordinate with the contractor for the future separate roof project.

A: The required coordination between the seed construction project and the roof replacement project can be found in Attachment 10, Statement of Work, under Paragraph 3.

Q: Does the facility conjoined with B852 have its own HVAC, electricity, and fire alarm systems? Will the contractor need to provide temporary coverage?

A: The facility conjoined with B852 has its own HVAC, electricity, and fire alarm systems, however there are interconnections. Therefore, in accordance with Attachment 12, Sheet MEP01, the contractor is responsible to provide temporary generator power and heating/cooling to the existing COMM room (within the construction zone, current room number 122A) network equipment, power, lighting, HVAC equipment and controls; the existing exterior lighting system and controls for the entire facility, the existing fire alarm and mass notification systems, and the existing building addition (the facility conjoined with B852) and all interconnections. These temporary services are required to be provided until such a point that the base building services are able to handle the loads. Please note that the existing building addition will be fully occupied throughout the construction period.

Q: Does the seed project require tuck-pointing of the entire facility?

A: Please reference Attachment 12 sheet AE201, KEY NOTES 12 and 14. Tuck-pointing is only required on the north exterior wall of the facility.

Q: Can the Government provide a photo of the roof where the contractor will need to install an access point?

A: 22d CES is unaware of a need to install an access point on the roof.

Q: Can the lighting occupancy centers be used to control the HVAC System?

A: No, the HVAC system will be controlled by occupancy schedules in accordance with the Sequence of Operations provided in Attachment 12, sheets M-701, M-702, M-703.

Q: Can the training items…