Attachment 19 - FY24 SABER Q and A Worksheet Amendment 0003.pdf
PDF 135 KB Posted
- Attached to
- Simplified Acquisition of Base Engineering Requirements (SABER-IDIQ) Federal contract opportunity
- Solicitation number
- FA303024R0004
About this file
This document is a Question and Answer worksheet related to a Request for Proposal (RFP) for a Simplified Acquisition of Base Engineering Requirements (SABER) Indefinite Delivery/Indefinite Quantity (IDIQ) contract at Goodfellow Air Force Base. The SABER IDIQ contract will provide a broad range of maintenance, alteration, repair, and minor construction work on real property at Goodfellow AFB and the Goodfellow AFB Recreation Camp. The RFP is set-aside for certified 8(a) business concerns and a single award will be made. The SABER IDIQ has a basic period of 365 days and four one-year option periods, with a guaranteed minimum of $750,000 and a maximum of $25,000,000 over the life of the contract. Key details include requirements for the offeror's management/organizational structure, bonding capacity, quality control plan, and seed project proposals. The RFP response is due July 5, 2024.
View the file
Other files for this federal contract opportunity
Show all 49
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Number Question Response
(B705 Renovate Changing Rooms)
Will there be the opportunity to create a storage/staging area for materials, and equipment before May?
Material staging area will be submitted and approved during the submittal process so yes a staging area will be provided at the site if needed. General, non-task order specific storage, will be available at the SABER
Trailer site on base as well.
(Water Mains Lancaster & Canberra)
Do the fire hydrants have to be made by specific manufacture?
No, but we have used Mueller Super Centurion Model
A423 that has a 5.25" barrel due to parts availability and stocked on Base.
(Overall IDIQ)
Will the project be tax exempt?
The project will not be tax exempt -SD
(Overall IDIQ)
The instructions to bidders stated that the estimates are to be completed in E4 clicks software or equivalent. This is an a RS means module.
Can the RS Means M2 Estimating software be used as an equivalent substitute and will we will not be scored differently or lower on our proposal. If awarded, an E4 clicks software module can be purchased going forward.
The base uses e4Clicks software to conduct Technical
Evaluations. As long as the software being used allows for cross compatibility with Gordians e4Clicks.
For the purposes of proposal submission the government will remove the need for an e4Clicks electrical file and will allow submission of a PDF of the line items proposed.
(B705 Changing Rooms)
The plans show the storage room as part of the area to be renovated. Please confirm this area is not part of the renovation. Will the exterior door of the storage room be included in the scope for the exterior renovation of the building? Painted or replaced?
The storage room is not part of the renovation. Yes the exterior door of the strorage unit is in the scope of the Task Order. Door and frame is to be painted.
(B705 Changing Room)
During the site visit it was explained that all fixtures, Soap, towel dispensers, will be removed and salvaged for installation after renovation?
Yes, all fixtures, Soap, towel dispensers, will be removed and salvaged for installation after renovation
(B705 Changing Rooms)
Can the government provide details or photos of baby changing station requested?
Photos of existing conditions in Building 121 are provided with amendment 0002.
Goodfellow AFB FY24 SABER Question &
Answer Worksheet -Revised 23 July 2024-
(Construct Raised Crosswalk)
During the walkthrough it was discussed that there would be work done on the crosswalk area crossing
Kearney blvd. This area is not included in the provided drawings. Can you confirm only the areas in the drawings will be included in the estimate?
Only the areas indentified in the drawings are to be included in this Task Order. Crosswalk area crossing
Kearney Blvd is not included in this scope.
(Construct Raised Crosswalk)
If the area on Kearney Blvd is included in the project scope ,will there be other set of drawings released that include the new area under scope?
Only the areas indentified in the drawings are to be included in this Task Order. Crosswalk area crossing
Kearney Blvd is not included in this scope.
(Replace Water Mains Hornet & Scherz)
During the on-site visit there was discussion of the project reaching Valent (Valiant) Street, but the plans show it ending well before then. Can you verify the
Bounds of the area in scope?
Revised SOW and Drawing posted with amendment
(Replace Water Mains Lancaster & Canberra)
During the site visit it was discussed that additional information was coming for waterline area. When will the government provide that data or additional information.
Revised SOW and Drawing posted with amendment
(Replace Water Mains Lancaster & Canberra)
If additional drawings are provided with additional work elements will there be another question-and-answer period?
Revised SOW and Drawing posted with amendment
0002. No additional site visits are scheduled nor does the Contracting Officer anticipate a need for a time extension.
(Overall IDIQ)
Section M, paragraph 2.1.2.1, page 6, states, “The
Government will consider and evaluate offeror's past performance information, to include the Relevant
Contracts (Attachment 11), PPQs (Attachment 10), Contractor Performance Assessment Reporting
System (CPARS)…”
Please confirm that CPARS are acceptable in lieu of
Attachment 10 PPQs for applicable contracts.
CPARS will be utilized seperately by the Government to review past performance. The Contractor may submit up to five (5) most recent contracts on
Attachment 10 - Relevant Contracts Worksheet
(Section M, para. 2.1.2.3). Also see Section L para.
4.0.1. If no additional past performance is submitted, the information contained in CPARS will be used. If neither PPQ's are submitted or CPARS are available, a rating of neutral will be given and factored into the overall performance confidence assessments.
(Overall IDIQ)
Section L, Table 2.1 - Proposal Organization, page 3, lists the maximum number of pages for Past
Performance as 35 pages but allows up to 5 most contracts for the prime contractor and each of its teaming partners, JVs, and/or significant subcontractors.
Please confirm that offerors are allowed to submit up to 5 contracts for each team member, each with a 5-page limit per contract, with no maximum page limitation for this section.
We acknowledge the page limitations and encourage you use brevity in your responses. Keep in mind the
Government must review all pages of all proposals, this is very time consuming. The total allowable page count for Volume II, Past Performance is limited to 35 pages.
(Overall IDIQ)
The technical volume encompasses several complex requirements, all within a 30-page limitation. Can the organizational chart be removed from the page limit for this volume?
Section M para. 2.1.1.1 Subfactor 1 -
Management/Organizational Structure provides that the block diagram be included in the Technical
Volume of each proposal. The government will allow one (1) additional page for the organizational chart.
(Overall IDIQ)
The technical volume encompasses several complex requirements, all within a 30-page limitation. Can the bonding capacity documentation be removed from the page limit for this volume?
Section M para. 2.1.1.2 Subfactor 2 - Bonding
Capacity requires Offerors to provide bonding capacity documents that meet the aggregate and project amounts, backed by a bonding surety with a best company rating of ‘A’. The document must also include the surety company’s name, address, phone number, and points of contact. The government will allow two (2) additional pages for the binding information
(Overall IDIQ)
The technical volume encompasses several complex requirements, including separate schedules for each of the seed projects, all within a 30-page limitation.
Can the graphic schedules be removed from the page limit for this volume?
Section M para. 2.1.1.4 Subfactor 4 - Seed Projects provides that Offerors provide schedules that demonstrate an approach and understanding of the required activities to execute the project. This requirment is to be included in the 30 page limit of
Techncial Volume 1. The government will allow one additional page per project for the schedule. This will total four (4) addtional pages
(Overall IDIQ)
Will 11” x 17” page size be permitted for the graphic schedule and organizational chart? How many pages will the 11” x 17” size count as?
Section L para. 2.2.1.1 Page Size and Format requires
11" x 14" page sizes for the proposal. These pages will be considered 1 page each. Adiitionally, we acknowedge the errors in page size being 11" x 14" when we intended to be 11" x' 17"
Section L, paragraph 4.0.1, page 9, states, “Recent past performance is defined as any relevant work completed within the past three (3) years from the date of issuance of this solicitation.”
Section M, paragraph 2.1.2.2, page 7, states, “To be recent, the effort must be ongoing or must have been performed during the past 3 years from the date of issuance of this solicitation.”
Section M, paragraph 2.1.2.3, page 8, states, “Recent past performance is defined as any relevant work completed within the past three (3) years from the date of issuance of this solicitation.
Sections L and M appear to have conflicting recency requirements. Will the Government please confirm that acceptable past performance examples can be ongoing?
According to Section M para. 2.1.2.2 "To be recent, the effort must be ongoing or must have been performed during the past 3 years from the date of issuance of this solicitation." Acceptable past performance can be projects that are ongoing and/or have been performed during the past three years.
To summarize the Government will accept relevant work that is completed in the last three years. The
Government will accept work that is ongoing or performed during the past three years from the date of issuance of this soliciation.
(Overall IDIQ)
Section L, paragraph 4.0.1, page 9, states, “Recent past performance is defined as any relevant work completed within the past three (3) years from the date of issuance of this solicitation.”
Section M, paragraph 2.1.2.2, page 7, states, “To be recent, the effort must be ongoing or must have been performed during the past 3 years from the date of issuance of this solicitation.”
Section M, paragraph 2.1.2.3, page 8, states, “Recent past performance is defined as any relevant work completed within the past three (3) years from the date of issuance of this solicitation.
Sections L and M appear to have conflicting recency requirements. If the intention is for the past performance examples to have been completed in the last three years, will the government accept a
SABER/JOC/MATOC/MACC – type contract that is ongoing, but has completed task orders within the last three years?
According to Sec L para. 4.0.1, Sec M para 2.1.2.2, Sec
M 2.1.2.3 The Government will accept relevant work completed in the last three years from the date of issuance of the soliciation. To be recent, the effort must be ongoing or must have been performed during the past three years from the date of issuance of the soliciation. Recent past performance is defined as any relevant work completed within the past three
(3) years from the date of issuance of this solicitation.
Examples include, but are not limited to, Simplified
Acquisition of Base Engineering Requirements
(SABER), Job Order Contracts (JOC), Multiple Award
Construction Contracts (MACC), Multiple Award Task
Order Contracts (MATOC), or simply evidence of simultaneous work completed on schedule.
To summarize the Government will accept relevant work that is completed in the last three years. The
Government will accept work that is ongoing or performed during the past three years from the date of issuance of this soliciation.
Section L, Subfactor 1 includes the following: “The offeror must provide design/documentation for the overall SABER IDIQ provided in Attachments 11-14.”
However, Section M, Subfactor 1 includes: “The offeror must provide design/documentation for the overall SABER IDIQ provided in Attachment 4.” Can the government please confirm which Attachment is correct here and clarify what design/documentation is required in the Management/Organizational Structure narrative?
Section M: TechnicalFactor, Subfactor 1, Para (a) has been stricken in its entirety. Sentence may have been placed in error during benchmarking.
(Overall IDIQ)
The instructions in Section L, Subfactor 4 include a line item (iv) for a price proposal for each seed project.
Please confirm that pricing should not be included in the Technical volume.
Section M para 2.1.1.4 Subfactor 4 - Seed Projects line
iv) requires that a price proposal for each seed project be submiited in accordance with the "measure of merit" criteria. Any pages containing ONLY RS
MEANS line items for seed project proposals will be excluded from the page count limitations in Volume 1
Pricing in the technical volume concerns itself with the four seed projects. The Pricing Volume requires the Offeror fill-in Attachment 9 - Coefficient Pricing
Worksheet.
(Overall IDIQ)
The instructions in Section L, Subfactor 4 include a line item (iv) for a price proposal for each seed project, including: “The proposal will be sent with a digital e4Clicks file, PDF, and conceptual drawings needed to evaluate proposed line items and quantities.” The instructions in Volume III do not include these requirements. Please confirm if a separate digital e4Clicks file is required.
Section M para 2.1.1.4 Subfactor 4 - Seed Projects line
iv) requires that a price proposal for each seed project be submiited in accordance with the "measure of merit" criteria.
For the purposes of proposal submission the government will remove the need for an e4Clicks electronic file and will allow submission of a PDF of the line items proposed. Any pages containing ONLY
RS MEANS line items for seed project proposals will be excluded from the page count limitations in
Volume 1
(Overall IDIQ)
The instructions in Section L, Subfactor 4 include a line item (iv) for a price proposal for each seed project, including: “The proposal will be sent with a digital e4Clicks file, PDF, and conceptual drawings needed to evaluate proposed line items and quantities.” Please confirm if alternative file types, such as Excel files, are acceptable in lieu of e4Clicks files for the purpose of this proposal submission.
A separate e4Clicks file will not be needed with the initial proposal, but will be needed directly after award to accommodate negotiations. Any pages containing ONLY RS MEANS line items for seed project proposals will be excluded from the page count limitations in Volume 1.
The instructions in Section L, Subfactor 4 include a line item (iv) for a price proposal for each seed project, including: “The proposal will be sent with a digital e4Clicks file, PDF, and conceptual drawings needed to evaluate proposed line items and quantities.” The instructions in Volume III do not include these requirements. Please confirm if conceptual drawings are required and, if so, if they should be submitted with the Seed Project narrative in Volume I or the price proposal in Volume III.
Any pages containing ONLY RS MEANS line items for seed project proposals will be excluded from the page count limitations in Volume 1. Any pages containing
ONLY drawings for the seed project proposals will be excluded from the page count limitations in Volume
1.
(Overall IDIQ)
Section L, Subfactor 3 includes a requirement for a draft Quality Control Plan. Please clarify if Offeror’s are to submit a separate corporate Quality Control
Plan. If so, where is this submitted, and does it count against the 30-page limit for Volume 1? Or is the requirement for a narrative within Volume I that describes the offeror’s QC processes and procedures?
The requirment for subfactor 3 - quality control (qcp) plan is met when the offeror provides a description of the contractor’s quality control processes and procedures, including a chart showing lines of authority. The QCP Manager shall report to the project manager or someone higher in the organization. The project manager in this context shall mean the individual with responsibility for the overall management of the project including quality and production. The QCP will be submitted as a draft with the offerors proposal. If an offeror becomes the awardee the draft QCP will required to become formalized no later than 20 calendar days after award (See Sec L, sub-factor 3 and
Section M, sub-factor 3).
(Overall IDIQ)
Section L and Specifications have conflicting personnel requirements. For example, Section L, paragraph 3.1.3, page 7, states, “Quality Assurance
Manager/ Foreman (minimum of 2 years experience),” whereas Section 01 45 00.10 20, paragraph 1.5.1.2, page 4, states a QC manager requires a minimum of 5 years combined experience.
Please clarify which document's requirements should take precedence.
Section L - Instructions to Offerors Subfactor 1 -
Management/Organizational Structure & Section M
Section 2.1.1.1 Subfactor 1 -
Management/Organizational Structure revised to reflect "five years combined experience," as stated in
Specifications 01 45 00.10 20 Sec 1.5.1.2
Due to the size, scope, and complexity of this project, please consider extending the current proposal due date an additional two (2) weeks to allow adequate time for the contracting community to fully understand the project requirements and ensure competitive pricing.
Due to end of year obligation requirements, the government cannot extend the proposal due date any further. You are encouraged to use your time wisely and submit your best proposal.
(Overall IDIQ)
RE: Attachment 1 - Section H Special Contract
Requirements, Section Non-Priced Work (b) (1) and
(2).
Q: Is the offeror to assume that no subcontractor’s overhead and profit will be applied to the non-priced items?
Attachment 1 - Section H Special Contract
Requirements addresses Non-Pre Priced Work.
Subcontractor pricing for both materials and labor must be fully develped to include all costs not attributable to the prime contractor coeffiecients.
(Overall IDIQ)
RE: Attachment 1 - Section H Special Contract
Requirements, 14. Testing of Materials B. requires concrete compressive strength tests cylinders or borings.
Q: This section does not state whether the cost of the testing can be included in the estimate as an UPB line item. Is the offeror to assume that the cost of testing can be included in the estimate as a UPB line item?
As stated in section B of the RFP Para (b): All direct expenses associated with the contract shall be included in your proposed coefficient. This includes all testing performed as a standard practice with any given trade. Therefore, will not be seperately priced using a UPB line item in each task order proposal.
(Overall IDIQ)
RE: Attachment 1 - Section H Special Contract
Requirements, 14. Testing of Materials C. requires compaction testing of fill materials.
Q: This section does not state whether the cost of the testing can be included in the estimate as an UPB line item. Is the offeror to assume that the cost of testing can be included in the estimate as a UPB line item?
As stated in section B of the RFP Para (b): All direct expenses associated with the contract shall be included in your proposed coefficient. This includes all testing performed as a standard practice with any given trade. Therefore, will not be seperately priced using a UPB line item in each task order proposal.
RE: Attachment 1 - Section H Special Contract
Requirements, 22. Construction Site Maintenance D.
states - All mud, dirt, debris, foreign objects, or spills of any kind from the Contractor's operations
(including subcontractors and suppliers) on streets and parking lots used as access to the work or staging areas, shall be cleaned off the same day.
Q: This section does not state whether the cost of the site clean-up can be included in the estimate as an
UPB line item. Is the offeror to assume that the cost of testing can be included in the estimate as a UPB line item?
As stated in section B of the RFP Para (b): All direct expenses associated with the contract shall be included in your proposed coefficient. This includes all testing performed as a standard practice with any given trade. Therefore, will not be seperately priced using a UPB line item in each task order proposal.
(Overall IDIQ)
RE: Attachment 1 - Section H Special Contract
Requirements, 22. Construction Site Maintenance F.
states - There are no approved concrete truck clean-out sites on base; however, concrete truck chutes may only be rinsed at the construction site. The
Contractor will be responsible for the cleanup of material generated as a result of the rinsing operation.
Q: This section does not state whether the cost of the clean-up can be included in the estimate as an UPB line item. Is the offeror to assume that the cost of testing can be included in the estimate as a UPB line item?
As stated in section B of the RFP Para (b): All direct expenses associated with the contract shall be included in your proposed coefficient. This includes all testing performed as a standard practice with any given trade. Therefore, will not be seperately priced using a UPB line item in each task order proposal.
(Overall IDIQ)
RE: Attachment 1 - Section H Special Contract
Requirements, 22. Construction Site Maintenance I.
states - Final clean-up costs associated with a project may be direct TO costs.
Q: Is the offeror to assume that the cost of final clean-up can be included in the estimate as a UPB line item?
As stated in section B of the RFP Para (b): All direct expenses associated with the contract shall be included in your proposed coefficient. This includes all testing performed as a standard practice with any given trade. Therefore, will not be seperately priced using a UPB line item in each task order proposal.
(Overall IDIQ)
RE: Attachment 2 – Section L Instructions to Offerors,
2.2 Organization/Number of Copies/Page Limits.
Q: This section does not state what volume the seed projects are to be included. Can the government provide guidance?
Section L para 3.1.3 provides the guidance for the
Technical Volume I and the four technical sub-factors included. Techncial Volume I sub-factor 4 will house the seed projects in the offerors proposal. Section M para 2.1.1.4 Subfactor 4 – Seed Projects also provides the description of sub-factor 4 as well as the measure of merit for which the sub-factor will be evaluated.
Please review accordingly.
RE: Attachment 2 – Section L Instructions to Offerors,
2.2.1 and 2.2.1.1 sections do not state how 11x14 pages will be counted as.
Q: Will the 11x14 pages fall within the page count? If so, will they be counted as 1 page or 2 pages?
Section L para. 2.2.1.1 Page Size and Format requires
11" x 14" page sizes for the proposal. These pages will be considered 1 page each. Adiitionally, we acknowedge the errors in page size being 11" x 14" when we intended to be 11" x' 17"
(Overall IDIQ)
RE: RE: Attachment 2 – Section L Instructions to
Offerors, Subfactor 3 – Quality Control Plan A. states -
Offeror shall provide a draft Quality Control Plan
(QCP).
Q: Table 2.1 only allows 30 pages for Volume I
Technical. A draft Quality Control Plan will be over 30 pages. Does the government want a draft plan or a summary of a plan? If the government wants a draft plan, will it be excluded from the page count?
The requirment for subfactor 3 - quality control (qcp) plan is met when the offeror provides a description of the contractor’s quality control processes and procedures, including a chart showing lines of authority. The QCP Manager shall report to the project manager or someone higher in the organization. The project manager in this context shall mean the individual with responsibility for the overall management of the project including quality and production. The QCP will be submitted as a draft with the offerors proposal. If an offeror becomes the awardee the draft QCP will required to become formalized no later than 20 calendar days after award (See Sec L, sub-factor 3 and
Section M, sub-factor 3). The page count limitation is to encourage brevity and precision in the response to this Reequest for Proposal.
(Overall IDIQ)
RE: RE: Attachment 2 – Section L Instructions to
Offerors, 4.0 Volume II – Past Performance, 4.0
General states - The offeror shall submit a consent letter in their format executed by each subcontractor, teaming partner, and/or joint venture partner, authorizing release of adverse past performance information to the offeror so the offeror can respond to such information.
Q: Does the government have a standard letter of consent you wish the offeror to use?
The Government does not have a standard letter of consent. Section L Volume II - Past Performance provides that the offeror submit their consent letter in their format (Para 4.0 General). Offerors will provide the consent letter in their companies format.
Combining all subcontractors on one letter with numerous signatures is also acceptable to cut down on pages needed for this response.
RE: Attachment 2 – Section L Instructions to Offerors,
4.0.1 Recent and Relevant Contracts states - Submit
up to five (5) most recent contracts on……, that are considered most relevant in demonstrating your ability to perform the proposed effort. Also, include information up to five (5) recent contracts performed by each of your …….. Joint Ventures.
Q: If an offeror is submitting under a joint venture, does the government want up to 5 contracts from the managing member (8(a)) of the joint venture, and up to 5 contracts from the partner member (non-8(a)) of the joint venture?
The Government's expectation in Section L para 4.0.1
Recent and Relevant Contracts is for the five (5) recent contracts submitted to provided by the Joint
Venture as its represented by its Unique Entity
Identifier (UEI) and its Commercial and Government
Entity (CAGE) code as represented in in the federal government's System for Award Management
(SAM.gov).
Revised 23 July 2024: A Joint Venture may submit up to five (5) recent contracts from the managing member and up to five (5) recent contracts from a partner member.
(Overall IDIQ)
RE: Attachment 3 – Section M Evaluation, 2.1
Evaluation Factors and Subfactors, 2.1 Evaluation
Factors and Subfactors identifies – The seed projects will be in 2.1.1Factor 1: Technical, 2.1.1.4 Subfactor 4:
Seed Project Task Order
Q: Since the seed projects estimates will have the offeror’s coefficient on it. Confirm that the seed project estimate will be in 2.1.1.4 Subfactor 4: Seed
Project Task Order and not 2.1.3 Factor 3: Price.
Confirmed. The seed project estimates will be contained the offerors Volume I Technical sub-factor
4 portion of the proposal. Also see response to question 23 above.
(Overall IDIQ)
RE: Attachment 3 – Section M Evaluation, 2.1.1.1
Subfactor 1 – Management/Organizational Structure,
iii) states - Also denote the PE or architecture firm used and specify whether they will be in house or subcontracted (IAW Specification Section 01 10 01
Part 1 Para. 1.8(D & E)).
Q: Should IAW Specification Section 01 10 01 Part 1
Para. 1.8(D & E)) read Section 01 10 01 Part 1 Para.
1.7 A?
Does appear to be an error and the reference should be 1.7A. This will be corrected and the revised document will be relased in an amendment to the solicitation. Confirm with CES/CENMP
File details come from the government source that posted it. Updated .