This document is a Storm Water Pollution Prevention Plan (SWPPP) for Scott Air Force Base in Illinois, detailing the base's comprehensive strategy for managing storm water runoff and preventing environmental contamination. The plan covers the base's 2,900-acre facility, which houses the 375th Air Mobility Wing and includes multiple units such as the Air Mobility Command, Surface Deployment Distribution Command, and various aircraft operations, with approximately 25% of the area covered by impervious surfaces.

The SWPPP identifies fifteen drainage areas that discharge into local waterways like Silver Creek and Ash Creek, and outlines specific industrial activities that could potentially introduce pollutants into storm water, including aircraft maintenance, vehicle maintenance, fuel storage, and hazardous material handling. The document is part of the base's compliance with the National Pollutant Discharge Elimination System (NPDES) General Permit No. ILR00 2659, which requires ongoing monitoring, quarterly inspections, annual reporting, and implementation of pollution prevention measures to minimize environmental impact from industrial activities.

View the file

Other files for this federal contract opportunity

Other files attached to FY25 Multiple Award Paving Contract (MAPC) - Recompete, newest first.
File Type Posted
Solicitation Amendment FA440725R00010002.pdf PDF
RFI Log Responses - FY25 MAPC Seed Project_Scott Drive.pdf PDF
Solicitation Amendment FA440725R00010001.pdf PDF
03-Section L (v3).pdf PDF
05a-FY25 MAPC PPQ v2.pdf PDF
04-Section M (v4).pdf PDF
Sign-In Sheet - MAPC Seed Project_Site Visit.pdf PDF
10-WD IL20250017 - 3.21.2025.pdf PDF
07-Construction_cost_estimate_breakdown.xlsx XLSX spreadsheet
06c-SOW ATCH 3 - 1149302 - Boring Results.pdf PDF
06d-SOW ATCH 4 - 1149302 - Utility Map.pdf PDF
06a-SOW ATCH 1 -1149302 - Work Areas.pdf PDF
08-Schedule_material_submittals.xlsx XLSX spreadsheet
Solicitation - FA440725R0001.pdf PDF
01c-ATCH C Scott AFB IFS 9-6-19 reduced.pdf PDF
11-Scott AFB Climogram_Feb 2025.pdf PDF
05a-FY25 MAPC PPQ.pdf PDF
01b-MAPC Gen Rqmts 15 Apr 25.pdf PDF
09-NAF Standard Clauses_1 May 2024.pdf PDF
16-Maximum Allowable Concentrations.pdf PDF
06f-SOW ATCH 6 - 1149302 - Traffic Control Example.pdf PDF
06b-SOW ATCH 2 - 1149302 - Contaminated Soils.pdf PDF
06g-SOW ATCH 7 - 1149302 - Contractor Requirements.pdf PDF
02-TO Procedures.pdf PDF
04-Section M (v3).pdf PDF
01a-ATCH A Scott AFB Map 3-4-25 reduced.pdf PDF
06-SOW - 1149302 REPAIR Full Depth Roadway Patching Along Scott Drive.pdf PDF
12-Real ID.pdf PDF
03-Section L (v2).pdf PDF
05-PPI.pdf PDF
14-Table 6-1. Fixed Wing Aprons.pdf PDF
15-Soil Testing and Disposal Procedure.pdf PDF
01-SOW 2025 MAPC.pdf PDF
13-DOD Safe.pdf PDF
Show all 34

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STORM WATER POLLUTION PREVENTION

PLAN

SCOTT AIR FORCE BASE

FEBRUARY 2021

Prepared for:

SCOTT AIR FORCE BASE

501 Hangar Road, Building 531 Scott Air Force Base, Illinois, 62225 ATTN: Joseph Weber

AIR FORCE CIVIL ENGINEER CENTER

Air Force Civil Engineer Center 604 Tyler Street Building 3198, Suite H Scott AFB, Illinois 62225-0000 ATTN: Troy Poorman

GENERAL SERVICES ADMINISTRATION

819 Taylor Street, Room 13A33 Fort Worth, Texas 76102-6144 ATTN: Jamela Jarrell

Prepared By:

1608 13th Avenue South, Suite 300 Birmingham, Alabama 35205 1-800-806-4001 • www.bhate.com

GSA Call Order No: ID07180032 GSA Contract No.: GS07Q16BGA0010 GSA Order No.: 47QFWA19F0049 CDRL No.: A001af Bhate Project No.: AFCBPA2.0032

This page intentionally left blank.

STORM WATER POLLUTION PREVENTION PLAN

February 2021 i

ABOUT THIS PLAN

This installation-specific Environmental Management Plan (EMP) was developed using the United States (U.S.) Air Force’s (AF) standardized Storm Water Pollution Prevention Plan (SWPPP) template. This Plan is not an exhaustive inventory of all storm water requirements and practices. Where applicable, external resources, including Air Force Instructions (AFIs); AF Playbooks; and federal, state, local, and permit requirements are referenced.

Each section of this SWPPP begins with standardized, AF-wide “common text” language that addresses AF, Department of Defense (DoD), and federal requirements, including the Environmental Protection Agency (EPA) Multi-Sector General Permit (MSGP) requirements. This common text language is restricted from editing to ensure that it remains standard throughout all plans. The common text language is maintained and updated by the designated Office of Primary Responsibility (OPR) with assistance from the Office of Collateral Responsibility (OCR), as appropriate. Immediately following the AF-wide common text sections are Installation sections. The Installation sections contain installation-specific content to address state, local, and installation-specific requirements. Installation sections are unrestricted and are maintained and updated by installation or Section personnel.

This document is optimized to be accessed and viewed electronically. The eDASH website at https://usaf.dps.mil/teams/10624/Scott/SitePages/Home.aspx is the primary communication tool for AF EMPs.

https://usaf.dps.mil/teams/10624/Scott/SitePages/Home.aspx ii February 2021

February 2021 iii

TABLE OF CONTENTS

ABOUT THIS PLAN..................................................................................................i CERTIFICATION .....................................................................................................v DOCUMENT CONTROL........................................................................................vi

OVERVIEW AND SCOPE......................................................................... 1-1 SWPPP Overview and Scope ..........................................................................................1-1 Installation Supplement Overview and Scope .................................................................1-1

Installation Description.......................................................................................1-1 Storm Water Permits...........................................................................................1-2 Drainage Basin Overview...................................................................................1-2 Storm Water Drainage System ...........................................................................1-2 Drainage Areas ...................................................................................................1-3 Regulatory Basis .................................................................................................1-6 Storm Water Pollution Prevention Plan Organization ........................................1-6

INSTALLATION PROFILE....................................................................... 2-1

ENVIRONMENTAL MANAGEMENT SYSTEM.................................... 3-1

GENERAL ROLES AND RESPONSIBILITIES....................................... 4-1

TRAINING .................................................................................................. 5-1 RECORDKEEPING AND REPORTING................................................... 6-1 MINIMUM CONTROL MEASURES........................................................ 7-1

Potential Pollution Sources ..............................................................................................7-1 Storm Water Control Measures .....................................................................................7-11

Minimize Exposure...........................................................................................7-11 Preventive Maintenance....................................................................................7-14 Good Housekeeping and Pollution Prevention Practices..................................7-14 Spill Prevention and Response .........................................................................7-27 Storm Water Management Practices.................................................................7-29 Sediment and Erosion Prevention.....................................................................7-30 Employee Training ...........................................................................................7-31 Deicing Chemical Storage ................................................................................7-33 Plastic Materials Requirements ........................................................................7-34

Schedules and Procedures for Monitoring.....................................................................7-35 Analytical Sampling .........................................................................................7-35

Inspections .....................................................................................................................7-35 Quarterly Facility Inspections...........................................................................7-36 Quarterly Visual Observation of Discharges ....................................................7-37 Deicing Season Inspections ..............................................................................7-38

Documentation for Eligibility Considerations under Other Laws .................................7-38

REFERENCES ............................................................................................ 8-1 ACRONYMS............................................................................................... 9-1 iv February 2021

Standard Acronyms..........................................................................................................9-1 Installation Acronyms......................................................................................................9-1

DEFINITIONS ............................................................................................ 10-1 Standard Definitions ...................................................................................................... 10-1

I ................................................. 11-1 Vehicle and Equipment Wash Water ............................................................................. 11-1 Deicing Chemical Usage................................................................................................ 11-1 Control Measures for Management of Melt Water ........................................................ 11-1

Tables

Table 1-1. Storm Water Drainage Area Information ................................................................................ 1-4 Table 2-1. Installation Profile and Permit Information ............................................................................. 2-1 Table 4-1. Storm Water Pollution Prevention Team Members ................................................................. 4-1 Table 6-1. General NDPES Permit ILR00 2659 Elements ....................................................................... 6-3 Table 7-1. Industrial Activities and Associated Pollutants ....................................................................... 7-1 Table 7-2. Areas of Site Where Potential Spills/Leaks Could Occur ....................................................... 7-3 Table 7-3. Evaluations for Unauthorized Non-Storm Water Discharges .................................................. 7-6 Table 7-4. Storm Water Analytical Summary, May 2020 ........................................................................ 7-9

Attachments

Attachment A General Location Map Attachment B Site Map Attachment C General National Pollutant Discharge Elimination System Permit No. ILR00 2659 Attachment D Significant Spills Attachment E Training Records Attachment F Inspection Records Attachment G Discharge Monitoring Reports Attachment H NPDES Permit No. IL0026859 vi February 2021

DOCUMENT CONTROL

Standardized SWPPP Template

In accordance with (IAW) the Air Force Civil Engineer Center (AFCEC) Environmental Directorate (CZ) Business Rule (BR) 08, EMP Review, Update, and Maintenance, the standard content in this SWPPP template is reviewed periodically, updated as appropriate, and approved by the Water Quality Subject Matter Expert (SME).

This version of the template is current as of 06/26/2020 and supersedes the 2018 version.

NOTE: Installations are not required to update their SWPPPs every time this template is updated. When it is time for installations to update their SWPPPs, they should refer to the eDASH EMP Repository to ensure they have the most current SWPPP version.

Record of Updates – The SWPPP is modified and updated IAW applicable permit requirements.

Page/Section Nature of Change Date of Change Approved By:

22 March 2024

22 March 2024

22 March 2024

Page i Updated eDASH link to current address 04 April 2024

February 2021 vii

Record of Review – IAW AFI 32-1067, Water and Fuel Systems, the SWPPP is reviewed based on permit requirements.

Review Date Review Participants Notes/Remarks Results in Plan

Update (Yes or No)

Version Table – A new version of the plan is created when pen and ink changes are incorporated. Below is a list of all versions updated under the current permit.

Version Number Description Date

April 2024 William Markham and Minor Updates / No Laura Schroeder NoApril 2024 viii February 2021

February 2021 1-1

OVERVIEW AND SCOPE

SWPPP Overview and Scope

This SWPPP specifies how installation personnel prevent discharges to storm water of potential pollution from industrial operations. It contains procedures intended to minimize the risk of industrial storm water pollution in drainage areas located within the installation’s boundaries. The SWPPP describes installation:

Identification and evaluation of activities and potential storm water pollution sources Identification and implementation of storm water Best Management Practices (BMPs) Pollution reduction measures and procedures Monitoring and inspection procedures

The installation Storm Water Pollution Prevention Team (SWPPT) is responsible for developing, implementing, and managing the SWPPP.

Installation Supplement Overview and Scope

Installation Description

Scott Air Force Base (AFB) is located in St. Clair County, Illinois (IL) in the southwestern portion of the State, approximately 25 miles east of downtown St. Louis, Missouri. The Scott AFB Location Map is presented in Attachment A and the Scott AFB Site Map is presented in Attachment B. The Base is located within the IL portion of the St. Louis metropolitan area known as Metro East. The setting is semi-rural at the edge of the Metro East area. The Base is surrounded by smaller municipalities, including O'Fallon, Belleville, Lebanon, and Mascoutah. The Base is bordered on the east by Silver Creek. The Base occupies approximately 2,900 acres (1.26 x 108 square feet). Approximately 25 percent of the Base is covered with impervious areas, such as pavement and buildings.

Currently, Scott AFB is the home of the 375th Air Mobility Wing (AMW). The 375th AMW is responsible for the operation, management, and maintenance of the mission of Scott AFB; managing an aeromedical evacuation system for the continental U.S.; and command and supervision of all active duty C-21 aircraft within the U.S.

The 375th AMW is host to the following commands:

The Air Mobility Command (AMC) and U.S. Transportation Command The 18th AF The 932nd Airlift Wing (AW) and 126th Air Refueling Wing (ARW) Surface Deployment Distribution Command The Defense Information Technology Contracting Organization

Scott AFB maintains an airport with an 8,000-foot runway, an air traffic control tower (built in 1997), and associated aircraft. The Base is also host to a number of tenant organizations. The 375th AMW operates C-21A and NC-21 aircraft from Scott AFB, Will Rogers World Airport, Joint Base Andrews, and Peterson AFB. The 932nd AW operates C-40 aircraft assigned to Scott AFB. The C-40 aircraft are flown and maintained by the 932nd AW and the 54th Airlift Squadron. The 126th ARW and the 906th Air Reserve Station operate KC-135R aircraft.

The Mid America Airport (MAA) is a joint-use venture between the AF and local governments. An additional runway was added to support commercial flights. Scott AFB extended their taxiway to connect with the airport and has access to the runway, but is not responsible for the operation or maintenance of the airport.

1-2 February 2021

The 126th ARW of the Illinois Air National Guard (ILANG) became operational in 1999 and added approximately 300 permanent personnel and 900 part-time personnel. The 126th ARW operates KC-135 aerial refueling aircraft from the ramp and maintenance facilities on the east side of the Base.

Storm Water Permits

Scott AFB has applied for and received permits as required by the Federal Water Pollution Control Act, also referred to as the Clean Water Act (CWA). The following is a list of Scott AFB storm water permits:

Permit Number (No.) ILR00 2659 General National Pollutant Discharge Elimination System (NPDES) Permit for Storm Water Discharges from Industrial Activities Permit No. ILR10 General NPDES Permit for Storm Water Discharges from Construction Activities Permit No. ILR40 0611 General NPDES Permit for Discharges from Small Municipal Separate Storm Sewer Systems (MS4s)

Under the General NPDES Permit for Storm Water Discharges from Industrial Activities (ILR00), Scott AFB falls under the following sectors:

Sector S: Air Transportation Sector N: Scrap Recycling Facilities, Sub-Sector N2 (Source-Separated Recycling Facilities) Sector P: Land Transportation and Warehousing

The Base has developed a Storm Water Management Program to reduce the discharge of pollutants from the MS4 and satisfy the MS4 permit requirements. The Storm Water Management Program is described in the Storm Water Management Plan (SWMP), a document separate from the SWPPP.

The Base also holds Permit No. IL00 26859 NPDES Permit to Discharge into Waters of the State. This permit regulates discharge from the Base Waste Water Treatment Plant (WWTP) into an unnamed tributary of Silver Creek.

Drainage Basin Overview

Scott AFB is located within the Silver Creek and Ash Creek drainage basins of the Kaskaskia River.

Elevations within the Kaskaskia River Watershed range from 350 to 500 feet above mean sea level. The Watershed is approximately 172 miles long and 67 miles wide running northeast to southwest with two flood control reservoirs, Lake Shelbyville in the northern portion of the basin and Carlyle Lake located just south of the middle of the Kaskaskia of the basin. Elevations on the Base range from 420 to 480 feet. The Base and surrounding areas are generally flat with gentle rolling hills.

Storm Water Drainage System

Storm water drainage at Scott AFB is provided by a series of enclosed storm sewers and open channels. As precipitation falls, it is conveyed to major drainage channels which exit to the south and east boundaries of Scott AFB. More specifically:

Silver Creek flows along the eastern boundary of Scott AFB and is the major receiving stream for runoff from the Base.

Drainage is also provided by Ash Creek, which flows through the Shiloh housing area and through the western and southern areas of the Base.

The South Ditch flows adjacent to the southern boundary of the Base and into Mosquito Creek.

A high-flow relief channel connects the western portion of South Ditch to Ash Creek.

February 2021 1-3

A portion of Patriots Landing Housing Area discharges to Loop Creek, which is a tributary to Silver Creek.

Cardinal Creek flows onto the base across the north boundary and through the Base golf course and the 126th ARW facilities and ultimately into Silver Creek.

The East Taxiway Ditch discharges storm water from approximately half of the active runway. It disperses into multiple channels in the Silver Creek Wetlands downstream from the Taxiway Ditch (Spill) Control Gate.

The storm water collection system at Scott AFB services administrative, industrial, commercial, and residential areas of the Base. Facilities with the most potential for storm water pollution include aircraft hangars and maintenance facilities, fuels storage and dispensing, office complexes, warehousing, residential and service facilities, runways, and recreational facilities.

Drainage Areas

Fifteen drainage areas have been identified on the Base, and are shown in Attachment B. Inflows to the Base include the designation “I” and a sequential number. Outfalls from the major drainage ways are designated with an “O” and a sequential number. Nine defined outfalls have been identified at Scott AFB.

Active facilities subject to industrial classification under storm water discharge regulations are located within eleven of these basins.

Drainage areas are generally governed by topography. This section presents the delineation of Scott AFB into outfalls or drainage areas subject to current storm water regulations and characterizes the storm water drainage system for each drainage area on the Base. It also identifies the potential operations and facilities that have the potential to adversely affect storm water and receiving water quality.

Table 1-1 summarizes the size, associated infalls or outfalls, area description, receiving waters, and impervious surface area for each drainage area. The table also identifies whether each drainage area contains industrial activity that could lead to contamination of storm water runoff, either from past or present industrial activities.

1-4 February 2021

Table 1-1. Storm Water Drainage Area Information

Drainage Area

Outfall/ Infall No.1 Description of Area

Receiving Waters

Industrial Activity

Drainage Area

Acreage Impervious

Acreage Percent (%) Impervious

Infall/Outfall Locations

Latitude Longitude

DA-1 N/A Ash Creek at Scott Road Ash Creek Yes 441 152.8 34.6 N/A N/A

DA-2

O-1

(O-AC1)

Ash Creek Behind Veterans Foreign Wars (turns to southeast) Ash Creek Yes 837.3 321.8 38.4 38.533159 -89.861548

DA-2

O-2

(O-SD1)

Across from Salt Barn Silver Creek Yes 837.3 321.8 38.4 38.535885 -89.833761

DA-3

O-8

(O-PL1)

Patriots Landing, Lively Ct.

(Near South fenceline) Loop Creek No 78.8 17.5 22.2 38.524732 -89.875782

DA-4 O-9 Near the southeast fencepost of Patriots Landing

Un-named Tributary No 79.9 21.6 27.1 38.524180 -89.864466

DA-5

O-6

(O-CC1)

Cardinal Creek Silver Creek Yes 571.2 92.8 16.3 38.548172 -89.840976

DA-6 N/A Taxiway Ditch Silver Creek Yes 183.2 64.2 35.0 N/A N/A DA-7 N/A East Drainage Area 7 Silver Creek Yes 17.1 6.4 37.1 N/A N/A DA-8 N/A East Drainage Area 8 Silver Creek Yes 17.0 5.4 32.1 N/A N/A DA-9 O-5 East Drainage Area 9 Silver Creek No 14.7 6.8 46.0 N/A N/A

DA-10 N/A East Drainage Area 10 Silver Creek Yes 33.3 5.1 15.2 N/A N/A

DA-11 O-7

(O-SL1) Outfall from Scott Lake Dam Silver Creek Yes 110.5 8.3 7.5 38.553165 -89.839421

DA-12 O-3

(O-MC1)

Landfill Culvert Entrance (Mosquito Creek & South

Ditch) Silver Creek No 524.6 18.3 3.5 38.536205 -89.832532

DA-12 O-4

(O-MC2)

Mosquito Creek Behind WWTP Silver Creek No 524.6 18.3 3.5 38.535312 -89.830950

DA-13 N/A WWTP East Silver Creek Yes 2.9 1.1 38.9 N/A N/A

February 2021 1-5

Drainage Area

Outfall/ Infall No.1 Description of Area

Receiving Waters

Industrial Activity

Drainage Area

Acreage Impervious

Acreage Percent (%) Impervious

Infall/Outfall Locations

Latitude Longitude

DA-14 N/A WWTP South Silver Creek Yes 3.6 1.1 31.2 N/A N/A

DA-15 N/A Area South of the South Ditch Silver Creek No 49.9 2.8 5.7 N/A N/A

DA-1 I-2

(I-AC1) Ash Creek at Seibert Road N/A N/A 441 --- --- 38.548648 -89.876442

DA-1 I-3

(I-AC2)

Southwest of Shiloh Housing (behind Buildings 2519 &

2517) N/A N/A 441 --- --- 38.541050 -89.879499

DA-5

I-1

(I-CC1)

Cardinal Creek Silver Creek N/A 571.2 --- --- 38.555030 -89.859780

Notes:

¹() represents the sampling locations described in Section 7.3, Schedules and Procedures for Monitoring % = percent DA = drainage area N/A = not applicable

1-6 February 2021

Regulatory Basis

In 1987, the CWA was amended by Congress to require implementation of a national program for addressing water quality impairment due to non-agricultural causes. In 1990, the EPA published final regulations in 40 Code of Federal Regulations 122 establishing permit application requirements for storm water discharges associated with industrial activities. The activities applicable to Scott AFB are listed as follows:

Landfills, land application sites, and open dumps that receive or have received industrial wastes from activities on the Base.

Transportation facilities that are involved in vehicle maintenance, equipment cleaning operations, or aircraft deicing operations.

Treatment works treating domestic sewage or waste water treatment device or system used in the storage, treatment, recycling, and reclamation of municipal or domestic sewage, including land used for the disposal of sewage sludge that is located within the Base boundary.

In response to regulatory requirements, the Illinois Environmental Protection Agency (IEPA) issued a General NPDES Permit for Storm Water Discharges from Industrial Activities (Permit No. ILR00 2659) to Scott AFB, which authorizes Scott AFB to discharge storm water from its property to waters of the State.

The permit is effective from April 5, 2017 to March 31, 2022, and as a condition of the permit, Scott AFB is required to maintain this SWPPP.

Storm Water Pollution Prevention Plan Organization

This SWPPP is organized to include the components specified by the Illinois Environmental Protection Agency (IEPA) per Section E of General NPDES Permit No. ILR00 2659. Major elements of the Plan include a description of potential storm water pollution sources, description of storm water management controls, certification of non-storm water discharges, completion of quarterly visual observations of discharges, and completion of annual facility inspections.

The SWPPP describes potential sources which may be expected to add significant quantities of pollutants to storm water discharges, as summarized below:

General Location Map: A map extending 1/4 mile beyond the property line, showing the facility, and surface water bodies is included in Attachment A.

Site Map: A map showing storm water conveyance and discharge structures, drainage areas of each storm water outfall, infall and outfall locations, paved areas and buildings, locations of exposed significant materials, structural storm water pollution control measures, surface water bodies and drainage ditches, and areas of existing and potential soil erosion are included in Attachment B. A map showing the locations of hazardous waste initial accumulation points, cooling towers, oil water separators (OWSs), and fueling areas where materials are potentially exposed to precipitation are also included in Attachment B.

Narrative Description: A description of the industrial activities occurring at the Base, including significant materials that are treated, stored, or disposed of in a manner to allow exposure with storm water; materials that are used, stored, or produced on site with emphasis on those materials that are exposed to storm water and have the potential of polluting storm water runoff; list of all measures to remove significant pollutants from storm water (containment devices, oil-grease separators, debris and sediment controls, and waste chemical disposal); and methods of onsite storage and disposal is included in Section 7.1, Potential Pollution Sources.

Types of Pollutants: A list of the types of pollutants with a potential to be present in storm water discharges in significant quantities is included in Section 7.1, Potential Pollution Sources.

February 2021 1-7

Size of Facility/Impervious Area: The size of the facility and the percent of the facility with impervious areas were described in Table 1-1., Storm Water Drainage Area Information.

Summary of Existing Sampling Data: The May 2020 sampling data for the infall and outfall areas is included in Section 7.3, Schedules and Procedures for Monitoring.

Storm water management controls, which will be implemented by Scott AFB, are described in the SWPPP and include:

Storm Water Pollution Prevention Personnel: The storm water pollution prevention personnel responsible for developing, implementing, and revising the SWPPP are identified in Chapter 4.0, General Roles and Responsibilities.

Preventive Maintenance: The inspection procedures for storm water conveyance system devices are described in Section 7.2, Storm Water Control Measures.

Good Housekeeping: Procedures for maintaining clean and orderly facilities are described in Section 7.2, Storm Water Control Measures.

Spill Prevention and Response: Areas where significant spills have the potential to enter the storm water conveyance systems and procedures for material handling and spill response are included in Section 7.2, Storm Water Control Measures.

Storm Water Management Practices: Measures to reduce the pollutants in storm water discharge are described in Section 7.2, Storm Water Control Measures.

Sediment and Erosion Prevention: Topographic areas that have a high potential for erosion of soil have been identified in Section 7.1, Potential Pollution Sources, and the methods to be employed to reduce such erosion are described in Section 7.2, Storm Water Control Measures.

Employee Training: The periodic training of all employees at all levels of responsibility, including who should be trained, frequency, and topics, is outlined in Chapter 5.0, Training.

Inspection Procedures: Qualified personnel should conduct periodic inspections, documenting such inspections and any corrective action to be initiated. Chapter 4.0, General Roles and Responsibilities, and Section 7.4, Inspections, assigns responsibilities and outlines inspection procedures.

The certification of testing/evaluation for non-storm water discharges is included in Section 7.2, Storm Water Control Measures.

Requirements and procedures for quarterly visual observations, to include performing and documenting quarterly visual observations of storm water discharges associated with industrial activities from each outfall, are described in Section 7.4, Inspections.

The requirements for annual facility inspections to ensure compliance with all elements of the SWPPP are described in Section 7.4, Inspections. Record keeping associated with annual inspections is outlined in Section 6.0, Recordkeeping and Reporting.

A description of additional federal and/or local programs that may affect storm water discharges (i.e., Integrated Contingency Plan (ICP) for Oil and Hazardous Substance Spill Prevention and Response is included in Section 7.5, Documentation to Support Eligibility Considerations Under Other Laws.

1-8 February 2021

February 2021 2-1

INSTALLATION PROFILE

Table 2-1. Installation Profile and Permit Information

Scope of Plan Scott AFB, IL

Facility Operator Office Symbol: Base Civil Engineer - 375 Civil Engineering Squadron (CES) / Commander (CC) Address: 701 Hangar Road City, State Zip Code: Scott Air Force Base, IL 62225 Telephone Number: (618) 256-2701 Latitude/Longitude: 38.5405/ -89.8345.

Office of Primary Responsibility

(OPR)

OPR: 375th CES/Civil Engineer, Installation (Management) Environmental

(CEIE)

CEIE has overall responsibility for implementing the SWPPP and is the lead organization for monitoring compliance with applicable federal, state, and local storm water regulations

Responsible Official/Legally Responsible Person

Office Symbol: 375 AMW / CC Name: Col Telephone Number: (618) 256-

Water Quality Program Manager (SWPPP Contact)

Name: Mr.

Title: Storm Water Pollution Prevention Coordinator (Water Quality Program Manager) Telephone Number: (618) 256-2 Email address: @us.af.mil

Permitting Authority

IEPA

Permit Type General

Permit Number/Permit Tracking Number

ILR00 2659

Permit Expiration Date

SIC Code(s) 9711

NAICS Code(s) 928110

General Location Map

Located in Attachment A

Site Map Located in Attachment B

2-2 February 2021

February 2021 3-1

ENVIRONMENTAL MANAGEMENT SYSTEM

The AF environmental program adheres to the Environmental Management System (EMS) framework and it’s Plan, Do, Check, Act cycle for ensuring mission success. Executive Order (EO) 13693, Planning for Federal Sustainability in the Next Decade, Department of Defense Instruction (DoDI) 4715.17, Environmental Management Systems, AFI 32-7001, Environmental Management, and International Organization for Standardization (ISO) 14001 standard, Environmental Management Systems – Requirements with guidance for use, provide guidance on how environmental programs should be established, implemented, and maintained to operate under the EMS framework.

IAW the installation EMS framework, the storm water program employs EMS-based processes to achieve compliance with all legal obligations and current policy drivers, effectively manage associated risks, and instill a culture of continual improvement. The SWPPP serves as an administrative operational control that defines compliance-related activities and processes.

3-2 February 2021

February 2021 4-1

GENERAL ROLES AND RESPONSIBILITIES

The SWPPP requires the involvement of multiple organizations and varied personnel on the installation, including contractors and other DoD organizations. The major roles/organizations involved in supporting the SWPPP at a typical installation include:

Installation Commander Base Civil Engineer Environmental Element Chief Water Quality Program Manager Storm Water Pollution Prevention Team (identified below) Installation Personnel

AFCEC

Unit Environmental Coordinator (UEC, see AFI 32-7001)

Installation Supplement – General Roles and Responsibilities

While storm water pollution prevention is the responsibility of everyone on Scott AFB, those primarily involved in the execution of the SWPPP are the Base-wide team of personnel who are responsible for training, developing, implementing, and revising the SWPPP. General NPDES Permit ILR00 2659, condition E.7., requires that these personnel be identified by job title, direct telephone number, and email address.

SWPPT members are identified by name or title, along with their individual responsibilities in the Storm Water Pollution Prevention Team Members table below.

Table 4-1. Storm Water Pollution Prevention Team Members

Job Title Organization Responsibilities Contact Information

SWPPT Leader (Base Civil Engineer)

375 CES Review and certification of the SWPPP, all modifications and updates, and signature authority for pertinent documents as required.

Authorization of funds to implement elements of the

SWPPP.

Lt. Col

Phone: (618) 256-2701 Fax: (618) 356-5934

4-2 February 2021

Job Title Organization Responsibilities Contact Information

SWPPT

Planning and Programming Coordinator (Water Quality Program Manager)

375 CES Ensures that Scott AFB is in compliance with the terms of the General NPDES Permit No.

ILR00 2659, General Permit for Storm Water Discharges from Industrial Activity.

Schedules and chairs regular and emergency meetings of the

SWPPT.

Updates the SWPPP as needed.

Performs annual inspections of affected industrial areas and evaluation of new or modified activity areas to determine if they must be included in the SWPPP.

Documents spill and leak cleanup as required by the SWPPP and the

MSGP.

Serves as technical resource to environmental representatives and/or operations personnel for facility and procedural changes identified to minimize pollutant exposure to storm water.

Ensures that storm water pollution prevention training is provided to all personnel working in affected industrial areas.

Communicates with regulatory agencies and the SWPPT as needed.

Phone: (618) 256-2 Fax: (618) 356-5934

Environmental Representatives

375 CES Each of the major Scott AFB operations that may contribute to storm water pollution has a designated Environmental Representative on the SWPPT.

The representatives coordinate with the Storm Water Pollution Prevention Coordinator to prevent storm water pollution in their areas of responsibility.

Varies

February 2021 5-1

TRAINING

The installation implements storm water training programs to ensure installation personnel, contractors, and visitors are aware of their roles in the program and the importance of their participation in its success.

DoDI 4715.10, Environmental Education, Training, and Career Development, implements policy and provides the procedures to obtain environmental education, training, and career development programs for DoD personnel. Installation leadership ensures that appropriate personnel complete required education, training, and certification necessary to perform their jobs. Priority for training is given to the use of AF-approved education/training sources such as the Air Force Institute of Technology (AFIT) training courses and official AF-approved computer-based training resources (e.g., The Environmental Awareness Course Hub [TEACH], Advanced Distributed Learning Service [ADLS], ArcNet, etc.) to meet training needs.

Specific training requirements are outlined in Section 7.2.7, Employee Training. Training records are maintained IAW the Recordkeeping and Reporting section of this Plan.

Installation Supplement – Training

SWPPP Training

The following personnel must understand the requirements of the MSGP and their specific responsibilities with respect to those requirements:

Personnel responsible for the design, installation, maintenance, and/or repair of controls (including pollution prevention measures) Personnel responsible for the storage and handling of chemicals and materials that could become contaminants in storm water discharges Personnel responsible for conducting monitoring and inspections Personnel responsible for documentation requirements for monitoring and inspections Personnel responsible for implementing and documenting corrective actions

Personnel must be trained in at least the following as related to the scope of their job duties (e.g., only personnel responsible for conducting inspections need to understand how to conduct inspections):

An overview of what is in the SWPPP Spill response procedures, good housekeeping, maintenance requirements, and material management practices The location of all BMPs and structural controls on the site required by the permit, and how they are to be maintained The proper procedures to follow with respect to the permit’s pollution prevention requirements When and how to conduct inspections, record applicable findings, and take corrective action

Employee training is essential to effective implementation of the SWPPP. Training activities address each component of the SWPPP, including how and why tasks are to be implemented. Annual training will be conducted to ensure that at least one member of each affected area is current on relevant storm water topics (see Attachment C). Each area representative is responsible for training others in their area. The SWPPP training tools used at Scott AFB include the following:

PowerPoint presentations Area-specific drills or practice runs Routine SWPPP meetings

5-2 February 2021

Public education and outreach information

At a minimum, training topics include the following:

Storm water pollution prevention program overview and regulations Base drainage areas, inflow, and outfall Facilities of concern to storm water management Storm water sampling Spill prevention and response Pollution prevention/ good housekeeping Compliance/ inspections

Spill Response Training

Scott AFB conducts spill response training, exercises, and drills related to the execution of their most recent ICP. This training meets the requirements of several regulators, including the EPA, Department of Transportation, Department of Interior, applicable AFI, and the Occupational Safety and Health Administration. Scott AFB conducts site-specific annual training throughout the year (drill year officially begins on 01 January).

February 2021 6-1

RECORDKEEPING AND REPORTING

Installation personnel as identified in this SWPPP implement measures to ensure compliance with applicable permit recordkeeping and reporting requirements. Records are stored and maintained IAW Air Force Manual 33-363, Management of Records, and records are archived and disposed IAW the Air Force Records Information Management System (AFRIMS) Records Disposition Schedule (RDS). The installation complies with permit reporting requirements

The installation maintains the following inspection, monitoring, and certification records with the SWPPP.

When possible, a link to the electronic version of the record is made available in the references section of this plan.

Copy of the Notice of Intent (NOI) Copy of the acknowledgement letter containing the permit tracking number Copy of the permit Description and dates of any significant spills, leaks, or other releases. Note: the installation maintains this information in Enforcement Actions, Spills, and Inspections Environmental Reporting (EASIER), and a link is available in the references section of this SWPPP.

Employee training records Documentation of maintenance and repairs of control measures Inspection reports Documentation of deviations from the schedule for monitoring or assessments and the reason for the deviation Documentation of corrective actions taken Documentation of benchmark exceedances and how they were responded to Documentation to support determination that pollutants of concern are not expected to be present above natural background levels if water is discharged directly to impaired waters when required by the permitting agency

Maintaining the SWPPP for Scott AFB requires several recordkeeping tasks. General NPDES Permit ILR00 2659 Part E.1 states that an electronic copy of the SWPPP will be submitted to the IEPA at the following email address: epa.indilr00swppp@illinois.gov. The SWPPP must also be available for inspection upon request.

In addition, Permit ILR00 2659 Part K.1 requires that an annual inspection report be submitted to document the results of the quarterly benchmark monitoring (if required) and quarterly facility inspections. The annual report must be submitted to the IEPA on or before 22 July (within 60 days of the 23 May anniversary of effective coverage under the Permit). The annual report will include at a minimum, a review and update of the SWPPP. The Permittee must submit modifications of the requirements of the SWPPP to the Agency with the Annual Report. The SWPPP must be updated within 180 days to comply with the new requirements and submitted with the next annual report. The annual report must also include documentation of any event (spill, treatment unit malfunction, etc.) which required an inspection, the results of the inspection, and any subsequent corrective maintenance activity performed. The report must be completed and signed by the authorized facility employee(s) who conducted the inspection(s). Copies of the annual reports must be kept with the SWPPP and maintained for at least 3 years.

Other recordkeeping requirements include the following:

Annual update of facility inventories

6-2 February 2021

Maintenance activities Storm water monitoring Record of spills at Scott AFB (included in Attachment D.

February 2021 6-3

Installation Supplement – Recordkeeping and Reporting

Table 6-1. General NDPES Permit ILR00 2659 Elements

Program Item Frequency Last Conducted/ Submitted Reference Notes

General NPDES Permit for Storm Water Discharges from Industrial Activities (ILR00 2659)

Every 5 Years 35 Illinois Administrative Code (IAC) Subtitle C, Chapter 1 and CWA

IEPA is responsible for updating the Permit. Permits are issued on a 5-year cycle.

https://www2.illinois.gov/epa/topics/forms/water-permits/storm-water/Pages/general-permits.aspx

SWPPP Update As changes occur to permit (every 5 years)

April 2 35 IAC Subtitle C, Chapter 1 NPDES Permit NO.

ILR00 2659, Part E.4

Original SWPPP March 1998 Previous SWPPP June 2004 Previous SWPPP June 2008 Previous SWPPP June 2011 Previous SWPPP April 2016 Submit to IEPA @ epa.indilr00swppp@illinois.gov

SWPPP Review Annually NPDES Permit No.

ILR00 2659, Part K.1

Review SWPPP and update as necessary.

Include a discussion of the SWPPP review and the SWPPP in the annual inspection report.

SWPPT Training Annually NPDES Permit No.

ILR00 2659, Parts E.9.e and F.2.g

This SWPPP specifies annual training on storm water pollution prevention for Scott AFB SWPPT members.

Inspection Report Annually June NPDES Permit No.

ILR00 2659, Part K.1

An annual inspection is required that includes a review of the SWPPP, as well as the facility to assure all measures and controls are operating properly. Submit the report electronically to the IEPA (epa.indannualinsp@illinois.gov) Due 22 July of each year

6-4 February 2021

Program Item Frequency Last Conducted/ Submitted Reference Notes

Routine Facility Inspections

Quarterly NPDES Permit No.

ILR00 2659, Part E.10.a.i and Parts G.1 and G.2

Inspections must be performed by qualified personnel with at least one member of the SWPPT participating.

Document the findings of the facility inspections and maintain this report with the SWPPP.

Include a summary of the routine facility inspections in the annual inspection report.

Visual Observation of Discharges

Quarterly NPDES Permit No.

ILR00 2659, Part E.10.a.ii and Part J.1

Perform and document a quarterly visual observation of a storm water discharge associated with industrial activity from each outfall.

SWPPP

Amendments

Within 14 days of significant construction, operation, or maintenance change

Varies NPDES Permit No.

ILR00 2659, Part E.4 and H.2

Submit to IEPA @ epa.indilr00swppp@illinois.gov

SWPPP

Modification required by IEPA

Within 30 days of notification

Not applicable NPDES Permit No.

ILR00 2659, Part E.3

Only required if the IEPA notifies Scott AFB that the SWPPP does not meet the requirements of the permit.

February 2021 7-1

MINIMUM CONTROL MEASURES

Potential Pollution Sources

Areas at the installation where industrial materials or activities are exposed to storm water are described in the Installation Supplement below.

Documentation of significant spills is maintained in the EASIER database. A link to EASIER is available in the references section of this plan.

Installation Supplement – Potential Pollution Sources

Activities, Associated Pollutants, and Potential Spills

Table 7-1. Industrial Activities and Associated Pollutants

Buildings/ Area Organization Industrial Activity Associated Pollutants

56, 60, 513, 514, 515, 516, 517, 542, 543, 546, 549

375 CES/CEO, 375

LRS

Civil Engineering shops and yard

Diesel, used oil, gasoline, solvents, batteries, paint

433, 450, 506 932 AMXS/MXAS,

932 AMXS/MXMG,

932 MXS/MXMFS

Aircraft maintenance Used oil, petroleum, oils, and lubricants (POLs), gasoline, solvents, diesel, Jet A

502 375 LRS Logistics Readiness Squadron port authority

None

548 375 LRS/LGRV,

Allied Trades/LGRV

Vehicle maintenance Used oil, POLs, gasoline, solvents, diesel

555 375 LRS Hazardous material element Hazardous materials and waste

560 375 LRS/LGRF Jet fuel receipt, storage and issue

Jet A

565 375 LRS/LGRF Military vehicle fueling Diesel, gasoline

Open lot near

375 LRS/LGRF Refueler parking Diesel, Jet A, POLs

750/751 375 CS/SCOTJ Military communications POLs

1640 AAFES/Firestone Fuel sales and auto maintenance

Used oil, POLs, gasoline, solvents, diesel

3163 375 CES/CEO Transformer storage yard Hazardous materials

3170 375 CES/CEF Fire training Firefighting foam

3200 375 CES/CEO Storage and maintenance of snow removal equipment and supplies

Diesel, gasoline, POLs

7-2 February 2021

Buildings/ Area Organization Industrial Activity Associated Pollutants

3201 375 CES/CEO Civil Engineering salt barn Salt

3285 375 SFS/CATM Firing range Ammunition, hazardous materials

3300 (and others)

375 CES/CEO Wastewater treatment POLs

3306 375 CES/CEIE Hazardous waste <90-day storage

Hazardous waste

East of 4001 Refuse Contractor Recycling Used oil, POLs

5002 126 CES/CEO 126th ARW Civil Engineering shops and yard

Used oil, POLs, gasoline, solvents, diesel

5006 126 LRS/LGRV 126th ARW vehicle maintenance

Used oil, POLs, gasoline, solvents, diesel

5020 126 MXS/MXMD 126th ARW Aircraft maintenance and operations

Used oil, POLs, gasoline, solvents, diesel, Jet A

5022 126 MXS/MXMFE,

126 MXS/MXMFS,

126 MXS/MXMFN,

126 MXS/MXMP, 126

MXS/MXMCR, 126

MXS/MXMV

126th ARW Aircraft maintenance and operations

Used oil, POLs, gasoline, solvents, diesel, Jet A

5024, 5026 126 MXS/MXMFS,

126 MXS/MXMCF,

126 MXS/MXMTC,

126 AMS/MXAA

126th ARW Aircraft maintenance and operations

Used oil, POLs, gasoline, solvents, diesel, Jet A

5038 126 LRS/LGRF 126th ARW Jet fuel receipt, storage and issue

Used oil, POLs, gasoline, solvents, diesel, Jet A

5046 126 CES/CEO 126th ARW Civil Engineering shops and yard

Used oil, POLs, gasoline, solvents, diesel

5498 375 FSS/FSCG Golf course maintenance yard and shop

Used oil, POLs, gasoline, diesel

6470 375 CES/EOD Explosive Ordnance Disposal bunker

Hazardous materials

Ramp area 375 OG Aircraft flight operations preparation

Used oil, POLs, gasoline, solvents, diesel, Jet A

Ramp areas 126 ARW 126th ARW Aircraft flight operations preparation

Used oil, POLs, gasoline, solvents, diesel, Jet A

N/A 375 CES/CEO Civil Engineering storage yard

Diesel, used oil

February 2021 7-3

Buildings/ Area Organization Industrial Activity Associated Pollutants

N/A Challenge Unlimited Challenge yard (grounds maintenance)

Diesel, used oil, gasoline

N/A 375 OG Taxiways and runway for flight operations

Used oil, Jet A, diesel

Spills and Leaks

Spill records at Scott AFB indicate that minor fuel spill incidents in the flight line ramp areas are fairly common. Ramp fueling operations are probably the most frequent source of potential pollutants in the area of the active runways. The table below identifies the areas where spills and leaks may occur. A list of spills and leaks from the past 3 years is included as Attachment D.

Table 7-2. Areas of Site Where Potential Spills/Leaks Could Occur

Location

Drainage Areas (Outfall[s]) BMP(s)*

Building No.

Activities Performed and/ or Occupant

56, 60, 513, 514, 515, 516, 517, 542, 543, 546, Civil Engineering shops and yard

DA-2 (O-1,

O-2)

HAZMAT stored in buildings, drip pans, spill kits, secondary containment for outside storage, covered dumpsters, covered storage areas.

433, 450, Aircraft maintenance

DA-2 (O-1,

O-2)

HAZMAT stored in buildings, covered storage areas for equipment, spill kits

502 Logistics Readiness Squadron port authority

DA-2 (O-1,

O-2)

Secondary containment spill pallets, spill kits, indoor storage

548 Vehicle maintenance

DA-2 (O-1,

O-2)

Covered dumpsters, drip pans, HAZMAT stored indoors, spill kits, drain plugs

555 Hazardous material element

DA-2 (O-1,

O-2)

Everything is stored indoors on spill pallets or in flammables lockers

560 Jet fuel receipt, storage, and issue

DA-2 (O-1,

O-2)

OWS, containment berms with draining procedures, containment at offloading headers, spill kits

565 Military vehicle fueling

DA-2 (O-1,

O-2)

Spill kits, emergency shut-off, quick disconnect hoses

Open lot near 744

Refueler parking DA-2 (O-1, O-2)

Storm water inlets connected to containment basin with draining procedures

7-4 February 2021

Location

Drainage Areas (Outfall[s]) BMP(s)*

Building No.

Activities Performed and/ or Occupant

750/751 Military communications

DA-2 (O-1,

O-2)

Underground storage tanks, covered area for equipment, aboveground storage tank (AST) is covered

1640 Fuel sales and auto maintenance

DA-1 (N/A) Covered dumpsters, covered tire storage areas, emergency shut off valves

3163 Transformer storage yard

DA-7 (N/A) Oil-containing transformers stored in containment area, transformers stored outside of containment area are either dry or have been drained, secondary containment berm with OWS, minimize number of transformers at yard

3170 Fire training DA-7 (N/A) Containment pond to collect surface runoff (outfalls to WWTP), capped outside storage tanks, spill kit

3200 Storage and maintenance of snow removal equipment and supplies

DA-2 (O-1,

O-2)

Containment around tanks, inside storage, spill kit, quick disconnect hoses, spill plan, double wall tanks, emergency shut off

3201 Civil Engineering salt barn

DA-2 (O-1,

O-2)

Ensure plugs are in empty containers, salt stored indoors, excess salt swept and disposed of after delivery, drip pans

3285 Firing range DA-12 (O-3) Closed collection drums for millings

3300 (and others)

Wastewater treatment

DA-2, DA-13

(O-1, O-2)

Materials stored under awning, secondary containment pallets, ensure trench drain is clean under awning, covered dumpsters

3306 Hazardous waste 90-day storage

DA-14 (N/A) Hazardous waste stored inside, secondary containment pallets, universal waste stored in trailer, ensure plugs in empty containers, store unused containment pallets upside down

East of

Recycling DA-2 (O-1, O-2)

Inspect area for surface litter, random dumping, and windblown debris; itemized containers;

frequent disposal of containers

5002 126th ARW Civil Engineering shops and yard

DA-5 (O-6) Secondary containment pallets, empty pallets stored upside down, drip pans, generators stored away from inlets; spill kit

5006 126th ARW vehicle maintenance

DA-5 (O-6) Secondary containment pallets, empty pallets stored upside down, drip pans, generators stored away from inlets, spill kit

February 2021 7-5

Location

Drainage Areas (Outfall[s]) BMP(s)*

Building No.

Activities Performed and/ or Occupant

5020 126th ARW Aircraft maintenance and operations

This is the start of the file's text. The full file is on GovTribe.