Q A__5_-_4_Nov_16.pdf
PDF 144 KB Posted
- Attached to
- (MACC) Multiple Award Construction Contract, McConnell AFB, KS 67221 Federal contract opportunity
- Solicitation number
- FA4621-16-R-0001
About this file
Questions Answers 5
View the file
Other files for this federal contract opportunity
Show all 39
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Pre-Proposal Conference Meeting Minutes - Attachment #3, Q&A
FA4621-16-R-0001 – MACC Solicitation
McConnell AFB, KS
QUESTION & ANSWERS (Q&A) #5
4 Nov 16
Question:
1. Question 16 of Q&A #4 talks about 4’ Tile Wainscot. This answer is not clear because I believe it is the intend to have a 4’ Wainscot but they are figuring to the ceiling because they are not sure what is the correct answer. Are they to figure the same as the as built attached to question Q&A #4?
Answer:
New bathroom tile should be installed according to the as-built attached to Amendment #2 with Q&A #4.
2. Do the fiber glass showers remain or will they get tile remove & replaced with tile?
Fiberglass shower units will remain and be reused.
3. Is the any tile / flooring in building #350?
There is no tile or flooring work in Bldg. 350.
4. Will the metal fence replacing the Mechanical Enclosures be the same height of the existing 8’ & 10’ or will it all be 8’ Tall?
New fences shall match the height of existing fences. This question will be clarified in Amendment #3.
5. On Drawing AE100 Detail 4, there is a note regarding a 1/8" aluminum security door width of ladder with continuous hinge. Can we get a better detail of this as it is not clear in that detail?
Answer:
This is the best detail that is available, and new details cannot be produced in a reasonable time that would prevent significant delays to the project. If the question can be re-phrased to ask more specifically what is unclear about the detail, we may be able to provide an answer.
6. Some brand name chillers cannot meet the -20oF low temperature operational rating of the specified chiller. Can other chillers be considered?
Answer:
Yes, other chillers with a low ambient kit that is capable of operation to -10oF (approx.) and that comply with all other requirements in drawings and specifications will be considered equal.
1240047841A Text Box Reminder: The new proposal due date is 18 Nov 16 @ 12:00 PM (Noon) local CST.
Final Questions are due no later than 9 Nov @ 12:00 PM (Noon) local CST.
Pre-Proposal Conference Meeting Minutes - Attachment #3, Q&A
7. Only one major brand of chiller has a continuously variable compressor speed. Can other chillers be considered?
Answer:
Yes, other major brands of chillers (Trane, McQuay, York, etc.) without a continuously variable compressor speed but similar efficiency, quality and other features, and that comply with all other requirements in drawings and specifications will be considered equal.
The intent of the chiller specifications and drawings is to provide a baseline level of quality in the chiller equipment; it is not the intent of the specifications or drawings to pinpoint certain brands and exclude other brands.
8. Can the Government please clarify the ceiling fan controller to be provided? Mechanical drawings show it shall be a digital speed controller while electrical drawings show that it shall be a solid state speed controller.
This question will be clarified in Amendment #3.
9. Specification 01 00 00, Paragraph 1.08 F mentions recycling. Can the Gov’t provide an explanation of the recycling to be done?
Answer:
Yes, construction debris (concrete, metal, etc.) should be recycled. The Contractor will provide tickets indicating the weight/cost/volume of recycled material. In addition, a letter may be submitted indicating that materials that can be reclaimed for use elsewhere (such as working temperature control units) have been set aside for use elsewhere.
10. Regarding the lighting in the work areas, what will the requirements be for securing the existing lighting while demo and rebuild are happening? Do we simply secure lights above ceiling for temporary, clean and reset them? Who is responsible for the foreseeable damage to fixtures if that method is used?
Do we remove all lighting and store it and install temporary lighting the construction areas? Some hard ceilings are going to drop ceiling, what lighting requirements will that entail due to the fact that different installation material will be required?
Answer:
There is wall lighting in the area where gypsum board ceilings are being changed to tile ceilings. In these areas, there are no ceiling mounted lights.
In other areas, where ceilings will be cut and patched, the protection of the lighting will be up to the
Contractor. Protection methods could include covering light, temporarily supporting light out of the way of the work, or removing and reinstalling light after the work is complete. The actual method to be used is at the Contractor’s discretion but it should reasonably fit the situation in the room being worked on.
Contractor will be responsible for any damage caused to light fixtures.
11. Since there is no equipment/disconnect schedule, are we to assume that disconnects exist and are reusing the existing?
Answer:
Unless it is specifically noted on the drawing otherwise, the Contractor will NOT be responsible for providing and installing disconnect switches.