Attach__6_-_Seed_Project__SOW.pdf
PDF 143 KB Posted
- Attached to
- (MACC) Multiple Award Construction Contract, McConnell AFB, KS 67221 Federal contract opportunity
- Solicitation number
- FA4621-16-R-0001
About this file
Attach 6 - Seed Project SOW
View the file
Other files for this federal contract opportunity
Show all 39
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FA4621-16-R-0001 Statement of Work (SOW) Attachment #6
(PRQE# 17-0125, 17-0145, 17-0146) for Seed Project
McConnell AFB
PRQE 17-0125, 17-0145, 17-0146
Statement of Work (SOW) for
Repair Dorms HVAC (Bldgs 340, 342, 350)
15 August 2016
FA4621-16-R-0001 Statement of Work (SOW) Attachment #6
(PRQE# 17-0125, 17-0145, 17-0146) for Seed Project
STATEMENT OF WORK
1. GENERAL: This Statement of Work is for Repair Dorm HVAC Bldg. 340 (PRQE 17-
0125), Bldg. 342 (PRQE 17-0145), and Bldg. 350 (PRQE 17-0146).
2. REQUIREMENTS: As indicated in the drawings and specifications, the Contractor shall:
2.1. Bldg. 340. Replace HVAC system. PRQE# 17-0125
The contractor shall complete all work associated with Bldg. 340, as described in the drawings and specifications. See Plans, Summary of Work, Page G-002. Line Item 0001AA
OPTION 1:
2.2. Bldg. 342. Replace HVAC system. PRQE# 17-0145
The contractor shall complete all work associated with Bldg. 342, as described in the drawings and specifications. See Plans, Summary of Work, Page G-002. Line Item 0001AB
OPTION 2:
2.3. Bldg. 350. Clean and flush hot water and chilled water system. PRQE# 17-0146
The contractor shall complete all work associated with Bldg. 350, as described in the drawings and specifications. See Plans, Summary of Work, Page G-002. Line Item 0001AC
3. GENERAL REQUIREMENTS: Construction will be phased. Refer to Summary of Work
Drawing G‐002 for phasing details.