RFI Log Responses - FY25 MAPC Seed Project_Scott Drive.pdf

PDF 116 KB Posted

Attached to
FY25 Multiple Award Paving Contract (MAPC) - Recompete Federal contract opportunity
Solicitation number
FA440725R0001
Issued by
Department of the Air Force Air Mobility Command

About this file

This document is a comprehensive Requests for Information (RFIs) log for the FY25 Multiple Award Paving Contract (MAPC) at Scott Air Force Base. The RFIs cover various technical details about a pavement and site utility project, including past performance requirements, contaminated soil handling, pavement and curb/gutter specifications, traffic control, and administrative questions. Key technical clarifications include allowing past performance references from within five years, confirming pavement disposal methods, specifying gutter and curb installation details, and addressing potential soil contamination in the southwestern patch area.

Notable administrative responses include confirming that tax should not be included in proposals, construction wage rates may change, no crosswalks will be painted, and contractors have flexibility in staffing safety and quality roles. The contract is a small business set-aside targeting eight awardees, with a two-year base period and three two-year option periods. The seed project is valued between $250,000 and $500,000, with a total aggregate ceiling of $45 million. The project involves roadway improvements at Scott Air Force Base, with the 375 CES responsible for current roadway maintenance.

View the file

Other files for this federal contract opportunity

Other files attached to FY25 Multiple Award Paving Contract (MAPC) - Recompete, newest first.
File Type Posted
Solicitation Amendment FA440725R00010002.pdf PDF
03-Section L (v3).pdf PDF
Solicitation Amendment FA440725R00010001.pdf PDF
05a-FY25 MAPC PPQ v2.pdf PDF
04-Section M (v4).pdf PDF
Sign-In Sheet - MAPC Seed Project_Site Visit.pdf PDF
01c-ATCH C Scott AFB IFS 9-6-19 reduced.pdf PDF
11-Scott AFB Climogram_Feb 2025.pdf PDF
05a-FY25 MAPC PPQ.pdf PDF
01b-MAPC Gen Rqmts 15 Apr 25.pdf PDF
09-NAF Standard Clauses_1 May 2024.pdf PDF
16-Maximum Allowable Concentrations.pdf PDF
06e-SOW ATCH 5 - 1149302 - SWPPP.pdf PDF
10-WD IL20250017 - 3.21.2025.pdf PDF
07-Construction_cost_estimate_breakdown.xlsx XLSX spreadsheet
06c-SOW ATCH 3 - 1149302 - Boring Results.pdf PDF
06d-SOW ATCH 4 - 1149302 - Utility Map.pdf PDF
06a-SOW ATCH 1 -1149302 - Work Areas.pdf PDF
08-Schedule_material_submittals.xlsx XLSX spreadsheet
Solicitation - FA440725R0001.pdf PDF
06f-SOW ATCH 6 - 1149302 - Traffic Control Example.pdf PDF
06b-SOW ATCH 2 - 1149302 - Contaminated Soils.pdf PDF
06g-SOW ATCH 7 - 1149302 - Contractor Requirements.pdf PDF
02-TO Procedures.pdf PDF
04-Section M (v3).pdf PDF
01a-ATCH A Scott AFB Map 3-4-25 reduced.pdf PDF
06-SOW - 1149302 REPAIR Full Depth Roadway Patching Along Scott Drive.pdf PDF
12-Real ID.pdf PDF
03-Section L (v2).pdf PDF
05-PPI.pdf PDF
14-Table 6-1. Fixed Wing Aprons.pdf PDF
15-Soil Testing and Disposal Procedure.pdf PDF
01-SOW 2025 MAPC.pdf PDF
13-DOD Safe.pdf PDF
Show all 34

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFI # Date Recv'd RFI Response

1 5-Jun-25

There was mention at the site visit that the past performance will be for the last 3 years. Can this be changed to 5 years due to Covid and also the fact that this contract will also have more than just pavement projects that include other site utility work that are not pavement work.

Past performance recency will be within five (5) years from the date of this solicitation.

2 5-Jun-25 Will the pavement that is removed from the area that is labeled as contaminated have to be disposed of as special waste or can it be recycled.

The pavement may be disposed of as the contractor would prefer. Special waste removal is not required.

3 10-Jun-25 Section L and Section M each state a different number of years (3 and 5) for past performance projects. Please clarify if contractors can use projects completed within the last 3 or 5 years.

Past performance recency will be within five (5) years from the date of this solicitation.

4 10-Jun-25 The asphalt pavement is currently covering the gutter in multiple areas. Will the new gutter pan need to be at the same elevations as the existing and adjacent asphalt surfaces?

New gutter pan shall be installed at the elevation of the existing asphalt surface.

5 10-Jun-25 There are two different sizes of curb and gutter on Scott Drive. Does the new curb and gutter in the patch sections need to be B6.18 or match surrounding?

New curb and gutter shall be B6.18. If existing curb and gutter differ. Contractor shall transition the curb and gutter within the limits of the patch to B6.18.

6 10-Jun-25

Please clarify how the contractor needs to identify, address, and dispose of contaminated soil in the southwest most patch.

The contractor will have to test the material and compare the analytical results to the MAC (Maximum Allowable Concentration) table. Exceedance of any of the MAC's will require the soil to disposed of as non-hazardous waste. Disposal of contaminated soil requires base Environmental to sign off on non-hazardous waste disposal documentation prior to the material leaving the base.

10-Jun-25

Are there contamination concerns in any other patch areas? Contamination concerns are only for the southwestern patch, as the rest have previously been tested as clean material.

10-Jun-25

Will contractors need to test soils in each patch area? No, the only soils that will require testing are the soils in the Southwestern patch as this patch is in very close proximity to soils that previously tested positive for contaminants

10-Jun-25

Is recycled CA6 acceptable for use under the concrete pavements? Yes, recycled CA6 is acceptable as long as it meets IDOT material requirements for course aggregate under Section 1004.04 of the 2022 IDOT Standard Specifications for Road and Bridge Construction.

10-Jun-25

During the pre bid meeting it was stated that the large patch in the south bound lane on Scott Dr.

could contain “hazardous” material, it is to be tested before excavating and then properly disposed of after testing. Will the fee associated for disposal be negotiated after testing is complete, or are assuming that attached soil analysis reports will suffice to true findings during construction?

No hazardous waste disposal shall be included with the bid. If contaminated material is determined to be present, a modification will be processed for the contractor to dispose of the contaminated material.

10-Jun-25

I understand that we cannot shut any north bound and south bound lanes down at the same time, correct? Can we shut either the north bound lanes or the south bound lanes down in their entirety and detour around the construction site?

Yes, both lanes in the same travel path can be shut down simultaneously.

10-Jun-25

It states that the curb and gutter will be poured separately from the pavement, could we incorporate a “tie bar” basket at the longitudinal joint between the curb and gutter and the pavement and pour together in some instances?

Yes, if the contractor would prefer to pour the section together this would be acceptable.

10-Jun-25

States that the transverse joints are to be spaced 10’ to 15’, is this going to be the discretion of engineering? These are full width patches so there will be no existing joints to match.

Yes, the contractor shall coordinate with the CE project manager for the joint layout.

10-Jun-25

Will all transverse and longitudinal joints be sealed with a “hot tar” sealer? Transverse and Longitudinal pavement joints shall be sealed with sealant conforming to Section

1050.03 or 1050.04 of the 2022 IDOT Standard Specifications for Road and Bridge Construction.

12-Jun-25 Are we responsible for the concrete drains within the curb and gutter leading to the ditches

(picture attached)?

These concrete flumes are not to be replaced. The contractor shall leave these in place and form the new curb to transition into this drain as existing.

Requests For Information (RFIs) - MAPC FA440725R0001

12-Jun-25

In the SOW, paragraph 3.1.8 it states “ The Contractor shall apply new paint markings to the new pavement”, is this the only painting we are doing? Not the entire section of road?

The contractor shall repaint markings on the new pavement only.

12-Jun-25 If it rains within the first 5 days after planting the new seed/fertilizer/mulch areas, are we still responsible for 2 waterings?

Yes, the contractor will be responsible for 2 waterings for the newly seeded areas.

12-Jun-25

There are (2) areas of patches that are near trees in the median, if we are to ensure base material is, at a minimum of 1-foot behind the curb, this will encroach on the roots of the trees. How would the base like us to approach this obstacle?

The contractor shall cut roots back to allow for the 1 foot minimum of base course.

12-Jun-25

SOW 3.1.8, states to apply traffic markings according to SDDCTEA 55-17, just looking for confirmation for the requirement of retro-reflectivity media applications.

There is no requirement for a specific method of applying the retro-reflective material, the government will inspect for even coverage of material across the entirety of the marking.

20 12-Jun-25 Will the sign-in sheet from the June 5th site visit be available in addendum? Yes it will be sent in an official amendment.

12-Jun-25

Please clarify if a superintendent can be a dual hat to cover the requirements of SSHO? Safety and quality is the responsibility of the contractor. The government does not direct how the contractors perform this work on this contract

12-Jun-25

If no to the question above, will the SSHO need to be full-time for this project? Safety and quality is the responsibility of the contractor. The government does not direct how the contractors perform this work on this contract

12-Jun-25

Please clarify if a superintendent can be a dual hat to cover the requirements of QA/QC? Safety and quality is the responsibility of the contractor. The government does not direct how the contractors perform this work on this contract

12-Jun-25

If no to the question above, will the QA/QC need to be full time for this project? Safety and quality is the responsibility of the contractor. The government does not direct how the contractors perform this work on this contract

12-Jun-25

Can a superintendent be a triple hat to cover the requirements of SSHO and QA/QC? Safety and quality is the responsibility of the contractor. The government does not direct how the contractors perform this work on this contract

26 12-Jun-25 Please confirm if tax should be included in our proposal? No, tax should not be included in the proposal.

12-Jun-25 Please confirm if the current prevailing wages will be consistent for the life of the project with no escalation?

No, Construction Wage Rates can change.

12-Jun-25

For the seed project, please confirm that the Northern Message Board refers to the “Message Board for South Bound Lanes” and the Southern Message Board refers to the “Message Board for North Bound Lanes” on the Atch 6 Drawings.

This is correct.

12-Jun-25

There is a requirement in the seed project SOW numbered 3.1.8 to apply new paint markings to the new pavement before the completion of the project. It is understood that the markings are to be in accordance with SDDCTEA Pamphlet 55-17, however can you provide drawings or additional indications on where the crosswalks should be placed and the guidelines for the striping to be done on the actual roadway?

There are no crosswalks to be painted as part of this project. Striping is to be completed only on the new pavement.

12-Jun-25 Will the traffic control plan need to be submitted with our initial seed project proposal? Or will it be proposed for review post-award?

Please refer to bullet point 3.1.7.5 of the SOW for traffic plan requirements.

12-Jun-25

Will a police officer be required for the traffic control plan? The contractor will not be required to provide a police officer for coordination, all coordination will go through Government personnel on base.

12-Jun-25 For market research, is someone on site currently maintaining the roadways that you can provide contact information for?

The 375 CES is responsible for maintaining all roadways on Scott AFB. The Contracting officer in the contact for the current multiple award paving contract.

12-Jun-25 Please confirm if all excess fill materials, including broken concrete and asphalt will be allowed to stay on property or shall be hauled offsite?

Excess fill materials must be removed from base by the contractor.

12-Jun-25 Please confirm if there is a separate staging area onsite for fill material to be stockpiled for re-use? There is no separate staging area planned for this project, all materials and equipment must be stored within the work area.

12-Jun-25

Will the site contractor be required to have operators trained and certified in all various levels of contamination handling?

Contractor shall follow all safety protocols in the SDS sheets of any chemical or substance used in this project. This area is not anticipated to contain hazardous materials, no certification required.

12-Jun-25

Will all contaminated soils be delivered to a location on site, turned over to Owner for disposal? If contamination is determined to be present, the contractor shall notify the Government and a modification shall be processed for the contractor to dispose of the contaminated material.

12-Jun-25

What are the requirements by the site contractor for the storage of contaminated soil on site? If contamination is determined to be present, the contractor shall notify the Government and a modification shall be processed for the contractor to dispose of the contaminated material.

12-Jun-25 Please confirm if we will be allowed to keep a locked storage container or conex box within the grounds.

The contractor may keep storage containers within the work area during construction.

12-Jun-25 Throughout the duration of the IDIQ, will a guard / escort be required at any restricted work areas including but not limited to buildings, outside areas?

A guard/escort can be required on select projects, supplied by the government.

12-Jun-25 Does the 12-point font-size-minimum requirement apply text within tables, images, and graphics? No

12-Jun-25

For the sanitized copy of the Past Performance Volume II, is there preferred terminology to refer to the prime contractor and/or subcontractors in lieu naming them? (i.e. using “The Contractor” or “The Subcontractor”, UEID numbers, etc.)

Sanitized copies of the past performance questionnaires are not required and the solicitation will be amended.

12-Jun-25

If we have available CPARS, can we use them within our proposal in lieu of requesting new or utilizing previous PPQs using the document that was provided with this solicitation?

Follow the instructions in Section L-2.2.2 Volume II - Past Performance.

12-Jun-25

Section L-2.2.1.5. in the proposal instructions; If we do not have income statements and balance sheets on file for all of the previous five fiscal years, may we submit tax returns in substitution?

Follow the instructions in Section L-2.2.1.5 Financial Resources

12-Jun-25 If a contractor is not awarded one of the 8 spots on the IDIQ, will there be future opportunities to join the contract vehicle?

See attachment 2 Task Order Procedures section (b) On/Off Ramp Procedures.

12-Jun-25

Are there any additional designations for set asides within the 8 small business awardees? (i.e. set number of Women Owned Small Business, Veteran Owned Small Business, etc.)

No

12-Jun-25

I am working on this information and needed a little clarity on the clauses and provisions.

Wasn’t this portion completed with the SAM renewal? Or is there a place to sign on the packet? Thanks for your assistance.

Refer to Section L - Instruction, Conditions, and Notices to Offerors. Specifically for this question L- 2.2.1.3